chapter 17: project management - … · chapter 17 - project management 17-3 blank forms to...
TRANSCRIPT
![Page 1: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/1.jpg)
Chapter 17 - Project Management
17-1
CHAPTER 17: PROJECT MANAGEMENT
Solutions
1. a.
Path
Expected
Path Time
1–2–4–7–10–12 23
1–2–5–8–10–12 24
1–3–6–9–11–12 31*
b.
Path
Expected
Path Time
1–2–4–6–8–9 41
1–2–5–6–8–9 48
1–2–5–7–8–9 55*
1–3–7–8–9 40
c.
Path
Expected
Path Time
1–2–5–12–16 44*
1–3–6–13–16 39
1–3–7–14–16 41
1–4–8–9–10–11–15–16 35
38 1–4–8–10–11–15–16
2. a. Choose topic Shop
Library res. Select
Outline Install
Write Paper
Grammar ck
Submit paper
b. 1. AOA diagram
.5
Grammar
2
Library
Select
Write Submit
Install Shop
Choose Outline
3 .2
.8
1
2
.6 .4 Start End
![Page 2: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/2.jpg)
Chapter 17 - Project Management
17-2
Solutions (continued)
2. AON diagram
c. 7.5 Shop, Select, Install, Write, Grammar, Submit
d. Parallel paths.
Write Grammar Submit
Select Shop Install
Library Choose Outline
Start End
![Page 3: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/3.jpg)
Chapter 17 - Project Management
17-3
Blank forms to distribute to students if desired:
3a. Bank location.
Weeks after start
Activity 2 4 6 8 10 12 14 16 18 20
1-2
1-3
2-4
2-5
3-5
4-5
5-6
b. Solved problem #2.
Weeks after start
Activity 2 4 6 8 10 12 14 16 18
1-2
2-5
2-4
1-3
3-4
4-5
3. a. Bank location.
Weeks after start
Activity 2 4 6 8 10 12 14 16 18 20
1-2
1-3
2-4
2-5
3-5
4-5
5-6
b. Solved Problem #2.
Weeks after start
Activity 2 4 6 8 10 12 14 16 18
1-2
2-5
2-4
1-3
3-4
4-5
![Page 4: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/4.jpg)
Chapter 17 - Project Management
17-4
Solutions (continued)
4. a.
Immediate
Activity Predecessor
A –
B –
C A
D A,B
E C
End D,E
4. b. Case 1: Activity-on-Node diagram
A
B
C
D
E
Dummy
a d
k
b e
f h
i g c
End
Start
Start
![Page 5: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/5.jpg)
Chapter 17 - Project Management
17-5
Case 2: Activity-on-Node diagram
m l
j
p n
k r
v
q
s
t w
End
Start
![Page 6: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/6.jpg)
Chapter 17 - Project Management
17-6
5. a.
Summary:
Activity ES EF LF LS Slack
1–2 0 4 11 7 7
2–4 4 13 21 12 8
4–7 13 18 26 21 8
7–10 18 20 28 26 8
10–12 21 24 31 28 7
2–5 4 12 19 11 7
5–8 12 19 26 19 7
8–10 19 21 28 26 7
1–3 0 10 10 0 0
3–6 10 16 16 10 0
6–9 16 20 20 16 0
9–11 20 25 25 20 0
11–12 25 31 31 25 0
12
4
28
21
19
12
26
18
1
2
5 8
9 6
3
12
11
26
19
28
21
19
12
11
4
0
0
10
10
16
16
20
20
25
25
31
31
25
25
20
20 16
16
10
10
26
18
28
20
31
24
21
13
7
0
21
13
26
19
10
4 7
9
5
2
3
6
5
4 6
10
4 8
7 2
11
4
LS
ES
LF
EF
![Page 7: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/7.jpg)
Chapter 17 - Project Management
17-7
Solutions (continued)
5. b.
Summary:
Activity ES EF LS LF Slack
1 0 5 0 5 0
2 5 23 5 23 0
3 5 18 20 33 15
4 23 26 37 40 14
5 23 33 23 33 0
6 33 37 40 44 7
7 33 44 33 44 0
8 44 53 44 53 0
9 53 55 53 55 0
LS
ES
LF
EF
1
2
8 9
6
3
0
0
37
23
40
26
5
5
4
7
5
5
5
23
23
5
18
23
23
33
33
40
33
44
37
44
44
53
53 53
53
55
55
33
33
44
44
20
5
33
18
10
13
11
9 2
4
3
![Page 8: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/8.jpg)
Chapter 17 - Project Management
17-8
Solutions (continued)
5. c. Activity ES EF LF LS Slack
1–2 0 15 16 1 1
2–4 15 27 28 16 1
4–7 27 33 34 28 1
7–9 33 36 37 34 1
4–9 27 32 37 32 5
1–3 0 8 8 0 0
3–6 8 16 30 22 14
6–9 16 23 37 30 14
3–5 8 17 17 8 0
5–8 17 31 31 17 0
8–9 31 37 37 31 0
32
27
15
a
34
33
37
36
37
32
30
16
16
15
1
0
8
8
17
17
22
8
28
27
34
33
31
31 17
17
8
8
37
37
28
27
16
15
0
0 30
16
1
2
8
9
6
3
4
7
5
31
31
37
23
f
8 8
g
h
9 j
14
i
7
k
6
12
b
6
c 3
e d
5
LS
ES
LF
EF
![Page 9: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/9.jpg)
Chapter 17 - Project Management
17-9
Solutions (continued)
6. The network diagram is given in Problem 1, Part a.
For path 1–2–4–7–10–12, the 13 weeks required for 1–2–4 has been reduced to 12 weeks. On
path 1–2–5–8–10–12, the 12 weeks required for 1–2–5 has been increased to (about) 14 weeks
[12+(8–6)]. However, 1–2–5–8–10–12 is not along the critical path and has a slack of 7 weeks.
Along path 1–3–6–9–11–12, the 13 weeks required to complete 1–3 and half of 3–6 has been
reduced to 12 weeks; a reduction of one week along the critical path.
The project may be completed in (31–1) = 30 weeks, if all following activities are completed
according to the original estimate.
7. a.
b. Activity te 2 Path
Expected
Duration
Std.
Dev. 24 Prob.
a 6 4/36 a–c–e 20.5 1.118 3.13 0.9991
b 8.5 9/36 d–f–g 21.5 1.344 1.86 0.9686
c 8.17 25/36 b–h–i 19.5 0.726 6.19 1.0000
d 12 36/36
e 6.33 16/36 For 21 Probability
f 6 4/36 (21 – 20.5) = .447 0.45
0.6736
g 3.5 25/36 1.118
h 4.17 1/36
i 6.83 9/36 (21 – 21.5) = –0.3721 –0.37
0.3557
1.344
(21–19.5) = 2.065 2.07
0.9808
0.7265
0.6736 x 0.3557 x 0.9808 = 0.235
1
2
5
3 6 8
7 4
c
e
g
i
f d
a
b
h
Start
End
![Page 10: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/10.jpg)
Chapter 17 - Project Management
17-10
Solutions (continued)
c. On the 8th day, the network could be reviewed as follows:
*Assume it is the beginning of the 8th day
Replace d by d and merge nodes (2) and (4) with (1).
d: te = 6: 2 = 4/36
7 days were used to complete activities a, b and one half of d. In the modified network:
Path
Expected Duration
from 8th day
Expected duration from
the start of the project Variance
1. c–e 14.50 14.50 + 7 = 21.5 41/36
2. d–f–g 15.5 15.5 + 7 = 22.5 33/36
3. h–i 11 11 + 7 = 18 10/36
Path Standard Dev. Z24 Probability (24)
1. c–e 1.0672 24 – 21.5 = 2.343
.9904
1.0672
2. d–f–g 0.9574 24 – 22.5 = 1.567
.9418
0.9574
3. h–i 0.5270 24 – 18 = 11.384
1.0000
0.527
.9904 x .9418 = .9328
Path Z21 Probability (21)
1. c–e 21 – 21.5 = –0.469
0.3192
1.0672
2. d–f–g 21 – 22.5 = –1.567
0.0582
0.9574
3. h–i 21 – 18 = 5.692
0.527
.3192 (.0582) = 0.0186
1
5
3
7
8 6
e (6.33)
f (6) d (6) g (3.5)
i (6.83) h (4.17)
c (8.17)
8th
day
![Page 11: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/11.jpg)
Chapter 17 - Project Management
17-11
d. Crash activities F, C, and G one day each for a total cost of $23,000. Decide if an additional
expenditure of $3,000 over budget would be worth the cost, or if it would be better to crash only
one day (Activity F for a cost of $7,000), or don’t crash at all.
8. Path Expected
Duration
Std. Dev. Z16 Z15 Z13
A 10 1.1 5.45 4.55 2.73
B 8 1.414 5.66 4.95 3.54
C 12 1. 4 3 1
D 15 1.7 0.59 0 –1.18
E 14 1.2 1.67 0.83 –0.83
![Page 12: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/12.jpg)
Chapter 17 - Project Management
17-12
Solutions (continued)
(a) Prob. (T 16) = 1 x 1 x 1 x 0.7224 x 0.9525 = 0.6881
(b) Prob. (T 15) = 1 x 1 x 1 x 0.50 x 0.7977 = 0.3984
(c) Prob. (T 13) = .9968 x 1 x 0.8413 x .1197 x .2023 = .0203
9. Solution
Path
Expected
duration Std. dev. z Probability
1–2–3 4 + 5 = 9 1.64 0.61 .7291
1–3 8 1.60 1.25 .8944
P(duration 10 weeks): 1 – .7291 (.8944) = .3479
10. Solution
a. Path
Expected
duration Std. Dev. z for 11 wk. Probability
1–2–4 4 + 6 = 10 1.14 0.88 .8106
1–3–4 3 + 9 = 12 2.00 –0.50 .3085
P(duration 11 weeks): .8106(.3085) = .2501. Yes, the manager should be concerned
because the probability of finishing on schedule is only about .25.
b.
Path
Expected
duration Std. dev. z for 12 wk. Probability
1–2–4 4 + 6 = 10 1.14 1.75 .9599
1–3–4 3 + 9 = 12 2.00 0 .5000
P(duration 12 weeks) = 1 – .9599(.5000) = .52.
11. Project Management
a. Path Mean Var. Std. Dev. z49 Prob. z46 Prob.
1–2–3–8–11 37.34 1.056 1.027 11.35 1 8.43 1
1–2–4–6–11 43 5.11 2.26 2.65 .996 1.33 .9082
1–2–4–7–11 40 0.8056 0.898 10.02 1 3.34 1
1–2–5–10–9–11 46.83 1.25 1.118 1.94 .9738 –0.74 .2296
b. P(T 49 wk.) = 1 – [(.9738) (.996)] = .0301
c. P(T 46 wk.) = .9082 (.2296) = .2085
![Page 13: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/13.jpg)
Chapter 17 - Project Management
17-13
Solutions (continued)
12.
Activity
Expected
Duration
Path
Mean Variance
Path
Variance
Path Std.
Dev.
a 4.
24.34
16/36
1.83
1.354 d 8. 16/36
e 9.17 25/36
h 3.17 9/36
f 4.5
15.5
25/36
1.58
1.258 g 7. 16/36
4.[a] 16/36
b 2.17
14.83
1/36
1.03
1.014 i 3.33 16/36
j 4. 4/36
k 5.33 16/36
c 8.17
26.17*
49/36
2.75
1.658 m 1. 0
n 7.5 25/36
o 9.5 25/36
*critical path duration
k
h
d
a
b
c
m
i j
g
f
e
End
n
Start
o
![Page 14: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/14.jpg)
Chapter 17 - Project Management
17-14
Solutions (continued)
Path Mean Std. Dev. z27 Prob. z26 Prob.
a–d–e–h 24.34 1.354 1.96 .9750 1.23 .8907
a–f–g 15.5 1.258 9.14 8.35
b–i–j–k 14.83 1.014 12.00 11.00
c–m–n–o 26.17 1.658 .50 .6915 –0.10 .4602
Prob. ($500): .9750 (.6915) = .6742
Prob. ($1000): .8907 (.4602) = .4099
13.
Activity
Duration (wk.)
first crash
second crash
1-2 5 $8 #2 $10 2-4 6 7 9 4-7 3 14 #3 15 1-3 3 9 11 3-4 7 8 9 1-5 5 10 #1 15 5-6 5 11 #2 13 6-7 5 12 #3 14
2
1
3
1
5
6
4
7
7 5
6
3
3
5
5
5
![Page 15: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/15.jpg)
Chapter 17 - Project Management
17-15
Solutions (continued)
Path Initial time After first crash After second crash After third crash
1-2-4-7
1-3-4-7
1-5-6-7
14 wk.
13 wk.
15 wk.
14 wk.
13 wk.
14 wk.
13 wk.
13 wk.
13 wk.
12 wk.
12 wk.
12 wk.
First Crash Second Crash Third Crash
Activity Cost
1 - 5 $10
Activity Cost
2 - 4 $7
5 - 6 11
$18
Activity Cost
4 - 7 $14
6 - 7 12
$26
14.
Length after crashing N weeks
Path N: 0 1 2 3 4 5
A–B–K 35
C–E–H–P 44 43 42 42 42 40
C–D–G–M 45 44 43 43
C–E–H–N 47 46 45 45 45 44
C–F–I–J–P 49 48 47 46 45 44
Activity
Crashed
– c c f f e,p
Cost – $5,000 5,000 12,000 15,000 36,000
Cum. Cost – $5,000 10,000 22,000 37,000 73,000
D
17 P
B
14
G
15
H
8
I
7
A
12
K
9
M
3 N
11
J
12
F
12
E
18
C 10
8
Start End
![Page 16: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/16.jpg)
Chapter 17 - Project Management
17-16
Solutions (continued)
15.
Weeks Crashed
Activity 1st week 2nd week 3rd week 1 2 3 4 5 6
1–2 $18 [2] $22 [6] – $18 $22
2–5 24 25 25
5–7 30 30 35
7–11 15 [1] 20 [3] – 15 20
11–13 30 [4] 33 [5] 36 30 33
1–3 12 [6] 24 26 12
3–8 – – –
8–11 40 40 40
3–9 3 10 12
9–12 2 7 10
12–13 26 – –
1–4 10 [5] 15 25 10
4–6 8 [4] 13 – 8
6–10 5 [3] 12 [6] – 5 12
10–12 14 15 –
$15 $18 $25 $38 $43 $46
Weeks Crashed
Path 0 1 2 3 4 5 6
1–2–5–7–11–13 35 wk. 34 33 32 31 30 29
1–3–8–11–13 32 32 31 30 29
1–3–9–12–13 20
1–4–6–10–12–13 33 33 32 31 30 29
![Page 17: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/17.jpg)
Chapter 17 - Project Management
17-17
Solutions (continued)
Summary:
Project
Length
Cum. wk.
Shortened
Cum. Crash
Costs ($0000)
Indirect Costs
($000)
Total Cost
($000)
35 0 0 35(40) = 1,400 1,400
34 1 15 34(40) = 1,360 1,375
33 2 33 33(40) = 1,320 1,353
32 3 58 32(40) = 1,280 1,338
31 4 96 31(40) = 1,240 1,336
30 5 139 30(40) = 1,200 1,339
29 6 185 29(40) = 1,160 1,345
1,300
Total
Cost
($000)
1,400
0 30 31 32 33 34 35
Product Length
(wk)
![Page 18: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/18.jpg)
Chapter 17 - Project Management
17-18
Solutions (continued)
16.
Project duration = 39 wk
Project
length
Shorten
activity
Crash
cost
39 wk – 0
38 Z 90
37 N, L 170 = (125 + 45)
36 Q 200
35 Q 225
34 M, N 345
Stop here; additional crashing will cost more than the $375 weekly penalty.
17. a. 18.5 (See table in part b.)
b.
Path
Expected Duration
Standard Deviation
Z17
Probability
1-2-4-6
1-3-5-6
5+8.17 +5.33 = 18.5
8.33 + 3 + 3.83 = 15.16
1.17
1.12
–.43
2.54
.3336
.9945
1 – .3336(.9945) = .6682 or approximately .67.
9
K
410, 415
5
Q
200, 225
7
Y
85, 90
7
L
125, -
4
M
300, 350
8
P
-, -
6
Z
90, -
5
N
45, 45
6
J
50,-
En
d
Start
![Page 19: CHAPTER 17: PROJECT MANAGEMENT - … · Chapter 17 - Project Management 17-3 Blank forms to distribute to students if desired: 3a. Bank location. Weeks after start Activity 2 4 6](https://reader034.vdocuments.us/reader034/viewer/2022051309/5b5742d17f8b9ad9688da53a/html5/thumbnails/19.jpg)
Chapter 17 - Project Management
17-19
18.
Event Probability Cost ($000) Exp. Cost
1 .25 15 3.75
2 .35 25 8.75
3 .20 55 11.00
4 .80 10 8.00
5 .10 77 7.70
6 .40 55 22.00
7 .60 50 30.00
80
60
5
3 6
7
40
Cost 20
2
1
4
0 .25 .50 .75 1.00
Probability of Occurring
The manager should probably be most concerned about event #7, which has a greater than 50%
chance of occurring and a relatively high cost. (Note its expected cost in table above is the highest.)
19.
200
160
120
3
2
Cost 80
40
1
6
5
4
0 .25 .50 .75 1.00
Probability of Occurring
The weather problems (4) and funding delays (5) are placed conservatively (i.e., using the worst likely
probabilities).