chapter 4 - appendix b
TRANSCRIPT
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 1
Chapter 4 - Appendix B Preliminary Screening Analysis
1
Option Description Candidate
Option
Coal Greenfield - IGCC
Coal Greenfield - IGCC with Pre-Combustion CCC
Coal Greenfield - Oxyfuel Coal with CCC
Coal Greenfield - Subcritical CFB
Coal Greenfield - Subcritical CFB with Amine-Based Post-
Combustion CCC
Coal Greenfield - Supercritical CFB
Coal Greenfield - USCPC
Coal Greenfield - USCPC with Amine-Based Post-Combustion CCC
Coal Meramec - Oxyfuel Coal with CCC
Coal Meramec - Subcritical CFB
Coal
Meramec - Ultra-Supercritical (USC) PC
Coal Meramec Repowering - CFB Boiler Replacement
Coal Meramec Repowering - Oxyfuel Coal Boiler Replacement
Coal Meramec Repowering - Unit 3 Boiler Replacement and STG
Rebuild
Coal Meramec Repowering - Unit 4 Boiler Replacement and STG
Rebuild
Coal Rush Island - Integrated Gasification Combined Cycle (IGCC)
Coal Rush Island - Oxyfuel Coal with CCC
Coal Rush Island - Subcritical CFB
Coal Rush Island - USCPC
Coal Efficiency Improvements to Existing Plants – Condenser Back-
pressure Reductions
Coal Efficiency Improvements to Existing Plants – Duct Draft
Reductions
Gas Goose Creek - Inlet Chilling SCCT Power Augmentation
Gas Goose Creek - Wetted Media SCCT Power Augmentation
Gas Greenfield - 2-on-1 501F CCCT
Gas Greenfield – 2-on-1 Wartsila 20V34SG Combined Cycle
Reciprocating Engine
Gas Greenfield - CCCT Amine-Based Post-Combustion CCC
Gas Greenfield – GE 7EA Cheng Cycle
Gas Greenfield - Molten Carbonate Fuel Cell
Gas Greenfield - Natural Gas Fueled Rankine Cycle
Gas Greenfield - Twelve Wartsila 20V34SG Simple Cycle
Reciprocating Engines
Gas Greenfield - Two 501F SCCTs (10% CF)
1 4 CSR 240-22.040(1)
Ameren Missouri Chapter 4 – Appendix B
Page 2 2011 Integrated Resource Plan
Option Description Candidate
Option
Gas Greenfield - Two 501F SCCTs (5% CF)
Gas Meramec - 2-on-1 501F CCCT
Gas Meramec Repowering - Unit 3 & Unit 4 STGs in a Shared CCCT
Conversion
Gas Meramec Repowering - Unit 3 & Unit 4 STGs in Separate CCCT
Conversions
Gas Meramec Repowering - Unit 3 Boiler NG Conversion
Gas Meramec Repowering - Unit 4 Boiler NG Conversion
Gas Meramec Repowering - Unit 4 STG in a 3-on-1 CCCT
Conversion
Gas Mexico - One GE LM6000 Sprint SCCT (10% CF)
Gas Mexico - One GE LM6000 Sprint SCCT (5% CF)
Gas Raccoon Creek - One GE 7EA SCCT (10% CF)
Gas Raccoon Creek - One GE 7EA SCCT (5% CF)
Gas Venice - 2-on-1 501F CCCT Conversion
4.1 Technology Characterization
Following the high-level fatal flaw analysis and elimination of several options, the list of
options to be evaluated as part of the second stage of the screening analysis was
reduced. Cost, performance, and operating characteristics were developed for each of
the remaining options in support of the Preliminary Screening with input from Ameren
Missouri and Black & Veatch‟s internal resources.
All performance and cost estimates were based on technologies fueled by the following
design fuels2:
Coal - All coal-fueled options are characterized such that they can operate on
either 100 percent Powder River Basin (PRB) coal or 100 percent Illinois Basin
No. 6 coal (or on any combination of the two). Thermal performance and
emissions estimates for the coal-fueled options assume 100 percent of the
feedstock is PRB coal. The air quality control systems (AQCS) for coal-fueled
options were selected to achieve target emissions limits for either coal assuming
representative fuel properties for Illinois Basin No. 6 coal.
Natural Gas - All gas-fueled options would be designed to operate on pipeline
quality natural gas, assumed to be 100 percent methane with 0.2 grain of sulfur
per 100 standard cubic feet, unless specified otherwise.
4.1.1 Capacity Ranges
Each of the generation technologies identified in the evaluated options list has sizing
limitations. The selection of practical size ranges for each of the technologies is based
2 4 CSR 240-22.040(1)(A)
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 3
on Ameren Missouri‟s ability to plan for and reasonably implement the technology.
Table 4.B.1 provides a summary of approximate size limitations for new generation
units3.
Table 4.B.1 Capacity Ranges
Full load thermal performance and emissions were developed for all evaluated options.
Thermal performance was estimated for a 95° F day and a 20° F day. Site conditions
were selected to reflect Ameren Missouri‟s service area. The following elevation and
ambient conditions were assumed for all performance estimates:
Elevation--500 feet above mean sea level.
20° F day ambient conditions:
o Dry bulb temperature--20° F.
o Relative humidity--60 percent.
95° F day ambient conditions:
o Dry bulb temperature--95° F.
o Relative humidity--60 percent.
Capacity and performance data for each evaluated option are presented in Table 4.B.12
and Table 4.B.13 under the Supporting Tables section.
4.1.2 Commercial Availability
The commercial status of each of the evaluated technologies was qualitatively
assessed. Technology maturity was assessed as either “mature” or “developing.”
3 4 CSR 240-22.040(1)(B)
Ameren Missouri Chapter 4 – Appendix B
Page 4 2011 Integrated Resource Plan
Technologies defined as mature were those that are proven and well established within
the electric power generation industry. Developing technologies consist of all other
technologies that may have limited experience, have been utilized in demonstration
projects, or consist of laboratory-tested conceptual designs.
4.1.3 Capital Cost Estimates
Screening level, overnight EPC capital cost estimates were developed for all evaluated
options and expressed in 2009 dollars. The values presented are reasonable for today‟s
market conditions, but, as demonstrated in recent years, the market is dynamic and
unpredictable. Power plant costs are subject to continued volatility and the estimates in
this report should be considered primarily for comparative purposes. The EPC costs
presented in this report were developed in a consistent manner and are reasonable
relative to one another.
The EPC estimates include costs for equipment and materials, construction labor,
engineering services, construction management, indirects, and other costs on an
overnight basis and are representative of “inside the fence” project scope. The
estimates were developed using Black & Veatch proprietary estimating templates and
experience. The overall capital cost estimates consist of three main components: EPC
Capital Cost, Owner‟s Cost (excluding AFUDC [Allowance for Funds Used during
Construction]), and Owner‟s AFUDC Cost. Capital costs for all evaluated options are
presented in Table 4.B.14 and Table 4.B.15.
An allowance has been made for Owner‟s costs (excluding AFUDC). Items included in
the Owner‟s costs include “outside the fence” physical assets, project development, and
project financing costs. These costs can vary significantly, depending upon technology
and unique project requirements. Black & Veatch has developed Owner‟s costs as a
percentage of the EPC capital cost as shown in the tables referenced above. Owner‟s
costs are assumed to include project development costs, interconnection costs, spare
parts and plant equipment, project management costs, plant startup/construction
support costs, taxes/advisory fees/legal costs, contingency, financing and
miscellaneous costs. Table 4.B.2 shows a more detailed explanation of potential
owner‟s costs.
For the purposes of characterizing all of the evaluated options, the AFUDC was
calculated by applying the Present Worth Discount Rate (PWDR) over half of the
construction duration, with the construction duration being defined as the time period
from Notice to Proceed (NTP) to Commercial Operation Date (COD).
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 5
Table 4.B.2 Potential Items for Owner’s Costs4
Project Development:
Site selection study
Land purchase/options/rezoning
Transmission/gas pipeline rights of way
Road modifications/upgrades
Demolition (if applicable)
Environmental permitting/offsets
Public relations/community development
Legal assistance
Utility Interconnections:
Natural gas service (if applicable)
Gas system upgrades (if applicable)
Electrical transmission
Supply water
Wastewater/sewer (if applicable)
Spare Parts and Plant Equipment:
Air quality control systems materials, supplies,
and parts
Acid gas treating materials, supplies and parts
Combustion turbine and steam turbine materials,
supplies, and parts
HRSG materials, supplies, and parts
Gasifier materials, supplies, and parts
Balance-of-plant equipment materials, supplies
and parts
Rolling stock
Plant furnishings and supplies
Operating spares
Owner’s Project Management:
Preparation of bid documents and selection of
contractor(s) and suppliers
Provision of project management
Performance of engineering due diligence
Provision of personnel for site construction
management
Plant Startup/Construction Support:
Owner‟s site mobilization
O&M staff training
Supply of trained operators to support equipment
testing and commissioning
Initial test fluids and lubricants
Initial inventory of chemicals/reagents
Consumables
Cost of fuel not recovered in power sales
Auxiliary power purchase
Construction all-risk insurance
Acceptance testing
Taxes/Advisory Fees/Legal:
Taxes
Market and environmental consultants
Owner‟s legal expenses:
• Power Purchase Agreement (PPA)
• Interconnect agreements
• Contracts--procurement & construction
• Property transfer
Owner’s Contingency:
Owner‟s uncertainty and costs pending final
negotiation:
• Unidentified project scope increases
• Unidentified project requirements
• Costs pending final agreement (e.g.,
interconnection contract costs)
Financing:
Development of financing sufficient to meet project
obligations or obtaining alternate sources of
funding
Financial advisor, lender‟s legal, market analyst,
and engineer
Interest during construction
Loan administration and commitment fees
Debt service reserve fund
Miscellaneous:
All costs for above-mentioned Contractor-excluded
items, if applicable
4 4 CSR 240-22.040(3); 4 CSR 240-22.040(6)
Ameren Missouri Chapter 4 – Appendix B
Page 6 2011 Integrated Resource Plan
4.1.4 Non-Fuel O&M Costs
Nonfuel O&M cost estimates were developed for each of the evaluated options. All
O&M cost estimates are presented in Table 4.B.14 and Table 4.B.15. First year O&M
costs (in 2009 $‟s) were estimated, and for the future years 3% escalation rate was
used.
The modes of dispatch used to establish maintenance intervals for many of the options
are as follows:
Baseload Dispatch Profiles – Excluding the IGCC options, all options evaluated at a
baseload dispatch mode were assumed to operate at full load at a capacity factor of 85
percent. An IGCC facility is not anticipated to be capable of operating at such a high
capacity factor because of the degree of process integration. All IGCC options were
assumed to operate at full load at a capacity factor of 80 percent. Options incorporating
Carbon Capture and Compression (CCC) were assumed to operate at the same
dispatch profile as their non-carbon capture counterparts.
Intermediate Load Dispatch Profiles – Two operating profiles were used for the
intermediate load technologies.
Profile 1 – Cycling Operation – Off Nights/Off Weekends: 6 months per year
operation at 5 days a week, 8 hours per day in 2x1 combined cycle mode, off-line
16 hours per day and on weekends. Shut down and laid up for 6 winter months
per year. Total full load operation of 1,043 hours per year and a capacity factor of
about 12 percent.
Profile 2 – Cycling Operation – Low Load Nights/Off Weekends: 6 months
per year at 5 days a week, 10 hours per day in 2x1 combined cycle mode, 14
hours per day in 1x1 combined cycle mode at minimum load on the steam
turbine, shut down on weekends. Shut down and laid up for 6 winter months per
year. This equates to a capacity factor of about 21 percent for the options
evaluated in this study.
Peaking Load Dispatch Profiles – All new unit combustion turbine options were
evaluated at a peaking dispatch mode, with capacity factors of 5 and 10 percent. It was
assumed that 90 starts were associated with a 5 percent capacity factor and 150 starts
with a 10 percent capacity factor.
Power augmentation and reciprocating engines operating in simple cycle were
evaluated at a 5 percent capacity factor.
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 7
4.1.5 Scheduled and Forced Outages
Scheduled maintenance intervals were obtained from original equipment manufacturers
(OEMs) or estimated on the basis of Black & Veatch experience for each of the
technologies. Where information was not available, maintenance intervals were
estimated using data gathered from comparable technologies. These scheduled
maintenance patterns were assumed to be the same for technologies employing CCC
equipment. The maintenance patterns are presented in Table 4.B.3.
Table 4.B.3 Scheduled Maintenance Outage Patterns5
Notes:
(1) 4 week boiler outage every 18 months and a 6 week STG major outage every 6 years.
(2) 3 week boiler outage every 12 months and a 6 week STG major outage every 6 years.
(3) Alternating 1 week and 3 week combined cycle outages yearly, alternating 3 week and 2 week
gasification outages yearly and a 4 week combined cycle outage every 6 years. This schedule is
representative of planned maintenance beginning in year 4. Longer gasification outage durations are
expected for years 1 through 3.
(4) 3 week boiler outage every 18 months and a 6 week STG major outage every 6 years.
(5) Siemens recommends the following: 1 week combustion inspection every 8,333 eq. hours, 2 week hot
gas path inspection every 25,000 eq. hours, and a 4 week major inspection every 50,000 eq. hours for
the combustion turbine. A 6 week major outage is recommended at 50,000 eq. hours for the STG.
(6) Short outages required every 2,000 to 3,000 hours of operation.
(7) 2 week per 8,000 hours, 3 weeks per 16,000 hours, and 4 weeks per 48,000 hours.
5 4 CSR 240-22.040(1)(G)
Ameren Missouri Chapter 4 – Appendix B
Page 8 2011 Integrated Resource Plan
(8) GE recommends the following: 1 week combustion inspection every 450 starts, 2 week hot gas path
inspection every 1,200 starts, and a 4 week major inspection every 2,400 starts.
(9) Siemens recommends the following: 1 week combustion inspection every 450 starts, 2 week hot gas
path inspection every 900 starts, and a 4 week major inspection every 1,800 starts.
(10) GE recommends the following: 1 week hot section rotable exchange every 25,000 hours and a 10
week (nominal) engine overhaul every 50,000 hours.
Where available, generic equivalent forced outage rate (EFOR) and equivalent demand
forced outage rate (EFORd) data were gathered for each of the technologies. The
EFOR and EFORd data are presented in Table 4.B.4. The information was taken from
the NERC GADS database and published literature to the extent that data were
available. When information was not available, values were estimated using data
gathered from comparable technologies. EFOR and EFORd were not estimated for
technologies employing CCC equipment. For this effort and at this stage of planning, it
is assumed that the availability of CCC equipment is independent of the generating
facility availability and does not affect EFOR and EFORd. The information is generic,
but representative for screening-level supply-side resource analyses.
Table 4.B.4 Forced Outage Rates6
6 4 CSR 240-22.040(1)(I)
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 9
4.1.6 Waste Generation
Wastewater and waste solids must be processed and properly disposed. Technologies
fueled by natural gas produce negligible solid waste, but can produce wastewater
streams. Coal-fueled technologies produce both wastewater and waste solids. Table
4.B.5 presents a summary of the production of wastewater and solid wastes for the
evaluated options.
Table 4.B.5 Waste Generation7
4.1.7 Potentially Useable Byproducts
A variety of solid materials may be generated from the combustion and gasification of
coal, including fly ash, bottom ash, byproducts from FGD operation, and byproducts
from coal gasification.
7 4 CSR 240-22.040(1)(K)2
Ameren Missouri Chapter 4 – Appendix B
Page 10 2011 Integrated Resource Plan
Fly Ash – The most widely known uses for fly ash are in the cement and concrete
industries. Fly ash has been used extensively for many civil engineering
purposes, including structural fill, flowable fill, and road base materials. The use
of fly ash is prevalent in road projects where large quantities of suitable soils may
not be available. Fly ash has been blended with hydrated lime and aggregated
materials to form road base materials that are stronger and more durable than
conventional crushed stone or gravel base. Other applications include mineral
fillers, mining applications, and agricultural uses.
Bottom Ash – Bottom ash is widely utilized in road bases and structural fill
projects. Other applications include use as a sand substitute in cement concrete
mixtures, surface material on composition roof shingles, and as an antiskid
material applied to roadways in the northeast part of the country.
FGD Byproducts – The primary factor affecting the type of byproduct from lime or
limestone-based wet scrubbers is the degree to which oxidation has taken place
within the FGD system. If oxidation is promoted, the byproduct will be primarily in
the form of calcium sulfate or FGD gypsum. If oxidation is not promoted, much of
the product will remain in the calcium sulfite form. In general, FGD gypsum is the
more desirable product because it is relatively easy to dewater and can be sold
in a variety of re-use markets, such as wallboard production. The minimum purity
requirement in the utility industry for marketing FGD gypsum is typically 95
percent or greater.
FGD gypsum is also commonly used in the cement industry. FGD gypsum is
used to replace natural gypsum as one of the final steps in the cement
manufacturing process. As with wallboard, the gypsum must be free from
contamination and consistent in composition. FGD gypsum has also been used
successfully as an engineered material in structural fills and road bases. Gypsum
is commonly used as an agricultural additive for soils deficient in calcium and
sulfur. The use of FGD gypsum as a substitute for natural gypsum in agricultural
applications is somewhat more flexible than in wallboard and cement
manufacture because less stringent specifications on sulfite, ash, and chloride
content can be tolerated.
Coal Gasification Byproducts – The IGCC technology evaluated in this study
employs a Claus sulfur recovery plant from which liquid elemental sulfur is
recovered. This sulfur is commonly used in a variety of industries such as the
rubber industry, fertilizer manufacturing, oil refining, wastewater processing, and
mineral extraction. The gasifier produces a molten slag that flows freely into a
water-filled compartment at the bottom of the gasifier. As the molten slag
contacts the water bath, the slag vitrifies into dense, glassy granules. The vitrified
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 11
slag produced by the gasifiers can be used for the fabrication of ceramic
products.
4.1.8 Coal Technology Options
Ultra-Supercritical (USC) Pulverized Coal (PC)
The following assumptions have been made for all ultra-supercritical PC options:
1. Single unit site, with a capacity of 900 MW net (nominal).
2. USC TC4F STG and USC PC boiler.
3. AQCS:
• Low nitrogen oxide (NOx) burners and selective catalytic reduction (SCR) for
nitrogen oxides (NOx) control.
• Wet flue gas desulfurization (FGD) for sulfur dioxide (SO2) control.
• Activated carbon injection for mercury control.
• Pulse-jet fabric filter for particulate matter (PM10) control.
• Sorbent injection for sulfur trioxide (SO3) control.
4. Turbine driven boiler feed pumps.
5. Throttle conditions – 3,800 psia (pounds per square inch absolute)/1,110° F main
steam/1,110° F reheat.
6. Single reheat steam cycle.
7. Eight feedwater heaters – Three high-pressure (HP), four low-pressure (LP), and one
deaerator (DA).
8. Ultra-supercritical PC options that employ carbon dioxide (CO2) capture and
compression (CCC) would utilize an amine-based chemical solvent to remove 90
percent of the CO2 from the flue gas stream. Staged compression would deliver the CO2
to the site boundary at a pressure of 2,200 psig (pounds per square inch gauge). CO2
transportation and sequestration are evaluated separately.
Oxyfuel Coal
The following assumptions have been made for all oxyfuel coal options:
1. Single unit site, with a fuel flow rate equal to the fuel flow rate for the ultra-
supercritical PC plant (Refer to Section 3.2.1).
2. USC TC4F STG and USC PC boiler.
3. AQCS:
• Low NOx burners and SCR for NOx control.
• Wet FGD for SO2 control.
• Activated carbon injection for mercury control.
• Pulse-jet fabric filter for particulate control.
• Sorbent injection for SO3 control.
Ameren Missouri Chapter 4 – Appendix B
Page 12 2011 Integrated Resource Plan
• 90 percent of the flue stream would be compressed and delivered to the site
boundary at a pressure of 2,200 psig. CO2 transportation and sequestration are
evaluated separately.
4. Flue gas recycle.
5. Air Separation Unit (ASU) – 95 percent oxygen (O2) purity.
6. Turbine driven boiler feed pumps.
7. Throttle conditions – 3,800 psia/1,110° F/1,110° F.
8. Single reheat steam cycle.
9. Eight feedwater heaters – Three HP, four LP, and one DA.
Circulating Fluidized Bed (CFB)
The following assumptions have been made for all CFB options:
1. Single unit site, with a capacity of 2 x 300 MW net (nominal) boilers and 1 x 600 MW
net (nominal) TC4F STG.
2. AQCS:
• Combustion controls and selective noncatalytic reduction (SNCR) for NOx
control
• Boiler limestone injection and polishing spray dry absorber for polishing
SO2/SO3 control.
• Activated carbon injection for mercury control.
• Pulse-jet fabric filter for particulate control.
3. Motor driven boiler feed pumps.
4. Single reheat steam cycle.
5. Eight feedwater heaters – Three HP, four LP, and one DA.
6. A mechanical-draft, counterflow, cooling tower assumed for heat rejection.
7. CFB options that employ CCC would utilize an amine-based chemical solvent to
remove 90 percent of the CO2 from the flue gas stream. Staged compression would
deliver the CO2 to the site boundary at a pressure of 2,200 psig. CO2 transportation and
sequestration are evaluated separately.
Subcritical CFB
1. Subcritical STG and subcritical CFB boilers.
2. Throttle conditions – 2,415 psia/1,050° F/1,050° F.
Supercritical CFB
1. Supercritical STG and supercritical CFB boilers.
2. Throttle conditions – 3,800 psia/1,050° F/1,050° F.
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 13
Integrated Gasification Combined Cycle (IGCC)
The following assumptions have been made for all integrated gasification combined
cycle (IGCC) options:
1. Two 50 percent dry fed, entrained-flow Shell Coal Gasification Process gasifiers.
2. Two General Electric (GE) 7FB8 combustion turbine generators (CTGs) with syngas
combustors.
3. Two 50 percent ASUs – 95 percent O2 purity.
4. One subcritical TC2F STG.
5. Two triple-pressure heat recovery steam generators (HRSGs).
6. AQCS:
• Nitrogen diluent, syngas saturation, and SCR for NOx control.
• Carbonyl sulfide (COS) hydrolysis, Selexol acid gas removal
(AGR), and Claus sulfur recovery unit (SRU) with tailgas recycle for SO2 control
and sulfur recovery.
• Candle filter for particulate control.
• Sulfided carbon bed adsorption for mercury control.
7. Inlet air evaporative cooling above 59° F.
8. A mechanical-draft, counterflow, cooling tower assumed for heat rejection.
9. No duct firing for the HRSG(s).
10. IGCC options that employ CCC would utilize a Genosorb physical solvent CO2
removal process to remove 90 percent of the CO2 from the syngas stream. Rather than
a Selexol process, options that employ CCC would utilize an MDEA (methyl
diethanolamine) acid gas removal process. Staged compression would deliver the CO2
to the site boundary at a pressure of 2,200 psig. CO2 transportation and sequestration
are evaluated separately.
Efficiency Improvements – Duct Draft Reductions9
The electrical auxiliary loads required to drive the forced draft (FD) and induced draft
(ID) fans are significant in a PC plant. Any reductions in air handling system pressure
loss will reduce the required auxiliary loads and, therefore, increase the net plant output
(NPO).
One method of calculating reduced pressure loss potential in the air handling system is
to perform cold flow modeling. According to Pollution Control Services, Inc. (PCS),
implementing modifications identified from modeling flows from the boiler economizer
through the SCR, air heater, ESP/baghouse, scrubber, ID fans and stack will typically
result in overall static loss reductions of 3 to 8 inches of water column (in-wc). Using the
information provided by PCS, Black & Veatch made a conservative assumption that five
8 Future offerings will be presented as “7FA Syngas.”
9 4 CSR 240-22.040(4)
Ameren Missouri Chapter 4 – Appendix B
Page 14 2011 Integrated Resource Plan
flow correction devices could be installed in each Ameren Missouri PC unit. Flow
correction devices attempt to restrict or divert the flows in an attempt to achieve more
uniform flow distribution and lower pressure drop. Some examples of flow correction
devices include turning vanes, splitters, egg crates, and perforated plates.
Assuming an average static loss reduction of 0.4 in-wc per flow correction device results
in an overall pressure loss reduction of 2.0 in-wc per unit. A reduction in pressure loss
would result in auxiliary load savings through the ID fan(s), increasing net output. Using
Ameren Missouri unit operating data, Black & Veatch estimated ID fan auxiliary load
savings for a 2.0 in-wc pressure drop reduction for Rush Island Unit 2. The performance
gains realized at Rush Island Unit 2 are representative of a ~ 600 MW pulverized coal
unit.
An order-of-magnitude capital cost estimate was developed using information provided
by PCS and recent Black & Veatch experience with such flow correction devices. PCS
suggested budget cost of $400,000 to $500,000 for 1:12 scale cold flow modeling of
Rush Island Units 1 and 2. Translated roughly, this equates to about $250,000 for cold
flow modeling at Rush Island Unit 2 only. Recent installations of flow correction devices
in nominal 500 MW – 600 MW pulverized coal plants have ranged in cost from
approximately $40,000 to $65,000 per flow correction device. With the fixed expense of
cold flow modeling, modifications made to the larger units will most likely be the most
economical.
Efficiency Improvements – Condenser Back-Pressure Reductions10
The performance of a condenser impacts STG performance, thereby, affecting unit
performance. Unit performance can be improved by increasing the condenser
cleanliness factors for plants utilizing once-through cooling systems. Debris filters can
reduce macro fouling and tubesheet pluggage in the condenser. Two types of debris
filters may be applied:
In-line debris filter – placed in the circulating water pipe near the condenser
waterbox.
Intake debris filter – placed at the intake structure and intended to replace the
traveling screens.
Costs for intake debris filters were developed for this analysis. The capital cost
requirements are greater for intake debris filters than for in-line debris filters. However,
with the implementation of in-line debris filters, it is recommended that traveling screens
remain in service. Traveling screens tend to have significant problems with carryover of
debris and are maintenance intensive. Intake debris filters are intended to replace
10
4 CSR 240-22.040(4)
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 15
traveling screens, likely reducing total system maintenance requirements and improving
overall unit reliability.
Black & Veatch believes that implementation of a condenser ball cleaning system, in
conjunction with debris filters, is the best approach to realizing significant condenser
performance improvements.
Black & Veatch spoke with Ameren Missouri engineers and utilized on-line Ameren
Missouri unit operating data and equipment design information to develop a
performance impact estimate for Rush Island Unit 2. A cost estimate for the intake
debris filters and condenser ball cleaning systems was developed from multiple vendor
budgetary quotations. The performance impact estimate represents average condenser
cleanliness factor increases of 25 percentage points for each hour Rush Island Unit 2
would operate above the design condenser backpressure assuming an existing
condenser cleanliness factor of 60 percent. The performance and cost estimates for
Rush Island Unit 2 are representative of a ~ 600 MW pulverized coal unit.
4.1.9 Natural Gas Technology Options
Meramec Unit 4 STG in Combined Cycle Conversion
The reuse of Unit 4‟s STG as part of a combined cycle was included as an alternative to
replacing Units 1 through 4 with an entirely new unit at Meramec. Reuse of the Unit 4
STG would entail the addition of three CTGs, each fitted with a Heat Recovery Steam
Generator (HRSG). Steam produced in the HRSGs would be sent to the Unit 4 STG.
Each of the HRSGs would be outfitted with duct firing to fully utilize the STG capacity.
The following assumptions have been made for the Meramec Unit 4 STG combined
cycle conversion option:
1. Three Siemens 501F CTGs and three HRSGs supplying steam to the existing Unit 4
STG.
2. AQCS:
• Dry low NOx burners and SCR for NOx control.
• CO oxidation catalyst for carbon monoxide (CO) and volatile organic
compounds (VOC) controls.
3. Inlet air evaporative cooling above 59° F.
4. Duct firing during hot day conditions to match the design limits of the Unit 4 STG.
5. Triple-pressure HRSGs.
6. No HRSG bypass dampers and stacks included.
7. Existing equipment removed from service:
• Unit 4 boiler.
• Unit 4 feedwater heaters.
• Unit 4 boiler feed pump(s).
• Existing Unit 4 feedwater and steam piping.
Ameren Missouri Chapter 4 – Appendix B
Page 16 2011 Integrated Resource Plan
• Plant control system.
• Unit 4 electrostatic precipitator (ESP).
• Unit 4 coal and limestone handling equipment.
• Units 1 through 3 in their entirety.
8. Equipment reused in combined cycle conversion:
• Unit 4 STG.
• Unit 4 STG control system.
• Unit 4 gland steam condenser.
• Unit 4 gland steam regulator.
• Unit 4 condenser.
9. Scope of work needed to refurbish reused equipment:
• STG intermediate pressure (IP) retrofit.
• STG high pressure (HP) stator rewind and rotor replacement.
• STG low pressure (LP) stator rewind and rotor replacement.
• STG static excitation retrofit.
• Condenser retubing.
Meramec Boiler Conversion to Natural Gas
The following scope of work applies to the Meramec Unit 3 and 4 options in which the
boilers would be converted to burn natural gas:
1. Burner replacement.
2. Reheater modifications.
3. Superheater modifications.
4. Desuperheater spray modifications.
5. Air heater modifications.
6. Boiler controls modifications.
Meramec Boiler Replacements and STG Rebuilds
The following scope of work applies to the Meramec Unit 3 and 4 options in which the
boilers would be replaced and the STG sets would be refurbished:
1. Boiler - New waterwalls.
2. Boiler - Major superheater and reheater retrofits.
3. Steam piping modifications (main steam, cold reheat, and hot reheat).
4. Feedwater system modifications.
5. Hot well pump overhaul.
6. DA replacement (excluding DA storage tank).
7. One feedwater heater replacement.
8. Condenser retubing.
9. Induced draft fan motor and rotor modifications.
10. Water cannon replacement.
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 17
11. Unit-specific bottom ash system.
12. Fly ash collection system.
13. Significant structural steel modifications.
14. Demolition.
15. STG intermediate pressure (IP) retrofit.
16. STG high pressure (HP) stator rewind and rotor replacement.
17. STG low pressure (LP) stator rewind and rotor replacement.
18. STG static excitation retrofit.
Combined Cycle
Performance, emissions, and cost estimates were prepared for the following combined
cycle technology:
• 2-on-1 Siemens combined cycle based on a Siemens 501F CTG.
The following assumptions have been made for all combined cycle options:
1. Two CTGs, two HRSGs, and one TC2F STG.
2. AQCS:
• Dry low NOx burners and SCR for NOx control.
• CO oxidation catalyst for CO and VOC controls.
3. Inlet air evaporative cooling above 59° F.
4. Duct firing during hot day conditions to match 600 MW net plant output.
5. Triple-pressure HRSGs.
6. A mechanical-draft, counterflow, cooling tower assumed for heat rejection.
7. No HRSG bypass dampers and stacks.
8. Combined cycle options that employ CCC would utilize an amine-based chemical
solvent to remove 90 percent of the CO2 from the flue gas stream. Staged compression
would deliver the CO2 to the site boundary at a pressure of 2,200 psig. CO2
transportation and sequestration are evaluated separately.
Venice Combined Cycle Conversion
Performance, emissions, and cost estimates were developed as part of a separate
study conducted by Black & Veatch for Ameren Missouri. The conversion of Venice
units 3 and 4 from two Siemens Westinghouse 501F combustion turbines to a 2-on-1
combined cycle required the following additional systems:
• Two HRSGs and one TC2F STG.
• Duct firing during hot day conditions to match the 600 MW net plant output.
• Triple-pressure HRSGs.
• A mechanical-draft, plume abated cooling tower assumed for heat rejection.
Ameren Missouri Chapter 4 – Appendix B
Page 18 2011 Integrated Resource Plan
The conversion of two simple cycle combustion turbines into a 2-on-1 combined cycle
block represents a net capacity increase. In addition, the combined cycle would likely be
dispatched more frequently than the current simple cycles, resulting in a net increase in
fuel consumption and operations expenses. For screening purposes, the Venice
combined cycle conversion option is treated as an incremental capacity increase to
exiting Venice Units 3 and 4 with fuel burn rate and fixed and non-fuel variable O&M
estimates equal to the entire 2-on-1 combined cycle block. For modeling purposes, the
Venice combined cycle conversion is treated as a 2-on-1 combined cycle block. All
model runs with the Venice combined cycle block exclude the existing Unit 3 and 4
simple cycles. All model runs with the existing Unit 3 and 4 simple cycles exclude the
Venice combined cycle block.
Fuel Cell
Performance, emissions, and cost estimates were prepared for the following fuel cell
technology:
• Generic, molten carbonate fuel cells.
The following assumptions have been made for the gas-fueled fuel cell facility:
1. Thirty-six (36) 2.8 MW (net, nominal) fuel cell packages.
Combined Cycle Reciprocating Engines
Performance, emissions, and cost estimates were prepared for the following
reciprocating engine technology:
• Wärtsilä 20V34SG
The following assumptions have been made for the gas-fueled combined cycle
reciprocating engine facility:
1. NOx reduction would be achieved through use of a urea-based SCR system located
in the HRSGs.
2. The power block would consist of two 20V34SG engines, one nonreheat STG, and
two HRSGs.
3. A mechanical-draft, counterflow cooling tower would be included.
Cheng Cycle
Performance, emissions, and cost estimates were prepared for the following
combustion turbine technology:
• GE 7EA
The following assumptions have been made for the gas-fueled Cheng Cycle facility:
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 19
1. The power block would consist of one modified GE 7EA CTG and one HRSG.
2. Emissions would be controlled through the use of Cheng Low NOx (CLN) combustion
with steam/fuel premixing.
3. Power augmentation would be achieved through use of the Advanced Cheng System
(ACS) and Cheng Boost steam injection.
Simple Cycle
Performance, emissions, and cost estimates were prepared for the following simple
cycle technologies:
• Large Frame – Siemens 501F.
• Small Frame – GE 7EA.
• Aeroderivative – GE LM6000 SPRINT.
The following assumptions have been made for all simple cycle options:
1. Dry low NOx (DLN) burners would be included for NOx control.
2. Units that are dispatched at a capacity factor of 5 percent would not include an SCR
system or CO oxidation catalyst.
3. Units that are dispatched at a capacity factor of 10 percent would include an SCR
system and CO oxidation catalyst.
Existing Simple Cycle Fleet Power Augmentation11
Characteristics for simple cycle power augmentation options were developed as part of
a separate study conducted by Black and Veatch. The objective of this study was to
identify a single preferred power augmentation technology for the block of turbines
located at each facility. The study considered the following commercially available
power augmentation technologies:
Wetted Media Evaporative Cooling.
Inlet Fogging Evaporative Cooling.
Wet Compression.
Inlet Chilling.
Inlet Chilling with Thermal Storage.
Water Injection.
Steam Injection.
GE SPRINT Package.
In total, 38 CTs distributed among seven sites were analyzed to determine the feasibility
of installing various commercially available power augmentation technologies. The
results of the power augmentation technology screening are presented in Table 4.B.6.
11
4 CSR 240-22.040(4)
Ameren Missouri Chapter 4 – Appendix B
Page 20 2011 Integrated Resource Plan
Table 4.B.6 CTG Power Augmentation Summary of Results
The two options included from that study were selected on the basis of cost of power
and capacity addition potential. The first option selected is the addition of wetted media
(commonly referred to as evaporative cooling) to six GE 7EA combustion turbines at
Ameren Missouri‟s Goose Creek facility. The second option selected is the addition of
inlet chilling to the 7EAs at Goose Creek. The first power augmentation option offers the
lowest cost on a dollar per kW basis at $150/kW with 3MW capacity increase on each of
the six units. However, the second option offers a more substantial capacity increase- a
total increase of 66 MW, but at a higher cost- $600/MW.
Reciprocating Engines (Simple Cycle)
Performance, emissions, and cost estimates were prepared for the following
reciprocating engine technology:
• Wärtsilä 20V34SG
The following assumptions have been made for the gas-fueled reciprocating engine
facility:
1. Units would be dispatched at a low capacity factor that would preclude SCR.
2. The power block would consist of twelve 20V34SG engines, for a 100 MW net
(nominal) output.
No additional operational characteristics, constraints or siting impacts that could affect
the screening results were identified. By the same token, no other technology
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 21
characteristics were identified that may make the technology particularly appropriate as
a contingency option under extreme outcomes.12
4.2 Preliminary Screening Analysis
Preliminary Screening Methodology
After each evaluated option was characterized, each was subjected to a preliminary
screening analysis. The preliminary screening analysis provided an initial ranking of the
technologies. A scoring methodology was developed to compare the different options
within their fuel group by an overall weighted score. This score was developed for each
option by comparing the following categories: levelized cost of energy, environmental
cost, risk reduction, planning flexibility, and operability. Criteria within those categories
were established, and numerical scores were assigned on the basis of the
differentiating qualitative technology characteristics. Criteria were established on the
basis of Black & Veatch‟s experience with consideration of Ameren Missouri‟s known
planning requirements. Categories and criteria, along with their assigned weightings,
are presented in Table 4.B.7.13
12
4 CSR 240-22.040(1)(J); 4 CSR 240-22.040(1)(K)4; 4 CSR 240-22.040(1)(L) 13
4 CSR 240-22.040(2)
Ameren Missouri Chapter 4 – Appendix B
Page 22 2011 Integrated Resource Plan
Table 4.B.7 Scoring Criteria
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 23
Risk Reduction – The scoring of the various options took the amount of risk associated
with development and operations into account. An option‟s commercial status,
constructability, and potential hazards were all evaluated.
Planning Flexibility – The time required to construct a resource option, the fuels an
option could burn to produce electricity, and Ameren Missouri‟s ability to properly plan
and integrate an option into its current service network were evaluated for this category.
Operability – An option‟s availability, load-following capability, and complexity of
operation were reviewed and scored accordingly.
Environmental Cost14 – A resource option‟s ability to meet current and potential future
environmental regulations was incorporated into the ranking process. Emissions
constituents considered for this category include, but are not limited to, CO2, particulate
matter, sulfur oxides (SOx), NOx, Hg, and CO. A schedule of emission costs used in the
utility cost estimates for screening is presented in Table 4.B.8.
Table 4.B.8 Emissions Costs and Escalation Rates
It was assumed that new resources would be required to meet more stringent
environmental regulations and, therefore, would not incur any additional mitigation
costs. For example, any new coal unit would include a scrubber for SO2, an SCR for
NOx, activated carbon injection for mercury, and in some cases carbon capture and
compression technology. Also, new natural gas units are assumed to include an SCR
for NOx control.
The scenarios described in Chapter 2 include alternative carbon regulation regimes,
including: „Cap-and-Trade‟, „Federal Energy Bill‟, and „Moderate EPA Regulation‟, with
33%, 57% and 10% probabilities, respectively, assigned in the probability tree. CAIR
and CAMR were modeled in the scenarios developed in Chapter 2 for SO2, NOx, and
Mercury regulations. It was assumed that new units would require Mercury reductions
of 60% by 2015 and 90% by 2020. As described in Chapter 2, the NOx and SO2 prices
vary by scenarios as they are sensitive to carbon policy and other aspects of the
scenarios. All candidate resource options will be evaluated against the scenarios
developed in Chapter 2.
14
4 CSR 240-22.040(2)(B); 4 CSR 240-22.040(2)(B)1; 4 CSR 240-22.040(2)(B)2; 4 CSR 240-22.040(2)(B)3; 4 CSR 240-22.040(2)(B)4; 4 CSR 240-22.040(9)(D)
SO2 NOx CO2
2009 $/ton $25.59 $430.82 $17.17
Escalation 3.00% 3.00% 7.45%
SourceCRA Study
6/2/09
Chicago Climate Fund
Exchange - issued 4/27/09
Ameren Missouri Chapter 4 – Appendix B
Page 24 2011 Integrated Resource Plan
At this point in the analysis Ameren Missouri is not screening any of its existing
resources. However, Chapter 8 describes two additional environmental scenarios to
better characterize the effects of more stringent environmental regulations on existing
Ameren Missouri generation resources, namely its coal assets. Furthermore, those
additional environmental scenarios facilitate the retirement analysis of Meramec plant.
Levelized Cost of Energy – One of the more significant criteria in the scoring was the
levelized cost of energy (LCOE). Financial factors, such as fuel costs, tax life, economic
life, escalation rates, present worth discount rate (PWDR), levelized fixed charge rate
(LFCR) that were used in the LCOE estimates in the screening in addition to other costs
presented earlier are listed in Table 4.B.9 and Table 4.B.10.
Table 4.B.9 Fuel Prices for LCOE Estimates
Table 4.B.10 Financial Inputs for LCOE Estimates
Annual costs for the LCOE estimates include levelized annual capital cost, fixed and
variable O&M, fuel cost, and emissions allowances if applicable; LCOE estimates were
developed in three different ways: without emission costs, with emissions costs for SO2
and NOx, and with emissions costs for SO2, NOx and CO2.15
15
4 CSR 240-22.040(2)(A)
LocationMeramec/
Rush
Meramec/
RushGreenfield Greenfield Greenfield
Type PRB Coal IL Coal PRB Coal IL Coal Natural Gas
2009 $/MMBtu $2.10 $2.86 $2.47 $3.03 $6.09
Escalation 3.81% 3.21% 3.84% 3.26% 2.71%
SourceAFS Nat Gas
Forecast 4/28/09RI Scrubber Study/2009-2013 Fuel Budget
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 25
Preliminary Screening Results
The levelized costs of energy and overall scorings of the evaluated options are
presented in Table 4.B.20a, Table 4.B.20b, Table 4.B.21a and Table 4.B.21b. All
levelized costs of energy and overall scorings are presented with and without SO2, NOx,
and CO2 price forecasts included. The following figures show the LCOE and total
screening scores.16
Figure 4.B.1 LCOE for Coal Options17
16
4 CSR 240-22.040(2)(B); 4 CSR 240-22.040(2)(B)1 17
4 CSR 240-22.040(2)
Ameren Missouri Chapter 4 – Appendix B
Page 26 2011 Integrated Resource Plan
Figure 4.B.2 LCOE for Gas Options18
Figure 4.B.3 Total Screening Score for Coal Options19
18
4 CSR 240-22.040(2) 19
4 CSR 240-22.040(2)(C)
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 27
Figure 4.B.4 Total Screening Score for Gas Options20
Based on the scoring results, Ameren Missouri selected 10 options to carry forward21.
The 2-on-1 501F based combined cycle options scored highest among the new capacity
options with intermediate dispatch load profiles. The Cheng cycle option ranked high in
large part due to its comparatively low costs of electricity. However, operational and
project development risks pushed their overall scores below that of the combined cycle.
The peaking option rankings favored the larger, 501F combustion turbines over the 7EA
combustion turbine, with the GE LM6000 and Wartsila 20V34SG reciprocating engines
rounding out the list.
The Venice combined cycle conversion will replace CTG Units 3 and 4 from a dispatch
perspective. Modeled as a 2-on-1 combined cycle, the Venice combined cycle
conversion option scored well and appears to offer a low total cost of energy. However,
the prerequisite retirement of Venice Unit 3 and 4 simple cycle units should weigh
heavily when considering other expansion.
As with the Venice combined cycle conversion, the repowering of existing units or the
addition of new units at Meramec will displace existing capacity. The repowering of the
20
4 CSR 240-22.040(2)(C) 21
4 CSR 240-22.040(2)(C); 4 CSR 240-22.040(9)(A)3
Ameren Missouri Chapter 4 – Appendix B
Page 28 2011 Integrated Resource Plan
Unit 4 STG in a combined cycle or the addition of a new coal unit at Meramec is
assumed to require the retirement of existing Units 1 through 4. Whether the option is to
repower, build a new unit, or rebuild existing units, the result will not necessarily result in
a net capacity increase from the site.
Environmental regulations and permitting strategies that are currently valid will likely
change within the next few years. In light of the current regulatory landscape, natural
gas fueled Meramec repowering options should be given preference over coal fueled
Meramec repowering options. The Meramec options would be subject to extensive
environmental permitting analysis if they were to be considered for further development.
Among the Meramec replacement capacity baseload dispatched options, the Meramec
Unit 3 and 4 boiler replacement and STG rebuild options received the highest scores
except when accounting for CO2 costs. When accounting for CO2 costs, the Unit 4 STG
in a combined cycle conversion ranked highest.
USCPC-Greenfield had the highest overall score among the coal technology options,
and therefore, was passed on as a candidate coal option. The Ameren Missouri team
also wanted to include an unconventional coal technology in addition to the
conventional technology and selected IGCC-Greenfield for further characterization as it
was the highest scoring unconventional coal option. Technologies that incorporated
carbon capture consistently lagged behind their non-carbon capture counterparts even
when accounting for CO2 costs. However, both USCPC and IGCC with carbon capture
were also passed on to the next step in the analysis with their non-carbon capture
counterparts. All other coal resource options were eliminated from further analysis to
keep the options to a manageable size as the four technologies selected would be more
than enough to represent coal supply side technologies.
Power augmentation options appear to score better than the other natural gas
technologies; however, since the capacity addition is much smaller compared to the
others, they were eliminated from further analysis for the purposes of this IRP.
Furthermore, the natural gas resource options that had an overall score lower than that
of the aero-derivative simple cycle (GE LM6000 SPRINT) were not considered for
further analysis.
4.3 Candidate Options
Using the preliminary screening results as a tool, Ameren Missouri selected 10
technologies to be characterized further for modeling and planning efforts. Table 4.B.11
presents a listing of the preliminary candidate options.
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 29
Table 4.B.11 Preliminary Candidate Options22
22
4 CSR 240-22.040(2)(C); 4 CSR 240-22.040(9)(A)2
Ameren Missouri Chapter 4 – Appendix B
Page 30 2011 Integrated Resource Plan
4.4 Supporting Tables
Table 4.B.12 Coal Options – Capacity and Performance
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 31
Table 4.B.13 Gas Options – Capacity and Performance
Ameren Missouri Chapter 4 – Appendix B
Page 32 2011 Integrated Resource Plan
Table 4.B.14 Coal Options – Cost Estimates23
23
4 CSR 240-22.040(1)(E); 4 CSR 240-22.040(1)(F); 4 CSR 240-22.040(1)(G); 4 CSR 240-22.040(8)(B); 4 CSR 240-22.040(8)(C)
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 33
Table 4.B.15 Gas Options – Cost Estimates24
24
4 CSR 240-22.040(1)(E); 4 CSR 240-22.040(1)(F); 4 CSR 240-22.040(1)(G); 4 CSR 240-22.040(8)(B); 4 CSR 240-22.040(8)(C)
Ameren Missouri Chapter 4 – Appendix B
Page 34 2011 Integrated Resource Plan
Table 4.B.16 Coal Options – Commercial Status, Construction Duration and Environmental Characteristics25
25
4 CSR 240-22.040(1)(C); 4 CSR 240-22.040(1)(D); 4 CSR 240-22.040(1)(K)1; 4 CSR 240-22.040(1)(K)3
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 35
Table 4.B.17 Gas Options – Commercial Status, Construction Duration and Environmental Characteristics26
26
4 CSR 240-22.040(1)(C); 4 CSR 240-22.040(1)(D); 4 CSR 240-22.040(1)(K)1; 4 CSR 240-22.040(1)(K)3
Ameren Missouri Chapter 4 – Appendix B
Page 36 2011 Integrated Resource Plan
Table 4.B.18 Coal Options – Economic Parameters and LCOE
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 37
Table 4.B.19 Gas Options – Economic Parameters and LCOE
Ameren Missouri Chapter 4 – Appendix B
Page 38 2011 Integrated Resource Plan
Table 4.B.20a Coal Options – Scoring Results27
27
4 CSR 240-22.040(2)(B); 4 CSR 240-22.040(2)(C); 4 CSR 240-22.040(9)(A); 4 CSR 240-22.040(9)(A)1
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 39
Table 4.B.20b Coal Options – Scoring Results28
28
4 CSR 240-22.040(2); 4 CSR 240-22.040(2)(A); 4 CSR 240-22.040(2)(B); 4 CSR 240-22.040(2)(B)1; 4 CSR 240-22.040(2)(C); 4 CSR 240-22.040(9)(A); 4 CSR 240-22.040(9)(A)1
Ameren Missouri Chapter 4 – Appendix B
Page 40 2011 Integrated Resource Plan
Table 4.B.21a Gas Options – Scoring Results29
29
4 CSR 240-22.040(2); 4 CSR 240-22.040(2)(A); 4 CSR 240-22.040(2)(B); 4 CSR 240-22.040(2)(B)1; 4 CSR 240-22.040(2)(C); 4 CSR 240-22.040(9)(A); 4 CSR 240-22.040(9)(A)1
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 41
Table 4.B.21b Gas Options – Scoring Results30
30
4 CSR 240-22.040(2); 4 CSR 240-22.040(2)(A); 4 CSR 240-22.040(2)(B); 4 CSR 240-22.040(2)(B)1; 4 CSR 240-22.040(2)(C); 4 CSR 240-22.040(9)(A); 4 CSR 240-22.040(9)(A)1
Ameren Missouri Chapter 4 – Appendix B
Page 42 2011 Integrated Resource Plan
4.5 Compliance References
4 CSR 240-22.040(1) ...................................................................................................... 1 4 CSR 240-22.040(1)(A) ................................................................................................. 2 4 CSR 240-22.040(1)(B) ................................................................................................. 3 4 CSR 240-22.040(1)(C) ......................................................................................... 34, 35 4 CSR 240-22.040(1)(D) ......................................................................................... 34, 35 4 CSR 240-22.040(1)(E) ......................................................................................... 32, 33 4 CSR 240-22.040(1)(F) .......................................................................................... 32, 33 4 CSR 240-22.040(1)(G) ..................................................................................... 7, 32, 33 4 CSR 240-22.040(1)(I) ................................................................................................... 8 4 CSR 240-22.040(1)(J) ................................................................................................ 21 4 CSR 240-22.040(1)(K)1 ....................................................................................... 34, 35 4 CSR 240-22.040(1)(K)2 ............................................................................................... 9 4 CSR 240-22.040(1)(K)3 ....................................................................................... 34, 35 4 CSR 240-22.040(1)(K)4 ............................................................................................. 21 4 CSR 240-22.040(1)(L) ................................................................................................ 21 4 CSR 240-22.040(2) ................................................................ 21, 25, 26, 38, 39, 40, 41 4 CSR 240-22.040(2)(A) ................................................................................... 24, 40, 41 4 CSR 240-22.040(2)(B) ................................................................. 23, 25, 38, 39, 40, 41 4 CSR 240-22.040(2)(B)1 ............................................................... 23, 25, 38, 39, 40, 41 4 CSR 240-22.040(2)(B)2 ............................................................................................. 23 4 CSR 240-22.040(2)(B)3 ............................................................................................. 23 4 CSR 240-22.040(2)(B)4 ............................................................................................. 23 4 CSR 240-22.040(2)(C) ........................................................... 26, 27, 29, 38, 39, 40, 41 4 CSR 240-22.040(3) ...................................................................................................... 5 4 CSR 240-22.040(4) ........................................................................................ 13, 14, 19 4 CSR 240-22.040(6) ...................................................................................................... 5 4 CSR 240-22.040(8)(B) ......................................................................................... 32, 33 4 CSR 240-22.040(8)(B)1 ........................................................................... 38, 39, 40, 41 4 CSR 240-22.040(8)(B)2 ........................................................................... 38, 39, 40, 41 4 CSR 240-22.040(8)(C) ......................................................................................... 32, 33 4 CSR 240-22.040(9)(A) ............................................................................. 38, 39, 40, 41 4 CSR 240-22.040(9)(A)1 ........................................................................... 38, 39, 40, 41 4 CSR 240-22.040(9)(A)2 ............................................................................................. 29 4 CSR 240-22.040(9)(A)3 ............................................................................................. 27 4 CSR 240-22.040(9)(D) ............................................................................................... 23
Chapter 4 – Appendix B Ameren Missouri
2011 Integrated Resource Plan Page 43
Chapter 4 – Appendix B
Preliminary Screening Analysis ....................................................................................... 1
4.1 Technology Characterization ................................................................................ 2
4.1.1 Capacity Ranges ............................................................................................. 2
4.1.2 Commercial Availability ................................................................................... 3
4.1.3 Capital Cost Estimates .................................................................................... 4
4.1.4 Non-Fuel O&M Costs ...................................................................................... 6
4.1.5 Scheduled and Forced Outages ...................................................................... 7
4.1.6 Waste Generation ........................................................................................... 9
4.1.7 Potentially Useable Byproducts ....................................................................... 9
4.1.8 Coal Technology Options .............................................................................. 11
4.1.9 Natural Gas Technology Options .................................................................. 15
4.2 Preliminary Screening Analysis .......................................................................... 21
4.3 Candidate Options .............................................................................................. 28
4.4 Supporting Tables .............................................................................................. 30
4.5 Compliance References ..................................................................................... 42