chapter 18 performance & remedies “it is an immutable law in business that words are words,...

25
Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but only performance is reality.” Harold S. Geneen, CEO of ITT, Managing (co-written with Alvin Moscow, 1984)

Upload: israel-marston

Post on 14-Jan-2016

218 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Chapter 18Performance & Remedies

“It is an immutable law in business that words are words, explanations are explanations, promises are promises – but only performance is reality.”

Harold S. Geneen, CEO of ITT, Managing (co-written with Alvin Moscow, 1984)

Page 2: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Learning Objectives

• Nature and types of conditions in contracts

• Performance of contracts

• Breach of contract

• Excuses for non-performance

• Remedies for breach of contract

18 - 2

Page 3: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

• Entering into a contract evidences an intention to perform (complete) obligations under the contract– Generally, each party performs the promise and

is discharged (released) from further obligation

• If a party fails to perform as expected, courts may be asked to determine the respective rights and duties of the parties

Overview

18 - 3

Page 4: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

• Sometimes a promisor’s duty to perform depends on the occurrence of some event or condition, an uncertain, future event

• A condition may be classified as a:– Condition precedent– Condition subsesequent– Condition concurrent

Conditions in a Contract

18 - 4

Page 5: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Condition Precedent

18 - 5

• A future, uncertain event creating a duty to perform– Example: Tisha contracts to buy a house on the

condition she is able to obtain financing. The contract arises and she is obligated to purchase the house once she obtains financing

Page 6: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Condition Concurrent

18 - 6

• When the contract calls for parties to perform at the same time– Example: Bryan promises to buy Stevie’s guitar

for $1000. Stevie must give Bryan the guitar when Bryan gives Stevie $1000.

Page 7: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Condition Subsequent

18 - 7

• A future, uncertain event that discharges the duty to perform– Example: Lee agrees to work for WoolCo until he

returns to college. Lee returns to college in August and discharges his obligation under the contract.

Page 8: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Excuse of Conditions

18 - 8

• Occurrence of a condition may be excused– When occurrence of condition was prevented or

hindered by party benefiting from the condition– Waiver: when a person whose duty is conditional

voluntarily gives up his right to the occurrence of the condition

– Estoppel: when a person whose duty is conditional leads other party to rely on his noninsistence on the condition

– When performance of the act that constitutes the condition becomes impossible

Page 9: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Silvestri v. Optus Software

• Facts: – Silvestri was hired under two-year employment

contract with “satisfaction clause” reserving right to terminate employment for “failure [to perform] duties… to the satisfaction” of the company

– Silvestri pleased the CEO for six months, but complaints against Silvestri began to increase

– Three months later, the CEO fired Silvestri– Silvestri filed suit claiming the dissatisfaction was

objectively unreasonable and a breach of contract

18 - 9

Page 10: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Silvestri v. Optus Software

• Procedural History and Legal Reasoning: – Trial court found for Optus– Appellate court reversed in favor of Silvestri– Issue: whether the employer’s satisfaction is

subject to an objective or subjective evaluation– A subjective standard typically is applied to

satisfaction clauses in employment contracts– In a satisfaction clause employment setting, there

must be honest and genuine dissatisfaction with the employee’s performance

18 - 10

Page 11: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Silvestri v. Optus Software

• Holding: – Company supplied objective evidence of

genuine dissatisfaction with Silvestri’s performance

– Thus, applying the test of genuineness, and not reasonableness, we conclude that Silvestri has not demonstrated that a dispute exists requiring submission of the matter to jury trial

– Reversed in favor of Optus

18 - 11

Page 12: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

• To determine whether a promisor is discharged by performance, courts consider the standard of performance expected

• A strict performance standard requires full or perfect compliance with the contract terms– Example: Buyer agrees to finalize a home purchase (close)

by 5:00 pm on Nov. 21. If Buyer does not close by that time, the contract ends. Buyer is discharged from buying and Seller is discharged from turning over the house, but there may be legal remedies to Seller for Buyer’s breach

Performance of Contracts

18 - 12

Page 13: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

• A substantial performance standard is slightly lower standard applied to duties that are difficult to perform without some deviation from perfection in minor respects– Example: Bob Builder built a home for Jason. Bob

met the contract terms except he didn’t paint the baseboards the right shade of white. Bob is discharged and Jason has the duty to pay the contract price less any damages (repainting) resulting from the defects in performance

Performance of Contracts

18 - 13

Page 14: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Substantial Performance

18 - 14

Page 15: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Breach of Contract

• Under the implied covenant of good faith and fair dealing, every contract includes an obligation to perform in good faith

• If a promisor fails to perform, breach occurs

• At minimum, breach of contract gives the non-breaching party the right to sue and recover for damages caused by the breach

• For a material (serious) breach, further legal remedies are available

18 - 15

Page 16: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Determining Materiality

• Standard for determining materiality is flexible, but generally based on the amount of the breach and timing for performance– Example: if contract contains a “time is of the

essence” provision, any delay by either party may constitute a material breach

– Example: if time for performance immaterial, promisee must accept late performance if within reasonable time after performance due, but may deduct costs of delay

18 - 16

Page 17: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Arnhold v. Ocean Atlantic Woodland Corp.

• Facts: – Sellers agreed to sell farmland to developer Ocean

Atlantic (Buyer), but delays and extensions ensued– After more negotiation and litigation, Sellers and Buyer

signed a settlement agreement containing a “time is of the essence” clause (basis of the lawsuit)

– Shortly before the closing date, Buyers again tried to extend the contract and Sellers refused, warning that “time is of the essence”

– Buyers assured Sellers they would close, but failed to do so; Sellers notifed Buyers of contract termination

18 - 17

Page 18: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Arnhold v. Ocean Atlantic Woodland Corp.

• Procedural History and Issue: – Buyers sued Sellers seeking specific

performance

– Trial court found for Sellers and Buyers appealed

– Issue: whether Buyers materially breached the agreement by failing to tender the purchase funds and close on the property on the specified date

18 - 18

Page 19: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Arnhold v. Ocean Atlantic Woodland Corp.

• Legal Reasoning and Holding:– The materiality inquiry focuses on two

interrelated issues: (1) the intent of the parties with respect to the disputed provision; and (2) the equitable factors and circumstances surrounding the breach of the provision

– Intent of the parties was clear – time was of the essence and timing was material

18 - 19

Page 20: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

Arnhold v. Ocean Atlantic Woodland Corp.

• Legal Reasoning and Holding:– In examining the totality of the circumstances,

the facts do not support Buyer’s argument• “Sellers displayed the patience of Job by

waiting nearly 3 1⁄2 years”

– Buyer treated material deadlines as trivial, thus Buyer has lost any right to purchase Sellers’ land

– Affirmed in favor of Sellers

18 - 20

Page 21: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

• When the promisor indicates before time for performance that promisor is unwilling or unable to carry out the contract, anticipatory repudiation or anticipatory breach occurs

• The promisee has choices:– Withhold his/her own performance and sue for damages

for total breach of contract immediately– Wait to sue until time for performance in case the other

party changes his mind and decides to perform– Waive his/her rights to performance

Anticipatory Breach

18 - 21

Page 22: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

• Nonperformance of a duty generally is a breach of contract, but nonperformance may be excused in certain circumstances:– Impossibility: “it cannot be done by anyone”

• See Bush v. ProTravel International, Inc.

– Impracticability: when unforeseen developments make performance highly impracticable, unreasonably expensive, or of little value to promisee (UCC 2–615)

Excuses for Non-Performance

18 - 22

Page 23: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

• Discharge by mutual agreement• Accord and satisfaction

– Accord is an agreement in which a promisee who has existing claim agrees with promisor that s/he will accept some performance different from that originally agreed on. When promisor performs the accord, that is called a satisfaction.

• Discharge by waiver of promisee

Other Reasons for Discharge

18 - 23

Page 24: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

• Discharge by alteration – One party alters and other does not consent

• Discharge by statute of limitations– One party takes too long to bring lawsuit

– UCC 2–725: four-year statute of limitations for contracts involving the sale of goods

• Discharge by decree of bankruptcy

Other Reasons for Discharge

18 - 24

Page 25: Chapter 18 Performance & Remedies “It is an immutable law in business that words are words, explanations are explanations, promises are promises – but

• Legal remedies (money damages)– Compensatory damages, nominal damages,

liquidated (contractual) damages, and in certain circumstances, punitive damages

• Equitable remedies– Specific performance or injunction

• Restitution

Remedies for Breach of Contract

18 - 25