chapter 4 - chapter-4.pdfbescom has informed that, it has already mandated all ht consumers to pay...
TRANSCRIPT
![Page 1: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/1.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 54
CHAPTER – 4
DETERMINATION OF RETAIL SUPPLY TARIFF FOR FY19
4.0 Revision of Retail Supply Tariff for FY19-HUKERI RECS’s Proposals and
Commission’s Decisions:
4.1 Tariff Application
As per the Tariff application filed by the HRECS, it has projected an unmet gap in
revenue of Rs.2316.80 Lakhs for FY19, which also includes the gap in revenue of
Rs.3204.79 Lakhs for FY17. In order to bridge this gap in revenue, HRECS has
proposed a uniform tariff increase of 73 paise per unit, in respect of all the
categories of consumers.
In the previous chapters of this order, the Annual Performance Review(APR) for
FY17 and the revision of ARR for FY19 has been discussed. The various aspects of
determination of tariff for FY19 are discussed in this Chapter.
4.2 Statutory Provisions guiding determination of Tariff
As per Section 61 of the Electricity Act, 2003, the Commission is guided inter-alia,
by the National Electricity Policy, the Tariff Policy and the following factors, while,
determining the tariff so that,
the distribution and supply of electricity are conducted on commercial basis;
competition, efficiency, economical use of resources, good performance,
and optimum investment are encouraged;
the tariff progressively reflects the cost of supply of electricity, and also
reduces and eliminates cross subsidies within the period to be specified by the
Commission;
efficiency in performance is to be rewarded: and
a multi-year tariff framework is adopted.
![Page 2: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/2.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 55
Section 62(5) of the Electricity Act, 2003, read with Section 27(1) of the Karnataka
Electricity Reform Act, 1999, empowers the Commission to specify, from time to
time, the methodologies and the procedure to be observed by the licensees in
calculating the Expected Revenue from Charges (ERC). The Commission
determines the Tariff in accordance with the Regulations and the Orders issued by
the Commission from time to time.
4.3 Factors Considered for Tariff setting:
The Commission has considered the following relevant factors for determination
of retail supply tariff:
a) Tariff Philosophy:
As discussed in the earlier tariff orders, the Commission continues to fix tariff
below the average cost of supply in respect of consumers whose ability to
pay is considered inadequate and also fix tariff at or above the average cost
of supply for categories of consumers whose ability to pay is considered to be
higher. Thus, the system of cross subsidy continues. However, the Commission
has taken due care to progressively bring down the cross subsidy levels as
envisaged in the Tariff Policy 2016, issued by the Government of India.
b) Average Cost of Supply:
The Commission has been determining the retail supply tariff on the basis of
the average cost of supply. The KERC (Tariff) Regulations, 2000, as amended
from time to time, require the licensees to provide the details of embedded
cost of electricity voltage / consumer category-wise. The distribution network
of Karnataka is such that, it is difficult to segregate the common cost
between voltage levels. Therefore, the Commission has decided to continue
the average cost of supply approach for recovery of the ARR. With regard to
the indication of voltage- wise cross subsidy with reference to the voltage-
wise cost of supply, the same is indicated in the Annexure to this Order.
![Page 3: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/3.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 56
c) Differential Tariff:
The Commission has been determining differential retail supply tariff for
consumers in urban and rural areas, beginning with its Tariff Order, dated 25th
November, 2009. The Commission decides to continue the same in the
present order also.
4.4 New Tariff Proposals:
(i) Increase in Billing demand for HT category:
The other ESCOMs, in their applications have submitted that, presently the billing
demand during unrestricted period should be the maximum demand recorded
during the month or 75% of the CD, whichever is higher. However, in the States
like Andhra Pradesh, Telangana, Maharashtra and Gujarat, the minimum billing
demand for the HT consumers is more than 75% of the CD. The ESCOMs in their
proposals have requested to increase the minimum billing demand to 85% of the
Contract Demand or Maximum Demand Recorded whichever is higher.
Commission’s Analysis and decision:
The Commission has examined the proposal and notes that the recovery of the
Fixed Charges from HT consumers at 75% of the CD or the actual maximum
demand recorded, whichever is higher has been in vogue for quite some time
and the same needs to be revised considering the present circumstances. In
view of the current level of competition in the energy market, there is a need to
provide a level playing field to all the stakeholders.
Further, the Commission notes that, the existing billing of demand charges at
maximum demand recorded or 75% of contract demand whichever is higher
has been in vogue by considering the shortage situation in power supply wherein
both energy cut and demand cut were imposed to meet the shortage situation.
In addition to this, both reliability and quality of power supply to HT consumers
![Page 4: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/4.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 57
were also reckoned while fixing the minimum billing demand of 75% of contract
demand.
The Commission takes note of the present uninterrupted system of power supply
without imposition of energy /demand cut and the reliability and quality of
power supply to the HT consumers. The Commission further notes that the fixed
expenditure incurred by the Distribution licensees is being recovered only to an
extent of 28.56%. Thus, the Commission is of the view that there is a need to
increase the recovery of fixed expenditure through a revised criterion for billing
demand of the HT consumers.
Hence, the Commission decides to increase the minimum billing demand from
the current level of 75% of the contract demand to 85% of the contract demand.
The revised demand charges are indicated in the respective HT tariff schedules.
(ii) Approval for allowing the expenditure incurred on promotion of payments
through Cards and Digital Means.
BESCOM in its application has submitted that, in the letter dated 07.11.2016
received from the Under Secretary(IT), Ministry of Power, New Delhi, where in it
was communicated the decision of the meeting held under the Chairmanship of
Secretary (DIPAM), to the effect that the Ministry of Power will persuade
States/DISCOMs to absorb MDR/Convenience fee on digital payment, as the
same stands factored in the tariff structure.
BESCOM in its application has submitted that, presently, the transaction charges
paid by BESCOM for the payments received through Bangalore One/ Karnataka
One / Mobile One and Post office is accounted as “Other Finance Cost” and the
same is being allowed in the tariff. However, the charges for card payment
made through other digital mode as made out below is borne by the consumer.
![Page 5: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/5.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 58
a) E-payment through Debit card, Credit card and Net Banking through BESCOM
website, bank website, Bangalore-one website.
b) ECS/NACH.
c) Mobile-apps (Mobile One, Paytm, Pay U).
d) NEFT & RTGS for HT Consumers.
e) Card swiping machines (Point of Sale machines). Provision for the same has
also been made in the ATP counters and action has been taken for its live
operations.
BESCOM has furnished details of the charges for payments made through these
modes by the HT Consumers depend on the amount paid at the bank’s slab rates
and the charges vary from bank to bank which are borne by the consumers.
In addition to this, if HT consumers are holding current accounts and if payments are
made through Cards as per the limit fixed by the Banks based on their transactions
and credit limit, then the transaction charges also need to be borne by BESCOM.
BESCOM has furnished the charges levied by various financial institution for making
payment of energy bills. Further, the BESCOM has submitted that, in respect of
charges to be absorbed in the case of digital online payments irrespective of the
amount of payment.
BESCOM has submitted that, if the HT consumers opt for RTGS/NEFT, Debit/Credit card
payment modes other than on-Line payment through BESCOM website, transaction
charges are more and needs to be borne by the Company and in turn it will have to
be passed on to all the consumers through tariff as per GoI initiative. Further, the
BESCOM has informed that, it has already mandated all HT consumers to pay
through online and requested the Commission to approve the On-line Payment
through BESCOM website or Electronic Bill Payment by selecting Net-Banking mode
wherein the applicable transaction charges per transaction is Rs. 5/- only.
Further, BESCOM has submitted that, in respect of the consumer paying through
Bangalore One, Karnataka One and IMI (Mobile Governance) by Digital mode, as
![Page 6: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/6.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 59
transaction charges are already being borne by BESCOM and if the MDR fees for
these said transactions is also borne by BESCOM, it will be an additional burden.
Apart from this, for the payment made through BBPS, the charges levied by the NPCI,
to be paid to BBPOU for ON-US and OF-US transaction are also required to be borne
by BESCOM.
BESCOM has requested the Commission to examine the matter and permit it to bear
the expenditure in this regard as per the directions of MOP, GoI and pass suitable
orders in this matter.
Commission’s analysis and decision:
The Commission has examined the proposal. In the long-run, all the payments
towards the energy charges in ESCOMs shall, as far as possible, be through the digital
mode in line with the directions issued by the MoP, GoI. This would avoid the hassles
of handling and accounting of physical cash. Hence in order to encourage the
consumers to opt for digital payments, the Commission decides to allow the ESCOMs
to accept the payment of power supply bills from the consumer by digital mode in
line with the directives issued by the MOP, GOI and allow it to incur the expenses
towards digital payments in the ARR (other than bank charges levied by the banker
to the consumer on payment directly by NEFT / RTGS). However, the Commission
after having noticed the higher transaction charges on the bill payment of bills
through debit/credit cards, decides to allow Distribution licensees to incur the
expenditure on payments through Debit/ Credit card, of power supply bills having
demand up to Rs.2000 only.
Further, the Commission directs the all the Distribution licensees to minimise the
expenditure to be incurred in this respect by encouraging the consumers to make
payments through other e-payment /digital mode charged with lower rate of
transaction charges.
![Page 7: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/7.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 60
(iii) Special Incentive Scheme to HT/EHT Industrial Consumers
As part of its efforts to bring back HT Consumers to its grid, the Distribution licensees
proposed to introduce an Incentive Scheme for HT Consumers in line with a similar
Scheme implemented in the year 2003 wherein the consumption over and above
the average consumption for the preceding year was billed at the rate of first slab
i.e., Rs.3.80.
This proposed incentive scheme is intended to generate additional revenue from HT
consumers (HT2-a i, ii & HT2-b I(i)(ii) and HT2c(ii) consumers) by encouraging them to
consume energy over and above the past 12 months’ average consumption by
offering a concessional tariff rate.
a. The salient features and procedural aspects of the scheme are as follows:
i. The scheme is applicable to all HT 2(a) (except railway traction, effluent
treatment plants and BMRCL), HT2 (b) and HT2(c)(ii) consumers in HRECS.
The benefit of the scheme will be extended to all eligible consumers
(exceeding the 1st slab in their respective tariff) upon their request.
ii. The rate applicable for eligible consumption under the scheme is less than
the second slab rate/kwh excluding tax as shown in the above table. The
normal consumption will be billed at the prevailing tariff rate applicable to
the respective category of consumers.
iii. Eligibility: The consumption over and above the base consumption fixed
for a month is eligible for incentive under the scheme. The base period is
defined as the past 12 month’s consumption. The base consumption will
be the average of monthly-billed energy supplied by HRECS during the
base period. Energy consumed under special scheme, if any, during the
base period will not be accounted for arriving at base consumption.
![Page 8: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/8.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 61
iv. The base consumption will be computed on the average of 12 months'
consumption excluding wheeled energy for the period from January, 2016
to December, 2016.
v. After opting for this scheme, if the consumers avail increased CD on a
permanent basis, the base consumption will be increased by 100 units per
KVA of the additional CD availed by the industry on permanent basis.
vi. For new industries serviced after January 2017, the criteria for these
industries to be eligible for this special scheme will be a minimum period of
six months.
vii. For new industries, which do not have 12 months' base consumption, the
base consumption will be computed on the actual consumption for the
months in the base period plus the consumption computed at 100 per
KVA per month for the remaining months of the base period.
viii. Distribution licensees will have flexibility in fixing base consumption.
ix. In order to avail the special scheme, 20% increase in contract demand will
be allowed to the availing consumers during the currency of the scheme
which is optional to the consumers. Penalty for exceeding the maximum
demand, by the consumers availing the scheme thus would be for the
contract demand(CD) exceeding 120% of the sanctioned CD. The
minimum billing demand will also be enhanced accordingly.
x. The scheme will continue till the end of the financial year. However,
Distribution licensees would endeavour to continue the scheme with the
approval of the Commission, for the ensuing year as well, with necessary
modifications to the rate structure based on the tariff rates approved by
KERC for the ensuing year.
![Page 9: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/9.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 62
xi. Consumer under the HT incentive scheme can avail any other incentives
in force.
Commission’s Analysis and Decision:
The Commission notes that many HT/EHT consumers are opting for open access
and are procuring power from sources other than the distribution licensees and
as a result, distribution licensees are deprived of the sales to the paying
consumers, impacting the finances of distribution licensees. The Commission is of
the view that significant number of such consumers can be weaned back by the
ESCOMs if attractive incentives are provided in the Tariff as in proposals made by
the ESCOMs. Such scheme would also encourage HT/EHT consumers to consume
power over and above their average consumption. The Commission also
considered that consumption by such consumers should be incentivized during
off peak hours and night hours.
Further, the industrial consumers participating in the Public Hearings held by the
Commission on the tariff petitions of the distribution licensees, have sought for
reduction in their tariff that is competitive with the open market rates and stated
that, if done so, they would avail power from the distribution licensees instead of
sourcing their requirement from open access.
Therefore, in this context, the Commission approves an incentive scheme to
HT/EHT consumers except Bengaluru Metro Rail Corporation Limited (BMRCL)
considering the proposal made by the ESCOMs with an effort to bring back
HT/EHT consumers who are availing power through open access.
The Commission, therefore hereby extends the following special consumers, in an
attempt to bring back HT / EHT consumers who are availing power through open
access.
![Page 10: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/10.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 63
Further, the Commission, considering that concessional tariff being extended to
the BMRCL and Railway traction, decides not to extend such special incentive
scheme and also ToD tariff to the installations of Bangalore Metro Rail Corporation
(BMRCL) and Railway traction.
The terms and conditions of the special incentive scheme are as under:
i. Eligibility:
a) The scheme is applicable to all HT (1), HT 2(a), H 2(b) and H2 (c) including sub-
categories in these tariff schedules and provided with ToD meters in the State,
at their options.
b) The quantum of energy consumed during non-peak day hours between 10.00
Hours and 18.00 Hours during the month over and above the average base
consumption corresponding to this time period is eligible under this incentive
scheme.
ii. Base consumption:
The monthly average consumption out of energy supplied by Hukeri RECS
during the non-peak hours’ period between 10.00 Hours and 18.00 Hours of the
day, during the period from 01-04-2017 to 31-03-2018 as recorded in Time of
Day (ToD) meter shall be reckoned as base consumption.
Note: Consumption of energy from sources other than Hukeri RECS shall not be
reckoned for computation of base consumption.
a. Computation of base consumption for existing consumers:
The base consumption of consumers existing as on 01.04.2017 shall be
determined based on their consumption between 10.00 Hours and 18.00 Hours
for the period from 01-04-2017 to 31-03-2018, irrespective of the date of request
by the consumer for opting for the Scheme.
![Page 11: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/11.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 64
b. Computation of base consumption for new consumers:
(i) In the case of consumers who have obtained the services after 01.04.2017
where the consumption for the past 12 months is not available, then the
available consumption subject to availability of a minimum of 6 month’s
consumption, shall form the basis for computing the base consumption.
If the actual consumption for a minimum of 6 months is not available, the
base consumption shall be worked out by considering 67 kWh per month
per kVA of contract demand for the installations. After 6 months, the base
consumption shall be reassessed on the basis of actual consumption
recorded between 10.00 Hours and 18.00 Hours for the 6 months from the
date of service.
(ii) In the case of new consumers availing the service during FY19, the base
consumption shall be worked out by considering 67 kWh per month per
KVA of contract demand for the first 6 months of service. After 6 months,
the base consumption shall be reassessed on the basis of actual
consumption recorded between 10.00 Hours and 18.00 Hours for the 6
months from the date of service.
Also, in the case of an existing consumer having CD below 500kVA and not
opted ToD tariff and willing to opt this special incentive scheme, then such
consumer should opt for ToD regime. The base consumption for such
consumers shall be worked out by considering 67 kWh per month per KVA
of contract demand for the first 6 months. After 6 months, the base
consumption shall be reassessed on the basis of actual consumption
recorded in the ToD meter between 10.00 Hours and 18.00 Hours for the 6
months from the date of fixing of ToD meter by opting this scheme.
(iii) In the case of eligible consumers who have increased their contract
demand on a permanent basis, during the currency of the scheme, the
![Page 12: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/12.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 65
existing base consumption shall be increased to the extent of additional
contract demand at the rate of 67 kWh/KVA per month, from the month in
which the additional contract demand has come into effect.
iii. Incentive:
Any energy consumed by the eligible consumers during the non-peak period
between 10.00 Hours and 18.00 Hours, over and above the average base
consumption as arrived at, shall be allowed a discount of Rs.1.00/- per unit in the
bill, to the eligible consumers.
Further, the eligible consumers would be allowed a discount of Rs.2.00 per unit in
the bill for the energy consumed during the period between 22.00 Hours and 06.00
Hours as against the normal ToD rebate of Re.1.00 per unit.
Note: The base consumption is not applicable for this additional discount for the
consumption during 22.00 Hours and 06.00 Hours. Further, the existing ToD benefit of
[ (-) one Rupee per unit] is not applicable to the consumers covered under this
scheme for usage during 22.00 Hours and 06.00 Hours. However, the ToD
tariff/penalty of (+) one Rupee per unit, is applicable for the energy consumed
during the peak periods between 06.00 Hrs. to 10.00 Hrs. and 18.00 Hours to 22.00
Hrs. For all other consumers who have not opted for this scheme, the approved ToD
tariff will apply as per the Tariff Order.
iv. Additional Security deposit:
No additional security deposit shall be collected for the additional units
consumed over and above the base consumption between 10.00 Hours and
18.00 Hours under this “incentive scheme”
v. Currency of this incentive scheme:
Further, to provide certainty to the Scheme, the Commission decides that, the
Scheme will remain in force initially for two years, subject to revision of the
![Page 13: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/13.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 66
incentive amount annually. However, the HRECSs may approach the
Commission for review of the Orders during this period. The consumer, under this
scheme can exit from the scheme by issuing a notice of at least 2 months
before, opting to exit from this scheme.
(iv) Simplification of tariff:
The other ESCOMs have submitted that a Committee was constituted by the
GoK vide Government Order No. EN70 PSR 2017, dated 04.09.2017, to study the
tariff simplification across the ESCOMs and also informed about the receipt of
proposal on the rationalisation of tariff structures made out by the Commission.
The ESCOMs have submitted the Committee report for simplification of Tariff
Structure for the consideration of the Commission.
Commission’s Analysis and decision:
Before the referred Committee was set up by the GoK, for simplification of Tariff
structure, the Commission had proposed certain simplification of tariff structure
and the suggestions of the ESCOMs were sought. But none of the ESCOMs have
furnished their views. However, some of the recommendations of the Committee
are in line with the suggestions made by the Commission.
Simplification of tariff structure is aimed at reducing the number of
subcategories. It need not necessarily involve converting the existing category to
some other category by charging a higher tariff. This exercise is basically
considered for restructuring the existing subcategories without converting the
existing domestic / other categories in to commercial categories.
To enable the Commission to examine the proposal, HRECS should have
furnished necessary details such as existing and projected number of consumers
under the proposed categories, sanctioned/ contract demand, Sales and the
revenue at the existing tariff and the proposed tariff etc. Without furnishing the
![Page 14: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/14.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 67
above details along with the proposed tariff, the estimation of revenue to meet
the ARR would not be proper.
Hence, the Commission is of the view that, while submitting any proposal for tariff
simplification recategorisation for approval of the Commission in the next filing,
all the ESCOMs shall furnish the above necessary details, without which it would
not be possible for the Commission to examine their requests.
(v) Tariff for Electric Vehicle Charging Stations:
BESCOM has submitted that, the Government of India and NITI Aayog are
working on a policy for promotion of e-vehicles to encourage and promote e-
mobility in the future. That charging stations are required for mass adoption of
electric vehicles, and that to encourage electric and hybrid vehicles, various
Companies are coming forward. As per the prevailing tariff structure approved
by the Commission, battery charging units are being billed under commercial
tariff.
In line with Karnataka State Electric Vehicle & Energy Storage Policy 2017,
BESCOM has requested the Commission to approve a separate tariff under both
HT and LT category with Time of Day tariff for Electric Vehicle Charging Stations.
Commission’s Views and Decisions:
The Commission takes note of the Karnataka State Electric Vehicle & Energy
Storage Policy, 2017 and the request made by the BESCOM to approve a
separate tariff under both HT and LT category for the Electric vehicle charging
stations to encourage and promote e- mobility in the future by use of electric
and hybrid vehicles in the State. The Commission, taking note of the benefit of
such incentive to the environment as well as to the society in the State of
Karnataka, decides to introduce a separate category of tariff for HT and LT
vehicle charging stations under LT6 tariff schedule with concessional rates to be
![Page 15: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/15.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 68
adopted in all the ESCOMs in the State. The rates approved to this category to all
the ESCOMs is indicated in the Tariff Schedule in the subsequent section of this
chapter.
4.5 Revenue at existing tariff and deficit for FY19:
The Commission in its preceding Chapters has decided to carry forward the gap
in revenue of Rs.2560.68 Lakhs of FY17 to the ARR of FY19. The gap in revenue for
FY19 is proposed to be filled up by revision of Retail Supply Tariff, as discussed in
the following paragraphs of this Chapter.
Considering the approved ARR for FY19 and the revenue as per the existing tariff,
the gap in revenue for FY19 is as follows:
TABLE – 4.1
Revenue Deficit for FY19
Rs. in Lakhs
Particulars Amount
Approved Net ARR for FY19 including gap of FY17 17678.60
Revenue at existing tariff 16751.10
(- )Deficit 927.50
Additional Revenue to be realised by Revision of Tariff 927.50
Accordingly, in this Chapter, the Commission has proceeded to determine the
Revised Retail Supply Tariff for FY19. The category-wise tariff as existing, as
proposed by HUKERI RECS and as approved by the Commission are as follows:
1. LT-1 Bhagya Jyothi:
The existing tariff and the tariff proposed by HUKERI RECS are given below:
Sl.No Details Existing as per 2017
Tariff Order
Proposed by HUKERI RECS
1 Energy charges
(including recovery
towards service main
charges)
592 Paise / Unit Subject
to a monthly minimum of
Rs.30 per installation per
month.
668 Paise / Unit Subject to
a monthly minimum of
Rs.30 per installation per
month.
![Page 16: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/16.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 69
Commission’s Views/ Decision
The Government of Karnataka has continued its policy of providing free power
to all BJ/KJ consumers with a single outlet, whose consumption is not more than
40 units per month, vide Government Order No. EN12 PSR 2017 dated
20th March, 2017 (instead of the earlier limit of 18 units per month). Based on the
present average cost of supply, the tariff payable by these BJ/KJ consumers is
revised to Rs.6.34 per unit.
Further, the ESCOMs have to claim subsidy for only those consumers who
consume 40 units or less per month per installation. If the consumption exceeds
40 units per month or if any BJ/KJ installation is found to have more than one out-
let, it shall be billed as per the Tariff Schedule LT 2(a).
Accordingly, Commission determines the tariff (CDT) in respect of BJ / KJ
installations as follows:
LT – 1 Approved Tariff for BJ / KJ installations
Commission determined Tariff Retail Supply Tariff determined
by the Commission
634 paise per unit,
Subject to a monthly minimum of
Rs.40 per installation per month.
-Nil-*
Fully subsidized by GoK
*Since GOK is meeting the full cost of supply to BJ / KJ installations, the Tariff payable by
these Consumers is shown as nil. However, if the GOK does not release the subsidy in
advance, a Tariff of Rs.6.34 per unit subject to a monthly minimum of Rs.40 per installation per
month, shall be demanded and collected from these consumers.
2. LT2 - Domestic Consumers:
HUKERI RECS’s Proposal:
The details of the existing and proposed tariff under this category are given in the
Table below:
![Page 17: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/17.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 70
Proposed Tariff for LT-2 (a)
LT-2 a (i) Domestic Consumers Category
Applicable to areas coming under City Municipal Corporations and all Urban
Local Bodies
Details Existing as per 2017
Tariff Order
Proposed by HUKERI RECS
Fixed Charges
per Month
For the first KW Rs.40 For the first KW Rs.40
For every additional KW
Rs.50
For every additional KW
Rs.50
Energy Charges
0-30 units
(life line
Consumption )
0 to 30 units:325
paise/unit 0 to 30 units: 400 paise/unit
Energy Charges
exceeding 30
units per month
31 to 100 units:470
paise/unit
31 to 100 units: 545 paise
/ unit
101 to 200 units:625
paise /unit
101 to 200 units:700 paise
/unit
Above 200 units:730
paise/unit
Above 200 units:805 paise
/unit
LT-2(a)(ii) Domestic Consumers Category
Applicable to Areas under Village Panchayats
Details Existing as per 2017 Tariff
Order
Proposed by HUKERI RECS
Fixed charges per
Month
For the first KW Rs.25 For the first KW Rs.25
For every additional KW
Rs.40
For every additional
KW Rs.40
Energy Charges
0-30 units ( life line
Consumption )
Upto 30 units:315 paise/
unit
0 to 30 units:390 paise/unit
Energy Charges
exceeding 30 Units
per month
31 to 100 units:440 paise/
unit
31 to 100 units:515 paise/
unit
101 to 200 units:595
paise/unit
101 to 200 units: 670
paise/unit
Above 200 units: 680
paise/unit
Above 200 units:755
paise/unit
![Page 18: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/18.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 71
Commission’s decision
As in the previous Tariff Order, the Commission decides to continue with the two
tier tariff structure in respect of the domestic consumers as shown below:
(i) Areas coming under City Municipal Corporations and all Urban Local Bodies.
(ii) Areas under Village Panchayats.
The Commission approves the tariff for this category as follows:
Approved Tariff for LT 2 (a) (i) Domestic Consumers Category:
Applicable to Areas coming under City Municipal Corporations and all Urban
Local Bodies
Details Tariff approved by the
Commission
Fixed charges per Month For the first KW: Rs.50/-
For every additional KW Rs.60/-
Energy Charges upto 30 units per month
(0-30 units)-life line consumption.
Upto 30 units: 345paise/unit
Energy Charges in case the
consumption exceeds 30 units per
month
31 to 100 units:495 paise/unit
101 to 200 units:650 paise/unit
Above 200 units: 755 paise/unit
Approved Tariff for LT-2(a) (ii) Domestic Consumers Category:
Applicable to Areas under Village Panchayats
Details Tariff approved by the
Commission
Fixed Charges per Month For the first KW: Rs.35/-
For every additional KW Rs.50/-
Energy Charges upto 30 units per month
(0-30 Units)-Lifeline Consumption
Upto 30 units: 335 paise/unit
Energy Charges in case the consumption
exceeds 30 units per month
31 to 100 units: 465 paise/unit
101 to 200 units:620paise/unit
Above 200 units: 705 paise/unit
![Page 19: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/19.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 72
LT2 (b) Private and Professional Educational Institutions, Private Hospitals and
Nursing Homes:
HUKERI RECS’s Proposal:
The details of the existing and the proposed tariff under this category are given in
the Table below:
LT 2 (b) (i)Applicable to areas under City Municipal Corporations Areas and all
urban Local Bodies
Details Existing as per 2017 Tariff Order Proposed by HUKERI RECS
Fixed
Charges per
Month
Rs.55 Per KW subject to a
minimum of Rs.85 per month
Rs.55 Per KW subject to a
minimum of Rs.85 per
month
Energy
Charges
For the first 200 units: 650
paise per unit
For the first 200 units : 725
paise per unit
Above 200 units: 775 paise per
unit
For the balance units : 850
paise per unit
LT 2 (b)(ii) Applicable to Areas under Village Panchayats
Details Existing as per 2017 Tariff Order Proposed by HUKERI RECS
Fixed
Charges per
Month
Rs.45 per KW subject to a
minimum of Rs.70 per Month
Rs.45 per KW subject to a
minimum of Rs.70 per Month
Energy
Charges
For the first 200 units: 595
paise per unit
For the first 200 units:670 paise
per unit
Above 200 units: 720 paise per
unit
For the balance units:795
paise per unit
Commission’s decision
As in the previous Tariff Order, the Commission decides to continue the two tier
tariff structure as follows:
![Page 20: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/20.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 73
(i) Areas coming under City Municipal Corporation and all urban local bodies.
(ii) Areas under Village Panchayats.
Approved Tariff for LT 2 (b) (i)
Private Professional and other private Educational Institutions, Private Hospitals
and Nursing Homes
Applicable to areas under City Municipal Corporations and all other urban Local
Bodies.
Details Tariff approved by the Commission
Fixed Charges per Month Rs.65 per KW subject to a minimum of Rs.90
per Month
Energy Charges 0-200 units: 670 paise/unit
Above 200 units: 795 paise/unit
Approved Tariff for LT 2 (b) (ii)
Private Professional and other private Educational Institutions, Private Hospitals
and Nursing Homes
Applicable to Areas under Village Panchayats
Details Tariff approved by the Commission
Fixed Charges per Month Rs.55 per KW subject to a minimum of Rs.75 per
Month
Energy Charges 0-200 units: 615 paise/unit
Above 200 units: 740 paise/unit
3. LT3- Commercial Lighting, Heating & Motive Power:
HUKERI RECS’s Proposal:
The existing and proposed tariffs are as follows:
![Page 21: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/21.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 74
LT- 3 (i) Commercial Lighting, Heating & Motive Power
Applicable to Areas coming under City Municipal Corporation and urban local
bodies
Details Existing as per 2017 Tariff
Order
Proposed by HUKERI RECS
Fixed charges per
Month
Rs.60 per KW Rs.60 per KW
Energy Charges For the first 50 units:750 paise
per unit
For the first 50 units:825 paise
per unit
For the balance units:850
paise per unit
For the balance units: 925
paise per unit
Demand based tariff (optional) where sanctioned load is above 5 KW but below 50
KW.
Details Existing as per 2017 Tariff Order Proposed by HUKERI RECS
Fixed
charges
Rs.75 per KW Rs.75 per KW
Energy
Charges
For the first 50 units:750 paise
per unit
For the first 50 units:825paise
per unit
For the balance units:850 paise
per unit
For the balance units:925
paise per unit
LT-3 (ii) Commercial Lighting, Heating & Motive
Applicable to areas under Village Panchayats
Details Existing as per 2017 Tariff Order Proposed by HUKERI RECS
Fixed Charges per
Month
Rs.50 per KW Rs.50 per KW
Energy Charges For the first 50 units: 700 paise
per unit
For the first 50 units: 775
paise per unit
For the balance units: 800
paise per unit
For the balance units: 875 paise
per unit
![Page 22: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/22.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 75
Demand based tariff (optional) where sanctioned load is above 5 KW but below
50 KW
Details Existing as per 2017 Tariff
Order
Proposed by HUKERI RECS
Fixed Charges per
Month
Rs.65 per KW Rs.65 per KW
Energy Charges For the first 50 units: 700
paise per unit
For the first 50 units: 775
paise per unit
For the balance units: 800
paise per unit
For the balance units: 875
paise per unit
Commission’s Views/ Decision
As in the previous Tariff Order, the Commission decides to continue with the two
tier tariff structure as below:
(i) Areas coming under City Municipal Corporations and other urban local
bodies.
(ii) Areas under Village Panchayats.
Approved Tariff for LT- 3 (i) Commercial Lighting, Heating & Motive
Applicable to areas under City Municipal Corporations and other Urban Local
Bodies
Details Approved by the Commission
Fixed Charges per Month Rs.70 per KW
Energy Charges For the first 50 units: 775 paise/ unit
For the balance units: 875 paise/unit
Approved Tariff for Demand based tariff (Optional) where sanctioned load is
above 5 kW but below 50 kW
Details Approved by the Commission
Fixed Charges per Month Rs.85 per KW
Energy Charges For the first 50 units:775 paise /unit
For the balance units:875 paise/unit
![Page 23: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/23.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 76
Approved Tariff forLT-3 (ii) Commercial Lighting, Heating and Motive
Applicable to areas under Village Panchayats
Details Approved by the Commission
Fixed charges per Month Rs.60 per KW
Energy Charges For the first 50 units: 725 paise per unit
For the balance units: 825 paise per unit
Approved Tariff for Demand based tariff (Optional)where sanctioned load is
above 5 kW but below 50 kW
Details Approved by the Commission
Fixed Charges per Month Rs.75 per KW
Energy Charges For the first 50 units: 725 paise per unit
For the balance units: 825 paise per unit
4. LT4-Irrigation Pump Sets:
HUKERI RECS’s Proposal:
The existing and proposed tariff for LT4 (a) are as follows:
LT-4 (a) Irrigation Pump Sets
Applicable to IP sets up to and inclusive of 10 HP
Details Existing as per 2017 Tariff
Order
Proposed by HUKERI RECS
Fixed charges per
Month
Nil Nil
Energy charges CDT 579 paise per unit CDT 654 paise per unit
Commission’s Decision
The Government of Karnataka has extended free supply of power to farmers as
per the Government Order No. EN 55 PSR 2008 dated 04.09.2008. As per this
policy of GoK, the entire cost of supply to IP sets upto and inclusive of 10 HP is
being borne by the GoK through tariff subsidy. In view of this, all the consumers
under the existing LT-4(a) tariff are covered under free supply of power.
![Page 24: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/24.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 77
Considering the cross subsidy contribution from categories other than IP Sets and
BJ/KJ Categories, the Commission determines the tariff for IP Sets under LT4(a)
category as follows:
Approved CDT for IP Sets for FY19
Particulars HUKERI
RECS
Approved ARR in Rs. Lakhs 17678.60
Revenue from other than IP & BJ/KJ installations in Rs. Lakhs 5219.70
Amount to be recovered from IP & BJ/KJ installations in Rs. Lakhs 12442.80
Approved Sales to BJ/KJ installations in MU 3.499
Revenue from BJ/KJ installations at Average Cost of supply in Rs. Lakhs 221.80
Amount to be recovered from IP Sets category in Rs. Lakhs 12221.00
Approved Sale to IP Sets in MU 201.999
Commission Determined Tariff (CDT) for IP set Category for FY19 in
Rs/Unit 6.05
Accordingly, the Commission decides to approve tariff of Rs.6.05 per unit as CDT
for FY19 for IP Set category under LT4 (a). In case the GoK does not release the
subsidy in advance, the tariff of Rs.6.05 per unit shall be demanded and
collected from these consumers.
Approved by the Commission
LT-4 (a) Irrigation Pump Sets
Applicable to IP sets up to and inclusive of 10 HP
Details Approved by the Commission
Fixed charges per Month Energy charges Nil*
CDT (Commission Determined Tariff): 605 paise per unit
* In case the GoK does not release the subsidy in advance, a tariff of Rs.6.05 per
unit shall be demanded and collected from these consumers.
![Page 25: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/25.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 78
The Commission has been issuing directives to ESCOMs for conducting Energy
Audit at the Distribution Transformer Centre (DTC)/feeder level for proper
assessment of distribution losses and to enable detection and prevention of
commercial loss. In view of substantial progress in implementation of feeder
segregation under NJY scheme, the ESCOMs were also directed to submit IP set
consumption on the basis of the meter readings of the 11 kV feeders at the
substation level duly deducting the energy losses in 11kV lines, distribution
transformers & LT lines, in order to compute the consumption of power by IP sets
accurately. Further, in the Tariff Order 2016, the ESCOMs were also directed to
take up enumeration of IP sets, 11 kV feeder-wise by capturing the GPS
co-ordinates of each live IP set in their jurisdiction. In this regard, the Commission
has noted that the ESCOMs have complied partly with these directions and have
initiated measures to achieve full compliance. The ESCOMs need to ensure full
compliance as this has direct impact on their revenues and tariff payable by
other categories of consumers.
The Government of Karnataka vide its letter dated 16.12.2017 has informed the
Commission that for FY19, an amount of Rs.8040.26 Crores is available for the
subsidized supply to BJ/KJ installations and IP sets, and that there is no change in
the Policy of the Government in the matter of free supply to BJ/KJ consumers
(consuming up to 40 Units) and IP sets consumers with a contract demand of 10
HP and below. It is also informed that in case, the amount required for the
subsidized supply to this is in excess of the available amount, the government is
unable to meet the balance amount in the subsequent year.
In reply to the above letter the Commission, in its letter dated 11.01.2018 has
informed the Government that as per the provisions of the Electricity Act, 2003
and in view of the Policy of the State Government to supply free power to BJ/KJ
installations (consuming up to 40 Units per month) and IP Sets having sanctioned
load of 10 HP and below, the Government has to fully meet the cost of such
subsidized supply. The Commission has made it clear to the Government that the
shortfall in subsidy cannot be passed on to the other consumers, who are
![Page 26: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/26.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 79
already paying tariffs with high level of cross subsidies and any increase in such
higher tariff of other consumers would correspondingly increase the cross subsidy
levels, which would be against the provisions of Electricity Act and the Tariff
Policy, that emphasize gradual reduction in cross subsidy at a level not
exceeding plus or minus 20% of the cost of supply. In view of the above the
Government was requested to consider the following alternatives:
a) In view of the Policy decision taken by the Government to supply free
power supply to BJ/KJ and IP sets installations, the Government has to
provide full subsidy as committed in the Government Order dated 4th
September, 2008, as the shortfall in the subsidy cannot be made good by
charging higher tariff to other consumers, as they are already cross
subsidizing beyond the maximum ceiling limit prescribed under the Tariff
Policy.
b) If the Government is not able to provide adequate subsidy towards free
power to the BJ/KJ and IP set installations, the present 7 hours three phase
power being supplied to the IP sets shall have to be proportionately
reduced. Based on the reduced allocation of subsidy the quantum of
power that could be supplied to IP sets would be 12597.28 MU and the
duration of supply could be four hours per day, instead of seven hours.
c) In case, the reduction of quantum of power is not possible, the shortfall in
the subsidy shall be made good by the IP set consumers.
The Commission has not received reply from the Government.
Under the circumstances, the Commission directs the ESCOMs as follows:
The ESCOMs shall manage supply of power to the IP sets for the FY19, so as to
ensure that it is within the quantum of subsidy committed by the GoK. While
doing so, they shall procure power which is proportionate to such supply. In
![Page 27: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/27.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 80
case, the ESCOMs choose to supply power to the IP sets in excess of the
quantum proportionate to the amount of subsidy available from the GoK for FY19,
the difference in the amount of subsidy relating to such supply shall be claimed
from the GoK. If the difference in subsidy is not paid by the GoK, the same shall
be collected from the IP set consumers.
LT4 (b) Irrigation Pump Sets above 10 HP:
HUKERI RECS’s Proposal
The Existing and proposed tariff for LT-4(b) category are as follows:
LT-4 (b) Irrigation Pump Sets:
Applicable to IP Sets above 10 HP
Details Existing as per 2017 Tariff
Order
Proposed by HUKERI
RECS
Fixed charges per
Month
Rs.50 per HP Rs.50 per HP
Energy charges for
the entire
consumption
300 paise per unit 375 paise per unit
The existing and proposed tariff for LT4(c) are as follows:
LT-4 (c) (i) - Applicable to Private Horticultural Nurseries, Coffee, Tea & Rubber
plantations up to & inclusive of 10 HP
Details Existing as per 2017 Tariff
Order
Proposed by HUKERI
RECS
Fixed charges per
Month
Rs.40 per HP Rs.40 per HP
Energy charges for
the entire
consumption
300 paise per unit 375 paise per unit
![Page 28: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/28.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 81
LT-4 (c) (ii) - Applicable to Private Horticultural Nurseries, Coffee, Tea & Rubber
plantations above 10 HP
Details Existing as per 2017 Tariff
Order
Proposed by HUKERI
RECS
Fixed charges per
Month
Rs.50 per HP Rs.50 per HP
Energy charges for
the entire
consumption
300 paise per unit 375 paise per unit
Approved Tariff:
The Commission decides to revise the tariff in respect of these categories as
shown below:
LT-4 (b) Irrigation Pump Sets:
Applicable to IP Sets above 10 HP
Fixed charges per Month Rs.60 per HP
Energy charges for the entire consumption 325 paise/unit
LT4(c) (i) - Applicable to Horticultural Nurseries,
Coffee, Tea &Rubber plantations up to & inclusive of 10 HP
Fixed charges per Month Rs.50 per HP
Energy charges 325 paise / unit
LT4 (c)(ii) - Applicable to Horticultural Nurseries, Coffee, Tea & Rubber
plantations above 10 HP
Fixed charges per Month Rs.60 per HP
Energy charges 325 paise/unit
![Page 29: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/29.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 82
5. LT5 Installations-LT Industries:
HUKERI RECS’s Proposal:
The existing and proposed tariffs under this category are given below:
LT-5 (a) LT Industries:
Applicable to areas under City Municipal Corporation
i) Fixed charges
Details Existing as per 2017 Tariff Order Proposed by HUKERI RECS
Fixed
charges
per Month
i) Rs. 40 per HP for 5 HP &
below
ii) Rs. 45 per HP for above 5 HP
& below 40 HP
iii) Rs. 60 per HP for 40 HP &
above but below 67 HP
iv)Rs. 120 per HP for 67 HP &
above
NA
Demand based Tariff (Optional)
Details Description Existing Tariff as per
2017 Tariff Order
Proposed by
HUKERI RECS
Fixed
Charg
es per
Month
Above 5 HP and less
than 40 HP
Rs.60 per KW of billing
demand
NA
40 HP and above but
less than 67 HP
Rs.85 per KW of billing
demand
67 HP and above Rs.170 per KW of
billing demand
ii) Energy Charges
Details Existing as per 2017
Tariff Order
Proposed by HUKERI RECS
For the first 500 units 510 paise per unit NA
For next 500 units 605 paise per unit
For the balance unit 635 paise per unit
![Page 30: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/30.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 83
LT-5 (b) LT Industries:
Applicable to all areas other than those covered under LT-5(a)
i) Fixed charges
Details Existing as per 2017 Tariff Order Proposed by HUKERI RECS
Demand based Tariff (optional)
Details Description Existing Tariff as per
2017 Tariff Order
Proposed by HUKERI
RECS Fixed Charges per Month
Above 5 HP and
less than 40 HP
Rs.55 per KW of
billing demand
Rs.55 per KW of
billing demand
40 HP and above
but less than 67 HP
Rs.80 per KW of
billing demand
Rs.80 per KW of
billing demand
67 HP and above Rs.160 per KW of
billing demand
Rs.160 per KW of
billing demand
ii) Energy Charges
Details Existing as per 2017 Tariff
Order
Proposed by HUKERI RECS
For the first 500 units 500 paise per unit 575 paise/ unit
For the next 500 units 590 paise per unit 665 paise/ unit
For the balance units 620 paise per unit 695 paise/ unit
Existing ToD Tariff for LT5 (a) & (b): At the option of the consumers
Time of Day Increase (+ )/ reduction (-) in energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 hrs 0
Fixed
Charges per
Month
i)Rs.35 per HP for 5 HP &
below
ii) Rs.40 per HP for above 5 HP
& below 40 HP
iii) Rs.55 per HP for 40 HP &
above but below 67 HP
iv)Rs.110 per HP for 67 HP &
above
i) Rs.35 per HP for 5 HP &
below
ii) Rs.40 per HP for above 5
HP & below 40 HP
iii) Rs.55 per HP for 40 HP &
above but below 67 HP
iv)Rs.110 per HP for 67 HP &
above
ToD Tariff
![Page 31: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/31.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 84
18.00 Hrs to 22.00 Hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
Proposed ToD Tariff for LT5 (a) & (b): At the option of the consumers
Time of Day Increase (+ )/ reduction (-) in energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 hrs 0
18.00 Hrs to 22.00 Hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
Commission’s Decision:
Time of the Day Tariff:
The decision of the Commission in its earlier Tariff Orders, providing for mandatory
Time of Day Tariff for HT2(a), HT2(b) and HT2(c) consumers with a contract
demand of 500 KVA and above is continued. The existing optional ToD will
continue for HT2(a), HT2(b) and HT2(c) consumers with contract demand of less
than 500 KVA. Further, for LT5 and HT1 consumers, the existing optional ToD is
continued.
The Commission takes note of the request made by the consumer of other
categories to extend the same concession as given in the energy charges to the
Effluent Treatment Plant situated within the industrial premises. The Commission
having considered the environmental and the social benefits from the Effluent
Treatment Plants and Drainage Water Treatment plants owned other than by
local bodies situated within the premises of the installation, decides to bill the
electricity consumed by the effluent plants and drainage water treatment plants
from the main meter or by sub-meter, at the same tariff schedule, as applicable
to the installations for which the power supply is availed.
ToD Tariff
![Page 32: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/32.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 85
The Commission notes the request made by the ESCOMs for billing the power
supply to Solid Waste processing plants under LT and HT industrial category. The
Commission by considering the environmental and social benefits in processing
of solid waste by such plants, decides to approve billing by ESCOMs for the
power supply arranged to such plants under LT/HT industrial tariff.
The Commission decides to continue with two tier tariff structure introduced in the
previous Tariff Orders, which are as follows:
i) LT5 (a): For areas falling under City Municipal Corporations
ii) LT5 (b): For areas other than those covered under LT5 (a) above.
Approved Tariff:
The Commission approves the tariff under LT 5 (a) and LT 5 (b) categories as
given below:
Approved Tariff for LT 5 (a):
Applicable to areas under City Municipal Corporations
i) Fixed charges
Details Approved by the Commission
Fixed
Charges per
Month
i) Rs.45 per HP for 5 HP & below
ii) Rs.50 per HP for above 5 HP & below 40 HP
iii) Rs.70 per HP for 40 HP & above but below 67 HP
iv) Rs.130 per HP for 67 HP & above
Demand based Tariff (optional)
Fixed
Charges per
Month
Above 5 HP and less than 40
HP
Rs.65 per KW of billing
demand
40 HP and above but less
than 67 HP
Rs.95 per KW of billing
demand
67 HP and above Rs.180 per KW of billing
demand
![Page 33: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/33.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 86
ii) Energy Charges
Details Approved by the Commission
For the first 500 units 530 paise/unit
For the next 500 units 625 paise/ unit
For the balance units 655 paise/ unit
Approved Tariff for LT 5 (b):
Applicable to all areas other than those covered under LT-5(a)
i) Fixed charges
Details Approved Tariff
Fixed
Charges
per Month
i) Rs.40 per HP for 5 HP & below
ii) Rs.45 per HP for above 5 HP & below 40 HP
iii) Rs.65 per HP for 40 HP & above but below 67 HP
iv)Rs.120 per HP for 67 HP & above
ii) Demand based Tariff (optional)
Details Description Approved Tariff
Fixed Charges per
Month
Above 5 HP and less
than 40 HP
Rs.60 per KW of billing
demand
40 HP and above but less
than 67 HP
Rs.90 per KW of billing
demand
67 HP and above Rs.170 per KW of billing
demand
iii) Energy Charges
Details Approved tariff
For the first 500 units 520 paise/ unit
For the next 500 units 610 paise/ unit
For the balance units 640 paise/unit
![Page 34: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/34.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 87
As discussed earlier in this Chapter, the approved ToD Tariff for LT5 (a) & (b): At the
option of the consumers
Time of Day Increase (+ )/ reduction (-) in energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
6. LT6 Water Supply Installations and Street Lights:
HUKERI RECS’s Proposal:
The existing and the proposed tariffs are given below:
LT-6(a) : Water Supply
Details Existing as per 2017 Tariff
Order
Proposed by HUKERI
RECS
Fixed charges per
Month
Rs.55/HP/month Rs.55/HP/month
Energy charges 425 paise/unit 500 paise/unit
LT-6 (b) : Public Lighting
Details Existing as per 2017 Tariff
Order
Proposed by HUKERI RECS
Fixed charges
per Month
Rs.70/KW/month Rs.70/KW/month
Energy charges
without LED bulbs
585 paise/unit 660 paise/unit
Energy charges
for LED /
Induction
485 paise/unit 560 paise/unit
Commission’s Decision:
The Commission approves the tariff for these categories as follows:
ToD Tariff
![Page 35: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/35.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 88
Tariff Approved by the Commission for LT-6 (a): Water supply
Details Approved Tariff
Fixed Charges per Month Rs.65/HP/month
Energy charges 440 paise/unit
Tariff Approved by the Commission for LT-6 (b): Public Lighting
Details Approved Tariff
Fixed charges per Month Rs.80 /KW/month
Energy charges 605 paise/unit
Energy charges for LED / Induction Lighting 505 paise/unit
Electric Vehicle Charging Stations (Newly Introduced Tariff)
As discussed earlier in this chapter, the Commission decides to introduce an
additional sub category of LT-6(c) under LT-6 tariff category for the supply of
power to Electric Vehicle Charging Stations under LT and HT supply.
The Commission approved tariff to this new sub category is as under:
Tariff Approved by the Commission for LT-6 (c)
Details Approved Tariff
Under LT Supply Fixed charges per KW Rs.50 /KW/month
Under HT Supply DC per KVA Rs.180 /KW/month
Energy charges per
KWH for both LT & HT)
485 paise/unit
7. LT 7- Temporary Supply & Permanent supply to Advertising Hoardings:
HUKERI RECS’s Proposal:
The existing rate and the proposed rate are given below:
Tariff Schedule LT-7(a)
Applicable to Temporary power Supply for all purposes.
a) Less than 67
HP:
Energy charge at 1000
paise per unit subject
Energy charge at 1075 paise
per unit subject to a weekly
Details Existing as per 2017
Tariff Order
Proposed by HUKERI RECS
![Page 36: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/36.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 89
to a weekly minimum
of Rs.190 per KW of
the sanctioned load.
minimum of Rs.190 per KW of
the sanctioned load.
TARIFF SCHEDULE LT-7(b)
Applicable to power supply to Hoardings & Advertisement boards
on Permanent connection basis.
a) Less than 67
HP:
Fixed Charge Rs.60
per KW/ month of the
sanctioned load
NA
Energy charge at 1000
paise per unit
Commission’s decision
As decided in the previous Tariff Order, the tariff specified for installations with
sanctioned load / contract demand above 67 HP shall continue to be covered
under the HT temporary tariff category under HT5.
With this, the Commission decides to approve the tariff for LT-7 category as
follows:
TARIFF SCHEDULE LT-7(a)
Applicable to Temporary Power Supply for all purposes.
LT 7(a) Details Approved Tariff
Temporary Power
Supply for all
purposes.
Less than 67 HP:
Energy charges at 1030 paise / unit
subject to a weekly minimum of Rs.200
per KW of the sanctioned load.
Details Existing as per 2017
Tariff Order
Proposed by HUKERI RECS
![Page 37: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/37.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 90
TARIFF SCHEDULE LT-7(b)
Applicable to Hoardings & Advertisement boards, Bus Shelters with Advertising
Boards, Private Advertising Posts / Sign boards in the interest of public such as
Police Canopy Direction boards, and other sign boards sponsored by Private
Advertising Agencies / firms on permanent connection basis.
LT 7(b) Details Approved Tariff
Power supply on
permanent
connection basis
Less than 67 HP:
Fixed Charges at Rs.75 per KW / month
Energy charges at 1030 paise / unit
H.T. Categories:
Time of Day Tariff (ToD)
The Commission decides to continue the mandatory Time of Day Tariff for
HT2 (a), HT-2(b) and HT2(c) consumers with a contract demand of 500 KVA and
above. Further, the optional ToD will continue as existing for HT2 (a), HT-2(b) and
HT2 (c) consumers with contract demand of less than 500 KVA. The details of ToD
tariff are indicated under the respective tariff category.
As discussed earlier in this Chapter, the existing demand charges levied on the
maximum demand recorded during the month or 75% of CD whichever is higher
has been revised to maximum demand recorded during the month or 85% of CD
whichever is higher.
8. HT1- Water Supply & Sewerage
HUKERI RECS’s Proposal:
The existing and proposed tariff are as given below:
![Page 38: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/38.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 91
The Existing and the proposed tariff – HT-1 Water Supply and Sewerage
Installations
Details Existing tariff as per 2017
Tariff Order
Proposed Tariffs by
HUKERI RECS
Demand
charges
Rs.200 / kVA of billing
demand / month
Rs.200 / kVA for billing
demand / month
Energy
charges
485 paise per unit 560 paise per unit
Existing ToD tariff to HT-1 tariff to Water Supply & Sewerage installations at the
option of the consumer
Time of Day Increase (+ )/ reduction (-) in energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
Proposed ToD Tariff to HT-1 category:
Time of day Increase (+) / reduction (-) in the energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
Commission’s decision:
As discussed earlier in this Chapter, the Commission approves the tariff for HT 1
Water Supply & Sewerage category as below:
Details Approved Tariff for HT 1
Demand charges Rs.200 / kVA of billing demand / month
Energy charges 500 paise/ unit
![Page 39: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/39.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 92
As discussed earlier in this Chapter, the approved ToD tariff to HT-1 tariff to Water
Supply & Sewerage installations at the option of the consumer is as follows
06.00 Hrs. to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 Hrs (+)100 paise per unit
22.00 Hrs to 06.00 Hrs next day (-) 100 paise per unit
9. HT2 (a) – HT Industries & HT 2(b) – HT Commercial
HUKERI RECS’s Proposal:
The existing and proposed tariff are as given below:
Details Existing tariff as per Tariff
Order 2017
Proposed Tariff by
HUKERI RECS
Demand charges Rs. 200 / kVA of billing
demand / month
Rs. 200 / kVA of
billing demand /
month
Energy charges
(i) For the first one lakh
units
(ii) For the balance units
660 paise per unit
680 paise per unit
735 paise per unit
755 paise per unit
Railway traction and Effluent Plants under HT2 (a).
Details Existing tariff as per
Tariff order 2017
Tariff Proposed by HUKERI
RECS
Demand
charges
Rs. 210 / kVA at
billing demand /
month
Rs. 210 / kVA of billing
demand / month
Energy charges 620 paise per unit for
all the units
695 paise per unit for all
the units
Time of day Increase (+) / reduction (-) in the energy
charges over the normal tariff applicable
HT – 2 (a) HT Industries
Applicable to all areas of HUKERI RECS
![Page 40: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/40.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 93
Existing ToD Tariff for HT-2(a)
Time of Day Increase (+ )/ reduction (-) in energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
Proposed ToD Tariff for HT-2(a)
Time of day Increase (+) / reduction (-) in the energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
Commission’s Decision:
The Commission in its previous Tariff Order has allowed in respect of Industries
availing HT power supply under HT2(a) tariff schedule, for the supply availed for
Effluent Treatment Plant situated within the premises by fixing a separate
sub-meter, a rebate of 50 paise per unit of electricity consumed by such Effluent
Treatment Plant in the applicable tariff schedule without reduction in the demand
of the main HT supply.
The Commission takes note of the request made by the consumer of other
categories to extend the same concession as given in the energy charges to the
Effluent Treatment Plant situated with in the industrial premises. The Commission
having considered the environmental and the social benefit from the Effluent
Treatment Plants and Drainage Water Treatment plants owned other than by local
bodies situated within the premises of the installation, decides to allow billing of
the electricity consumed by the Effluent Treatment Plants and Drainage Water
![Page 41: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/41.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 94
Treatment plants from the main meter or by sub-meter, at the same respective tariff
schedule as applicable to the installations for which the power supply is availed.
The Commission notes the request made by the ESCOMs for billing the power
supply to Solid Waste processing plants under HT industrial category. The
Commission by considering the Environmental and Social benefits in processing of
the solid waste by such plants, decides to approve billing by ESCOMs of the power
supply arranged to such plants under HT industrial tariff.
Approved Tariff for HT – 2 (a):
As discussed earlier in this chapter, the Commission approves the tariff for HT 2(a)
category as below:
i) Approved Tariff for HT2(a)
Applicable to all areas under HUKERI RECS
Details Tariff approved by the Commission
Demand charges Rs.200 / kVA of billing demand / month
Energy charges
For the first one lakh units 675 paise/ unit
For the balance units 700 paise/ unit
As discussed earlier in this Chapter, the approved ToD tariff to HT2(a)(i) & (ii)
tariff.
06.00 Hrs. to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 Hrs (+)100 paise per unit
22.00 Hrs to 06.00 Hrs (-)100 paise per unit
Note: ToD Tariff is not applicable to Railway Traction installations.
Time of day Increase (+) / reduction (-) in the energy
charges over the normal tariff applicable
![Page 42: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/42.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 95
iii) Railway Traction under both HT2(a)(i) & HT 2(a)(ii)
Details Tariff approved by the Commission
Demand charges Rs. 210 / kVA of billing demand / month
Energy charges 600 paise / unit for all the units
The Commission, by considering the concessional tariff extended to the Railway
traction, decides not to extend the new special incentive scheme approved in this
Tariff Order and the ToD tariff to the installations of Railway traction.
iv) Effluent Treatment Plants independently serviced outside the premises of any
installation under both HT2(a)(i) & HT 2(a)(ii)
Details Tariff approved by the Commission
Demand charges Rs. 210 / kVA of billing demand / month
Energy charges 640 paise / unit for all the units
Note: The ToD tariff is applicable to these installations, if the New Special
Incentive Scheme is not opted.
10. HT-2 (b) HT Commercial
HUKERI RECS’s Proposal:
The existing and proposed tariff are as given below:
Existing and proposed tariff HT – 2 (b) HT Commercial
Applicable to all areas of HUKERI RECS
Details Existing tariff as per
Tariff Order 2017
Tariff Proposed by
HUKERI RECS
Demand charges Rs.220 / kVA of billing
demand / month
Rs.220 / kVA of billing
demand / month
Energy charges
(i) For the first two lakh units 825 paise per unit 900 paise per unit
(ii)For the balance units 835 paise per unit 910 paise per unit
![Page 43: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/43.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 96
xisting ToD Tariff for HT-2(b)
Time of Day Increase (+ )/ reduction (-) in energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
Proposed ToD Tariff for HT-2(b)
Time of day Increase (+) / reduction (-) in the energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
Commission’s Decision
The Commission notes the issue raised by the consumer of Diagnostic centres
and their request to classify under HT-2(c)(ii) category. The Commission
examined the issue in detail and decided to classify the HT power supply to
Diagnostic centres running on commercial lines under HT-2(b) category.
As discussed earlier in this chapter, the Commission approves the following tariff
for HT 2 (b) consumers:
Approved tariff for HT – 2 (b) - HT Commercial - Applicable to all areas of HUKERI
RECS
Details Tariff approved by the Commission
Demand charges Rs.220 / kVA of billing demand / month
Energy charges
(i) For the first two lakh units 845 paise per unit
(ii) For the balance units 855 paise per unit
Note: The above tariff under HT2 (b) is not applicable for construction of new industries.
Such power supply shall be availed only under the temporary category HT5.
![Page 44: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/44.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 97
Approved ToD Tariff for HT-2(b)
06.00 Hrs. to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 Hrs (+)100 paise per unit
22.00 Hrs to 06.00 Hrs next day (-)100 paise per unit
11. HT – 2 (c) – Applicable to Hospitals and Educational Institutions:
The existing and proposed tariff are given below:
Existing and proposed tariff for HT – 2 (c) (i)
Applicable to Government Hospitals & Hospitals run by Charitable Institutions & ESI
Hospitals
and
Universities, Educational Institutions belonging to Government, Local Bodies and Aided
Institutions and Hostels of all Educational Institutions
Details Existing tariff as per
Tariff Order 2017
Tariff Proposed by
HUKERI RECS
Demand charges Rs.200 / kVA of billing
demand / month
Rs.200 / kVA of billing
demand / month
Energy charges
(i) For the first one lakh units 640 paise per unit 715 paise per unit
(ii) For the balance units 680 paise per unit 755 paise per unit
Existing and proposed tariff for HT – 2 (c) (ii) –
Applicable to Hospitals and Educational Institutions other than those covered under HT2(c) (i)
Details Existing tariff as per
Tariff Order 2017
Tariff Proposed by
HUKERI RECS
Demand charges Rs. 200 / kVA of billing
demand / month
Rs. 200 / kVA of billing
demand / month
Energy charges
(i) For the first one lakh units 740 paise per unit 815 paise per unit
(ii) For the balance units 780 paise per unit 855 paise per unit
Time of day Increase (+) / reduction (-) in the energy
charges over the normal tariff applicable
![Page 45: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/45.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 98
Existing ToD Tariff for HT-2(c)(i) & (ii)
Time of Day Increase (+ )/ reduction (-) in energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
Proposed ToD Tariff for HT-2 HT-2(c)(i) & (ii)
Time of day Increase (+) / reduction (-) in the energy
charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
Commission’s Decision:
The Commission approves the following tariff for HT2(c) consumers.
Approved tariff for HT – 2 (c) (i)
Applicable to Government Hospitals, Hospitals run by Charitable Institutions, ESI
Hospitals,
Universities and Educational Institutions belonging to Government& Local Bodies, Aided
Educational Institutions and Hostels of all Educational Institutions
Details Approved Tariff
Demand charges Rs.200/ kVA of billing demand / month
Energy charges
(i) For the first one lakh units 660 paise per unit
(ii) For the balance units 700 paise per unit
![Page 46: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/46.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 99
Approved tariff for HT – 2 (c) (ii)
Applicable to Hospitals/Educational Institutions other than those covered under HT2(c) (i)
Details Approved Tariff
Demand charges Rs.200 / kVA of billing demand / month
Energy charges
(i) For the first one lakh units 760 paise per unit
(ii) For the balance units 800 paise per unit
As discussed earlier in this Chapter approved ToD for Tariff to HT-2(c) (i) & (ii)
06.00 Hrs. to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 Hrs (+)100 paise per unit
22.00 Hrs to 06.00 Hrs next day (-)100 paise per unit
12. HT-3(a) Lift Irrigation Schemes under Government Departments / Government
owned Corporations/ Lift Irrigation Schemes under Pvt ./Societies:
The existing and proposed tariff are given below:
Existing and proposed tariff for HT – 3 (a) –Lift Irrigation Schemes
HT 3(a) (i) Applicable to LI Schemes under Government Departments /
Government owned Corporations
Details Existing charges as per Tariff
Order 2017
Proposed charges by
HUKERI RECS
Energy
charges/
Minimum
charges
225 paise / unit
Subject to an annual minimum
of Rs.1240 per HP / annum
300 paise / unit
Subject to an annual
minimum of Rs. 1240
per HP / annum
HT 3(a) (ii) Applicable to Pvt. LI Schemes and Lift Irrigation Societies:
Fed through Express / Urban feeders
Details Existing Tariff as per Tariff
Order 2017
Proposed by HUKERI
RECS
Time of day Increase (+) / reduction (-) in the energy
charges over the normal tariff applicable
![Page 47: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/47.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 100
Fixed charges Rs. 50 / HP / Month of
sanctioned load
Rs.50 / HP / Month of
sanctioned load
Energy charges 225 paise / unit 300 paise / unit
HT 3(a) (iii) Applicable to Pvt. LI Schemes and Lift Irrigation Societies:
other than those covered under HT-3 (a)(ii)
Details Existing Tariff as per Tariff
Order 2017
Proposed by HUKERI
RECS
Fixed charges Rs.30 / HP / Month of
sanctioned load
Rs.30 / HP / Month of
sanctioned load
Energy charges 225 paise / unit 300 paise / unit
Commission’s Decision:
The Commission approves the following tariff for HT3(a) consumers:
Approved tariff for HT 3 (a) (i)
Energy charges /
Minimum charges
250 paise/ unit subject to an annual
minimum of Rs.1360 per HP / annum
Approved tariff for HT 3 (a) (ii)
Applicable to Private LI Schemes and Lift Irrigation Societies fed through express
/ urban feeders
Fixed charges Rs.60 / HP / Month of sanctioned load
Energy charges 250 paise / unit
Approved tariff for HT 3 (a) (iii)
Applicable to Private LI Schemes and Lift Irrigation Societies other than
those covered under HT 3 (a) (ii)
Fixed charges Rs.40 / HP / Month of sanctioned load
Energy charges 250 paise / unit
13. HT3 (b) Irrigation & Agricultural Farms, Government Horticulture farms, Private
Horticulture Nurseries, Coffee, Tea, Coconut & Arecanut Plantations:
Applicable to LI schemes under Govt. Dept. / Govt. owned Corporations
![Page 48: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/48.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 101
HUKERI RECS’s Proposal:
The existing and the proposed tariff are given below:
HT3 (b)- Irrigation & Agricultural Farms, Government Horticulture farms, Private
Horticulture Nurseries, Coffee, Tea, Coconut & Arecanut Plantations:
Details Existing Tariff Order 2017 Proposed tariff by HUKERI
RECS
Energy charges /
minimum
charges
425 paise / unit subject to
an annual minimum of
Rs.1240 per HP of
sanctioned load
500 paise / unit subject to
an annual minimum of
Rs.1240 per HP of
sanctioned load
Commission’s Decision
The Commission approves the tariff for this category as indicated below:
Approved Tariff
HT3 (b)- Irrigation & Agricultural Farms, Government Horticulture farms, Private
Horticulture Nurseries, Coffee, Tea, Rubber, Coconut & Arecanut Plantations:
Details Approved Tariff
Energy charges /
minimum charges
450 paise / unit subject to an annual minimum of
Rs.1360 per HP of sanctioned load
14. HT4- Residential Apartments/ Colonies:
HUKERI RECS’s Proposal:
The existing and the proposed tariff for this category are given below:
Existing and proposed tariff for HT – 4 - Residential Apartments/ Colonies
HT – 4 Applicable to all areas.
Details Existing Tariff Order 2017 Tariff Proposed by
HUKERI RECS
Demand charges Rs.120 / kVA of billing
demand
Rs.120 / kVA of billing
demand
Energy charges 620 paise per unit 695 paise/ unit
![Page 49: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/49.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 102
Commission’s Decision
As discussed earlier in this chapter, the Commission approves the tariff for this
category as indicated below:
Approved tariff
HT – 4 Residential Apartments/ Colonies Applicable to all areas
Demand charges Rs.120 / kVA of billing demand
Energy charges 640 paise/ unit
15. TARIFF SCHEDULE HT-5
HUKERI RECS’s Proposal:
The existing and the proposed tariffs are given below:
HT – 5 – Temporary supply
67 HP and above: Existing Proposed
Fixed charges /
Demand Charges
Rs.240/HP/month for the
entire sanction load /
contract demand
Rs.240/HP/month for the
entire sanction load /
contract demand
Energy Charge 1000 paise / unit 1075 paise / unit
Commission’s Views/Decisions:
TARIFF SCHEDULE HT-5
(i) As approved in the Commission’s Tariff Order dated 6th May, 2013, this
Tariff is applicable to 67 HP and above hoardings and advertisement
boards and construction power for industries excluding those categories
of consumers covered under HT2(b) Tariff schedule availing power supply
for construction power for irrigation and power projects and is also
applicable to power supply availed on temporary basis with the contract
demand of 67 HP and above of all categories.
![Page 50: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/50.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 103
Approved Tariff for HT – 5 – Temporary supply
67 HP and above: Approved Tariff
Fixed Charges /
Demand Charges
Rs.250 /HP/month for the entire sanction load /
contract demand
Energy Charges 1030 paise / unit
The Approved Tariff schedule for FY19 is enclosed in Annexure – IV of this Order.
4.6 Wheeling and Banking Charges:
HRECS in their Tariff Petition had not furnished the details of wheeling charges &
cross subsidy surcharge applicable for FY-19. Hence, the Commission had
directed HRECs to submit the same.
Hukeri RECS in its reply has stated that there is no consumer who are eligible or
willing to wheel electricity at 11 KV level and therefore it would be unnecessary
to determine the wheeling charges. It is further stated that the Hon’ble
Commission is determining the wheeling charges & cross subsidy surcharge on
the basis of the same formula which are applied in HESCOM for segregating the
ARR between distribution business and retail supply business. Therefore, HRECS
has submitted that the same may be followed for FY19 also.
The Commission has noted the replies furnished by HRECS. Since HRECS has not
proposed wheeling charges and has also not provided the segregation of cost
between distribution and retail supply business, the Commission has segregated
the ARR between distribution business and retail supply business in the same
proportion as in HESCOM. Further, the allocation of loss is based on the energy
flow diagram furnished for FY19 by HRECS. As such the wheeling charges for
HRECS is as indicated below:
4.6.1 Wheeling within HUKERI RECS Area:
The wheeling charges to each voltage level are worked out as under:
![Page 51: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/51.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 104
Paise/unit
HT-network 22.21
LT-network 51.83
In addition to the above, the following technical losses are applicable to all
open access/wheeling transactions:
Loss allocation % loss
HT 6.66
LT 6.71
Note: Total loss is allocated to HT, LT & Commercial loss based on energy flow diagram furnished by HUKERI
RECS.
The actual wheeling charges payable (after rounding off) will depend upon the
point of injection & point of drawl as under:
Injection point
Drawl point
HT LT
HT 22(6.66%) 74(13.37%)
LT 74(13.37%) 52(6.71%)
Note: Figures in brackets are applicable losses
The wheeling charges as determined above are applicable to all the open
access or wheeling transactions for using the HRECS network, subject to
paragraphs 4.6.3 & 4.6.4 below with respect to renewable sources of energy.
4.6.2 WHEELING OF ENERGY USING TRANSMISSION NETWORK OR NETWORK OF MORE
THAN ONE LICENSEE
In case the wheeling of energy [other than RE sources wheeling to consumers
within the State] involves usage of Transmission network or network of more than
one licensee, the charges shall be as indicated below:
![Page 52: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/52.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 105
i. If only transmission network is used, transmission charges determined by the
Commission shall be payable to the Transmission Licensee.
ii. If the Transmission network and the ESCOMs’ network are both used, Transmission
Charges shall be payable to the Transmission Licensee.
Wheeling Charges of the ESCOM where the power is drawn shall be shared
equally among the ESCOMs whose networks are used.
Illustration:
If a transaction involves both transmission network and HUKERI RECS’s network
and 100 units are injected, then at the drawal point the consumer is entitled for
83.96 units, after accounting for Transmission loss of 3.08% & HUKERI RECS’s
distribution loss(Technical) of 13.37%.
The Transmission charge in cash as determined in the Transmission Tariff Order
shall be payable to KPTCL & Wheeling charge of 74 paise per unit shall be
payable to HUKERI RECS. In case, more than one ESCOM is involved, the above
74 paise shall be shared by all the ESCOMs involved.
iii. If distribution licensees’ network only is used, the Wheeling Charges of the
distribution licensee where the power is drawn is payable and it shall be shared
equally among the distribution licensees whose networks are used.
Illustration:
If a transaction involves injection to BESCOM’s network & drawal at HUKERI
RECS’s network, and 100 units are injected, then at the drawal point the
consumer is entitled for 86.63 units, after accounting HUKERI RECS’s loss of 13.37%.
The Wheeling charges of 74 paise per unit applicable to HUKERI RECS shall be
equally shared between HUKERI RECS & BESCOM.
4.6.3 CHARGES FOR WHEELING OF ENERGY BY RE SOURCES (NON-REC ROUTE) TO
CONSUMERS IN THE STATE
![Page 53: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/53.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 106
The separate orders issued by the Commission from time to time in the matter of
wheeling and banking charges for RE sources (non-REC route), wheeling energy
to consumers within the State shall be applicable.
4.6.4 Charges for wheeling energy by RE sources wheeling energy from the State to a
consumer/others outside the state and for those opting for Renewable Energy
Certificate [REC]
In case the renewable energy is wheeled from the State to a consumer or others
outside the State, the normal wheeling charges as determined in paras 4.6.1 and
4.6.2 of this order shall be applicable. For Captive RE generators including solar
power projects opting for RECs, the wheeling charges as specified in the Orders
issued by the Commission from time to time shall be applicable.
4.6.5 BANKING CHARGES AND ADDITIONAL SURCHARGE
These charges as specified in the Orders issued by the Commission from time to
time shall be applicable.
4.6.6 Cross Subsidy Surcharge (CSS):
The Commission in its preliminary observations had directed HRECS to furnish CSS
applicable for FY-19 along with working details.
In response to the observations made by the Commission, HUKERI RECS has
stated that there are no consumers who are eligible or willing to wheel electricity
at 11 kV level and therefore it would be unnecessary to determine the CSS.
Further, it is stated that the Commission is determining wheeling charges & cross
subsidy surcharge on the basis of same formula which are applied in HESCOM for
segregating the ARR between distribution business and retail supply business.
Therefore, HRECS has submitted that the same may kindly be followed for FY-19
also.
![Page 54: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/54.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 107
As the Commission has determined a common cross subsidy surcharge for all the
ESCOMs, the same shall be applicable to Hukeri RECS also. As such the
applicable cross subsidy surcharge is indicated below:
Paise/unit
Particulars
66 kV
&
above
HT level-11
kV/33kV
HT-1
Water Supply 114 104
HT-2a
Industries 169 169
HT-2b
Commercial 204 204
HT-2 (C)(i) 154 154
HT-2 (C)(ii) 174 174
HT3 (a)(i)
Lift Irrigation 0
0
HT3 (a)(ii)
Lift Irrigation 0
0
HT3 (a)(iii)
Lift Irrigation 0
0
HT3 (b)
Irrigation &
Agricultural Farms
26
0
HT-4
Residential
Apartments
137 137
HT5
Temporary 307 307
![Page 55: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/55.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 108
The cross subsidy surcharge determined in this Order shall be applicable to all open
access/wheeling transactions in the area coming under HRECS. However, the above
CSS shall not be applicable to captive generating plant for carrying electricity to the
destination of his own use and for those renewable energy generators who have been
exempted from CSS by the specific Orders of the Commission.
The Commission directs the Licensees to account the transactions under open access
separately. Further, the Commission directs the Licensees to carry forward the amount
realized under Open Access/wheeling to the next ERC, as it is an additional income to
the Licensees.
4.7 Other Issues:
4.7.1 Tariff for Green Power:
In order to encourage generation and use of green power in the State, the
Commission decides to continue the existing Green Tariff of 50 paise per unit as
the additional tariff over and above the normal tariff to be paid by HT-
consumers, who opt for supply of green power from out of the renewable energy
procured by distribution utilities over and above their Renewable Purchase
Obligation (RPO).
4.8 Other tariff related issues:
i) Rebate for use of Solar Water Heater:
The Distribution licensees have requested the Commission to continue the
Solar water heater rebate to consumers, whereas the consumers have
requested to increase the Solar water heater Rebate. Since the use of Solar
Water Heaters is advantageous to both the ESCOMs /HRECS and the
consumers, the Commission decides to retain the existing rebate of 50 paise
per unit subject to a maximum of Rs.50 per installation per month for use of
solar water heaters.
![Page 56: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/56.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 109
ii) Prompt payment incentive:
The Commission had approved a prompt payment incentive at the rate of
0.25% of the bills amount (i) in all cases of payment through ECS; and (ii) in the
case of monthly bill exceeding Rs.1,00,000/- (Rs.one lakh), where payment is
made 10 days in advance of due date and (iii) advance payment of
exceeding Rs.1000 made by the consumers towards monthly bills. The
Commission decides to continue the same.
iii) Relief to Sick Industries:
The Government of Karnataka has extended certain reliefs for
revival/rehabilitation of sick industries under the New Industrial Policy 2001-06
vide G.O. No. CI 167 SPI 2001, dated 30.06.2001. Further, the Government of
Karnataka has issued G.O No.CI2 BIF 2010, dated 21.10.2010. The
Commission, in its Tariff Order 2002, had accorded approval for
implementation of reliefs to the sick industries as per the Government policy
and the same was continued in the subsequent Tariff Orders. However, in
view of issue of the G.O No.CI2 BIF 2010, dated 21.10.2010, the Commission
has accorded approval to the ESCOMs/Hukeri RECS for implementation of
the reliefs extended to sick industrial units for their revival / rehabilitation on
the basis of the orders issued by the Commissioner for Industrial Development
and Director of Industries & Commerce, Government of Karnataka / BIFR.
iv) Power Factor(PF):
The Commission in its previous order had retained the PF threshold limit and
surcharge, both for LT and HT installations at the levels existing as in the Tariff
Order 2005. The Commission decides to continue the same in the present
order as indicated below:
LT Category (covered under LT-3, LT-4, LT-5 & LT-6 where motive power is
involved): 0.85
HT Category: 0.90
![Page 57: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/57.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 110
v) Rounding off of KW / HP:
In its Tariff Order 2005, the Commission had approved rounding off of fractions
of KW / HP to the nearest quarter KW / HP for the purpose of billing and the
minimum billing being for 1 KW / 1HP in respect of all the categories of LT
installations including IP sets. This shall continue to be followed. In the case of
street light installations, fractions of KW shall be rounded off to the nearest
quarter KW for the purpose of billing and the minimum billing shall be for a
quarter KW.
vi) Interest on delayed payment of bills by consumers:
The Commission, in its previous Order had approved collection of interest on
delayed payment of bills at 12% per annum. The Commission decides to
continue the same in this Order also.
vii) Security Deposit (3 MMD/ 2 MMD):
The Commission had issued the KERC (Security Deposit) Regulations, 2007 on
01.10.2007and the same has been notified in the Official Gazette on
11.10.2007. The payment of security deposit shall be regulated accordingly,
pending orders of the Hon’ble High Court in WP No.18215/2007.
viii) Mode of Payment by consumers:
The Commission, in its previous Tariff Order had approved payment of
electricity bills in cash/cheque/DD of amounts up to and inclusive of
Rs. 10,000/- and payment of amounts exceeding Rs.10,000 to be made only
through cheque. The consumers can also make payment of power bills
through Electronic Clearing System(ECS)/ Credit card/ online E-payment up
to the limit prescribed by the RBI, and the collection of power supply bills
above Rupees One lakhs through RTGS / NEFT at the option of the consumer.
![Page 58: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/58.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 111
ESCOMs in their applications have requested the Commission, to also it to
allow to collect the power supply bills through various new modes of digital
payments including by Debit / Credit Cards, BBPS and allow to bear the
charges incurred on such transaction and pass on to the consumer in the
retail supply tariff. The Commission as discussed earlier in this Chapter, in order
to encourage the consumers to opt for digital payments in line with the
direction of the MOP, GoI decides to allow ESCOMs to collect payment of
monthly power supply bill through Electronic clearing system (ECS)/ Debit /
Credit cards / RTGS/ NEFT/ Net Banking through ESCOMs / Bank/ Bangalore
one and Karnataka One websites, on-line E-Payment / Digital mode of
payments in line with the guidelines issued and the payment up to the limit
prescribed by the RBI wherever such facility is provided by the Licensee and
allow to incur and claim the expenditure on such transaction in the ARR as
approved in pre-paras. However, the Commission decides to allow Hukeri
RECS to incur the expenditure on the payment for power supply bills received
through Debit / Credit Cards having demand upto Rs.2000/- only.
4.9 Cross Subsidy Levels for FY19:
The Hon’ble Appellate Tribunal for Electricity (ATE), in its Order dated
8th October, 2014, in Appeal No.42 of 2014, has directed the Commission to
clearly indicate the variation of anticipated category-wise average revenue
realization with respect to overall average cost of supply in order to implement
the requirement of the Tariff Policy that tariffs are within ±20% of the average
cost of supply, in the tariff orders being passed in the future. It has further
directed the Commission to also indicate category-wise cross subsidy with
reference to voltage-wise cost of supply so as to show the cross subsidies
transparently.
In the light of the above directions, the variations of the anticipated category-
wise average realization with respect to the overall average cost of supply
and also with respect to the voltage-wise cost of supply of HRECS and the
cross subsidy thereon, is Indicated in ANNEXURE- III of this Order. It is the
![Page 59: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/59.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 112
Commission’s endeavour to reduce the cross subsidies gradually as per the
Tariff policy.
4.10 Effect of Revised Tariff:
As per the KERC (Tariff) Regulations 2000, read with the MYT Regulations 2006,
the Hukeri RECS has to file their applications for ERC/Tariff before 120 days of
the close of each financial year in the control period. The Commission
observes that the ESCOMs including Hukeri RECS have filed their applications
for revision of tariff on 30th November, 2017. As the tariff revision is effective
from 1st April, 2018 onwards, the Hukeri RECS would be recovering revenue as
per the revised tariff for eleven months of the current Financial Year (except in
case where the billing cycle is lesser than a month).
A statement indicating the proposed revenue and approved revenue is
enclosed vide Annexure-III and detailed tariff schedule is enclosed vide
Annexure-IV.
4.11 Summary of the Tariff Order:
The Commission has approved for Hukeri RECS an ARR of Rs.17678.60 lakhs for
FY19, which includes the deficit for FY17 of Rs.2560.68 Lakhs with a net gap in
revenue of Rs.927.50 Lakhs as against HRECS’s proposed ARR of Rs.21228.26
lakhs.
The Commission has allowed recovery of the entire gap in revenue with
additional revenue of Rs.927.50 Lakhs on Tariff Revision as against the
additional revenue of Rs.2316.80 Lakhs proposed by HRECS for FY19.
HRECS in its filing dated 30.11.2017 had proposed an increase of 75 paise per
unit for all categories of consumers resulting in average increase in retail
supply tariff by 12.25%. The Commission has approved an average increase of
33paise per unit. The average increase in retail supply tariff of all the
consumers for FY19 is 5.54%.
![Page 60: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/60.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 113
The Commission has allowed recovery of additional revenue, partly by
increase in fixed charges ranging from Rs.5 per KW/HP/KVA to Rs.22 per
KW/HP/KVA.
The Commission has allowed recovery of additional revenue, partly by
increase in the energy charges in the range of 15 paise per unit to 30 paise
per unit.
The increase in the energy charges for domestic category up to 30 units is
Rs.20 paise per unit and 25 paise per unit for the consumption above 30 units
The increase in the LT industries category is 20 paise per unit and for other
categories, the increase is in the range of 15 paise per unit to 30 paise per
unit.
In order to increase the sales under HT industry, HT commercial and HT
Hospital and Educational Institutions category, the increase made in energy
charges is 20 paise per unit.
Time of the day tariff which was made mandatory in the previous Tariff Orders
for installations under HT2 (a), HT2 (b) and HT2(c) with contract demand of
500KVA and above with the inclusion of morning peak period from 06.00 Hrs to
10.00 Hrs is continued in this Order except Railway Traction Installation.
The Commission in order to boost the energy sales and to attract the
consumers to consume power from Hukeri RECS has decided to introduce
Special Incentive Scheme to HT category, as follows:
The Commission has decided to offer Special Incentive of Rs.2/- per
unit as incentive for the energy consumption made during night hours
from 22.00 Hours to 6.00 Hours (Next Day) off-peak period, to those HT
consumer who opt for special incentive scheme.
For the consumption between 10.00Hrs to 18.00Hrs over and above
the base consumption of FY18, a reduction of Rs.1/- per unit is allowed
![Page 61: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/61.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 114
as special incentive, to those HT consumer who opt for the special
incentive scheme.
The Commission, has allowed concessional tariff of Rs.5.00 per unit to the
BMRCL.
The Commission, has allowed concessional tariff of Rs.6.00 per unit to the
Railway Traction installations.
The Effluent Treatment Plant and Drainage Water Treatment Plants installed
within the premises of the consumer’s installations by drawing power from the
main meter or through sub-meter shall be billed at the respective tariff
category for which the power supply is availed for the installation.
The Commission by considering the environmental and social benefits in
processing of the Solid Waste has decided to bill the power supply arranged
to Solid Waste Processing Plant under LT/HT Industrial Category.
The Commission has introduced new sub-category of LT-6(c) under LT -6 Tariff
Schedule for the power supply arranged to the Electric Vehicle Charging
Stations, at reduced rates.
Green tariff of additional 50 paise per unit over and above the normal tariff,
which was introduced a few years ago for HT industries and HT commercial
consumers at their option, to promote purchase of renewable energy from
ESCOMs, is continued in this Order.
As in the previous Orders, the Commission has continued to provide a
separate fund for facilitating better Consumer Relations /Consumer
Education Programmes.
![Page 62: CHAPTER 4 - CHAPTER-4.pdfBESCOM has informed that, it has already mandated all HT consumers to pay through online and requested the Commission to approve the On-line Payment through](https://reader033.vdocuments.us/reader033/viewer/2022052501/607fde9b3662f7712c5933c8/html5/thumbnails/62.jpg)
Karnataka Electricity Regulatory Commission Tariff Order 2018 HUKERI
RECS
Chapter – 4 : Determination of Tariff for FY19 Page 115
The Commission, as decided in the previous tariff Order, has decided to
continue to impose penalty upto Rs.one lakh per subdivision on Hukeri RECS
if it fail to conduct Consumer Interaction Meetings at least once in three
months and such penalty would be payable by the concerned officers of
the Hukeri RECS.
Order
1. In exercise of the powers conferred on the Commission under Sections 62
and 64 and other provisions of the Electricity Act, 2003, the Commission
hereby determines and notifies the retail supply tariff of Hukeri RECS for FY19
as stated in Chapter-6 of this Order.
2. The tariff determined in this Order shall be applicable to the electricity
consumed from the first meter reading date falling on or after 1st April 2018.
3. This Order is signed dated and issued by the Karnataka Electricity Regulatory
Commission at Bengaluru this day, the 14th May, 2018.
-Sd- -Sd- -Sd-
(M.K.Shankaralinge Gowda) (H.D. Arun Kumar) (D.B. Manival Raju)
Chairman Member Member