chapter 2-1 - project development · transportation projects are in general agreement regarding the...

39
Project Development 2.11 SECTION 2 - CHAPTER 1 Project Development This section of the Transportation Management Plan (TMP) provides the basis for how transportation funding is spent, and provides guidance on what projects or programs the City should be focusing on to provide transportation services for the businesses and residents of Norwalk. While the third section of this section of the TMP makes several specific recommendations about certain intersections and roadways, it is also intended to be a document that is reviewed and updated regularly as projects are completed; new projects are brought before the City; and as new opportunities or dynamics create the need to change how projects are completed. This chapter provides an overview of how projects should be developed and advanced to the City for evaluation and consideration. Later, processes for evaluating the need for a project as well as its effectiveness are presented. 1.1 Project Development Project Development is the process that takes a transportation improvement from initial concept through final construction. There are several goals for this process: To ensure context sensitivity though an open, consensus‐building dialog among project proponents, reviewers, the public, and other parties. To foster thinking beyond the roadway pavement to achieve the optimum accommodation for all modes. To encourage early planning, public outreach, and evaluation so that project needs, goals and objectives, issues, and impacts can be identified before significant resources are expended. To achieve consistent expectations and understanding between project proponents and those entities who evaluate, prioritize, and fund projects. To ensure allocation of resources to projects that address local, regional, and statewide priorities and needs.

Upload: others

Post on 24-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

  Project Development  2.1‐1 

SECTION 2 - CHAPTER 1

Project Development 

ThissectionoftheTransportationManagementPlan(TMP)providesthebasisforhowtransportationfundingisspent,andprovidesguidanceonwhatprojectsorprogramstheCityshouldbefocusingontoprovidetransportationservicesforthebusinessesandresidentsofNorwalk.WhilethethirdsectionofthissectionoftheTMPmakesseveralspecificrecommendationsaboutcertainintersectionsandroadways,itisalsointendedtobeadocumentthatisreviewedandupdatedregularlyasprojectsarecompleted;newprojectsarebroughtbeforetheCity;andasnewopportunitiesordynamicscreatetheneedtochangehowprojectsarecompleted.ThischapterprovidesanoverviewofhowprojectsshouldbedevelopedandadvancedtotheCityforevaluationandconsideration.Later,processesforevaluatingtheneedforaprojectaswellasitseffectivenessarepresented.

1.1 Project Development 

ProjectDevelopmentistheprocessthattakesatransportationimprovementfrominitialconceptthroughfinalconstruction.Thereareseveralgoalsforthisprocess: Toensurecontextsensitivitythoughanopen,consensus‐buildingdialogamong

projectproponents,reviewers,thepublic,andotherparties.

Tofosterthinkingbeyondtheroadwaypavementtoachievetheoptimumaccommodationforallmodes.

Toencourageearlyplanning,publicoutreach,andevaluationsothatprojectneeds,goalsandobjectives,issues,andimpactscanbeidentifiedbeforesignificantresourcesareexpended.

Toachieveconsistentexpectationsandunderstandingbetweenprojectproponentsandthoseentitieswhoevaluate,prioritize,andfundprojects.

Toensureallocationofresourcestoprojectsthataddresslocal,regional,andstatewideprioritiesandneeds.

Page 2: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐2  Project Development    

Aclearandopenprocesscanflushoutissuesearlysothatopportunitiesforprojectdelaysandescalatingcostsareidentifiedanddealtwithearlyintheprocessandsothatthosepartiesinvolvedarenotdiscouraged.Additionally,itcanpreventfrustrationbyavoidingbuildingprojectsinawaythatdoesnotmeetexpectationsinaddressingtheperceivedneeds.Thisprojectdevelopmentframework,andtheprinciplesthatitembraces,will: Helpcarryoutprojectseffectively;

Ensuregoodprojectplanning,design,andimplementation;and,

Setthestageforlong‐termsuccess.

Effectivepartnershipsonprojectsareimportantthroughoutprojectdevelopmentandrequirestrongcommitmentandactionfromallinvolved,whethertheybeelectedofficials,localplanningandpublicworksprofessionals,citizens,orconsultants.Realpartnershipsrequireongoingrelationshipsoftrustandcollaboration.Theprojectdevelopmentprocessisoneofasetoftoolsneededtoachievecontext‐sensitivedesign.Theprocessisstructuredtoencouragepublicoutreachthroughoutplanning,design,environmentalreview,andconstructionsothatthoseaffectedbytransportationprojectsareingeneralagreementregardingtheproject’sneed,theselectedapproachtomeetthisneed,andtherefinementstotheprojectthatresultastheprocessevolves.Thisprojectdevelopmentprocessiscomplementedbytheinclusionoftheproject’scontextasabasicdesigncontrol.Flexibilityfordeterminingspecificdesignelementsthatsatisfytheprojectneed,andareresponsivetothecontextoftheproject,isessentialandmethodstoaccomplishthesegoalshavebeenpresentedthroughoutthisreport.

1.1.1 Project Development Process Overview 

Theprojectdevelopmentprocessisinitiatedinresponsetoanidentifiedneedinthetransportationsystem,anditcoversarangeofactivitiesstartingwiththisidentificationtoafinishedsetofcontractplans,andfinallytoconstruction.Theidentifiedtransportationneedmightincludeoneormoreofthefollowing:acongestionproblem,asafetyconcern,facilityconditiondeterioration,aneedforbettermulti‐modalaccommodation,anenvironmentalenhancement,oraneconomicimprovementopportunity.Thedevelopmentofsolutionstoaddresstheseneedsofteninvolvesinputfromtransportationplanners,communityleaders,citizens,environmentalspecialists,landscapearchitects,naturalresourceagencies,localpublicworksofficials,permittingagencies,designengineers,financialmanagers,andagencyexecutives.Solutionsmight

Page 3: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐3 

targetasinglemodeoftransportation,oraddresstherangeofroadusersincludingpedestrians,bicyclists,transitoperators,automobiledrivers,andtruckersmovingfreightandgoods.Itiscriticaltothesuccessofaprojecttoengagetherightteamofpeopleontheprojectfromthebeginning.Thesequenceofdecisionsmadethroughtheprojectdevelopmentprocessprogressivelynarrowstheprojectfocusand,ultimately,leadstoaprojectthataddressestheidentifiedneeds.Thereshouldbeampleopportunitiesforpublicparticipationthroughouttheprocess.Transportationdecision‐makingiscomplexandcanbeinfluencedbylegislativemandates,environmentalregulations,financiallimitations,agencyprogrammaticcommitments,andpartneringopportunities.Decision‐makersandreviewingagencies,whenconsultedearlyandoftenthroughouttheprojectdevelopmentprocess,canensurethatallparticipantsunderstandthepotentialimpactthesefactorscanhaveonprojectimplementation.Aseven‐stepprojectdevelopmentprocessisdefinedtomoveaprojectfromproblemidentificationtocompletion,asillustratedinExhibit2‐1‐1.Itshouldbenotedthatthisprocessisgearedtowardscapitalimprovementprojects,andthereforemaintenanceprojectsaswellastrafficcalmingprojectsmayfollowdifferentprocesses.WithinSection2oftheTMP,Chapter2discussesPoliciesandStrategiesthatthecityshouldundertake;Chapter3discusseshowtheCityshouldapproachTravelDemandManagement;,Chapter4discussestheCity’sapproachtoTrafficCalming,andChapter5presentshowTrafficImpactStudiesshouldbeconducted.

Page 4: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐4  Project Development    

 

Exhibit 1‐1  Overview of Project Development 

STEPI Project/Need/OpportunityIdentification

STEPII Planning/PreliminaryDesign

STEPIII ProgramInitiation,Prioritization,andProgramming

STEPIV Environmental,Design,andROWProcess

STEPV Procurement

STEPVI Construction

STEPVII ProjectAssessment

Thesesevenstepsaredescribedindetailinthesubsequentsectionsofthischapter.

1.2 Step I: Problem/Need/Opportunity Identification 

Projectsbeginwiththeidentificationofaproblem,need,oropportunity.Theseprojectsreachacrossallmodesoftransportation(bus,rail,bike,pedestrian,auto,etc.)tomakemodalconnectionsandimprovementsconsistentwithsoundlanduseplanning.AnewprojectproposalcanresultthroughplanninginitiativesfromtheCityofNorwalkortheState,aswellasarisefromcommunity,legislative,orcitizeninput.

Page 5: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐5 

Asproblems,needs,oropportunitiesforimprovementsarisetheycanbesimpleandstraightforward,orcomplexinnaturewithoutanobvioussolutionatthestart.Asafirststepintheprojectdevelopmentprocess,theproponentwouldleadaneffortto: Definetheproblem,need,oropportunitybasedonobjectivecriteria;

Establishpreliminaryprojectgoalsandobjectives;and,

Definethescopeofplanningandpublicoutreachneeded.

1.2.1 Goals  

Throughpublicoutreach,discussionswithCitystaff,andstakeholderinterviews,asetofgoalswillbeestablished.ThegoalsreflecttheCityofNorwalk’sprioritiesforthemulti‐modaltransportationnetworkandwillenabletheCitytoprioritizetransportationimprovementsbasedonadata‐drivenneedsassessmentforeachpotentialproject.ThegoalsfortheCityshouldbeasfollows:

1.2.1.1 Goal 1: Safety 

Goal1aimstoquantifyexistingsafetydeficiencieswiththeobjectiveofimprovingtheCityofNorwalk’stransportationsysteminawaytominimizecrashesandothersafetyrelatedincidents.

1.2.1.2 Goal 2: Vehicular Access and Mobility 

Goal3aimstoimprovetheCityofNorwalk’sroadwaysystemtherebyreducingcongestionwithintheCitywiththeobjectivesoffacilitatingcommercialmovementandaccesstoactivitycentersandredevelopmentareas,minimizinguseofresidentialstreetsascut‐throughandtruckroutes,andimprovingoverallmobilityfordrivers.

1.2.1.3 Goal 3: Pedestrian and Bicycle Access and Mobility 

Goal3aimstoenhancethepedestrianandbicycleexperienceintheCityofNorwalkwiththeobjectivesofprovidingafriendly,safeandconvenientenvironmenttobetteraccommodateexistingpedestrianandbicyclistsaswellastoencouragemorepeoplewithintheCitytoutilizethesealternatemodes.

1.2.1.4 Goal 4: Degree of Support 

Goal4aimstoallowforpublicinputindecisionsconcerningtheCityofNorwalk’stransportationsystemwiththeobjectiveofprovidingatransparentforumthatconsidersawidevarietyofsuggestionsandconcerns.

Page 6: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐6  Project Development    

1.2.2 Transportation Evaluation Criteria 

Transportationevaluationcriteria(TEC)aretypicallyusedtoassesswhetherproposedtransportationprojectsshouldbesupportedwithfunding.CriteriafortheCityofNorwalkweredevelopedaftertheoverallgoalsdescribedabovewereestablished.AspartofthedevelopmentoftheTMP,unifiedweightswereassignedtoeachgoalandapointsystem(orlevelofeffectiveness/importance)wasdevelopedforeachcriteriontoreflecttheCity’spriorities.

1.2.2.1 Goal 1: Safety 

CrashRatio(RA/RC)‐Safetyisoftenevaluatedbylookingatthehistoryofcrashestoindicatewheresafetyissuesmayexist.Intersectionsorroadwaysthathavethegreatestnumberofcrashespervehiculartrafficvolumemayindicatethatapre‐existingconditionexiststhatisaffectingthesafetyoftheroadway.Locationswiththehighestcrashratesshouldbeprioritizedforimprovements.

NumberofFatalCrashes–Althoughnumberofcrashesisimportanttoassessalocation’ssafetylevel,theseverityofthecrashcanalsoinformofficialsofanunsafelocation.Ifafatalityoccurredataparticularlocation,itwarrantstheneedofathoroughevaluationandprioritizationforimprovements.

SLOSSSListInclusion–AlocationincludedintheSLOSSSlistindicatesitpresentssafetydeficiencies.TheSLOSSSlistismaintainedbyConnDOTforlocationsunderStatejurisdiction.LocationsundertheCityofNorwalkjurisdictionmayalsobeevaluated,however,byusingthesamemethodology.IfalocationhasaCrashRatiogreaterthan1andanumberofcrashesgreaterthan15,thenthislocationshouldbetreatedasifitwasincludedintheSLOSSSlist.

Pedestrian/BicycleCrashes–Pedestriansandbicyclistsaremorevulnerablethanpeopleprotectedbyvehicles.Thus,locationswiththesetypeofcrasheswillbeprioritizedforimprovements.

VehicularSpeeds–Oneoffactorsthatcontributetowardsunsafeconditionsisspeeding.Locationswherespeedsareconsistentlyabovethespeedlimitcreateapotentiallyunsafeenvironmentfordrivers,pedestriansandbicyclists.

1.2.2.2 Goal 2: Pedestrian and Bicycle Access and Mobility 

ConditionofPedestrianFacilities–Adequate,convenientandwell‐maintainedfacilitiesareessentialtoprovideasafeandcomfortablepedestrianenvironment.Locationswithinadequateorlackingpedestrianfacilitieswillbeprioritizedforimprovements.

ExistingPedestrianVolumes–Pedestrianvolumesisagoodindicationoftheneedforpedestrianfacilitiesataparticularlocation.Locationswithhighpedestrianvolumeswillbeprioritizedforimprovements.Ifappropriate,locationsthat

Page 7: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐7 

currentlyhavelowpedestrianvolumes,butwouldlikelyseeanincreaseiffacilitieswereprovided,mayconsiderusingprojectedfuturevolumes.

ConditionofBicycleFacilities–Adequate,convenientandwell‐maintainedfacilitiesareessentialtoprovideasafeandcomfortablebicyclingenvironment.Locationswithinadequateorlackingbicyclefacilitieswillbeprioritizedforimprovements.

ExistingBicycleVolumes–Bicyclevolumesisagoodindicationoftheneedforbicyclefacilitiesataparticularlocation.Locationswithhighcyclistvolumeswillbeprioritizedforimprovements.Ifappropriate,projectedfuturevolumesmaybeusedasinsomesituationslowbicyclevolumesaretheresultofthelackinginbicyclefacilities.

DesignatedPedestrian/BicycleCorridor–TheCityofNorwalkhasrecentlycompletedthePedestrian&BikewayTransportationPlan1whichpresentsadetailedplanforcurrentconditionsofbike/pedestrianfacilities,prioritycorridors,schematicdesigns,andarecommendedimprovementPlanfortheCity.Theseprioritycorridorswereidentifiedaslocationsdeemedmostappropriateforusebypedestriansand/orcyclistsbytheCityandshouldbeconsideredwhendevelopingProjectNeedstatements.Thesefacilitieswillbeprioritizedforimprovements.Additionally,thereareanumberofotherstudiesandprojectsthatareon‐goinginandaroundtheCitythatshouldalsobeconsidered.AcompleteandupdatedlistingoftheseprojectsandplanscanbefoundontheCityofNorwalk’swebsite,andinclude:

o Norwalk’sConnectivityPlan

o CentralNorwalkTransportation&PedestrianMasterPlan

o CirculatorStudy

o OysterShellParkPlan

o TheConnecticutStatewideBicycleandPedestrianPlan

o SWRPABicycle&PedestrianStudies(includingtheMerrittParkwayTrailStudy,theNorwalkRiverValleyTrail,andtheConnecticutCoastalAccessGuide).

PrimaryAccesstoTransitService–Efficientuseoftransitservicesrequirethatadequate,convenientandsafeaccesstostationsandstopsbeprovided.Thus,pedestrianfacilitiesinparticular,butalsobicyclefacilities,thatconnectpeopletotransitwillbeprioritizedforimprovements.

PrimaryAccesstoActivityCenter–Facilitiesthatprovideaccesstoanactivitycentersuchasschools,libraries,churches,parksorrecreationareas,neighborhoodcentersandhospitals,amongothers,willbeprioritizedforimprovements.

1 Norwalk Pedestrian & Bikeway Transportation Plan, Fitzgerald & Halliday, Inc. (FHI), 2011 

Page 8: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐8  Project Development    

1.2.2.3 Goal 3: Vehicular Access and Mobility 

ExistingTrafficVolume–Onecomponentofimprovingaccessandmobilityistotargetprojectsthatimprovetravelforthegreatestnumberofpeople.Trafficvolumesprovideanindicationofwhichfacilitiesreceivethegreatestusebasedonexistingtravelpatterns.Therefore,roadlinkswithhighertrafficvolumesindicateagreaterexistingtraveldemandandshouldreceivepriorityoverlinkswithlowertrafficvolumes.

HeavyTruckTraffic–Economicdevelopmentisakeycomponentofaccessandmobility.Thoseroadwaysorintersectionsthatcarryheavytrucktrafficareassumedtobecriticaltoeconomicdevelopmentandwillbeprioritizedoverfacilitiesthatdonotcarryheavytrucktraffic.Conversely,whentrucktraffictravelsalongresidentialstreets,itcreatesanundesirableenvironment.Inthiscase,residentialroadwaysorintersectionthatcarryheavytrucktrafficareassumedtopresentaneighborhoodissueandshouldreceivepriorityoverotherresidentialfacilitiesthatdonotsufferfromheavytrucktraffic.

Operations–Congestionisoneofthemaindeterrentsinallowingforgoodvehicularaccessandmobility.Unaccountablehoursofproductivityarelosttocongestioneveryday.Assuch,heavilycongestedlocationswillbeprioritizedforimprovements.Ifappropriate,theseimprovementsmayoccuratanearbyfacility(suchasaparallelroute)incaseofcut‐throughsituationsorinadequateuseofafacilitybasedonitsfunctionalclassification.

PavementCondition–Thequalityofthepavementconditionisamajorfactorinprovidinghigh‐qualityaccessandmobility.Therefore,roadwayswithlowerpavementconditionratingswillreceivehigherprioritythanlinkswithhigherratings.

PrimaryAccesstoCommercialAreas–TheCityofNorwalk’stransportationnetworknotonlyprovidesaccessforresidents,italsoplaysacriticalroleineconomicdevelopmentwithintheCity.Therefore,facilitiesthatareproximatetoPriorityDevelopmentzonesand/ortargetedcommercialareasmayserveasimportantaccessroutesforeconomicdevelopmentactivitiesandshouldreceivepriorityoverroadwaylinksthatarefurtherfromtheseareas.ConsultationwiththeCity’sRedevelopmentand/orPlanningandZoningStaffshouldbemadetodetermineiftheareafallswithinornearoneoftheCitieseconomicdevelopmentareas.

TransitCorridor–Transithastheabilityoftransportingamuchlargernumberofusersthananyothermodeoftransportation.Assuch,emphasisonfacilitiesthatservepublictransportationcanpotentiallybenefitmobilitytothegreatestextent.Transitcorridors,consequently,willbeprioritizedforimprovements.

Page 9: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐9 

1.2.2.4 Goal 4: Degree of Support 

DegreeofPublicSupport–AsemphasizedthroughoutthisChapter,publicinvolvementduringallstepsofthisprocessiscrucial.AprojectthatiswellreceivedbymostinterestedpartieshasahigherchanceofsuccessandislikelytobemorebeneficialtotheCity.Thus,projectswithahigherlevelofsupportwillbeprioritizedforimprovements.

PotentialFundingSources‐AvarietyoffundingalternativesexistsfortransportationimprovementsasidefromCitymoneys.Projectswithalternatefundingsources,eitherpartialorfull,havesomeadvantageoverthosethatwouldrequirefullCityfunding.

1.2.3 Project Need Form 

ThisstepintheprojectdevelopmentprocessleadstocompletionofaProjectNeedForm(PNF).ThePNFprovidessufficientmaterialtoallowCitystafftounderstandthetransportationneed(s),andresultsinoneofthefollowingthreeoutcomes: Verificationoftheproblem,need,oropportunitytoenableittomoveforwardfor

considerationofdesignefforts;

Determinationoftheleveloffurtherprojectplanningwarranted;or,

Dismissalofaprojectfromfurtherconsideration.

AcopyoftheProjectNeedFormisprovidedinAppendixofthisreport.ElectronicversionsofthisformandinstructionsforcompletioncanbefoundontheCityofNorwalk’swebsite(www.norwalkct.org).Atthebeginningofthisprocess,theproponentshouldmeetwithappropriateCitystaff.Thisproactive,informalreviewandconsultationcanhelpensuretheprojectwilldevelopwithfewerproblemsinfuturephases.TheProjectNeedFormisimportanttodefinethecondition,deficiency,orsituationthatindicatestheneedforaction—theprojectneed.Thestatementshouldbesupportedbyfacts,statistics,orevenbyplansorphotographstotheextentthatinformationisavailable.Itiscriticalthattheproponentunderstandthatproject“need”isnotaproject“description”(suchas“replaceabridge”or“reconstructaroad”).Thatapproach“decides”theprojectoutcometooearlyintheprocess.AgoalofthePNFistostate,ingeneralterms,thedeficienciesorneedsrelatedtothetransportationfacility(suchas“thebridgeisstructurallydeficient”or“thepavementisinpoorcondition”).TheProjectNeedFormshoulddocumenttheproblemsandexplainwhycorrectiveactionisneeded.Exampleofaneedcouldbe:

Page 10: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐10  Project Development    

Theintersectionishazardous.Thehigh‐crashrateattheintersectionillustratesthisproblem.

Thereissignificantcongestionattheintersection.Duringpeakperiods,trafficfromthesidestreethasdifficultyexitingontothemainstreetandlongqueuesdevelop.

Thereisnoformalaccommodationforbicyclesorpedestriansbetweentheelementaryschoolandthelargeresidentialneighborhoodtothenorthwhereasignificantportionofthestudentbodylive.

Thepurposeofaprojectisdrivenbytheseneeds.Asexamples,thepurposemightbetoimprovesafety,toenhancemobility,toenhancecommercialdevelopment,toimprovestructuralcapacity,toenhancepedestrianandbicyclemovement,etc.,orsomecombinationofthese.TheTransportationEvaluationCriteriadiscussedabovearepartoftheProjectNeedForm,andwillallowtheCitytoobjectivelydevelopapreliminaryprojectprioritylist.

1.2.3.1 Identify Project Constituents and Public Outreach Plan 

Whendefiningtheprojectneed,theproponentshouldalsothinkaboutpublicsupportoftheproject.Toachievethis,theProjectNeedFormincludesadegreepublicsupportsection.Todemonstratethedegreeofsupport,theProponentshouldincludewiththeProjectNeedForm: Identificationlikelyinterestedpartiesandstakeholders;

Documentationofpublicoutreachandfeedbacktodate(ifany);and

Outlineofapublicparticipationprocessformovingforward.

Itisimportantthattheproponentbefairandobjectiveinselectingwhomightbeinterestedinaparticularproject.Simplyidentifying“supporters”and“likeminded”individuals,whileexcludingpotential“detractors”and“alternativeminded”individuals,doesnotservetoadvancetheprojectcooperatively.Ifunsure,theproponentshouldworkwiththeCitystafftoidentifyandseekassistanceinreachingouttoallpossiblyaffectedparties.

1.2.3.2 Project Need Form Review 

OncetheProjectNeedFormisprepared,itissubmittedtotheCitystaffforinitialreview.TheintentoftheProjectNeedFormreviewprocessistoallowtheproponenttoproposeaprojectatitsmostbasicleveltotheCity.Throughthisprocess,Citystaffcanprovideguidanceforprojectscopingandplanningconsiderations,inadditiontosuggestionsforlikelystepsneededforprojectapprovals.Thisguidancecanbeveryvaluable,especiallyifgivenbeforetheproponentinvestssignificanttimeandresourcesintheprojectdesign.

Page 11: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐11 

Throughthisreview,theproponentmaybeaskedtoanswerquestionsthatarisefromthePNFreview,toprovidefurtherdocumentationonthealternativesconsidered,and/ortocomplete(additional)publicoutreach.AftertheProjectNeedFormhasbeenreviewedandevaluatedbytheCity,theprojectwouldbeinsertedonthepreliminaryprioritylistbasedonthepointsscoredonthePNFpertheTransportationEvaluationCriteriadiscussedpreviously.Iftheprojectplaceshighenoughonthelist,itwouldthenbecomeeligibletomoveintoPlanning/PreliminaryDesign(StepII).Someprojectsthatarestraightforward,oraresupportedbypriorplanningstudies,areexpectedtomovedirectlytoProjectInitiation(StepIII).

Step I Outcomes 

ThefollowingarepotentialoutcomesfromStepIofthedevelopmentprocess: AgreementbytheprojectproponentandtheCityontheproblemandproject

definition(extentandmagnitude)toenableittomoveforwardintoplanning/design(nofurtherdocumentationrequired);

Determinationthatthereisaproblem,need,oropportunitytoaddressbutfurtherprojectplanningiswarrantedtobetterdefinetheprojectneed(resubmissionofPNF);

Adviceonalternativestoconsiderintheplanning/preliminarydesignprocess;

Placementoftheprojectinthepreliminaryprioritylist;or

Arecommendationthattheprojectneedisnotgreatenoughtoadvancetoimplementation/designeffortsand(initscurrentform)shouldbedismissedfromfurtherconsideration.

1.3 Step II: Planning/Preliminary Design 

Inthisphase,theproponentadvancestheprojectdesignataminimumtotheextentthatissues,impacts,andpotentialapprovalsrequiredcanbeidentified.TheProjectNeedFormanditsreviewwillhelptooutlinethescopeofissuestobeconsideredinthisphase.Thelevelofplanninganddesignneedwillvarywidelybasedonthecomplexityoftheproject(fromstreamlinedtomoreinvolvedandcomplex).Amoreinvolvedalternativesanalysisisintegratedaspartofthisprocessforallnewfacilities.Itisalsorequiredforimprovementorexpansionprojectswherethefeasibilityofachievingthedesiredenhancementswithacceptableimpactsandreasonableinvestmentisunclearattheoutset.DuringthereviewoftheProjectNeedForm,thenecessarylevelofeffortandresponsibilitiesforplanningwillbedetermined.TypicalplanningrequirementsfordifferentprojecttypesareillustratedinExhibit1‐2.

Page 12: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐12  Project Development    

Forastraightforwardproject(examplesmightincludeasidewalkproject,roadwayresurfacing,oratrafficsignalequipmentupgrade),theproponentcanseekapprovaltoproceeddirectlytoProjectInitiationfromtheProjectNeedForm.Inthiscase,theproponentdefinestheactionsproposedtoaddresstheprojectneed(s),describesthealternativesconsidered(ifnecessary),anddocumentsanyanticipatedimpactsaspartoftheProjectNeedForm.(Thismayalsobethebestapproachwheredetailedplanningfortheprojecthasalreadyoccurredandisdocumented).Formorecomplexprojects(asexamples,ifthereareseveralalternativestoconsider,iftherearecontextualconstraintswhichaddcomplexitytothesolution,orifthereiskeenpublicinterest),theproponentshouldadvancetheproposedprojectfurthertoprovidetheCitywithsufficientinformationforthenextstepintheprocess,ProjectInitiation.

Page 13: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐13 

 

Exhibit 1‐2  Likely Planning Approaches for Different Types of Projects 

Likely Planning Approach

Project Need

Form

Project Planning Focused on a Clear and Feasible Solution and

Minor Variants

Full Alternatives

Analysis System Preservation Roadways, Sidewalks, and Multiuse Paths Resurfacing Reconstruction/Reconfiguration within Existing Pavement

Bridges Rehabilitation Replacement System Improvement or Expansion New Roadway or Multiuse Path Widened Roadway, Sidewalk or Addition or Multiuse Path Widening

Intersection, Roundabout, or Traffic Signal Modification

New Interchange or Interchange Reconfiguration Median, Roadside Safety, or Signage Improvements Traffic Calming, Streetscape, Lighting, or Transit Enhancements

New or Widened Bridge New or Expanded TDM/Park-and-Ride Lot New or Expanded Traffic Management System Required Suggested for projects categories indicated and required for more complex projects with each category

1.3.1 Project Planning Report/Preliminary Design  

ProjectsthatrequirefurtherplanningwillresultinthepreparationofaProjectPlanningReport.Manytraditionalplanningstudiessuchascorridorstudies,functionaldesignreports,andlocationstudiescanserveasaprojectplanningreportifdoneinafashionthatisconsistentwiththeprinciplesofthisTransportationDesignGuideandcompletedwithpublicparticipation.AgeneralizedoutlineforthebasicprojectplanningprocessisprovidedinExhibit1‐3.Itisexpectedthatthisoutlinewillbetailoredforeachproject.Theprocessdescribedisnotintendedtobeoverlyprescriptiveorburdensome.Rather,theprojectproponentisencouragedtotailoractivitiesappropriatetotheextent,complexity,andtypeofprojecttoensurethatallprojectbenefits,impacts,andcostsareobjectivelyestimated.Aspartofthisprocess,theproponentshouldalsoconductapublicparticipationprogram,provideinformationregardingtheproject’sconsistencywithstateandregionalpolicies,

Page 14: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐14  Project Development    

anddecide,basedonalltheinformationgatheredintheplanningprocessaswellaspublicinput,whethertocontinuetheprojectdevelopmentprocessandsubmitaProjectInitiationForm(PIF)underStepIII.Regularcheck‐inmeetingswiththeCityarehelpfulthoughthisprocess.Thedetailedstepsintheplanningprocess,asoutlinedinExhibit1‐3,arefurtherdescribedinthefollowingpages.Exhibit 1‐3  Overview of Project Planning Tasks 

Part A: Define Existing Context, Confirm Project Need(s) Establish Goals and Objectives

Inventory and Data Collection/Site Walk Definition of the Community Context Definition of Transportation and Land Use Functions Project Goals and Objectives

Part B: Initial Public Outreach

Early Local Issues Meeting Environmental Agencies Coordination Individual Outreach Meetings

Part C: Project Definition

Development of Alternatives (if necessary) Establishment of Basic Design Controls Define Future Conditions (if necessary) Screening of Alternatives Project benefits Project Impacts Consistency with appropriate policies and plans Cost

Part D: Project Review and Refinement

Project Presentation Meeting Resource Agencies Coordination Alternative Refinement Concept Engineering Plans Evaluation Matrices

Part E: Final Recommendations

Project Definition Description of the proposed project and project alternatives considered

Project Benefits and Impacts Project Consistency with City Policies and Plans Public Participation Process Documentation of planning public participation process

Final Recommendations

Page 15: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐15 

1.3.1.1 Part A: Define Existing Context, Confirm Project Need(s), Establish Goals and Objectives 

Thefirststepistoconfirmprojectneedthroughaninventoryofexistingconditions.Oncetheprojectneedisconfirmed,theproponentshouldclearlyarticulatethegoalsandobjectivesfortheproject.Thelevelofalternativesanalysisanddetailnecessaryisdirectlyrelatedtothecomplexorstraightforwardnatureoftheproject.

Inventory and Data Collection/Site Walk 

Asitevisitshouldbethefirststepinprojectplanning/preliminarydesignasitprovidesanopportunitytoviewtheprojectareainmoredetail.Ifappropriate,localprojectconstituentsandtechnicalspecialistsfamiliarwiththefeaturesorconcernsrelatedtotheprojectshouldbeinvitedtoprovideadditionalperspectives.Informationshouldbecompiledorcollectedtoprovidetherangeofdataappropriatefortheproject.Keyitemstoinvestigateduringasitevisitaredescribedbelow: Contextresources(environmental,cultural,historic,andman‐madeconstraints)are

mappedfortheprojectarea.

Traveldemands(forallmodes)andcrashdataarenecessarytoidentifyanycapacityand/orsafetyproblems,orpotentialsafetyproblems.SomeorallofthesedatamayalreadyhavebeencollectedtocompletetheProjectNeedsForm.

Pavementandstructuresufficiencyandinventoryinformationishelpfulindeterminingtheextentoftreatmentnecessaryforthesefeatures.Apavementmanagementsystemevaluationandratingisrecommended,alongwithphotodocumentationofthesite.Onceagain,someorallofthesedatamayalreadyhavebeencollectedtocompletetheProjectNeedsForm.

Anaccessaudittosurveyaccessibilityelementssuchas:curbramplocations,slopes,andobstacles;locationofcrosswalks;audiblesignals;transportationsignage;sidewalkwidth,slope,andobstacles;connectivity;anddriveway/sidewalkintersections.

Hydraulicanalysistohelptodeterminehydraulicadequacyofthestructureortheeffectonthefloodplainwherebridgesorstructuresareinvolved.

Right‐of‐wayinformationhelpstoidentifypropertyownersandpropertylines.

Utilityinformationisusefulindetermininganyspecialneedsrequiredforutilityrelocation(s).

Adetailedsurveyoftheprojectareahelpstoidentifythelocationofvariousfeaturesandresourcespotentiallyaffectedbytheproposedimprovement(althoughitisnotnecessaryatthispointintheprojectdevelopmentprocess).

Page 16: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐16  Project Development    

Definition of Community Context 

Itisimportantfortheprojectproponenttounderstandtheplanningcontext,landuses,andcharacteroftheprojectlocationandsurroundingcommunity.Localknowledgeorasitevisitisimportantinunderstandingsurroundinglandusesandcommunitycharacter.AUSGStopographicbasemap,GISmappinginformation,andorthographicphotoscanbeusedtoidentifyanddocumentvariousaspectsofthearea.Theseguidescanshowsurroundinglandusesandlandcover(openfields,forestandforesttypeifknown,agriculturalland,town,village,city,orcommercialcorridors);visuallydistinctareassuchasbuildings,landforms,valleys,hilltops,notches,waterbodies,rivers,streams,andwatercourses;prominentviewsandvistasalongtheroad;publicfacilitiesorplaces;recreationalfacilities;trees;andtherelationshiptointersectingroadsandactivitycenters.SomeofthisinformationmayalsobeavailablefromthepreviouslycompletedPNF.

Definition of Transportation and Land Use Functions 

Itisimportantfortheprojectproponenttounderstandthemulti‐modalaspectsoftheprojectlocation.Duringthesitevisit,theprojectproponentmustbecognizantofbicycleandpedestrianmovements,orthepotentialforthesemovements,andpublictransportationavailability.Theproponentshouldalsobeawareoftheproximityofconnectionpointsforothermodesoffreightandpassengertransportation.Anytransportationsolutionmustconformwithlocalandregionalplans.Pertinentsectionsofthelocalandregionallanduseandtransportationplansshouldbereviewedaspartofthisprocess.Thisincludestransportationandlanduse,localandregionalpoliciesastheyrelatetotheprojectlocation,theroadwayinvolved,andtheneighborhood.Designatedgrowthareas,historicdistricts,designatedscenicroadsandareas,uniquenaturalareas,andareasdesignatedforfutureaccessmanagementbyofficialcitymapsshouldbeacknowledgedinthevicinityoftheprojectlocation.Itisimportantthatfutureplannedlandusesbeunderstoodandthecity’sgoalsforgrowth,protectionofnaturalandhistoricresources,andfuturetransportationfacilitiesbeacknowledged.

Project Goals and Objectives 

Frominformationobtainedduringdatacollectionandtheinputreceivedfrominterestedparties,theprojectproponentwilldefinegoalsandobjectivesfortheprojectconsistentwiththeplansandpoliciesoftheCity.Theneedsfortheprojectmustconclusivelyshowthattheprojectisjustified.Thelanguageshouldbeclearandunderstandabletothelayperson.

1.3.1.2 Part B: Initial Public Outreach 

Publicoutreachandinputinaprojectshouldbeginearlyinprojectplanningandbeforethereisarecommendedcourseofaction.Thisprocessstartswithanearlyinformationalmeetingandcontinuesatstrategicmilestonesduringtheplanningprocess.Effortshouldbemadetoreachabroadspectrumofinterestedpartiesatthisearlyprojectstage.

Page 17: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐17 

PlanningforlargerormorecomplexprojectsmightalsobewellservedbytheestablishmentofanadvisoryTaskForceorSteeringCommitteeattheoutset.Thelevelofpublicoutreachatthisstageshouldbecommensurabletothecomplexityoftheproject.GeneralpublicoutreachguidelinesandtoolsaredescribedinSection2‐1.9ofthischapter.

Local Issues Meeting 

A“LocalIssuesMeeting”shouldbeheldearlyintheplanningprocess,aimedprimarilyatgatheringlocalcomments.Thismeetingisnotaforumtopresentproposalsordevelopsolutions.(Forlargerprojects,morethanoneLocalIssuesMeetingmayberequired.)Thismeetingshouldalsoservetofosteraworkingrelationshipwithlocalcommunitymembers.Thisisaccomplishedbylisteningtoissuesandideasandmakingeveryattempttoincorporatesoundandcosteffectivesuggestionsintotheanalysisofalternatives.CommentsfromtheLocalIssuesMeetingneedtobedocumentedandmadeavailabletoallwhowerepresent,ortothosewhorequestthem.TheminutesoftheLocalIssuesMeetingshouldbeincludedintheprojectreportandkeptatanaccessiblecentrallocationattheCityoffices.FollowingtheLocalIssuesMeeting,theprojectproponentmustevaluatethecommentsreceivedandensurethatappropriatedetailsareintegratedintotheproject.Oncetheissueshavebeenidentified,oneoftheprojectproponent’sbiggestchallengesistobalancetheseissueswithalloftheotherprojectissuesandworktoincorporatecommunityconcernsinprojectdecision‐makinganddesign,asappropriate.Itisimportanttogivedueconsiderationtoallcommentsexpressedthroughthepublicprocess.

Environmental Agencies Coordination  

RegulatoryagenciesthathavearoleinprotectingtheCity’sresourcesandaresponsibilitytoissuepermitsfortransportationprojectsthataffecttheseresources,incoordinationwithregional,and/orstateresourcestaff(ifapplicable),mayprovideavailableresearchinformationfortheLocalIssuesMeeting.Dependingonthecomplexityoftheprojectandresourcespresentintheprojectarea,theseagenciesshouldbeinvitedtothemeetingandgivenanopportunitytopresentissuesorconcerns,eitherinwritingbeforethemeetingorinpersonatthemeeting.Theagency’spreliminarycommentsregardingwhetherresourcesarepresentintheproblemareaandtheirextentandpotentialsignificanceisvaluableinsightatthisstageofprojectdevelopment.Theresourceagenciesshouldbegivenasmuchadvancenoticeofthemeetingaspossible.Ideally,environmentalissuesareidentifiedthroughthisprocessandpublicresponsetotheissuesissought,asappropriate,atthemeeting.However,theformalinter‐agencydiscussionandresolutionofregulatoryissuesoccursduringlaterstepsintheProjectDevelopmentProcess.

Helpful information on public outreach is provided in Section 1.9 of this chapter.

Page 18: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐18  Project Development    

Individual Outreach Meetings 

Theremaybekeyindividuals,localofficials,agencies,oradvocacygroupsthatmaynotbeattheLocalIssuesMeetingbutwhomaybeworthseekingoutforvaluableinput.Theseindividualsorgroupsareoftenidentifiedatthelocalmeetingbyalocalofficialorresidentsaying“youshouldreallyspeaktosoandso…”Theprojectteamshouldallowtimetoconductinformaloutreachmeetingstoroundoutitsunderstandingofprojectissues,opportunities,andconstraints.Anysignificantissuesthatdevelopoutoftheindividualmeetingsshouldberecountedtothecommunityastheprocessevolves.

1.3.1.3 Part C: Project Definition 

Afterinitialpublicoutreach,thenextstepsaretorefineprojectgoalsandobjectives,reviewalternatives,anddefinetheproject.Thesestepsshouldreflectcommentsreceivedduringthepublicandagencyoutreachdescribedabove.

Development of Alternatives  

Severalreasonablebuildalternativesmightneedtobeinvestigatedandconsidered.AlternativesshouldbedevelopedusingthedesignguidanceprovidedinthisTransportationManagementGuide.Insomecases,onlycursoryreviewofalternativesmayberequired.Ifoneormorebuildscenariosaredeveloped,theyshouldincludethefollowinginformation: Alternativetypicalroadwaysectionsaddressingtheneedsofallusers.

Multi‐modalaccommodationandoperationalassumptionsregardingallocationofright‐of‐way,trafficcontrols,andenhancements.

Accessibilityissues,especiallyslopeorcross‐slopeconcernsthatmaybedifficulttoresolve.

Compatibilitywithadjacentlandusesanditsassociatedactivity.

Conceptualroadwayorprojectalignment(existingandproposed),approximatelimitsofimpact,andapproximateboundariesofresources.Ascaleof100feetperinchisusefulfortheseconcepts.Forsmallerproblemareassuchasurbanlocations,intersections,andbridges,asmallerscale(40or50feettotheinch)shouldbeused.(Profilesheetswouldonlybedevelopedfortheareaswithproposedgradechanges.)

Criticalcross‐sections,definedaspointswherestructuresandresourcesareavoidedorimpactedbythetypicalsection.Structuresaredefinedasbuildings,bridges,walls,andculverts(48inchesorlarger).

Costestimates

Page 19: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐19 

Theprojectproponentmusttakecaretoexaminemulti‐modalneedsandpossibilitiesforimprovementsduringthealternativedevelopmentprocess.Thesepossibilitiesaretobeaddressedandthefeasibilityandpotentialofeachoptiondiscussed.TransportationSystemsManagement,TravelDemandManagement,TrafficCalming,andIntelligentTransportationSystemsmayalsobereasonablealternativestoevaluate.

Establishment of Basic Design Controls 

Basicdesigncontrolsserveasthefoundationforestablishingthephysicalform,safetyandfunctionalityofthefacility.Somedesigncontrolsareinherentcharacteristicsofthefacility(forexample,itscontextandtheexistingtransportationdemandsplaceduponit).Otherbasicdesigncontrolsareselectedordeterminedbythedesigner,workingwiththeproponent,toaddressaproject’spurposeandneed(forexample,thelevelofserviceprovidedtopedestrians,bicyclists,anddrivers).Selectingappropriatevaluesorcharacteristicsforthesebasicdesigncontrolsisessentialtoachieveasafe,effective,contextsensitivedesign.Section1,Chapter2oftheTMPillustratesthebasicdesigncontrolsandtheirinfluenceonthephysicalcharacteristicsofaroadway: RoadwayContext,includingAreaType,RoadwayType,andAccessControl(Section

1,Chapter2.2)

RoadwayUsers(Section1,Chapter2.3)

TransportationDemand(Section1,Chapter2.4)

MeasuresofEffectiveness(Section1,Chapter2.5)

Speed(Section1,Chapter2.6)

SightDistance(Section1,Chapter2.7)

Thesebasicdesigncontrols,onceestablished,arecarriedforwardthroughprojectdesign.

Define Future Conditions  

Projectsthataredevelopedshouldserveausefulfunctionforsometimeintothefuture.Projectsthatinvolvesignificantcapitalinvestmentaregenerallyassumedtohavea20‐yearlifewhileprojectsoflesserinvestmentaregenerallyassumedtohaveafive‐yearorten‐yearlife.Thisassumptionrequirestheplannertoanticipatewhatisgoingtohappentotransportationdemandsinthefuturewithandwithouttheprojecttoassesstheproject’seffectivenessatmeetingneeds.Section1,Chapter3(Subsection3.4),presentsimportantconsiderationsinforecastingtransportationdemandforprojects.

Screening of Alternatives 

Ifseveralalternativesarebeingconsidered,theyshouldbefullydescribedwithconciseandillustrativegraphicsorplans.Totheextentthatprojectdesignelements(i.e.,sidewalks,bikelanes,travellanes,bridgetypes,etc.)areknown,theyshouldbedescribed.

Visual depictions of project alternatives are useful to convey the full extent of the project.

Page 20: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐20  Project Development    

Alternativesshouldbedevelopedtocomparablelevelsandtheproject’seffectsshouldbedescribedtothemaximumextentknownatthispointintheprocess.Theanalysisthatiscompiledandsummarizedshouldcharacterize: Benefits

Impacts

Consistencywithcityplansandpolicies

Costs

Thecostofaprojectisasignificantportionofthetransportation‐relateddecisionmakingprocessandshouldbejustifiedbyimprovementsinsafety,publicneedand/orassetmanagement,balancedwithenvironmentalandothercontextualconstraints.Therefore,thecostestimateproceduremustbeunbiasedandcomprehensive(toincludeallengineeringandpermitting,right‐of‐way,utilityrelocationcosts,mitigationcosts,andconstructioncosts).Itmustplaceallreasonablealternativesonthesamelevelforfairnessintheselectionprocess.Analternativewithtoohighofanestimatemightbeeliminated,whileanalternativewithalowestimatecouldbeselectedduetomisrepresentation.Atthisstage,itisalsoappropriatetostartthinkingaboutprojectfunding.Thisincludesanexplorationoffundingsources,theirrequirementsandrestrictions,obligationsforlocalshareofprojectcosts,otherpartneringopportunities,etc.

1.3.1.4 Part D: Project Review and Refinement 

Oncealternativeshavebeenconsideredandtheprojectbetterdefined,theproponentneedstoensurecontinuedpublicandagencyinvolvementintheprojectreviewandrefinementprocess,asoutlinedbelow.

Project Presentation Meeting 

Theprojectproponentshouldholdapublicmeetingandinvitetheconstituentsaspreviouslydefinedtooverviewthealternativesconsidered,theproposedproject,andtosolicitinput.Iftheprojectasdefinedisunacceptable,theprojectproponentshouldattempttoresolveanyconflicts.Failingthis,theprojectproponentshoulddevelopnewalternatives,andscheduleanewProjectPresentationMeeting.Thisprocessshouldcontinueuntilapreferredalternativeisdetermined.Duringthesemeetings,itishelpfultoprovidehandoutmaterialsthatpresenttheprojectanditsalternativessothattheparticipantshaveareferencetoreview.Avisualdepictionofeachbuildalternativeisbeneficial.Thevisualrepresentationshouldbepreparedsothatalaypersoncanunderstandthealternativebeingpresented.An

Page 21: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐21 

exampleofhowaprojectmightbepresentedisprovidedinExhibit1‐5.Theprojectproponentshouldfacilitateadiscussionofhoweachalternativeaddressestheneedsoftheprojectaswellasitsdrawbacks.   Exhibit 1‐5 Example of Visual Representation of a Project Alternative  

Plan View

Cross-sectional View

Source: King Street Corridor Study, Northampton, MA 2003

MinutesoftheProjectPresentationMeetingneedtobedocumentedandmadeavailable.Theseminutesareimportanttodocumentpubliccommentsthatmaybevaluableinput

Page 22: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐22  Project Development    

tothedesignprocessandtoensurethattherearenomisunderstandingsconcerningoverallpublicconsensusontheprojectasdefined.Theminutesshouldbesenttoallattendees,cityofficials,andotheragenciesthathaveprojectjurisdictionorspecialexpertise,andmadeavailabletothepublicatanaccessiblemunicipallocation.Therecipientsoftheminutesshouldhaveasettimeperiodfromthepostmarkeddatetocontestthemandaddclarifications.

Resource Agencies Coordination 

Forprojectswithanticipatedimpactstosensitivenaturalandmanmaderesources,thisisanappropriatetimeintheprocesstoassessfuturerequirementsforprojectdevelopmentwithaffectedregulatoryagencies.Theproponentshouldsolicitcommentsfromresourceagenciesregardingtheirviewsonthevariousalternativesunderconsideration,therequiredenvironmentalpermits,andtheprocessmovingforward.

Alternative Refinement 

Inputreceivedfromthepublicortheaffectedenvironmentalresourceagenciesmayrequirerefinementtothepreferredalternative(s).Theserefinementsmayinvolveminorchangestopreviouslydevelopedconceptsorthedevelopmentofaconceptualengineeringplanforthepreferredactioningreaterdetail.(Itisimperativethattheagenciesbeinformedofanyprojectchangesthattakeplaceduringthe“ProjectPlanning”and“ProjectDesign”phasesofthedevelopmentprocess.)Theinformationdevelopedduringthistaskshouldbeasaccurateaspossibleatthisstageofprojectdevelopmentasitmaybethebasisforearlyenvironmentaldocumentationoraspartofanapplicationforprojectfunding.

1.3.1.5 Part E: Final Recommendations 

Inthislastcomponent,theproponentdocumentstheprocess,publicoutreach,anddecisionsmade,asdescribedbelow.

Draft Report 

Followingpublic,local,andenvironmentalagencyreviewofthealternativesandproposedproject,theplanningreportcanbecompletedandmadereadyforreview.Theplanningreportdocumentstheneedfortheproject,existingandfutureconditions,alternativesconsidered,publicoutreachoutcome,andthesolutionrecommended.Itisimportantthat,ataminimum,thereportsummarizethe: ProjectDefinition:

Descriptionoftheproposedprojectandprojectalternativesconsidered

ProjectBenefitsandImpacts

ProjectConsistencywithCityPoliciesandPlans

Page 23: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐23 

PublicOutreachProcess:

Documentationofpublicoutreachduringplanningprocess

FinalRecommendations

Theprojectproponentmay,attheirowndiscretion,distributethedraftreporttotheappropriatelocalofficials,staff,orkeyprojectconstituentsforreview.Theprojectproponentmayalsoelecttohavefinalpublicreviewoftheplanningrecommendationsbyholdinganadditionalpublicmeetingorbynotifyingpastprojectparticipantsoftheavailabilityofthedraftplanningreportatanaccessiblemunicipallocationforreview.

Final Planning Report 

Uponreceiptofcommentsandpublicinput(ifsoughtonthedraftreport),theprojectproponentwillfinalizethereport.

1.3.2 Detailed Alternatives Analysis 

Amorecomplexsetofneedsmaywarrantamoredetailedplanningandconceptualengineeringreviewofalternatives,theirimpactsandbenefits,andimplementationissues.Thisisparticularlytruewhenitisunclearwhatactionsare“feasible”toaddresstheidentifiedneeds.Inthiscase,theproponentshoulddevelopbaseinformation,documentresources,andcompletetransportationplanninganalysisandconceptualengineeringofthealternativesinmoredepthtoverify“projectfeasibility”andthepreferredaction.Thislevelofalternativesanalysisisappropriateforallnewfacilitiesandforimprovementorexpansionprojectswherethefeasibilityofachievingthedesiredenhancementswithacceptableimpactsandreasonableinvestmentisunclearattheoutset.Thekeyobjectivesofthiseffortaretoassessalternativestodeterminetheirengineeringfeasibility,environmentalimpactsandpermitability,economicviability,andpublicacceptance.

1.3.3 Review of Planning Efforts 

Uponcompletionoftheprojectplanning/preliminarydesigneffort,theprojectproponenthasessentiallytwooptionsbasedonitsoutcome:delayordroptheprojectfromconsideration,orsubmititwithaProjectInitiationFormandPriorityWorksheettoadesignatedDPWStaffPlanReviewTeam(orsimilarbodydevelopedforthisprocess)forreview,asdiscussedinthenextsection.Theintentofthisprocessistoallowtheproponenttopresentaprojectforreviewandpreliminaryfundingconsideration.

Page 24: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐24  Project Development    

Throughthisreview,theDPWStaffPlanReviewTeamcanprovideinsightonprojectdesignconsiderationsinadditiontolikelystepsneededforprojectapprovals.Withthisapproach,valuableguidancecanbeprovidedpriortotheproponentinvestingsignificanttimeandresourcesinprojectdesign.Ideally,atthisstage,theprojectwillbewelldocumented,locallyreviewedandendorsed,andproceedtoStepIII:ProjectInitiation,asoutlinedinthefollowingsection.

Step II Outcomes 

Thedecisionsthatareexpectedatthispointintheprojectdevelopmentprocessare: Consensusonprojectdefinition(orprojects,wheremultipleprojectsresultfromthe

planningprocess)anddecisiontosubmitaProjectInitiationFormtoenableittomoveforwardintoenvironmentaldocumentationand/ordesign;or

Arecommendationthattheprojectbedismissedfromfurtherconsiderationordelayed.(ThiswouldreflectacasewheretheinterestintheprojectmayhavewanedthroughtheProjectPlanningReportreviewif,inthesponsor’sanalysis,theissuesidentifiedcounterbalancetheexpectedbenefits,thusreducingtheproject’slikelihoodforafavorableoutcomeinthesubsequentreviewandprogrammingphase.)

1.4 Step III:  Project Initiation, Prioritization, and Programming 

IfaprojectistobeconstructedwithCityfunds,theprojectneedstobeapproved,prioritized,andprogrammedbyCityStaffandtheDPWStaffPlanReviewTeam.Thethirdstepintheprocessformallybeginsthereview,evaluation,prioritization,andprogrammingoftheproject.ThisstepisillustratedinExhibit1‐6.Theprogrammingoftransportationimprovementscanbeacomplexandsometimeslengthyprocessinvolvinglocal,state,andfederalagencyapprovals,dependingonthescopeoftheproject.Publicsupportfortheprojectiscriticalandcansignificantlyaltertheimplementationprocessandschedule.

1.4.1 Project Initiation Form 

TheProjectNeedFormorProjectPlanningReportdetailthefinalrecommendationsfortheprojectresultingfromearlyprojectplanning.ThenextstepintheprojectdevelopmentprocessinvolvessummarizingthefindingsanddirectiondefinedinaProjectInitiationForm(PIF)usedbyCityStaffandtheDPWStaffPlanReviewTeamforprojectreview,evaluation,andpotentiallyprioritizationandprogramming.ThePIFwill

Page 25: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐25 

becompletedbytheProponentandreviewedbyCityStaffandincludesthefollowinginformation: ProjectTypeandDescription,includinglocusmap

EvaluationoftheeffectivenessoftheProjectataddressingidentifiedneeds/issuesfromtheProjectNeedForm

AssessmentofthereadinessleveloftheProject,relatingtoprojectplandevelopmentandoutreach

Evaluationofprojectdetails,includingconceptualcostestimate,airqualitybenefitsandimpactstoright‐of‐way,environmentalresources,cultural/historicalresources,andenvironmentaljustice

ProjectNeedFormorProjectPlanningReportasanattachment

TheProjectInitiationFormforuseinthisprocessisprovidedintheAppendixtothischapter.

Page 26: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐26  Project Development    

Exhibit 1‐6  Step III:  Project Initiation, Prioritization, and Programming 

City Staff Preliminary Review of Project Initiation Form

DPW Staff Plan Review Team review of Project Initiation Form

City Staff Compiles Preliminary Transportation Improvement

Program

Comments to Proponent

DPW Staff Plan Review Team Approves and adds to a Draft of

the City-wide Transportation Improvement Program

Project Does Not Proceed

Public Comments on Draft Transportation Improvement

Program

Development of Project Management Plan

Programming in City Budget

Environmental, Design and ROW Process

DPW Staff Plan Review Team Approves Final Transportation

Improvement Program

Project Initiation Form

Page 27: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐27 

1.4.2 Project Review and Evaluation 

Atthisstage,theproposedprojectiswellenoughdefinedtobesubjectedtoaformalreview.Thisreviewfacilitatescomparisonoftheproject’sviabilitytootherprojectscompetingforlimitedfunds.ThePIFandprojectplanningdocumentsarereviewedbyCityStaffforcompletenessandtoidentifyissuesforconsiderationbytheDPWStaffReviewTeamduringtheirformalconsiderationoftheproject.TheDPWStaffReviewTeam,iscomprisedofstaffDPW,Planning,Citycounselors,andEngineeringandischairedbytheDPWCommissioner.TheDPWStaffReviewTeammustapprovealltransportationprojectstobeimplementedusingCityfunding.TheDPWStaffReviewTeammeetsmonthly,butonlyeverythreemonthsorsowouldbeaskedtoreviewProjectInitiationFormsandrecommendationspreparedbyCityStafftoverifyneeds,theeffectivenessoftheproposedprojectapproach,andtoprovidedirectiononnextsteps.ApreliminaryevaluationoftheprojectforfundingandprogrammingwithintheprioritiesoftheCityismadeduringthisstep(theprogrammingprocessisdiscussedinsubsequentsectionsofthisStep).Itisanticipatedthatadviceandguidanceforthenextstepsintheprojectdevelopmentprocesswillalsobeofferedatthisstage.Atthispoint,theDPWStaffReviewTeamcouldreachoneofthreeconclusions: Determinethatadditionalplanningisnecessarybeforeadecisioncanbereached

regardingthefutureoftheproject;

Determinethataprojectshouldmoveforwardintoprioritizationandpotentialdesignandprogramming;

Recommendthattheprojectbedismissedfromfurtherconsiderationduetolackofcurrentavailablefundsortheproject’slackofeffectivenessinaddressingidentifiedneeds.

ADPWStaffReviewTeampositiverecommendationdenotesthataprojectshouldbeconsideredeligibleforfunding.However,itdoesnotguaranteethattheprojectactuallyhasdedicatedfunding.

1.4.3 Project Prioritization 

AfterapprovalbytheDPWStaffReviewTeam,projectsareforwardedtoCityStaffforreviewandassessmentforfuturetransportationresourceallocations.CityStaffalsoreviewprojectsthatarenotapprovedbytheDPWStaffReviewTeamandprovideadditionalcommentstotheProponentsothatfuturesubmissionscanbestreamlined.CityStaffmaintainalistofprojectsthatreceivedapprovalbytheDPWStaffReviewTeamduringafiscalyear.PriortotheCity’sannualbudgetdevelopmentprocess,projectsareprioritizedbasedonthetotalscoresfromtheProjectInitiationFormto

Page 28: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐28  Project Development    

developaPreliminaryTransportationImprovementProgram.Anyprojectsthatwereonthepreviousfiscalyear’sTransportationImprovementProgramthatwerenotcompletedarere‐prioritizedonthecurrentDraftofTransportationImprovementProgram.

1.4.4 Project Programming 

ThePreliminaryTransportationImprovementProgramdevelopedbyCityStaffisreviewedbytheDPWStaffReviewTeamforprojectprogrammingduringitsannualapprovalprocess.TheDPWStaffReviewTeamwillhavereviewedtheprojectspreviouslyandisthereforefamiliarwiththemeritsandissuesassociatedwitheach.TheDPWStaffReviewTeamvotesonapprovingeachprojectforinclusionintheDraftTransportationImprovementProgram,whichispresentedtothepublicforreview.Afterpublicreview,theDPWStaffReviewTeamvotesonapprovingeachprojectforinclusionintheFinalTransportationImprovementProgramwhichwillhavebeenamendedbasedonpublicinput.AtthistimetheDPWStaffReviewTeamestablishesaProjectManagementPlantodefinerolesandresponsibilitiesforthesubsequentfinaldesign,environmental,right‐of‐wayandconstructionstepsintheprocess.ThismayincludetheCitystaffadvancingthedesignthroughthenextsteps,hiringofoutsideconsultantstoadvancedesignefforts,and/orperhapsaskingproponentstofundadvancementofdesignelements.FundingforaprojectcanonlybeallocatedoncetheFinalTransportationImprovementProgramisapprovedandtheprojectisreadytomoveforward.

1.5 Step IV:  Environmental, Design and ROW Process 

StepIVbeginstheprocessofenvironmentalreview,projectdesign,andright‐of‐way(ROW)acquisition(ifnecessary)sothattheprojectcanbeconstructed.Thisprocessinvolvesfourdistinct,buttightlyintegrated,elements: PublicOutreach

EnvironmentalDocumentationandPermitting

ProjectDesign

Right‐of‐wayconfirmation/acquisition

Publicoutreachactivitiesandrequirementsareintegratedwithineachofthetechnicaltasks.Thiscontinualinvolvementwillhelptoensuretheproject’sultimatesuccess.Althoughthetechnicalrequirementsforenvironmental,design,andROWeffortsarepresentedsequentiallyinthisPlan,theseactivitiesareconductedconcurrentlyandina

Page 29: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐29 

coordinatedprocesstoensurethattheultimateprojectisacceptable,constructible,permittable,andaddressesthecustomer’sneeds.Alltheseactivitiesarekeyedtothedesignprocessschedule.

1.5.1 Public Outreach Plan and Requirements for the Environmental, Design, and Right‐of‐Way Process 

Continuedpublicoutreachinthedesignandenvironmentalprocessisessentialtomaintainpublicsupportfortheprojectandtoseekmeaningfulinputonthedesignelements.Thispublicoutreachisoftenintheformofrequiredpublichearings,butcanalsoincludelessformaldialogueswiththoseinterestedinandaffectedbyaproposedproject.Atthispointintime,apublichearing,oropportunityforapublichearing,isrequiredforallhighwayprojectsaspartofaprocessthatalsoencouragesavarietyofcitizeninvolvementtechniquessuchasinformalpublicmeetings,briefings,workshops,orcharrettes.Publichearingsarerecognizedformalmeetingsheldatparticulartimesduringtheprojectdevelopmentanddesignphases.APublicHearingisrequiredforanyprojectthat: Requiresadditionalright‐of‐way;

Substantiallychangesthelayoutorfunctionsofconnectingroadwaysorofthefacilitybeingimproved;

Hasasubstantialadverseimpactonabuttingproperty;or

Hasasignificantenvironmental,socialoreconomic,orothereffect.

Anadditionalpublichearingwillbeprovidedwhentherehasbeen: Asignificantchangeintheproposedproject(ordesigndetails);

Identificationofsignificantenvironmental,social,oreconomiceffectsnotconsideredatearlierPublicHearings;

Substantialunanticipateddevelopmentintheprojectarea;and,

Anunusuallylongtimelapse(forexample,morethantwoyears)sincethelastpublichearing.

TherearemanyopportunitiesforpublicmeetingsorhearingsontheprojectthroughouttheprojectdevelopmentprocessasdescribedinSection2‐1.9ofthischapter.Allmeetingsshouldbeheldinaccessiblelocationswithmaterialsrelevanttothemeetingmadeavailableinalternativeformatsuponrequest.

Page 30: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐30  Project Development    

1.5.2 Environmental Documentation and Permitting 

Earlyinvolvementbytheprojectproponenttounderstandanddevelopaplanofactiontoaddresstheanticipatedenvironmentalconsequencesoftheprojectisessential.Thiseffortcanalsoshapeamoreenvironmentallyresponsiveandsustainabledesign.Thissectiondescribessomestandardprocedureswhichhelptoidentifyinitialprojectdesignparameters,initiateearlycoordinationwiththecommunitytoidentifyissuesspecifictotheproject,anddefineessentialinformationtoincorporateintothePreliminaryDesigntoinitiateearlyenvironmentalreviews.

1.5.2.1 Early Coordination 

Earlycoordinationwithappropriateagenciesbytheprojectproponentshouldbeconducted.Someexamplesinclude: Localenvironmentalboardsandcommissionstoreviewtheprojectareaand

identifyanyspecificissuesorconcerns.

Localhistoricalcommission(s)byrequestingtheirreviewandcommentontheproposedscopeofworkand/oralocusplanshowingprojectlimits

CTDOT

Allcorrespondencefromtheearlycoordinationtasksshouldbedocumented,copiedtokeyprojectparticipants,andmadepartoftheproject’spermanentrecord.

1.5.2.2 Determine Other Applicable Federal, State and Local Environmental Laws and Requirements 

Theproponent,ortheirdesignateddesigner,willberesponsibleforidentifyingandcomplyingwithallotherapplicablefederal,stateandlocalenvironmentallawsandrequirements.PreparingandprocessingthisenvironmentaldocumentationshouldoccurconcurrentwiththedevelopmentofthePreliminaryDesignplans.Theprojectproponentshoulddevelopachecklistoftheanticipatedenvironmentaldocumentationandpermitsandscheduleacoordinationmeetingwiththeappropriatepartiestoreviewtheseassumptionsandtheirrequirementsifnecessary.Projectdelayscanbeminimizedbyearlyandon‐goingcoordinationwithFederal,state,andlocalagencieswithjurisdictionbylaworspecialexpertise.

1.5.2.3 Preliminary Submission Environmental Review 

TheCitywillevaluatethedatacollectedduringthePreliminaryDesignprocessandtheplanssubmitted.Theywilldeterminewhethertheprojectcanbedesignedtodesireddesigncriteria,orifdesignchangesormitigationplanswillberequiredtoresolveenvironmentalissuesandcommunityconcerns.IftheproposedprojectisunderStatejurisdiction,thentheproponentwillfollowtheOSTAguidelinesandprocess.Similarly,

Before initiating design, the designer should take time to review all prior planning documents and public input received on the project.

Page 31: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐31 

iftheproposedprojectisunderFHWAjurisdiction,thentheproponentwillfollowtheirprocess.

1.5.2.4 Define and Initiate Permit Process 

Environmentalclearancesandpermitsshouldbesecuredasearlyoninthedesignprocessasispracticable.WhenusedinthisPlan,theterm"PermitProcess"referstoanyprocessorregulatoryprogramthatinvolvesobtainingapermitorsomeothertypeofsign‐offfromafederal,state,orlocalagency.IdentificationofapplicablepermitsiscompletedpriortothePreliminaryDesignSubmission.Initialcoordination,datagatheringcontinuesthroughoutthedesignprocess.Formalsubmissionofapplicationstoregulatoryagenciesshouldbedoneassoonastherequiredinformationisavailable,butnolaterthantheFinalDesignSubmission.Theprojectproponentisresponsibleforobtainingallrequiredpermits,butmayreceivesupportfromotherparties.

1.5.2.5 Complete Permit Processes 

DuringtheperiodfromPreliminarybutnolaterthanFinalDesign,thedesignershouldcompleteandsubmitallnecessaryformsorapplicationstotheappropriateagenciesfortherequiredpermits.

1.5.3 Project Design 

Therearegenerallythreemajorphasesofdesign,including: PreliminaryDesign

FinalDesign

Plans,Specifications,andEstimate(PS&E)

Astheprojectmovesintodesign,theprojectdefinedintheProjectPlanningphaseisdevelopedinmoredetailanddesigndocumentsfortheprojectareproduced.Itisimperativethatthedesignerisknowledgeableaboutthecontextoftheproject,abouttheissuesraisedduringplanning,andaboutthedesiresofthecommunity,theCity,andtheregulatoryagenciesconcerningprojectimplementationpriortoinitiatingthedesign.ThedesignprocessshouldcomplywithCityrequirementsand/orStateandFederalrequirementsifapplicable.

1.5.4 Right‐of‐Way 

Layoutplans,descriptions,andordersoftakingarerequiredtoestablishhighwayrightofwayforallprojectswhichinvolvelandacquisitions.Allproposedlayoutsmustbeaccuratelycomputed.

Page 32: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐32  Project Development    

Theprocessforacquiringrightofwayoreasementsneedstobeprogressedasthedesignprogresses.

1.5.4.1 Preliminary Right‐of‐Way Plans (Preliminary Design) 

Whenlandacquisitionoreasementsareinvolved,thedesignershouldidentifyexistingandproposedlayout(locations)lines,easements,propertylines,cornermarkings,namesofpropertyowners,accesspoints,andthedimensionsandareasofestimatedtakingsandeasementsaspartofthePreliminaryDesign.

1.5.4.2 Preliminary Right‐of‐Way Plans (Final Design) 

ThedesignerwillconfirmtheacquisitionsinthePreliminaryROWsubmittalareadequatefortheFinalDesign,orproviderevisedROWPlans.ROWacquisitioninformationshouldbepostedonthepreliminaryROWplanbythedesignerwhenthedesignerobtainstheinformation.

1.5.4.3 Final Right‐of‐Way Plans (PS&E Design) 

AftertheLayoutorTakingdocumentsarerecorded,thepreliminaryROWplanwillbecomethefinalROWplan.

Finalize Layout Plans and Order of Taking 

AssoonasfeasibleaftertheFinalDesignprojectapproval,LayoutPlansandtheOrderofTakingarefinalizedbythedesigner.

1.5.5 Completion of Environmental Permitting/Design/Right‐of‐Way Process 

Theconditionsunderwhichtheprojectdesignandenvironmentalpermittingarecompleteandapprovediswhenalldocumentsnecessarytopublishthebiddocumentsarecomplete.Inadditiontoensuringcompletenessofthedesignandright‐of‐wayprocess,theproponentneedstoensurethatallnecessaryenvironmentalpermitsandclearancesarecomplete.

Step IV Outcomes 

Adesignedandpermittedprojectreadyforconstruction.

1.6 Step V: Procurement 

Onceadesigniscomplete,theprojectisorganizedwithinaconstructioncontract,andanopeninvitationtobiddersispublishedfollowingapplicableCity,State,andFederalprocurementprocedures.

Page 33: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐33 

1.7 Step VI: Construction 

Afteraconstructioncontractisawarded,theproponentandthecontractorwillneedtodevelopaconstructionmanagementplan.Thepermittingagencies,localauthorities,andaffectedmembersofthegeneralpublicneedtobeinformedoftheplan.Theseentitiesshouldalsobenotifiedaschangesinconstructionareasandactivitiesoccurthroughouttheproject.

1.7.1 Public Participation During Construction 

Beforeconstructionactivitiesbegin,theproponentandconstructionmanagermustdeterminetheappropriatetypeofpublicnotificationandparticipationneeded.Differentprojectsresultindifferenttypesofdisruptiontotransportationandothernearbyactivities.Forsimpleprojects,includingresurfacing,aminimaldegreeofpublicparticipationmaybeneeded.Forthesetypesofprojects,theproponentshould,ataminimum,notifyabuttersoftheimpendingconstructionactivity.Forcomplexprojects,theproponentmayneedtoscheduleaconstructionmanagementplanmeetingwithabuttersandotherprojectparticipants(localboards,interestgroups,businessassociations,etc.).Atthismeeting,theproponentcandescribethetypesofconstructionactivityneeded,constructionphasing,anddurations.Issuesandconcernsassociatedwiththeconstructionperiodcanbeidentifiedandadjustmentsmadetotheconstructionmanagementprogramtominimizecommunityimpactsasaresult.

1.7.2 Construction Management and Monitoring 

Carefulmanagementandmonitoringofconstructionactivitiesisnecessaryformostprojectstoensurethatqualitystandardsaremaintained,environmentalcommitmentshonored,andcommunityexpectationsaremet.

1.8 Step VII: Project Assessment 

ProjectAssessmentcanbeusedasatooltofurtherimprovetheprojectdevelopmentanddeliveryprocesses.Althoughcompletionofthisprocesswilldependupontheproponent,threeimportantpiecesofinformationcanbegatheredthroughthisbrief,informalprocess.Theseinclude: Constituentinputintoprojectdevelopmentprocess:

Weretheproponent’sexpectationsforguidance,review,andfeedbackmet?

Wastheprojecttimelinereasonable?

Wasthepublicoutreachprogramfortheprojectappropriateandeffective?

Page 34: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐34  Project Development    

Werecommunityconcernsabouttheprojectaddressedandcommunitycommentsincorporatedintotheplanninganddesignprocesses?

Wereappropriatedesigncontrolsselectedfordeterminingthedesignoutcome?

Wastheprojectconstructioneffectivelymanagedsothatcommunityimpactswereminimized?

Constituentreviewoftheprojectdesignelements

Wastheprojectneedaddressed?

Istheresultingprojectconsistentwithitscontext?

Whatspecificdesignelementsarejudgedtobesuccessfulandrecommendedforfutureprojects?

Whatspecificdesignelementsarejudgedtobeunsuccessfulandshouldbereconsidered,andwhy?

Follow‐upofPunchListitems

Arethereprojectelementsthatstillneedtobecompleted?

Hastheprojectresultedinanysituationsrequiringfollow‐uporadjustmenttomeettheoriginalornewly‐createdprojectneeds?

1.8.1 Public Outreach 

Publicoutreachisanticipatedthroughouttheprojectdevelopmentprocesstoensurethattheprojectcontinuestomeetitsintendedpurpose,benefitsfrominputandfeedbackfrominterestedcitizens,localandregionalgroups,andelectedofficials,andmaintainsstrongsupport.Publicoutreachisintegratedintoeverystepoftheprojectdevelopmentprocessdefinedinthischapter.Thisactiveparticipationwillensurearoleforthepublictohelpshapetheprojectthatemergesfromtheprocess.Itisparticularlyimportanttoprovideopportunitiesforpublicoutreachearlyinprojectplanning.

1.8.1.1 Identify Project Constituents 

Earlyintheprojectdevelopmentprocess,theproponentshouldconsiderthepublicsupportfortheprojectandtheconstituencythatitserves.Projectconstituentsaregroupsandindividualsthatareinvolvedin,haveaninterestin,orareaffectedbyaproposedproject.Theycaneitherbeformalparticipantsintheprocess,orcanberepresentedbyotherparticipantsintheprocess.Differenttypesofprojectsinvolvedifferentconstituents,anddifferentlevelsofplanningandreview.Projectconstituentsincludesomeorallofthefollowingentities: FederalHighwayAdministration(FHWA)

ConnecticutDepartmentofTransportation(CTDOT)

Page 35: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐35 

MetropolitanPlanningOrganizations

RegionalPlanningAgencies(e.g.SouthwesternRegionalPlanningAgency–SWRPA)

RegionalTransitAuthorities(e.g.NorwalkTransitDistrict,MetroNorthRail)

TransportationProviders(e.gMerritt7Shuttle)

StateandFederalRegulatoryAgencies

NationalParkService

U.S.CoastGuard

OtherStateAuthorities

ElectedOfficials,PublicWorksDepartments,LocalBoards,andCommissions,includingConservationCommission

Facilityusers(commuters,residents,visitorsbyallmodes)

Neighborsandcitizengroups

RegionalIndependentLivingCenter(s)

Advocacyandinterestgroups(suchaslocalpedestrianorbicyclingcommittees,truckingassociations,preservationgroups,etc.)

Privateareabusinesses

Localemergencyresponders

Utilities(includingrailroads)

Regionalwatershedorrivermanagementcouncils

Ataminimum,theproponentshouldcontacttheappropriatelocalplanningandpublicworksstaff,planningcommissionchair,conservationcommissionchair,selectboardchair,andmajorlocalpropertyownersinthevicinityoftheprojectareatohelpdetermineinitialconcernsandissues.TheproponentshouldconferwithCityofficialstodeterminewhichpropertyownersmayhavelegitimateissuesthatshouldbeaddressedbytheproject.Thiseffortwillhelpidentifyimportantlocalgroupssuchasneighborhoodassociations,businessassociations,historicalsocieties,recreationandopenspacecommittees,transportationproviders,andotherswhoshouldbeinformedoftheproject.ItisbettertobeasinclusiveaspossibleearlyintheProjectDevelopmentProcesstoallowthepublictoparticipateandbeaffordedanopportunitytocontributetothedecision‐makingprocessfortheproject.(Itshouldalsobemadecleartoallthoseattendinghowcommentswillbetreatedandhowanyexpectedfollow‐upwillbehandled).Identifyingthelikelypartiesthatmayhaveinterestintheprojectatthebeginningoftheprojectdevelopmentprocesshelpstheprojectproponenttailorthepublicoutreachprogramappropriately.Theprojectproponentshoulddefineapublicparticipationplan

Page 36: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐36  Project Development    

attheoutsetofeachstepoftheprojectdevelopmentprocess.ToolsavailableforthisoutreacharedescribedinSection1.9.3.

1.8.1.2 Public Outreach Approach 

Thelevelofinterestandroleofthepublicvarieswidelybyprojecttypeandcomplexity.Differenttypesofprojectsarelikelytoelicitdifferentlevelsofcommunity,resourceagency,andlocalboardinterest.Theseprojecttypesaregroupedintosystempreservationprojects,andsystemimprovementorexpansionprojectswithguidanceprovidedontheappropriatelevelofpublicoutreach,asexplainedfurtherinthefollowingparagraphs.Theprojectproponentshouldcarefullyconsiderthebest‐suitedapproachtopublicoutreach,dependinguponthecomplexityoftheproject.Somegeneralapproachestoincreaseawarenessofaprojectandsolicitinputaredescribedbelow: NotificationofAbutters—Projectproponentsforallprojects,otherthanroutine

maintenance,should,ataminimum,notifyabuttersoftheconstructionprogramanticipatedanditspotentialimpactstopropertyand/oroperations.Thiscanbeinformallydonethroughneighborhoodflyersorposters,throughnewspapernotices,ormoreformallydonebycertifiedmail.

NotificationofUtilities—Projectproponentsshouldnotifyutilitiesoftheconstructionprogramanticipatedanditspotentialimpactstotheirservicesoroperations.Itisimportanttonotifyutilitiesevenforroutineresurfacingandrehabilitationprojectstocoordinateanyplannedutilitywork.Thisisespeciallytrueforanoverlay,sincepavementlifeisshortenedconsiderablyfollowingautilitycut.

CommunityNotification—Asprojectsbecomemorecomplex,disruptive,andoflongerduration,notificationshouldbemadetothecommunityasawholeusingthepublicoutreachtoolsdiscussedinthenextsection.Thiscommunitynotificationhelpstoincreaseknowledgeoftheprojectanditspotentialconstruction‐relatedimpacts.Beyondsimplenotification,theproponentshouldactivelyinvolveabutters,specificlocalinterestgroups,andutilitiestogetagoodcross‐sectionofpeopletoparticipate.

EarlyInvolvementofLocalBoardsandCommissions—Theproponentshouldconsiderinvolvinglocalboardsandcommissionsattheoutsetoftheproject.Thisinvolvementcanhelptheproponentidentifyissuestheprojectislikelytofaceandcanhelptheproponentgaugethetypeofadditionaloutreachactivitiesthatmaybemostappropriateiftheprojectproceeds.Outreachtolocalboardsandcommissionscanalsobehelpfulforcomplexmaintenanceandresurfacingprojects.ItissafertonotifyallCitydepartments/boardsofaproject’sscopebeforemuchdesignworkisstartedtominimizelaterconcernsorneedsforprojectchanges.

EarlyLocalIssuesMeeting—Anearlylocalissuesmeetingisimportantforprojectswheretransportationfacilitiesarebeingsubstantiallymodified,expanded,

Page 37: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐37 

orreplaced.Itisrecommendedthatthismeetingbewidelyadvertised,asdiscussedbelow.Thismeetingprovidesaforumforprojectconstituentstomaketheirconcernsknownbeforeacourseofactionisdetermined.Forstraightforwardprojects,thisearlylocalmeeting,coupledwithlateropportunitiesforpublichearingsduringdesignandpermitting,maybesufficient.Formorecomplexprojects,severalearlylocalissuesmeetingsmaybenecessary.

PublicForumsorHearingsatSeveralStagesofPlanningandDesign—Asprojectcomplexitycontinuestoincrease,thepublicparticipationshouldincludeseveralopportunitiesforpublicinvolvementduringtheplanninganddesignphasesinadditiontotheearlylocalissuesmeetingdescribedabove.Targetedmailingscanbeusedtogenerateinterestandensurethatconcernedpartiesarecontacted.Keymilestoneswherepublicinvolvementisespeciallyimportantincludealternativesanalysisduringtheplanningprocess,atkeydesignmilestones,oriftheprojectelementschangesubstantiallyduetoincreasingrefinementofthedesign.Detailedmeetingminutesarerecommendedforeachsession.

ActiveCommunicationaboutProjectProgress—Inadditiontointeractivepublicforums,activecommunicationaboutprojectprogressishelpfulformaintainingconsensusandkeepingprojectconstituentsinformedabouttheprojectstatus.Severaladditionaltoolsforcommunicatingprojectprogressarehighlightedinthefollowingsection.

FormationofanAdvisoryTaskForce—Anadvisorytaskforceofprojectconstituentscanbeparticularlyhelpfulformaintaininginvolvementfromaconsistentgroupofindividuals,representingacross‐sectionofinterestsintheproject.Thisformalizedtypeofpublicoutreachisgenerallyreservedformorecomplexprojectswithawiderangeofalternatives,benefitsandpotentialimpacts.Inalmostallcases,formationofanadvisorytaskforcedoesnotreplacetheneedfortheotherpublicoutreachapproachesdescribedabove.Typically,taskforcesareadvisorybodiesthatofferinputtotheprocessandsuggestrecommendations.

1.8.1.3 Public Outreach Tools 

Therearemanyaspectsofpublicoutreachassociatedwithtransportationprojectsincluding: Informingconstituentsofapotentialproject;

Activeparticipationofprojectconstituentsinplanninganddesign;

Formalizedpublicmeetingsandhearings;and

Communicationabouttheprogressofaproject

Withineachoftheseaspects,therearevariousoutreachtoolsavailablewhichservedifferentpurposesandtargetdifferentaudiences.Thesetoolsareapplicablethroughouttheprojectdevelopmentprocess.

Page 38: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

2.1‐38  Project Development    

Thefirststageinpublicoutreachistomakepeopleawareofapotentialproject.Legalnoticesaloneareineffectiveatinformingthecommunityaboutupcomingprojectmeetings.Theprojectproponentshouldconsideradditionalwaystocommunicatetheopportunitytoparticipateinthetransportationprojectdevelopmentprocess,suchas: Localnewspaperarticlesoreditorialletters

Noticestolocalboards,committees,andlocaladvocacygroups

Postersatcivicbuildingsorchurches,orinneighborhoods

Localcabletelevisioncommunityeventcalendars

Acommunitywebsitepostingorcommunity‐widemailing

Pressreleasestomediaoutlets

Acommunity‐widemeetingnoticeornewslettermailing(oremail)

Flyerstoprojectabutters

Notethattherearesomepublichearings,oropportunitiesforpublichearings,thatarerequiredtobeheldforlegalreasons.Forexample,theFHWArequiresPublicHearingsforFederal‐Aidhighwayprojectsaspartofaprocessthatalsoencouragesavarietyofcitizeninvolvementtechniquessuchasinformalpublicmeetings,briefings,andworkshops.Publichearingsarelegallyrecognizedformalmeetingsheldatparticularstagesoftheprojectdevelopmentprocess.Someenvironmentalorresourceagencypermitsorclearanceprocessesalsorequirepublichearings.Allpublicmeetingsandhearingsshouldbeheldinfacilitiesthatarefullyaccessibleforpeoplewithdisabilities,andnoticesaboutthesemeetingsshouldusetheInternationalSymbolofAccessibilitytoindicatethatthelocationisaccessible.Handoutmaterialsavailableinalternativeformats—Braille,largeprint,and/oraudiocassette—aswellasotheraccommodations(signlanguageinterpreters,CARTreporters,etc.)shouldbeindicatedinthemeetingnoticesalongwithspecificallyhowtorequesttheseaccommodations.Formalenvironmentalanddesignhearingsaresometimesineffectiveinelicitingcommunityconcernsandaddressingindividualissues.Otherwaystocommunicatewiththoseinterestedinoraffectedbyprojectsinclude: PublicMeetings—informalgatheringsofdesigners,officials,andlocalcitizensto

shareanddiscussproposedactions.Thesemeetingsprovideanopportunityforinformal,lessstructuredconversationsaboutaproject,thedesignelements,anditspotentialbenefitsandimpacts.

OpenHouses—mechanismsforinterestedpartiestogathermoredetailedinformationonaproject.Openhousesfacilitatethediscussionofparticulardetails

Page 39: Chapter 2-1 - Project Development · transportation projects are in general agreement regarding the project’s need, the selected approach to meet this need, and the refinements

Section 2 - Chapter 1

  Project Development  2.1‐39 

ofinteresttoindividualsmoreeffectivelythantraditionalhearingsorpublicmeetings.

WorkshopsorCharrettes—smallergroupsthatfacilitateproblemsolvingarounddesignissuesforwhichseveraloptionsareavailableandthebestsolutionisunclear.

OtherCommunicationToolsthatareeffectiveinprovidinginformationtothepublicandsolicitingtheirinputinclude:

Newsletters—provideaforumformeetingnotificationandperiodicupdatesonprojectstatusanddecisions.Newsletterscaneitherbetraditionallymailedorelectronicallytransmitted.

Websites—allowfrequentupdatesofprojectstatus,enablinginterestedpartiestoreviewmaterialsontheirownschedule,andfacilitatecorrespondenceofquestionsandresponses.

ProjectInformationBoards—illustrateprojectdetailsandprovidecontactinformationattheprojectsitefacilitatinginvolvementinotherformsofoutreach.

Successfulpublicmeetingsrequiregoodadvancecommunicationsandcoordinationwithcommunityleaders,electedofficials,theRegionalPlanningAgencies,andCTDOTbeforehandinordertosettheagendaandestablishtheframeworkforappropriatefollow‐upandcontinuedcommunication.Theproponentshouldworkcloselywithlocalandregionalofficialsonmeetinglogistics,includinglocation,time,andformat.