    Chapter 2

    Testing in SDLC

  • 7/29/2019 Chapter 2 - Testing in SDLC

    2/26

    Satyam Computer Services Limited2

    Objective

    Testing in Different Development Lifecycles

    The V concept of testing

    Verification and Validation

    Testing Levels/Stages Component Test Issues

    Integration Testing

    System and Acceptance Testing Maintenance and Regression Testing

    Static Vs Dynamic testing

  • 7/29/2019 Chapter 2 - Testing in SDLC

    3/26

    Satyam Computer Services Limited3

    Process models

    The following process models are used for

    development of software.

    Waterfall model

    Modified waterfall model

    V - Model

    Prototype model

    RAD Spiral model

    Agile Model (newly followed)

  • 7/29/2019 Chapter 2 - Testing in SDLC

    4/26

    Satyam Computer Services Limited4

    Waterfall model

    Testing in done after

    development

    Testing is last activity

    before delivery

    The waterfall model is a sequential software development model (a process for the creation of software) in which

    development is seen as flowing steadily downwards (like a waterfall) through the phases of requirements analysis,

    design, implementation, testing (validation), integration, and maintenance. The origin of the term "waterfall" is often cited

    to be an article published in 1970 by W. W. Royce; ironically, Royce himself advocated an iterative approach to software

    development and did not even use the term "waterfall". Royce originally described what is now known as the waterfall

    model as an example of a method that he argued "is risky and invites failure".

  • 7/29/2019 Chapter 2 - Testing in SDLC

    5/26

    Satyam Computer Services Limited5

    Waterfall Strengths

    Easy to understand, easy to use

    Provides structure to inexperienced staff

    Milestones are well understood

    Sets requirements stability

    Good formanagement control (plan, staff, track)

    Works well when quality is more important than

    cost or schedule

  • 7/29/2019 Chapter 2 - Testing in SDLC

    6/26

    Satyam Computer Services Limited6

    Modified waterfall models

    In response to the perceived problems with the "pure"

    waterfall model, many modified waterfall models have

    been introduced. These models may address some or

    all of the criticisms of the "pure" waterfall model. Many

    different models are covered by Steve McConnell in the

    "lifecycle planning" chapter of his book Rapid

    Development: Taming Wild Software Schedules.

    Royce's final model

    Royce's final model, his intended improvement upon his

    initial "waterfall model", illustrated that feedback could

    (should, and often would) lead from code testing to

    design (as testing of code uncovered flaws in the

    design) and from design back to requirementsspecification (as design problems may necessitate the

    removal of conflicting or otherwise unsatisfiable /

    undesignable requirements).

  • 7/29/2019 Chapter 2 - Testing in SDLC

    7/26 Satyam Computer Services Limited7

    Waterfall Deficiencies

    All requirements must be known upfront Deliverables created for each phase are

    considered frozeninhibits flexibility

    Can give a false impression of progress

    Does not reflect problem-solving nature ofsoftware development iterations of phases

    Integration is one big bang at the end

    Little opportunity for customerto preview thesystem (until it may be too late)

  • 7/29/2019 Chapter 2 - Testing in SDLC

    8/26 Satyam Computer Services Limited8

    Modified waterfall models

    The "sashimi" model

    The name "Sashimi" comes from a Japanese

    hardware development model (from Fuji-Xerox) and

    refers to the Japanese style of presenting

    overlapping slices of raw fish.

    It is sometimes simply referred to as the "waterfall

    model with overlapping phases" or "the waterfall

    model with feedback".

    For example, since the design and implementation

    phases will overlap in the sashimi model,

    implementation problems may be discovered during

    the "design and implementation" phase of thedevelopment process. This helps alleviate many of

    the problems associated with the Big Design Up

    Front philosophy of the waterfall model.

  • 7/29/2019 Chapter 2 - Testing in SDLC

    9/26 Satyam Computer Services Limited9

    Modified waterfall models

    The "sashimi" model

    The name "Sashimi" comes from a Japanese

    hardware development model (from Fuji-Xerox) and

    refers to the Japanese style of presenting

    overlapping slices of raw fish.

    It is sometimes simply referred to as the "waterfall

    model with overlapping phases" or "the waterfall

    model with feedback".

    For example, since the design and implementation

    phases will overlap in the sashimi model,

    implementation problems may be discovered during

    the "design and implementation" phase of thedevelopment process. This helps alleviate many of

    the problems associated with the Big Design Up

    Front philosophy of the waterfall model.

  • 7/29/2019 Chapter 2 - Testing in SDLC

    10/26 Satyam Computer Services Limited10

    V model

    A variant of the Waterfall

    that emphasizes the

    verification and validation

    of the product.

    Testing of the product is

    planned in parallel with a

    corresponding phase of

    development

  • 7/29/2019 Chapter 2 - Testing in SDLC

    11/26 Satyam Computer Services Limited

    11

    V-Model Strengths

    Emphasize planning forverification and

    validationof the product in early stages of

    product development

    Each deliverable must be testable

    Project management can track progress

    by milestones

    Easy to use

  • 7/29/2019 Chapter 2 - Testing in SDLC

    12/26 Satyam Computer Services Limited

    12

    V-Model Weaknesses

    Does not easily handleconcurrent events

    Does not handle iterationsor phases

    Does not easily handle dynamic changesin requirements

    Does not contain risk analysis activities

  • 7/29/2019 Chapter 2 - Testing in SDLC

    13/26 Satyam Computer Services Limited

    13

    Prototyping Model

    A preliminary project plan is developed

    An partial high-level paper model is created

    The model is source for a partial requirementsspecification

    A prototype is built with basic and critical attributes The designer builds

    the database

    user interface

    algorithmic functions

    The designerdemonstrates the prototype, the userevaluates for problems and suggests improvements.

    This loop continues until the user is satisfied

  • 7/29/2019 Chapter 2 - Testing in SDLC

    14/26 Satyam Computer Services Limited

    14

    Rapid Application Model (RAD)

    Requirements planning phase (a workshoputilizing structured discussion of businessproblems)

    User description phase automated toolscapture information from users

    Construction phase productivity tools, such ascode generators, screen generators, etc. inside

    a time-box. (Do until done) Cutover phase -- installation of the system, user

    acceptance testing and user training

  • 7/29/2019 Chapter 2 - Testing in SDLC

    15/26 Satyam Computer Services Limited

    15

    RAD Strengths

    Reduced cycle time and improved productivitywith fewer people means lower costs

    Time-boxapproach mitigates cost and schedulerisk

    Customer involved throughout the completecycle minimizes risk of not achieving customersatisfaction and business needs

    Focus moves from documentation to code

    (WYSIWYG). Uses modeling concepts to capture information

    about business, data, and processes.

  • 7/29/2019 Chapter 2 - Testing in SDLC

    16/26

    Satyam Computer Services Limited16

    RAD Weaknesses

    Accelerated development processmust givequick responsesto the user

    Risk ofnever achieving closure

    Hard to use with legacy systems Requires a system that can be modularized

    Developers and customers must be committedto rapid-fire activitiesin an abbreviated time

    frame.

  • 7/29/2019 Chapter 2 - Testing in SDLC

    17/26

    Satyam Computer Services Limited17

    Spiral SDLC Model

    Adds risk analysis,and 4gl RAD

    prototyping to the

    waterfall model

    Each cycle involvesthe same sequence of

    steps as the waterfall

    process model

  • 7/29/2019 Chapter 2 - Testing in SDLC

    18/26

    Satyam Computer Services Limited18

    Agile SDLCs

    Speed up or bypass one or more life cycle

    phases

    Usually less formal and reduced scope

    Used for time-critical applications

    Used in organizations that employ

    disciplined methods

  • 7/29/2019 Chapter 2 - Testing in SDLC

    19/26

    Satyam Computer Services Limited19

    Some Agile Methods

    Adaptive Software Development (ASD)

    Feature Driven Development (FDD)

    Crystal Clear

    Dynamic Software Development Method(DSDM)

    Rapid Application Development (RAD)

    Scrum

    Extreme Programming (XP)

    Rational Unify Process (RUP)

  • 7/29/2019 Chapter 2 - Testing in SDLC

    20/26

    Satyam Computer Services Limited20

    Verification

    Verification ensures that the system

    (software, hardware, documentation, and

    personnel) complies with an organizations

    standards and processes, relying onreview or non-executable methods

    Did we built the right system ?

  • 7/29/2019 Chapter 2 - Testing in SDLC

    21/26

    Satyam Computer Services Limited21

    Verification

  • 7/29/2019 Chapter 2 - Testing in SDLC

    22/26

    Satyam Computer Services Limited22

    Validation

    Validation physically ensures that the

    system operates according to plan by

    executing the system functions through a

    series of tests that can be observed andevaluated.

    Did we build the system right?

  • 7/29/2019 Chapter 2 - Testing in SDLC

    23/26

    Satyam Computer Services Limited23

    Validation

  • 7/29/2019 Chapter 2 - Testing in SDLC

    24/26

    Satyam Computer Services Limited24

    Testing levels

    Unit

    Integration

    System Acceptance

    Regression

  • 7/29/2019 Chapter 2 - Testing in SDLC

    25/26

    Satyam Computer Services Limited25

    Static testing Vs Dynamic testing

    Static testing is performed using the

    software documentation. The code is not

    executing during static testing.

    Dynamic testing requires the code to be in

    an executable state to perform the tests.

  • 7/29/2019 Chapter 2 - Testing in SDLC

    26/26

    S t C t S i Li it d26

    Points to remember

    Waterfall model does not all modification after

    reaching to its next phase

    Prototyping is an iterative model

    Regression testing is also called as selective re-testing

    All the reviews are called as Verification

    Unit, integration, system, acceptance testing arethe various levels of testing