chapter 5 status quo of current construction …status quo of current construction practices 5.1...
TRANSCRIPT
Chapter 5
STATUS QUO OF CURRENT CONSTRUCTION
PRACTICES
5.1 Introduction
This chapter presents the outcomes of an investigation into the status quo of the current
construction practices for the purpose of generating scenarios of the future construction
supply chain management (CSCM). The investigation involved finding out the magnitude
of which technology is being used in construction sites and the industry’s readiness to
adopt new technology through a researcher-administered questionnaire survey. Case
studies were conducted to investigate into the current construction logistics practices,
problems encountered, utilisation of ICT tools and the possibility of using digital
technologies such as Wi-Fi tags and Personal Digital Assistant (PDA) for managing
construction project activities. The need for a context-aware system for logistics services
management was also investigated.
Eight construction practitioners participated in both the survey and case studies involving
questionnaire and in-depth face-to-face semi-structured interviews. The results of these are
presented in the following sections. For case studies, the cases are first presented
individually and then comparisons made between them. Finally, the conceptual model of
the proposed context-aware system is presented based on the current logistics practices
discovered from interviews.
5.2 Survey
A survey was carried out among construction practitioners to learn the extent to which ICT
is being used in construction sites and to investigate the construction industry’s readiness
to adopt new technology. By learning these will give early indications as to how the
Context-Aware Services Delivery in the Construction Supply Chain
115
proposed context-aware application for construction supply chain will be accepted by
construction practitioners.
5.2.1 Survey Objective
The objectives of the survey were to:
To analyse the level of IT facilities in the management of site logistics
To investigate the level of acceptance of using wireless communication and sensor
technology among construction practitioners
5.2.2 Questionnaire
To achieve the above objectives, a questionnaire was designed objectively to investigate
the level of acceptance of using wireless communication network technology in improving
logistics services within the construction supply chain network as a whole and the
magnitude of which technology was being used at construction sites. Relevant questions
relating to the use of communication and information tools, construction logistics services
and digital technologies were developed. This questionnaire utilised both closed and open-
ended questions. Respondents were asked to give ratings based on five-point Lickert scale
(e.g. 1 – unnecessary, 2 – somewhat unnecessary, 3 – neutral, 4 – recommended and 5 –
strongly recommended) for all listed items.
The questionnaire was divided into three parts, i.e. Q1, Q2 and Q3. Q1 dealt with the
general communication and information tools used/practiced on site. Respondents were
asked to tick the items if they observed it at their organisation and gave rating of their
recommendation of their usage/practice at site. They were also asked to indicate if there
were issues or problems encountered relating from or relating to the communication and
information tool. Q2 dealt with the logistics services at construction site and Q3 dealt with
the use of digital technologies. A copy of the questionnaire is provided in Appendix A.
5.2.3 Respondents
Eight respondents knowledgeable in construction as well as in dealing with logistics as
their main scope of works, therefore, deemed as experts, were selected. Among them were
a construction manager for a multi-storey building project in a busy traffic area, a logistics
Context-Aware Services Delivery in the Construction Supply Chain
116
project manager for an airport project (high security area), a logistics technical director for
a project on a university campus and a project manager for a museum in a city centre.
Other respondents included a senior project manager, project manager, facilities manager
and contracts manager of various construction projects of various sizes in different
locations. Size of projects is not defined as it is not in the scope of this research.
5.2.4 Survey Process
During the early stage, the selected respondents were contacted and notified through email
and telephone to request their participation and co-operation in the research by supplying
the information needed. They were told that their personal information would be kept
confidential to ensure fidelity of the data. Appointments were made and the questionnaire
was e-mailed to them prior to the meeting. They were asked to peruse the questionnaire in
their free time so that they knew what was expected of them during the appointed meeting.
The researcher-administered questionnaire survey was conducted in each of the
respondent’s respective site office. They were all briefed on the overall questionnaire
before starting to fill in their answers. This had been done in order to ensure the validity
and reliability of the survey data. In addition, their answers were discussed for clarification
and/or to collect additional information, hence eliminate misunderstandings. This
questionnaire provided a basis for the ensuing face-to-face in-depth interview for each case
study.
5.3 Survey Results
The survey data were analysed based on the eight responses gathered by counting the
number of respondents (frequency) who had observed certain issues/tools at their
organisations and calculating the average score (out of 5) for their level of
recommendation for each issue/tool. The results from the questionnaire are presented in the
following sub-sections.
5.3.1 General Communication and Information Tools
This part of the questionnaire addressed the communication and information tools that
were observed to have been used by the construction organisation in their daily works or
Context-Aware Services Delivery in the Construction Supply Chain
117
activities. This question was designed to identify the most common and least used tools for
communication and for conveying information in daily works. Table 5-1 shows the number
of observations and average scores for the level of recommendations from the respondents
on communication and information tools. The survey results show that all the respondents
had observed the following tools being practiced and used at their organisations: face-to-
face meeting, e-mail, telephone, plans and drawings, design specifications, scope of works
and Gantt chart. Consequently, they also rated these tools with high scores, i.e. either ‘5’
for ‘strongly recommended’ or ‘4’ for ‘recommended’. Not surprisingly, plans and drawing
received the rating ‘5’ from all the respondents. On the other hand, items or tools that were
seldom or never observed at their organisations, especially on construction sites, like video
conferencing, text messaging, multimedia messaging and facsimile were given low ratings,
i.e. either ‘1’ for unnecessary or ‘2’ for somewhat unnecessary’. On some items that they
were unsure or had no opinion of, some respondents gave the rating ‘3’ for ‘neutral’.
Table 5-1: Observation and Recommendation for Communication and Information Tools
General communication and information tools Number of
Observation Level of
Recommendation
Meetings (face-to-face) 8 4.75
Video conferencing 1 2.25
E-mail 8 4.63
Text messaging (SMS) 2 2.13
Multimedia Messaging (MMS) 0 2.13
Telephone 8 4.88
Facsimile 2 2.50
Plans and Drawings 8 5.00
Design specifications 8 4.50
Scope of works 8 4.75
Scheduling (Gantt chart) 8 4.75
In the same category of the questionnaire, the question asked about the issues/problem
encountered at the respondents’ organisations related to the use of communication and
information tools identified above. In this analysis, the column chart was selected to study
the pattern of the survey data. From the survey data shown in Fig. 5-1, it shows that
problems such as information not readily available, slow retrieval and limited sharing
stood out as the main concern. The others gave a cause for concern too. There was a mix of
Context-Aware Services Delivery in the Construction Supply Chain
118
opinions for problems of documents being lost and culture/attitude problem when using the
existing communication and information tools.
Fig. 5-1: Problems encountered using existing communication and information tools
Other issues arising from communication and information tools were inaccurate as-built
drawings and the fact that some companies did not keep up with technology. Limited e-
mail size storage used to be a problem, but with the implementation of VPN (Virtual
Private Network), this was no longer the case. It had been remarked that video
conferencing was unusual at construction sites, while opportunities for SMS and MMS
were not explored therefore underutilised and it was unnecessary for information to travel
in real-time.
Recommendations for improvement include:
Implementation of appropriate communication system and procedures, e.g. web
management system for managing drawings, RFI and schedules and to ensure that
contractors and designers are competent to use them.
Use of smartphone, PalmPC or PDA with good software.
Issue mobile phones to workers.
‘Real’ collaborative working.
75 5
67
46
76 6
54
0123456789
Info
not
avai
lab
le
Info
not
real
-tim
e
Tra
dit
ion
al m
od
es
Info
not
accu
rate
Lim
ited
sh
arin
g
Docu
men
t lo
st
Dif
ficu
lt to h
and
le
Slo
w r
etri
eval
Nee
d b
igger
sto
rage
(pap
er/d
ocu
men
t)
Mix
ed h
and
lin
g o
f d
ata
Lac
k o
f se
curi
ty
Cu
ltu
re/A
ttit
ude
pro
ble
m
Disagree
Agree
Problems Encountered Using Existing Communication and Information Tools
No
. o
f R
esp
onse
s
Context-Aware Services Delivery in the Construction Supply Chain
119
5.3.2 Logistics Services at Construction Site
The second part of the questionnaire addressed the work planning, work implementation
and tracking and monitoring system practiced or used by construction organisations in their
work related activities. This question was designed to identify the most common and least
used tools for logistics services in their daily work. Table 5-2 shows the number of
observations and average scores for the level of recommendations from the respondents on
the work planning. From the survey result, it can be observed that material flow, materials
order and delivery, material handling and traffic flow were the main activities being
seriously looked into by the logistics personnel or construction management during the
planning and design stages. The planning of storage, machinery and equipment and
manpower supply were also frequently observed. Information flow and modes of
communication also received high scores.
Table 5-2: Observation and Recommendation for Work Planning
Work Planning Number of
Observation Level of
Recommendation
Material orders and delivery 8 4.38
Material flow 8 4.88
Material handling 8 4.75
Information flow 6 4.00
Modes of communication 6 4.13
Storage 7 4.63
Traffic flow 8 4.75
Machinery and equipment 7 4.38
Manpower supply 7 4.63
In terms of work implementation at site, Table 5-3 shows that material delivery was
observed to be given the highest priority compared to other items but the importance of
work safety and health rules were observed equally. Construction activities and efficient
use of labour and equipment were mostly observed to be as planned. Similar to previous
cases, the level of recommendation closely follow the trend of the observation.
Context-Aware Services Delivery in the Construction Supply Chain
120
Table 5-3: Observation and Recommendation for Work Implementation
Work Implementation Number of
Observation Level of
Recommendation
Material delivery as scheduled 8 4.88
Minimization of material handling 6 4.63
Work safety and health rules 8 4.38
Construction activities as planned 7 4.75
Efficient use of labour and equipment 7 4.75
Relationship with supplier 5 4.38
For the use of tracking and monitoring system in logistics services, responses indicated that
monitoring or tracking of materials delivery, manpower, equipment and assets rarely
occurred and could be said to be mostly unnecessary on construction site as shown in
Table 5-4.
Table 5-4: Observation and Recommendation for Tracking and Monitoring System
Tracking and monitoring system Number of
Observation Level of
Recommendation
Material delivery and handling 5 3.88
Mobile worker / manpower 3 3.63
Machinery, equipment and tools 4 3.75
Assets and inventory 4 3.75
Problems encountered in logistics services include information not readily available, not
aware of material delivery schedule, material delivery not according to schedule, delays,
resupply, double handling of materials, material damage, storage, transparency, security
and culture. From Fig. 5-2, it can be observed that the listed problems in logistics services
were mostly agreed with by all respondents. Site accessibility, material being misplaced,
tracking material and information inaccuracy were rated close second. However, for the
problems of tracking of mobile workers and plants, the respondents had divided opinions
regarding these occurring.
Some of the other logistics management tools named by the respondents were waste
management plan, procurement system, physical and manned security, fire safety and
patrols, manual handling assessment, BREEAM for local suppliers and materials
return/delivery sheet. It has been remarked that it was essential for contractors to organise
Context-Aware Services Delivery in the Construction Supply Chain
121
and plan all logistics activities effectively and have contingency plan in place in case of
something unexpected. Ability to adapt to unplanned construction activities/events was
considered vital. Needless to say that it was also essential to understand construction
activities in order to plan for site logistics.
Fig. 5-2: Problems encountered in logistics services
There was a concern that some sites did not hire enough gatemen or security guards in
order to cut cost, also information about delivery schedule not being communicated to
these gatemen effectively.
Recommendations for improvement of logistics management include:
Employ reliable known contractors
Build up a relationship with regular suppliers
Encourage major material suppliers to see construction site
Understand and plan for material flow and material handling
Raise awareness of the benefits of ‘managed logistics’ throughout the industry
Raise awareness that logistics is not just for very large projects.
5.3.3 Digital Technologies at Construction Site
Tables 5-5 to 5-9 show the results of the third part of the questionnaire. This part dealt with
the digital technologies at construction site which include communication technology,
7 7 7 7 7 6 7 7 6 7
46 5
7 6 7 7
0123456789
Info
rmat
ion
not
read
ily
avai
lab
le
Not
awar
e of
del
iver
y
sch
edu
le
Del
iver
y n
ot
acco
rdin
g
sch
edu
le
Del
ays
Re-
sup
ply
Acc
essi
bil
ity
Dou
ble
han
dli
ng
Mat
eria
l d
amag
e
Mat
eria
l m
isp
lace
Sto
rage
Tra
ckin
g w
ork
er
Tra
ckin
g m
ater
ial
Tra
ckin
g p
lan
ts
Tra
nsp
aren
cy
Inac
cura
cy
Sec
uri
ty
Cu
ltu
re
DisagreeAgree
Problems Encountered in Logistics Services
No
. o
f R
esp
onse
s
Context-Aware Services Delivery in the Construction Supply Chain
122
communication device, tracking/monitoring technology and project management software.
The questions were designed to address the IT and wireless technology system that have
the potential of being used for logistics services. Respondents were asked to indicate
whether they observed the use of such technology at site, and to rate it with ‘1’ for ‘not
effective at all’ to ‘5’ for ‘very effective’. From Table 5-5 it can be observed that the use of
internet was observed by all the respondents, and it was also seen as the most effective way
of communicating compared with other wireless system network.
Table 5-5: Observation and Recommendation for Communication Technology
Communication technology Number of
Observation Level of
Effectiveness
Internet 8 4.25
Wireless Wide Area Network (WWAN) 1 2.63
Wireless Local Area Network (WLAN/Wi-Fi) 2 3.63
Wireless Personal Area Network (WPAN/ Bluetooth) 0 2.50
Global Positioning System (GPS) 0 3.25
Personal computer (PC) was the most preferred communication device tool compared to
smartphone, PDA, notebook, tablet PC or walkie-talkie as shown in Table 5-6. This is
rather surprising particularly in relation to smartphone and tablet PC because they are
widely used. PC received the highest average rating for effectiveness but, interestingly, for
the other devices the ratings do not correspond to the number of observations.
Table 5-6: Observation and Recommendation for Communication Device
Communication device Number of
Observation Level of
Effectiveness
Smartphone 6 3.13
Personal Digital Assistant (PDA) 4 3.88
Tablet PC 4 3.25
Notebook (laptop computer) 6 4.50
Personal Computer (PC) 8 4.75
Walkie-Talkie 5 4.00
For tracking of material flow, equipment location and personnel activities, all the proposed
sensor technology such barcode, RFID, Wi-Fi tags, CCTV and webcam were classified as
Context-Aware Services Delivery in the Construction Supply Chain
123
not effective tools as shown in Table 5-7. These were not observed to be used much for
tracking or monitoring materials and assets at construction sites.
Table 5-7: Observation and Recommendation for Tracking/Monitoring Technology
Tracking/monitoring technology Number of
Observation Level of
Effectiveness
Bar codes 3 2.75
Radio Frequency Identification (RFID) 3 2.38
Wi-Fi Tags 0 2.50
CCTV 3 3.75
Webcam 4 3.75
Table 5-8 shows that the most observed and preferred management software was Microsoft
Project (MSP) compared to other less popular and perhaps expensive ones. Primavera
Project Planner came close second. Web-based project management software was
categorised as not effective for the logistics services application as indicated by table 5-9.
The reason for the low number of observation and low rating of effectiveness was because
different organisations used different project management software and the respondent
from each organisation only found the software that they were familiar with to be effective,
hence giving low scores to the others.
Table 5-8: Observation and Recommendation for Desktop Project Management Software
Desktop Project Management Software Number of
Observation Level of
Effectiveness
Microsoft Project (MSP) 4 4.00
Micro Planner X-Pert (X-Pert) 1 2.38
Primavera Project Planner 3 3.00
Table 5-9: Observation and Recommendation for Web-based Project Management Software
Web-based Project Management Software Number of
Observation Level of
Effectiveness
Microsoft Office Project Server 1 2.88
eGroupWare 1 2.13
Project.net 1 2.13
Oracle Applications 1 2.25
Enterprise Resource Planning (ERP) 1 2.88
Context-Aware Services Delivery in the Construction Supply Chain
124
From Fig. 5-3, it can be observed that there were two main problems encountered in the
application of digital technologies: cost-effectiveness and training. Maintenance and
services came second, followed by issues of poor coverage, licensing, communication flow
overload, different technology, time consuming and cultural. Opinions were divided
regarding interoperability and security and privacy. Lack of automation and robustness
were not seen as a problem.
Fig. 5-3: Problems Encountered Using IT Technologies
It was remarked that bar coding of key construction elements from factory could assist and
speed-up construction as key members of staff could easily locate important structure
elements. If ‘fit-out’ items (e.g. light fitting) were bar coded and registered on database,
critical path items like air-conditioning would never become a reason why a building could
not be handed-over. The general workforce would prefer a technology that provides a
simple ‘hit-button’ – when it is pressed things happen. They need to see substantial
benefits in adopting such technology and the management would need to see the proof of
its cost-effectiveness.
7
5
76
54
2 2
45
3
5 5 5
0
1
2
3
4
5
6
7
8
9
Not
cost
-eff
ecti
ve
Poor
net
work
cover
age
Tra
inin
g
Mai
nte
nan
ce a
nd
ser
vic
es
Lic
ensi
ng
Inte
rop
erab
ilit
y
Lac
ks
auto
mat
ion
Lac
ks
rob
ust
nes
s
Sec
uri
ty a
nd
pri
vac
y c
on
cern
s
Com
mu
nic
atio
n f
low
over
load
ed
On
e w
ay c
om
mu
nic
atio
n
Dif
fere
nt
tech
nolo
gy
Tim
e co
nsu
min
g
Cu
ltu
ral
Disagree
Agree
Problems Encountered Using IT Technologies
No
. o
f R
esp
onse
s
Context-Aware Services Delivery in the Construction Supply Chain
125
Recommendations for improvement include:
Application needs to suit the site requirement, e.g. limited site access, limited time
for delivery (working in city centre – London), security check-up (working with
Ministry of Defence).
Application needs to be operated and managed by a logistics company/
subcontractor.
Training and continuity of software including upgrades.
5.4 Key Findings from Survey
It can be observed that the face-to-face meeting and communication through phone were
highly recommended and dominated the communication and information delivery in
construction organisations. The planning of logistics activities were highly observed and
recommended, however during work implementation the recommendations remained high
but the number of observations became less. For tracking and monitoring of logistics
activities, these became even less. The internet and PC were the only communication
technology and device that all respondents were happy with. None of the tracking and
monitoring technologies were believed to be effective and the most popular project
management software was Microsoft Project. The fact that some companies did not keep
up with technology was the main concern about communication and information tools.
Also, respondents felt that it was unnecessary for information to travel in real-time.
Recommendations to improve logistics management included employing reliable known
contractors, building up a relationship with regular suppliers and understanding and
planning for material flow and material handling. Raising awareness throughout the
industry of the benefits of ‘managed logistics’ and that logistics is not just for very large
projects were the other recommendations.
Implementing and adopting a new technology would be a challenge because the general
workforce prefers a technology that is simple and easy to use, while the management is
concerned with its cost-effectiveness. On the whole, it is clear that only the basic and low
level IT facilities are currently available and being utilised at construction sites and
construction practitioners are not ready to use digital and wireless technologies in their
day-to-day work.
Context-Aware Services Delivery in the Construction Supply Chain
126
5.5 Case Studies
Case studies of construction projects were carried out to investigate the current logistics
practices in the construction industry for the purpose of generating construction supply
chain scenarios which are discussed in the next chapter. As previously revealed in Chapter
2, logistics as the back bone of the construction supply chain processes plays a great role in
optimising the flow of materials, equipment and people from the point of supply to the
point of use. Logistics creates value within the supply chain through managing customer
service, orders, inventory, transportation, storage, handling, packaging, information,
forecasting, production planning, purchasing, cross docking, repackaging, preassembly,
facility location and distribution (Hamzeh et al., 2007). Materials handling, transportation
and warehousing are known to be the critical services that serve the logistics operation
processes by optimising the movement of raw materials, optimising the transportation
mode, locating and designing facilities.
Six construction projects were investigated to learn the running of their daily logistics
activities in building their projects. These involved in-depth semi-structured interviews
with those responsible for materials management and site logistics of the chosen
construction projects. The current situations with regard to logistics services management
were identified based on the problems encountered in managing site logistics, the
approaches taken to address the problems, the utilisation of information and
communication tools (as listed in Table 5-1), the possibility of using digital technologies
(as listed in Tables 5-5 to 5-7) for improving the current construction project activities and
the current methods used by the site managers to track materials and assets.
5.5.1 Objectives of the Case Studies
The aim of the case studies was to learn the running of the day-to-day logistics activities at
construction project sites. The main objectives of the case studies undertaken were as
follows:
To investigate the current practices and problems of logistics services management
in construction projects.
To identify the approaches to address site logistics problems.
To examine the implementation of ICT in logistics services management processes.
Context-Aware Services Delivery in the Construction Supply Chain
127
To explore the potential of digital technologies (such as Wi-Fi tags and PDA) in
logistics services management on construction projects.
5.5.2 Choice of Case Studies
Case study research was selected to acquire more insight into the current construction
logistics practices, problems encountered, information and communication tools and the
potential use of digital technologies. The case studies were undertaken to discover the site
logistics management practices on six construction projects (Case A - Case F). The data
collected were based on semi-structured interviews with the managers responsible for site
logistics services which include the management of materials. The semi-structured
interview questions were designed in three parts. The first part was aimed at capturing the
general information about the site managers and the project they were in charge of. The
second part examined the current practices and the information and communication tools
used in the logistics services management. The third part of the semi-structured interview
was intended to investigate the potential use of digital technologies such as Wi-Fi tags and
PDA for material, asset and personnel monitoring and the needs for a context-aware
system for logistics services management.
For the purpose of this research, the ‘unit of analysis’ was geared towards achieving the
study objective, which was to investigate the potential of implementing digital
technologies for improving on-site logistics services management on construction projects.
The ‘unit of analysis’ for this study was based on the six construction projects and with six
‘embedded unit of analysis’ as follows:
Site logistics services problem: This explored the most significant problems that
occurred in the site logistics management practices
Approaches to addressing problems: This aimed to identify strategies used by site
managers to solve site logistics management problems on the construction site
Information and communication tools: This sought to identify the use of
information and communication tools at construction site.
Use of digital technologies: This investigated the potential of the digital
technologies to facilitate site logistics management practices.
Logistics information and services system: This sought to identify the current
methods used by site managers to facilitate materials, personnel and asset tracking
Context-Aware Services Delivery in the Construction Supply Chain
128
on construction sites.
ICT implementation issues: This investigated the issues that arose from the
implementation of ICT at site.
Data analysis involved both single case and cross-case analyses as shown in Fig. 5-4.
Single case analysis was conducted to produce individual case reports in order to obtain the
information on the current site logistics management practices, problems encountered on
site and the utilisation of information and technology tools. Amaratunga and Baldry (2001)
Case A
EUA 1
EUA 6 EUA 5
EUA 4 EUA 3
EUA 2
Case B
EUA 1
EUA 6 EUA 5
EUA 4 EUA 3
EUA 2
Case C
EUA 1
EUA 6 EUA 5
EUA 4 EUA 3
EUA 2
Case D
EUA 1
EUA 6 EUA 5
EUA 4 EUA 3
EUA 2
Case E
EUA 1
EUA 6 EUA 5
EUA 4 EUA 3
EUA 2
Case F
EUA 1
EUA 6 EUA 5
EUA 4 EUA 3
EUA 2
Key Cross-Case Analysis
EUAI Embedded Unit of Analysis 1: Site Logistics Services Problem
EUA2 Embedded Unit of Analysis 2: Approaches to Addressing Problems
EUA3 Embedded Unit of Analysis 3: Information and Communication Tools
EUA4 Embedded Unit of Analysis 4: Use of Digital Technologies
EUA5 Embedded Unit of Analysis 5: Logistics Information and Services System
EUA6 Embedded Unit of Analysis 6: ICT Implementation Issues
Fig. 5-4: Single Case and Cross Case Analysis (reproduced from Yin (2003))
Context-Aware Services Delivery in the Construction Supply Chain
129
suggested that this allows the unique patterns of each case to emerge before pushing
towards generalised patterns across cases. Cross-case analysis was used to make a
comparison of the embedded unit of analysis across the various case studies (Yin, 2003).
This involved the examination of the six ‘embedded unit of analysis’ between each case
study to provide the key findings from an argumentative interpretation.
The details of the case studies undertaken and a summary of the key findings, which are
grouped according to the six main ‘embedded unit of analysis’, are discussed in the
following section.
5.6 Case Study Projects
Case studies involving six construction projects were undertaken to explore the current
practices. Problems faced in the logistics services management and the information and
communication tools to facilitate the logistics services management processes were also
investigated. The case studies were also used to obtain information relating to materials
and asset stracking and the potential use of digital technologies such as Wi-Fi tags and
other wireless technologies and to observe the differences and similarity of logistics
services management issues within different projects.
The selection of construction organisations (cases) was based on the adequate access to
explore the relevant logistics management issues to be investigated and the willingness of
the individuals within the organisations to participate and share their experience in
managing their construction sites. The same construction practitioners who participated in
the previous questionnaire survey were interviewed in these case studies. Two of them
were not included in this study because they were not directly involved in managing a
project. One of them was a facilities manager for a client and the other was a third party
logistics director hired by the same client to plan and oversee the multiple projects owned
by the client. The interviewees under study were all experienced construction professionals
with at least ten years experience on the construction site while the cost of projects varied
from £11.8 million to £750 million. The background information on the six construction
projects involved in the case studies are presented in Table 5-10.
Context-Aware Services Delivery in the Construction Supply Chain
130
Table 5-10: List of Case Studies
Case Type of Project Person Interviewed Cost (£)
A Academic Building Extension
Project Project Manager 22 million
B Academic Building Refurbishment
Project Project Manager 11.8 million
C New Commercial Office
Development Project Construction Manager 46 million
D Museum Extension Project Contracts Manager 61 million
E New Airport Terminal Project Logistics Project Manager 750 million
F Students Residential Halls Project Senior Project Manager 49 million
The construction organisations were visited and in-depth semi-structured interviews took
place with the project/site manager or other personnel involved in the logistics
management on construction projects. The interviews were conducted in each of the
manager’s site office. The following sub-sections present the outcomes of the interviews.
5.6.1 Case A: Academic Building Extension Project
Project A involved the construction of a large lecture theatre, three smaller theatres,
numerous offices, seminar rooms and administration and study areas for an academic
building with a total cost of £22 million. The design of the building had a number of novel
features that involved suppliers and specialist subcontractors from overseas. The site
location was fairly tight due to its position at the very front of a university campus. The
project manager of the main contractor for this project was interviewed in order to
understand the current site logistics services practice and the related problems.
(a) Site Logistics Services Problems
Generally, there were several site logistics services problems faced by the project manager
responsible for this project:
Material supply, storage and handling: From time to time, there was a shortage of
materials due to inadequate stock and late delivery. Sometimes, there was a need
Context-Aware Services Delivery in the Construction Supply Chain
131
for resupply of material due to incorrect delivery where materials did not comply
with standard requirements, not in good condition or of poor quality. At other
times, delivery was incomplete due to insufficient or damaged materials during
delivery. Materials delivered were often placed or stored temporarily at a
designated area before being transported to their point of use causing double
handling of materials. There were also site storage constraints where the
compound space was insufficient and lacked security.
Logistics problem: The site’s vicinity to the main campus road meant that there
were limited loading and unloading areas.
Project location challenge: The project was located on a university campus having
site access constraints. All delivery transport had to undergo security checks and
required entry permit to enter the campus. There were problems of congestion
when many vehicles were entering the campus during peak hours. Material
delivery transport caused disruption to traffic flow and posed hazards to students
or pedestrians passing by. Limited parking space was also a problem.
(b) Approaches to Addressing Problems
Site logistics activities mainly involved the delivery and handling of materials. Materials
logistics problems were often affected by the activities of transportation of materials to the
construction site due to limited access and loading area and traffic congestion. There were
several approaches initiated by the organisation to try and address some of the
aforementioned problems.
Material delivery system: Project A had implemented a material delivery booking
system to ensure that suppliers did not make deliveries at the same time hence
avoiding unnecessary queue and traffic congestion. It was a manual booking
system, i.e. logbook, implemented by the main contractor. All subcontractors were
required to book a time slot for their suppliers to deliver and unload materials. The
site had no actual logistics management and subcontractors had to organise their
own material handling equipment. Having very limited unloading areas and very
tight turning space, the implementation of these time slots had to be quite rigid.
Suppliers arriving late and not able to unload within the time slot were turned away
Context-Aware Services Delivery in the Construction Supply Chain
132
and the subcontractors were asked to book another time slot so as not to disrupt the
material delivery schedule of the day.
Storage: Being located on a fairly tight site, subcontractors were allocated limited
site storage for their materials on site. Therefore, they were encouraged to adopt the
JIT concept whenever possible. JIT material delivery was especially crucial when
involving specialised materials/components from overseas specialist suppliers who
needed to install their materials/components themselves. It made sense for the
materials/components to be delivered only at the time when they were required for
the project. Furthermore, due to the unsafe and unprotected storage area, the
subcontractors had to make sure that no materials were left on site for long periods
for fear of theft.
Site access: Parking spaces on the university campus were very limited, therefore
access to the campus was restricted to permit holders only. Having implemented a
manual material delivery booking system, the main contractor’s gatekeeper had to
inform the client’s security guard about daily material delivery schedule. Suppliers’
transports were only allowed on the campus and the construction site after getting
clearance from the security guard. Any suppliers arriving too early or not as per
schedule would be turned away by the security guard. This had to be done because
there were no waiting areas anywhere on campus and queuing would only cause
traffic congestion on the already busy main and access roads. To address the
problem of parking spaces, workers had to park their vehicles outside the campus.
Safety: Considerations for traffic flow and pedestrians’ safety were given when
allocating time slots, for example, there were no material deliveries during peak
hours to avoid congestion on the already busy traffic on the main and campus
roads.
Waste management: Skips were provided on site for the subcontractors to manage
their waste and surplus materials. A specialised subcontractor was hired to empty
the skips on a daily basis.
Security: From observation it was discovered that the owner of the project installed
CCTV and webcam on nearby buildings to monitor the project progress and to
reduce theft at site.
Context-Aware Services Delivery in the Construction Supply Chain
133
(c) Information and Communication tools
Generally, this project utilised all the basic information and communication tools that were
highly observed and recommended in the previous survey (Table 5-1). Apart from
drawings which were managed using the client’s web management system, all other
communications were done manually. The site used notice boards and toolbox talks to
brief workers about safety issues and activities for the day to ensure all workers knew their
own tasks and were aware of others’ tasks. Face-to-face meetings, telephone and e-mail
system were the most common and preferred type of communicating tools between all
parties involved in the construction project.
(d) Use of Digital Technologies
The project did not employ any digital technologies such as wireless-system to support
materials, personnel and asset tracking on the construction site. However, digital
technologies were used for general communication purposes. The communication
technology and devices that the project employed were the internet, WLAN, notebook, PC
and walkie-talkie.
(e) Logistics Information and Services System
Manual practices were used in this project for managing the logistics services. For tracking
and checking material delivery and stock inventory, no specific tools or techniques were
used to aid the handling of materials on site. However, the interviewee was aware of the
use of tagging technologies such as bar-coding, Radio Frequency Identification (RFID) and
the potential use of Wi-Fi tagging for tracking materials and assets.
(f) ICT implementation issues
The implementation of ICT at site had brought up several issues that needed to be
addressed such as the requirements for training, time consuming (due to lack of training or
long training period) and maintenance and services. There were concerns that many
workers were not bothered to use or learn using new technology due to traditional work
culture. Problems regarding information flow were mostly regarding information being
inaccurate, limited information sharing facilities and slow to retrieve information/data
because not everyone checked e-mail regularly.
Context-Aware Services Delivery in the Construction Supply Chain
134
5.6.2 Case B: Academic Building Refurbishment Project
Project B involved the fit-out and refurbishment works for an existing purpose-built
academic building with a total cost of about £11.8 million. The project included
remodelling existing lecture theatres, building an additional café and fit out work for air
conditioning, electrical services, decorations, carpet, suspended ceilings, demountable
partitioning and furniture. This project was technically complex because it involved many
suppliers. Located on the same university campus as Project A meant this project also
encountered similar problems to Project A. The project manager of the main contractor for
this project was interviewed in order to understand the current site logistics services
practice and the related problems.
(a) Site Logistics Services Problems
In managing this site, the project manager identified several problems relating to logistics
services management as follows:
Material supply, storage and handling: This project also experienced similar
problems as Project A. In addition, improper handling of materials was sometimes
a problem when material handling equipments were not available during materials
delivery causing other available equipment to be used instead.
Logistics problem: The site’s vicinity to other blocks meant that there were limited
loading and unloading areas. Furthermore, an existing parking lot was used as the
loading and unloading area on this site meaning the parking spaces had been
reduced and became limited.
Project location challenge: This project also experienced similar problems as
Project A due to its location.
(b) Approaches to Addressing Problems
There were several approaches used to address the site logistics services problems in this
project.
Material procurement system: The project implemented a procurement system and
ensured that all subcontractors knew about it. All communications were also done
electronically using the main contractor’s own system. Ordering of materials was
Context-Aware Services Delivery in the Construction Supply Chain
135
done via e-mail system by filling in the standard ordering form. The project
employed reliable known (quality checked) contractors by building up a good
relationship with regular suppliers. All suppliers were required to book
electronically a time slot for delivering and unloading materials. Implementation of
these time slots were also rigid as suppliers that did not book a time slot were not
allowed entry to the site. The reason for this rigid implementation was because the
building was in use and preparation for material handling equipment took some
careful planning.
Site Access: Similar to project A, access to the campus was restricted to permit
holders only. To address the problem of parking spaces, a grass field on the campus
area was temporarily converted into a contractors’ parking lot.
Safety: The existing parking lot was used as a material unloading area and the
existing building was in use, therefore considerations for students’ safety were
always given priority when unloading materials.
(c) Information and Communication tools
Apart from drawings which were managed using the client’s web management system, all
other communications were done electronically. Having the same client as Project A, the
site also conducted toolbox talks to brief workers about safety issues and activities for the
day to ensure all workers knew their own tasks and aware of others’ tasks. Telephone and
e-mail system were the most common and preferred type of communicating tools between
all parties involved in the construction project. Face-to-face meeting occurred on a weekly
basis.
(d) Use of Digital Technologies
As in Project A, the project did not employ any digital technologies to support materials,
personnel and asset tracking on the construction site. Digital technologies were used for
general communication purposes only. The communication technology and devices that
the project employed included the internet, notebook, PC and walkie-talkie.
Context-Aware Services Delivery in the Construction Supply Chain
136
(e) Logistics Information and Services System
Manual practices were used in this project for managing the logistics services. For tracking
and checking materials delivery and stock inventory, the project used bar-coding of key
construction elements and fit-out items. The interviewee was also aware of the use of other
tagging technology such Radio Frequency Identification (RFID) and the potential use of
Wi-Fi tagging for tracking materials and assets.
(f) ICT implementation issues
The implementation of ICT at site had brought up several issues that needed to be
addressed, such as subcontractors and suppliers did not use the same technology, and
information received was often not in the format required. Some workers did not bother to
use or learn new technology. Problems regarding information flow were mostly regarding
information being inaccurate, limited information sharing facilities and slow to retrieve
information/data because not everyone checked e-mail regularly.
5.6.3 Case C: New Commercial Office Development Project
Project C involved the construction of a 12-storey steel structure supported by a concrete
core commercial office building. It consisted of ten floors of open plan office
accommodation and two levels of basement car parking costing about £46 million. This
was a major and complex project involving numerous work tasks and many subcontractors.
The high specification office building which incorporated renewable energy systems was
built to a highly distinctive and sustainable design. Works also included diversion works to
live water main and extensive external works. The construction manager of the main
contractor who was responsible for first phase of this project was interviewed.
(a) Site Logistics Services Problems
In managing the construction site, the construction manager interviewed identified several
problems relating to logistics services management as follows:
Material supply, storage and handling: Occasionally, double handling of materials
occurred due to logistics problem where materials delivered were placed
temporarily on the site before being transported to their point of use. There was
Context-Aware Services Delivery in the Construction Supply Chain
137
also material handling equipment distribution problem. The high degree of demand
for tower crane operations made it difficult to move materials that required lifting
by crane. There were also site storage constraints where the compound space was
insufficient.
Project location challenge: This project faced project location problems due to the
project being situated in a city centre which affected the activities of materials
delivery at the construction site. The site was immediately adjacent to a main rail
line and major roads. Parking space on site was non-existence.
Logistics Problems: The project had logistics problems as the construction site was
surrounded by public infrastructure such as rail station, railways and main roads. It
was therefore especially difficult to transport large materials and concrete into the
construction site. There was also limited loading and unloading areas.
Site access constraints: The single site access point led to traffic congestion
especially during peak hours.
Regulation consideration: The contractor had to seek permission from the local
authority to deal with materials delivery into the construction site.
(b) Approaches to Addressing Problems
In managing the construction site, the construction manager interviewed identified several
problems relating to logistics services management as follows:
Material delivery system: In order to overcome the logistics and distribution of
tower crane problems, regular discussions and coordination meetings with all
subcontractors were undertaken. There was also provision for a proper schedule of
the tower crane activities to record all the operations within the construction site.
JIT technique was implemented in this project to deal with double handling,
inadequate site storage space and the small loading area for the delivery of
materials to the construction site.
Security: Security guards were employed on the project to deal with the single
access problems and to manage the flow of traffic into and out of the construction
site. The security guards were also responsible for ensuring the safety of materials,
equipment and many valuable things at the construction site. CCTV and webcam
were used to monitor the site security and progress of the project.
Context-Aware Services Delivery in the Construction Supply Chain
138
(c) Information and Communication tools
Basically, this project utilised all the basic information and communication tools. Face-to-
face meetings, telephone and e-mail system were the most common and preferred type of
communicating tools between all parties involved in the construction project.
(d) Use of Digital Technologies
The project did not employ any digital technologies to support materials, personnel and
asset tracking on the construction site. They were used for general communication
purposes only. The communication technology and devices that the project employed
included the internet, WLAN, notebook, tablet PC, PC and walkie-talkie.
(e) Logistics Information and Services System
Manual practices were used in this project for managing the logistics services. For tracking
and checking materials delivery and stock inventory, the project used RFID for key
construction elements. The interviewee was also aware of the potential use of Wi-Fi
tagging for tracking materials and assets.
(f) ICT implementation issues
The implementation of ICT at site had brought up several issues that needed to be
addressed, such as: high capital investment cost, training, maintenance and services,
licensing (including software licensing), interoperability, security and privacy concerns
and communication flow overload. Problems regarding information flow were mostly
regarding information not being retrieved from e-mail regularly.
5.6.4 Case D: Museum Extension Project
Project D involved an extension to an existing museum situated in a city centre. It was part
of the redevelopment work carried out for the museum establishment. The new building
comprised of five floors with level access throughout, housing 39 new galleries including
four temporary exhibition galleries, a new education centre, state-of-the-art conservation
studios and a rooftop restaurant. The total cost of redevelopment was £61 million. The
construction site was fully enclosed by other buildings. The new building was as close as
Context-Aware Services Delivery in the Construction Supply Chain
139
25 millimetres on two sides to other buildings. The only access to the site was through
making use of a four-metre-wide lane to the public street. The problem was that they had
to cross a busy walkway which many hundreds of pedestrian passed everyday. Material
deliveries were completely impossible during an annual festival. During those days, the
construction site could only be accessed on foot.
(a) Site Logistics Services Problems
The most significant challenges faced by the project were as follows:
Material supply, storage and handling: Insufficient space was given for use as a
storage area for materials at the construction site. Delivery of materials into the
construction site was affected by delays due to city traffic congestion.
Project location challenge: This project faced project location problems due to the
project being situated in a city centre which affected the activity of materials
delivery at the construction site. It was almost impossible to deliver materials on
time during peak hours due to traffic congestion. Parking space on site was non-
existence.
Logistics Problems: The project had logistics problems as the construction site was
surrounded by other buildings and main roads. It was therefore especially difficult
to transport large materials and concrete into the construction site and equally
difficult to unload due to inadequate unloading area.
Site access constraints: The single site access point led to traffic congestion
especially during peak hours.
(b) Approaches to Addressing Problems
There were several approaches to dealing with all the problems mentioned above.
Communication system: The consultant of the project implemented a web-based
communication system where all parties involved in the project were required to
use. This system allowed drawings and other project documents to be downloaded
from the server and enabled information sharing with the design team and
subcontractors.
Context-Aware Services Delivery in the Construction Supply Chain
140
Material delivery system: Subcontractors were given full responsibility to order and
handle their own materials. Considerations to pedestrians and traffic flow were
given when planning for materials delivery.
Waste management: Waste management plan was also in place to get rid of the
surplus materials and rubbish.
(c) Information and Communication tools
Generally, this project utilised the basic information and communication tools that were
commonly observed and recommended in the previous survey. Face-to-face meetings,
telephone and e-mail system were the most common and preferred type of communicating
tools between all parties involved in the construction project.
(d) Use of Digital Technologies
Digital technologies were used for general communication purposes but not to support the
tracking of materials, personnel and assets on the construction site. The communication
technology and devices that the project employed were the internet, PDA, tablet PC,
notebook, PC and walkie-talkie.
(e) Logistics Information and Services System
Manual practices were used in this project for managing the logistics services but the
interviewee was aware of the use of tagging technology like bar-coding, RFID and the
potential use of Wi-Fi tags for tracking materials and assets.
(f) ICT implementation issues
The implementation of ICT at site had brought up several issues that needed to be
addressed such as training, communication flow overload and subcontractors and/or
suppliers not using the same technology.
5.6.5 Case E: New Airport Terminal Project
Project E involved the construction of a new airport terminal with a total construction cost
of about £750 million. This project consisted of 16 major projects and over 147 sub-
projects on a 260 hectare site. It encompassed a vast and hugely complex programme of
Context-Aware Services Delivery in the Construction Supply Chain
141
work. This involved extensive civil engineering works such as excavation, substructure
concrete, paving concrete, reinforcement, curtain walling, roofing and tunnelling. Other
works included a network of new roads, car parking, waste management and retail and
airport facilities.
(a) Site Logistics Services Problems
In managing this project, the main problems faced by the logistics project manager were as
follows:
Material supply, storage and handling: This project had difficulty with delays in
supplying materials into the construction site due to the huge amount of materials
and dealing with various suppliers. These delays also included suppliers from
outside the country which required more time for materials delivery. Problems with
materials not complying with specific standard requirements which needed to be
returned back to suppliers affected the processes of materials delivery into the
construction site. There was also inadequate storage area for materials on the
construction site.
Regulation consideration: The activities of supplying materials into the
construction site had to obtain entry permission due to project being in high
security area.
Supply chain challenge: The variety and vast amount of suppliers and materials
created challenges with the commitment of suppliers and contractors to do the job.
Project size challenge: The scale/size of the project posed a challenge.
Logistics Problems: Physical access was a problem due to traffic overflow and
surrounding local roads near the construction site.
(b) Approaches to Addressing Problems
In managing the construction site, the interviewee identified several problems relating to
logistics services management as follows:
Material delivery system: Being a large and established organisation, the client of
this project had a well-established web-based booking system and a logistics centre
(LC). All construction material deliveries must be booked onto this material
Context-Aware Services Delivery in the Construction Supply Chain
142
delivery booking system. Having done so, suppliers were allocated a time slot at
which to arrive at the LC. To be able to access the system, suppliers must first
register and could only gain access after approval. Implementation of these time
slots were very rigid and suppliers had to ensure that they arrived in plenty of time,
taking into consideration the queuing time required to pass several gates and
security checks before arriving at the LC. The queues were normally long. The
client employed a third party (3PL) company to take care of the site logistics.
Storage: LC was implemented to facilitate the huge amount of materials involved
in this project. The LC provided a temporary storage compound as one stop centre
for materials delivery. The practice of JIT concept ensured that the materials were
delivered to the required place when needed. This also overcame late delivery
problems. As in Case A, certain materials were delivered JIT without going through
the LC first. Excellent collaboration was noted between contractors and suppliers in
achieving good management of materials delivery to construction sites. The
combination of LC and JIT had been employed to address the problem of
inadequate site storage for this project.
Site access: Suppliers delivering materials to the LC or construction site had to pass
several gates and security checks before arriving at their designated locations. Once
a supplier had successfully booked a time slot for material delivery, they would
receive a confirmation note. This, together with a copy of purchase order and
delivery order were required to be shown at each check point to obtain entry
clearance. Provided all the authority’s regulations had been complied with and all
the necessary documents were in order, gaining access to the LC was not a
problem.
(c) Information and Communication tools
Generally, this project utilised the basic information and communication tools. Face-to-
face meetings, telephone and e-mail system were the most common and preferred type of
communicating tools between all parties involved in the construction project.
(d) Use of Digital Technologies
The project did employ digital technologies to support the tracking of materials on the
construction site, but not personnel and assets. These were also used for general
Context-Aware Services Delivery in the Construction Supply Chain
143
communication purposes. The communication technology and devices that the project
employed included the internet, PDA, notebook, PC and walkie-talkie.
(e) Logistics Information and Services System
For tracking and checking of materials delivery and stock inventory, the project used bar-
codes and RFID. Bar-coding was utilised in the LC operation to facilitate effective
materials management. The process involved the identification and validation of material
delivery in order to know the specific location, time and date. Also bar-coding was used to
aid tracking and controlling of the rebar at the LC during rebar delivery. The
implementation of RFID was for tracking precast column and PDA was used to assist the
checking of construction daily activities. The interviewee was also aware of the potential
use of Wi-Fi tagging for tracking materials and assets.
(f) ICT implementation issues
The implementation of ICT at site had brought up several issues that needed to be
addressed, such as training, maintenance and services, licensing, interoperability, lacking
in automation and robustness, security and privacy concerns and communication flow
overload. Problems regarding information flow were mostly regarding information not
being retrieved from e-mail regularly.
5.6.6 Case F: Student Residential Halls Development Project
Project F involved the construction of student residential halls with a total cost of £49
million. The redevelopment project consisted of two new buildings, comprising of 563
student bedrooms in a six-storey hall and 402 bedrooms in a four-storey hall. All the
accommodation was arranged in 8 and 10 bed flats connected to shared kitchens. Both
halls contained a resident tutor flat with an adjoining resident tutor office and both halls
had a committee room. The construction technique used was one of prefabricated concrete
panels for the rooms and pre-fabricated pods for the en-suite bathrooms. A new catering
building, a student laundrette and office facilities were also part of the project. The
interviewee was a senior project manager.
Context-Aware Services Delivery in the Construction Supply Chain
144
(a) Site Logistics Services Problems
In managing this project, the interviewee identified several problems relating to materials
management as follows:
Material supply, storage and handling: Incomplete delivery due to insufficient
materials or damage to materials during delivery sometimes occurred. So did the
improper handling of materials because of material handling equipments were
sometimes not available during materials delivery. Site storage was also a problem
due to inadequate storage spaces.
Project location challenge: This project faced project location problems due to the
project being situated in a crowded location, surrounded by other buildings and
public infrastructure such as other residential halls, houses and narrow main roads
which affected the activity of materials delivery at the construction site.
Logistics Problems: Because of its location, the project experienced logistics
problems which made it especially difficult to transport large materials and
concrete into the construction site.
Site access constraints: The site only had a single access. It was located near a
housing area, schools and other public buildings. The main road leading to the site
access road was part of a bus route and was always experiencing constant traffic
congestion especially during peak time. The road was not only narrow but double
parked at all times making turning into the access road quite impossible at times.
(b) Approaches to Addressing Problems
Material delivery system: The main contractor, having several projects on the same
campus, employed a third party (3PL) company to manage the logistics of their
projects. This 3PL company implemented a web-based booking system for
suppliers to book the material delivery time slots. As with the previous cases,
implementation of this system was adhered to quite rigidly because of the site
location challenge and site access problem. This eliminated the occurrence of many
transport vehicles arriving at any one time causing queues and congestion due to
waiting time to enter the site and unload materials at a specific storage area.
Storage: Having utilised mainly prefabricated materials/components, this project
practiced JIT concept to address the problem of inadequate site storage. Same as
Context-Aware Services Delivery in the Construction Supply Chain
145
Case A, subcontractors were allocated limited site storage for their materials on
site.
Site access: Apart from the need to adhere to local authority’s regulations, gaining
access to site was not a major problem because suppliers only needed to obtain
entry permit once at the gate.
Security: The project utilised CCTV and webcam to monitor the progress site and
for security purposes.
Waste management: The organisation had a policy of reducing waste so that only a
very small percentage of waste was sent to landfill, therefore materials were reused
and recycled as much as possible.
(c) Information and Communication tools
Drawings were downloaded from the client’s web management system. The client also
provided unlimited e-mail storage size for information storage and communication
purposes. Face-to-face meetings, telephone and e-mail system were the most common and
preferred type of communicating tools between all parties involved in the construction
project.
(d) Use of Digital Technologies
Digital technologies were only used for general communication purposes. The
communication technology and devices that the project employed included the internet,
extranet, PDA, tablet PC, notebook and PC.
(e) Logistics Information and Services System
Manual practices were used in this project for managing the logistics services. No specific
tools or technique was used for tracking and checking materials delivery and stock
inventory on site. The interviewee was also aware of the use of tagging technologies such
as bar-coding, RFID and the potential use of Wi-Fi tagging for tracking materials and
assets.
Context-Aware Services Delivery in the Construction Supply Chain
146
(f) ICT implementation issues
The implementation of ICT at site had brought up several issues that needed to be
addressed such as high capital investment cost, training, maintenance and services,
licensing, security and privacy concerns and cultural issues.
5.7 Key Findings from Case Studies
On the whole, it can be said that site logistics activities from the case studies mainly
involved the delivery and handling of materials. It was found that the current construction
logistics were being practiced differently according to the size of undertaken project.
5.7.1 Existing Material Delivery System
For most construction sites, there was at least some sort of a booking system for the
contractors to book the time for their suppliers to deliver construction materials. There are
three different types of construction logistics models that can be drawn from the case
studies. These are shown in the following Fig. 5-5 to Fig. 5-7.
Context-Aware Services Delivery in the Construction Supply Chain
147
Main Contractor’s Material Delivery Booking System
The material delivery booking system model shown in Fig. 5-5 describes the construction
logistics model for Cases A, B, C and D. The project manager prepared a log book or web-
based system for the contractors to book time slots for their suppliers to deliver materials
and components to site. These projects were relatively small projects, having site access
constraint and limited loading and unloading area. This booking system focused on
materials delivery only. Contractors ordered their own materials, components, equipment
and machinery and booked time slot for their suppliers to deliver them to site.
Gate keeper
Log book or
web-based
system
Owner
Main Contractor
(Project Consultant & Execution)
Project Manager
(On-site Project Coordinator)
Subcontractors
Suppliers
Supply Houses
Construction Site
Fig. 5-5: Material delivery information and communication system for Cases A, B, C and D
Context-Aware Services Delivery in the Construction Supply Chain
148
Client’s Web Based Material Booking System
The material delivery booking system model shown in Fig. 5-6 describes the construction
logistics model for Case E. The client prepared a web-based booking system for the
suppliers to book time slots online to deliver materials and components. Case E was a
mega project and in high security area. Its client established a web-based material delivery
booking system and a logistics centre (LC). Suppliers booked material delivery time slots
via the web-based system and had to arrive at the LC with enough time to unload materials
within the time slots allocated. Suppliers could also deliver material direct to site if JIT
concept was agreed on. The client also employed logistics consultant (3PL) to manage the
materials delivery and other logistics services/activities.
Owner
Project Consultants
(Designing)
Main Contractor
(Project Execution)
Project Manager
(On-site Project Coordinator)
Web Based Booking
System
Logistics
Consultant
Subcontractors
Fig. 5-6: Material delivery information and communication system for Case E
Context-Aware Services Delivery in the Construction Supply Chain
149
Third Party Logistics Service
The material delivery booking system model shown in Fig. 5-7 describes the construction
logistics model for Case F. Case F had limited access and was prone to congestion. The
main contractor had multiple projects and employed a logistics consultant (3PL) who
prepared a web-based booking system for the suppliers to book time slots online to deliver
materials and components. The logistics consultant owned the material delivery software
and suppliers booked time slots for material deliveries via the logistics application software.
The logistics consultant also managed other logistics services/activities at all the different
projects.
Owner
Project Consultants Main Contractor
(Project Execution)
Project Manager
(On-site Project Coordinator)
Third Party (3PL)
(Logistics Services Coordinator
and Controlling) Subcontractors
Suppliers
Supply Houses
Construction Site
Fig. 5-7: Material delivery information and communication system for Case F
Context-Aware Services Delivery in the Construction Supply Chain
150
5.7.2 Case Studies Analysis
The problems identified from the case studies revealed that each case study experienced
similar problems with site access problem, project location challenge and inadequate
storage area at construction site. The problems and approaches to logistics services
management, information and communication tools, use of digital technologies, logistics
information and services system and ICT implementation issues are summarised in Table
5-11 and discussed below. The discussion involves a cross-case analysis between the six
case studies and grouped into six ‘embedded units of analysis’ investigated as follows:
Embedded Unit of Analysis 1: Site Logistics Services Problem
Embedded Unit of Analysis 2: Approaches to Addressing Problems
Embedded Unit of Analysis 3: Information and Communication Tools
Embedded Unit of Analysis 4: Use of Digital Technologies
Embedded Unit of Analysis 5: Logistics Information and Services System
Embedded Unit of Analysis 6: ICT Implementation Issues.
Context-Aware Services Delivery in the Construction Supply Chain
151
Table 5-11: Cross-Case Analysis
Element of Analysis Case A Case B Case C Case D Case E Case F
Site logistics services
problems Late delivery
Site storage problems
Logistics problem
Incorrect delivery
Incomplete delivery
Inadequate loading area
Site access problem
Project location
challenge
Limited parking space
Late delivery
Site storage problems
Logistics problem
Site access problem
Material damages
Improper handling
Material handling
equipment problem
Inadequate loading area
Supply chain challenge
Project location
challenge
Limited parking space
Site storage problems
Logistics problem
Inadequate loading area
Site access problem
Regulation
consideration
Congestion time
Material handling
equipment problem
Supply chain challenge
Project size challenge
Project location
challenge
No parking space
Late delivery
Site storage problems
Logistics problem
Incorrect delivery
Incomplete delivery
Inadequate loading area
Site access problem
Congestion time
Project location
challenge
No parking space
Late delivery
Site storage problems
Site access problem
Regulation
consideration
Supply chain challenge
Project size challenge
Project location
challenge
Site storage problems
Logistics problem
Incomplete delivery
Site access problem
Congestion time
Improper handling
Material handling
equipment problem
Project location
challenge
Regulation
consideration
Approaches to
addressing problems Implementation of
material delivery
system – log book
Consider pedestrians
and traffic flow when
allocating material
delivery time slot
Full responsibility for
the subcontractors to
order and handle their
own materials
Use site notice boards,
toolbox talks to brief
workers about safety
issues and activities for
the day
Waste management
CCTV/webcam to
monitor site
Implement an electronic
communication system
and ensure that
contractors and
suppliers use it
Build up a relationship
with regular suppliers
Use of standard forms
Provide material
handling equipments as
required
Use toolbox talks to
brief workers about
safety issues.
Consider pedestrians and
traffic when unloading
material
Waste management
Understand and plan for
material flow and
material handling
Implementation of
procurement, material
delivery and waste
management systems
Provide material
handling equipments as
required
Information sharing
with design team.
Regular discussions and
meetings
Employ security guards
CCTV/webcam to
monitor site
Provide an web-based
communication system
Information sharing with
design team, and
subcontractors
Provide unlimited e-mail
storage size
Full responsibility for
the subcontractors to
order and handle their
own materials.
Waste management
Implementation of
material delivery system
– web-based
Suppliers to book
material delivery time
slot via web-based
system
Suppliers deliver
materials to construction
site JIT or to Logistics
Centre (LC )
Site logistics services
operated and managed
by a third-party logistics
company employed by
client
Subcontractors order
their own materials.
Site logistics services
managed by a third-
party logistics (3PL)
company employed by
main contractor
Suppliers book material
delivery time slots via
web-based system
belonging to 3PL.
CCTV/webcam to
monitor site
Context-Aware Services Delivery in the Construction Supply Chain
152
Information and
communication tools Meetings
Telephone
Plans and Drawings
Design specifications
Scope of works
Scheduling
Meetings
Telephone
Plans and Drawings
Design specifications
Scope of works
Scheduling
Meetings
Telephone
Plans and Drawings
Design specifications
Scope of works
Scheduling
Meetings
Telephone
Plans and Drawings
Design specifications
Scope of works
Scheduling
Meetings
Telephone
Plans and Drawings
Design specifications
Scope of works
Scheduling
Meetings
Telephone
Plans and Drawings
Design specifications
Scope of works
Scheduling
Use of digital
technologies Internet
W-LAN/Wi-Fi
Notebook
PC
Walkie-Talkie
Internet
Notebook
PC
Walkie-Talkie
Internet
W-LAN/Wi-Fi
Tablet PC
Notebook
PC
Walkie-Talkie
Internet
PDA
Tablet PC
Notebook
PC
Walkie-Talkie
Internet
PDA
Notebook
PC
Walkie-Talkie
Internet
Extranet
PDA
Notebook
Tablet PC
PC
Logistics Information
and Services System Manual
CCTV
Webcam
Manual
Bar codes
Manual
RFID
CCTV
Webcam
Manual
Bar codes
RFID
Manual
CCTV
Webcam
ICT implementation
issues Training
Time consuming
Maintenance and
services
Cultural issues/not
bothered
Information not
accurate
Limited information
sharing facilities
Slow retrieval of
information
Subcontractors and/or
suppliers do not use the
same technology
Cultural issues/not
bothered
Info format - *.dwg file
required, but often large
file sizes, and replaced
with *.pdf file instead.
Information not accurate
Limited information
sharing facilities
Slow retrieval of
information
High capital investment
cost
Training
Maintenance and
services
Licensing (including
software licensing)
Interoperability
Security and privacy
concerns
Communication flow
overloaded
Slow retrieval of
information
Training
Communication flow
overloaded
Subcontractors and/or
suppliers do not use the
same technology
Slow retrieval of
information
Training
Maintenance and
services
Licensing
Interoperability
Security and privacy
concerns
Communication flow
overloaded
High capital investment
cost
Training
Maintenance and
services
Licensing
Security and privacy
concerns
Cultural issues/not
bothered
Information not accurate
Limited information
sharing facilities
Slow retrieval of
information
Context-Aware Services Delivery in the Construction Supply Chain
153
5.7.3 Site Logistics Services Problem
Generally, the findings from the case studies revealed that the major problems in term of
logistics management activities relate mostly related to materials management. Constraints
on site storage, site logistics with regards to materials handling and distribution, late
delivery of materials to the construction sites and information flow problem were common
(see Table 5-12). It was evident that site storage constraints, site access constraints and
project location challenge were the highest occurring problems. Logistics problem and
congestion time were the second highest occurring problem with five cases (all cases
except Case E). Four cases (Cases A, B, D, E) experienced late delivery problems, another
four (Cases A, B, C, D) experienced inadequate loading area and limited parking space.
Incomplete delivery, improper handling, material handling equipment problem, supply
chain challenge and regulation consideration were also problems for three cases. The cases
were Cases A, D and F for incomplete delivery; Cases C, D and F for both improper
handling and material handling equipment problem; and Cases B, C and E for regulation
consideration. Other issues such as incorrect delivery affected Cases A and D, project size
challenge affected Cases C and E and material damage only affected Case B.
Table 5-12: Site Logistics Services Problem from Case Studies
Site Logistics Services Problem Case A Case B Case C Case D Case E Case F
Late delivery √ √ √ √
Site storage problems √ √ √ √ √ √
Logistics problem √ √ √ √ √
Incorrect delivery √ √
Incomplete delivery √ √ √
Inadequate loading area √ √ √ √
Site access problem √ √ √ √ √ √
Regulation consideration √ √ √
Congestion time √ √ √ √ √
Material damages √
Improper handling √ √ √
Material handling equipment problem √ √ √
Supply chain challenge √ √ √
Project size challenge √ √
Project location challenge √ √ √ √ √ √
Limited parking space √ √ √ √
Context-Aware Services Delivery in the Construction Supply Chain
154
5.7.4 Approaches to Addressing Problems
The lack of adequate site storage to store materials on site was experienced by all projects.
However, this problem affected larger scale projects more due to the variety and large
amount of materials utilisation. Some approaches that had been undertaken to overcome
these problems included the implementation of JIT techniques (Cases A, C and E) and
implementation of LC (Case E). Materials logistics problems were affected by the
activities of transportation of materials to the construction site due to single access,
constraints of public regulations and traffic congestion during peak time. In reducing these
problems there were a few approaches implemented such as JIT (Case A, C and E),
communication system (Cases B and D) and carrying out regular discussions or meetings
(Case C).
The issue of late delivery was experienced from time to time by many construction projects.
There were many approaches to addressing the late delivery problems which differed from
one case to another. Cases A, B, E, and F implemented strict material delivery booking
system. In dealing with these problems, Case B also used quick response to inform
suppliers if any unexpected event happened, whist Case E implemented an LC to provide a
temporary storage compound for material delivery to avoid late delivery problems.
Excellent collaboration was noted as being needed between contractors and suppliers in
order to achieve better management of materials delivery to construction sites.
The JIT technique was implemented to address inadequate loading area and site access
problems (Cases A and C). The logistics centre had been set-up in order to overcome the
inadequate loading area, congestion time, supply chain challenge and project size
challenge for Case E. In order to deal with regulations requirements, these projects
complied with the local authority regulations to overcome site access problems.
5.7.5 Information and Communication Tools
On the whole, all projects utilised the basic information and communication tools such as
face-to-face meetings, e-mail, telephone, plans and drawings, design specifications, scope
of works and scheduling (Gantt chart) which were mostly paper-based. Face-to-face
meetings, telephone and e-mail system were the most common and preferred type of
Context-Aware Services Delivery in the Construction Supply Chain
155
communicating tools between all parties involved in the construction project. Facsimile,
although still available, were hardly used anymore.
5.7.6 Use of Digital Technologies
The projects in most of the case studies did not employ any digital technologies to support
logistics services management such as materials, personnel and assets tracking on the
construction site. Digital technologies were used for general communication purposes. The
popular communication technology and devices among the project were internet, extranet,
PDA, notebook, Tablet PC, PC and Walkie-talkie. The implementation of digital
technologies could help speed up ordering, improve materials and assets tracking, reduce
paper work and facilitate the efficient control and checking of materials and assets.
5.7.7 Logistics Information and Services System
Manual practices were used in almost all of these projects for managing logistics services.
No specific tools or techniques were used for tracking and checking materials delivery and
stock inventory on site. These involved many human errors and excessive paperwork. All
interviewees were aware of the use of tagging technologies like bar-coding, RFID and the
potential use of Wi-Fi tagging for tracking materials and assets. Some of the projects
(Cases A, C and F) utilised CCTV and webcam to monitor the progress site and security
and safety purposes. All the projects in the case studies utilised project management
software to track their work progress.
In Case E, bar-coding was utilised in the logistics centre operation to facilitate effective
materials management. The process involved the identification and validation of materials
delivery in order to know the specific location, time and date. Also bar-coding was used to
aid tracking and controlling of the rebar at the logistics centre during rebar delivery. The
implementation of RFID for Case E was for tracking precast column and PDA was used to
assist the checking of construction daily activities.
5.7.8 ICT Implementation Issues
There are clear business benefits from having one ICT system that can manage the flow of
demand and supply within the CSCM. This is very important because CSC needs to be
Context-Aware Services Delivery in the Construction Supply Chain
156
operated in a precise manner through information sharing and information exchange, i.e. in
enhancing the link between the main contractor and other supply chain partners (consultant,
owner and suppliers). From the case studies, it shows that the issues that had arisen from
the implementation of ICT at site from all the case studies were influenced by financial,
social and technical factors. Implementation of ICT or new technology involves high
capital investment cost. Sometimes, it is not cost-effective due to training, maintenance
and services and licensing (including software licensing) costs. Other issues arising from
the implementation of ICT at site from all the case studies were security and privacy
concerns, communication flow overload and interoperability when subcontractors and/or
suppliers did not use the same technology. Additionally, some companies did not keep up
with technology. This was made worse by general workers not bothered to learn new
technology because training was too time consuming.
The critical aspect in implementing ICT is to tie all the organisations as one network. The
potential benefits from implementing ICT in the CSCM can be seen from various angles
but in the construction practice the main issue is to tackle information and communication
barriers that produce waste at critical level.
5.8 Limitations of Current Practices
All projects from the case studies were affected from limitations of site storage area. Other
constraints include: single access to construction site, surrounding public infrastructure
such as roads and railways, traffic congestion during peak time and regulation
considerations. The implementation of JIT and logistics centre techniques could solve
logistics and storage problems for materials management processes. These techniques
could provide the solution to materials congestion due to inadequate storage space at
construction sites.
Generally, almost all cases used manual methods for the tracking of materials delivery,
identification of materials at storage area and controlling materials from damages. All
these activities involved human errors and massive paperwork. Unfortunately, the
implementation of JIT and LC techniques were unable to overcome human errors such as
double handling and paper-based reports that were used to record and exchange
information related to the materials/components within the CSC. The case studies
Context-Aware Services Delivery in the Construction Supply Chain
157
undertaken only revealed the widespread use of basic ICT tools to assist communication.
There was an inadequate use of modern ICT tools such as PDA, RFID and Wi-Fi tags to
assist with an automatic identification of material and asset tracking which could provide
real-time information of materials usage and equipment utilisation. There was also a lack
of ICT tools that could associate materials, labour and plant in one system with high level
programming and scheduling technology.
5.9 The Need for Context-Aware System
It is important to transform manual practices to automatic to improve the overall
performance of managing assets and materials. In order to be more efficient and effective,
site managers need to be provided with real-time information. Context-aware system
utilising digital technologies has the potential of assisting with the managing of site
logistics, tracking activities to overcome human error in assets, materials identification and
reducing material locating time caused by the constraints of site storage. This computer
based logistics management system has the ability to manage large, complex and multiple
construction projects.
Unfortunately, from the literature review and case studies findings there is a lack of
positive examples of such tools having been used effectively. Site managers experienced
difficulties in managing site logistics which involve assets and materials management in
the current practices. The key findings from case studies include inadequate techniques to
overcome human errors and inadequate use of modern ICT tools to assist assets and
materials tracking. An integrated framework for real-time assets and materials tracking in
the form of a context-aware system is needed in order to provide an intelligent system for
logistics services management on the construction site.
The proposed development of the context-aware system is intended to improve assets and
materials tracking and the overall process of logistics services management on construction
site. The proposed system is described in Chapter 8. In developing the proposed context-
aware system, a conceptual model for logistics management needs to be developed first.
This proposed model is presented in the next section.
Context-Aware Services Delivery in the Construction Supply Chain
158
5.10 The Proposed CSCM Model with Context-Aware System
Based on the material delivery and logistics services models (Fig. 5-5 to Fig. 5-7) drawn
from the case studies, a context-aware services delivery model has been proposed as shown
in Fig. 5-8. The proposed CSCM flow model consists of an information services delivery
system which is to be managed by an IT unit. The implementation of this system will only
be successful if it is initiated by the client and managed by an IT manager, a third party
employed by the main contractor as part of a contractual project requirement. The
deployment of IT unit as the backbone in the overall organisation structure is to ensure that
mobile workers (internal and external supply chain actors) are supported in their daily
tasks with services and awareness within their working environment by providing them
with as-needed information (Anumba and Aziz, 2006; Aziz et al., 2006). The proposed
context-aware system is an ICT application that plays an important role in delivering
information and services by supporting internal supply chain actors’ interaction with the
external ones through the push and synchronisation of personalised real-time information.
For example, in logistics services, the information and services related to materials
delivery such as the responsible project team members, supplier, crane operator, the
method of delivery and handling, material details and delivery schedule have been pre-
programmed in the project planning application and stored in the project planning/database
server. The relevant information or services will be pushed to the right actor at the right
time and the right location.
The logistics practices learned from the case studies, together with the logistics operation
and planning described by Sobotka and Czarnigowska (2005) have provided the basis for
generating scenarios of the future CSCM.
Context-Aware Services Delivery in the Construction Supply Chain
159
5.11 Summary
The survey results revealed that face-to-face meeting and communication through
telephone were the most common forms of communication in construction organisations.
The planning of logistics activities was highly observed but their implementation was
observed less despite being highly recommended. For the tracking and monitoring of
Construction/Building
Project Consultants (Design/Procurement/Project/Scheduling)
Main Contractor
Logistics Manager
(Logistics Services)
Owner
Supply and Delivery
Suppliers
Manufacturers
Raw Materials Suppliers
Project Manager
(Building Services)
IT Manager (Context-Aware Supply Chain
Delivery System)
Subcontractors
Fig. 5-8: Proposed CSCM model with context-aware
Context-Aware Services Delivery in the Construction Supply Chain
160
logistics activities, this became even less. The internet and PC were the only
communication technology and device that all respondents were happy with. The survey
results indicated that construction practitioners were not ready to adopt new technology.
This is based on the fact that only low level ICT facilities were used at construction sites.
None of the tracking and monitoring technology was believed to be effective as confirmed
by the case studies where most of the construction projects used manual method for
tracking and monitoring materials. Overall, the results of the survey confirmed the case
study findings.
Findings from the case study analysis showed that many of the cases had similar problems
with storage constraints. Handling and monitoring activities on site (such as assets and
materials tracking) were facilitated by manual operations in most of the case studies with
the potential for human errors and excessive paperwork. In order to improve the assets and
materials tracking system and the overall process of logistics services management in
construction projects, there were suggestions to have a transformation from current manual
practices to automated tracking, identification and control of assets and materials to reduce
damage and reduction in massive paperwork. It was also suggested to provide ICT tools
which could integrate materials, labour and plant into one system, i.e. context-aware
system.
The scenarios of the future construction practices are discussed in the next chapter and the
description of the proposed system is described in Chapter 8.
Context-Aware Services Delivery in the Construction Supply Chain
161
References
Amaratunga, D. and Baldry, D. (2001): "Case Study Methodology as a Means of Theory
Building: Performance Measurement in Facilities Management Organisations."
Work study 50(3): 95-105.
Anumba, C. and Aziz, Z. (2006): Case Studies of Intelligent Context-Aware Services
Delivery in Aec/Fm. Lecture Notes in Computer Science. I. F. C. Smith.
Berlin/Heidelberg, Springer-Verlag. LNAI 4200: 23-31.
Aziz, Z., Anumba, C. J. and Law, K. (2006): Using Context-Awareness and Web-Services
to Enhance Construction Collaboration. Joint International Conference on
Computing and Decision Making in Civil and Building Engineering. Montreal,
Canada: 3010-3019.
Hamzeh, F. R., Tommelein, I. D., Ballard, G. and Kaminsky, P. M. (2007): "Logistics
Centers to Support Project-Based Production in the Construction Industry."
Proceedings IGLC 15.
Sobotka, A. and Czarnigowska, A. (2005): "Analysis of Supply System Models for
Planning Construction Project Logistics." Journal of Civil Engineering and
Management XI(1): 73-82.
Yin, R. K. (2003): Applications of Case Study Research, SAGE Publications.