chapter 1 overview

11
Technical Manual Environmental Processes Manual August 2013

Upload: shubham-mishra

Post on 27-Sep-2015

215 views

Category:

Documents


2 download

DESCRIPTION

Chapter

TRANSCRIPT

  • Technical Manual Environmental Processes Manual August 2013

  • Environmental Processes Manual, Transport and Main Roads, August 2013

    Copyright

    http://creativecommons.org/licenses/by/3.0/au/

    State of Queensland (Department of Transport and Main Roads) 2013

    Feedback: Please send your feedback regarding this document to: [email protected]

  • Amendment Register

    Issue / Rev no.

    Reference section Description of revision Authorised by Date

    1 First issue (Draft_EPM_September 2011) Environmental Sustainability Unit Sept 2011

    Review from project Working Group and Consultation Group Working Group Consultation Group

    Nov 2011

    2 Second issue (Draft_EPM_December 2011 Environmental Sustainability Unit Dec 2011

    Review from project Working Group, Consultation Group and Environmental Operations Group (EOG)

    Working Group Consultation Group Environmental Operations Group

    Jan 2011

    3 Third consultation (Draft_EPM_December 2011) Environmental Sustainability Unit Jun 2012

    4 Final processes sequence queries to ESU management, Working Group, EOG and CTS (Environment)

    Environmental Sustainability Unit Working Group Environmental Operations Group CTS (Environment)

    June 2012

    5 Final review and issue State Program Office July 2013

    Environmental Processes Manual, Transport and Main Roads, August 2013 i

  • Contents

    1 Overview .........................................................................................................................................1 1.1 Introduction ..................................................................................................................................... 1 1.2 Previous version ............................................................................................................................. 1 1.3 Scope.............................................................................................................................................. 1 1.4 Aims ................................................................................................................................................ 1 1.5 Objectives ....................................................................................................................................... 2 1.6 Manual structure ............................................................................................................................. 2

    1.6.1 Environmental processes alignment to the OnQ framework..........................................3 1.7 Infrastructure projects environmental processes flow chart ........................................................... 5 2 Project management methodology..............................................................................................6 2.1 Environmental input to transport infrastructure projects................................................................. 6 2.2 Component project ......................................................................................................................... 6

    2.2.1 Internal management of component project...................................................................6 2.2.2 External component project delivery ..............................................................................7 2.2.3 Accountabilities & responsibilities ..................................................................................7

    2.3 Project management streams......................................................................................................... 8 2.3.1 Process management ....................................................................................................8 2.3.2 Work management .........................................................................................................8

    2.4 Environmental management system (EMS) ................................................................................... 9 3 Project classification...................................................................................................................10 3.1 Project classification ..................................................................................................................... 10

    3.1.1 Overall (OnQ) project classification..............................................................................10 3.1.2 Environmental project classification .............................................................................10 3.1.3 Nil or negligible environmental risk...............................................................................11

    3.2 Risk ............................................................................................................................................... 12 3.2.1 Risk management.........................................................................................................12

    3.3 High level project classification..................................................................................................... 12 3.3.1 Significant project environmental impact assessment .................................................13

    3.4 Medium level project classification ............................................................................................... 13 3.5 Low level project classification (including emergency response works)....................................... 13 4 Legislation and department requirements................................................................................16 4.1 Environmental Legislation Register (ELR).................................................................................... 16 4.2 Other departmental manuals, standards and systems................................................................. 16 5 Scoping.........................................................................................................................................19 5.1 The scoping process..................................................................................................................... 20 5.2 Completing the environmental scoping report (ESR) ................................................................... 20

    5.2.1 Scoping process initiation.............................................................................................20 5.2.2 Communicate project scope.........................................................................................20 5.2.3 Strategic level scoping for link study ............................................................................21 5.2.4 Scoping assessment ....................................................................................................21 5.2.5 Environmental project classification .............................................................................23 5.2.6 Project approval triggers - scoping...............................................................................26 5.2.7 Options analysis ...........................................................................................................26 5.2.8 Component project cost estimate.................................................................................27

    Environmental Processes Manual, Transport and Main Roads, August 2013 ii

  • 5.2.9 Environmental scoping report (ESR) management recommendations........................27 5.3 Environmental management plan (site investigation) EMP(SI) ................................................. 28 5.4 Input to business case .................................................................................................................. 29 6 Environmental assessment ........................................................................................................30 6.1 The environmental assessment process ...................................................................................... 30 6.2 Completing the environmental assessment report (ear) .............................................................. 31

    6.2.1 Environmental assessment initiation............................................................................31 6.2.2 Scoping confirmation or commencement.....................................................................32 6.2.3 Review of environmental factors (REF)........................................................................32 6.2.4 Environmental management plan (planning) EMP(P)...............................................33

    6.3 Detailed cost estimates................................................................................................................. 34 6.4 Preliminary design ........................................................................................................................ 34

    6.4.1 Review preliminary design ...........................................................................................34 6.4.2 Environmental design report (EDR) for preliminary design..........................................35

    6.5 Detailed design ............................................................................................................................. 36 6.5.1 Review detailed design ................................................................................................36 6.5.2 Environmental design report (EDR) for detailed design...............................................36 6.5.3 Input to tender documentation......................................................................................37

    6.6 Development of scheme prototype............................................................................................... 38 6.7 Tendering process ........................................................................................................................ 38 6.8 Project contracts ........................................................................................................................... 39 6.9 Project data entry into departmental GIS systems ....................................................................... 42 7 Environmental management.......................................................................................................43 7.1 The environmental management process .................................................................................... 43 7.2 Completing the environmental management plan (construction) EMP(C) ................................ 44

    7.2.1 Environmental management initiation ..........................................................................44 7.2.2 Environmental officer input to the EMP(C)...................................................................45 7.2.3 EMP(C) development ...................................................................................................45 7.2.4 EMP(C) document review ............................................................................................45 7.2.5 Interim EMP(C).............................................................................................................46 7.2.6 Tender review phase....................................................................................................46 7.2.7 EMP(C) implementation audit ......................................................................................46 7.2.8 Environmental harm incident reporting (work improvement note (W.I.N.) system) .....47

    8 Project finalisation and network management .........................................................................49 8.1 Post implementation review.......................................................................................................... 49

    8.1.1 Defect liability period ....................................................................................................50 8.2 Surrender of approvals ................................................................................................................. 50 8.3 Handover report ............................................................................................................................ 50 8.4 Nomination of a significant environmental area (sea) .................................................................. 51 8.5 Maintenance of infrastructure network ......................................................................................... 51

    8.5.1 Program maintenance ..................................................................................................51 8.5.2 Routine maintenance ...................................................................................................51 8.5.3 Environmental management plan (maintenance) EMP(M) .......................................52 8.5.4 Emergency works (under maintenance contract).........................................................53

    8.6 Road corridor permits ................................................................................................................... 53 Glossary ................................................................................................................................................55

    Environmental Processes Manual, Transport and Main Roads, August 2013 iii

  • Environmental Processes Manual, Transport and Main Roads, August 2013 iv

    Table of Figures

    Table 1.6.1 - Alignment of Key Environmental Processes 4

    Figure 1.7 Environmental Processes Flow Chart.................................................................................... 5

    Figure 2.1 - Overall Project and Component Project .............................................................................. 6

    Figure 3.1.2 - Project Classification....................................................................................................... 11

    Table 4.2-A - Summary of other departmental documents related to environmental assessment and management.......................................................................................................................................... 17

    Figure 5 - Environmental Scoping Report (ESR) Process .................................................................... 19

    Figure 5.2.5 - Outcome of the Environmental Project Classification..................................................... 24

    Figure 6 - Environmental assessment process ..................................................................................... 30

    Table 6.8-A - Environmental input to various departmental contracts .................................................. 39

    Figure 7.1 - Environmental management process ................................................................................ 43

  • Overview

    1 Overview

    1.1 Introduction

    This manual provides the governance for environmental assessment and management of transport infrastructure projects undertaken by the Department of Transport and Main Roads (the department).

    This manual integrates environmental risk assessment and impact management within the departmental project management framework.

    The manual ensures the quality and consistency of environmental assessment and management processes within the department.

    1.2 Previous version

    This manual supersedes the Road Project Environmental Processes Manual (2004).

    1.3 Scope

    This manual establishes the processes for assessing and managing the environmental impacts of transport infrastructure projects undertaken by the department.

    The environmental processes described in this manual are structured to align with the principles of the departmental project management framework, OnQ (Section 1.6.1).

    This manual describes a process methodology and tools for the department to deliver its program of work, Queensland Transport and Roads Investment Program (QTRIP). The environmental process methodology and tools described in this manual may also be applied to other departmental projects and activities (non-QTRIP project works).

    This manual distinguishes between Process Management (Section 2.3.1) and Work Management (Section 2.3.2). This manual describes the Process Management required for departmental projects and describes a process for project delivery. Work Management documentation is not provided in this manual. The departmental Environmental Management System (EMS) (refer to Section 2.4) is the repository for Work Management documentation, and is referenced throughout this manual.

    Project teams may be flexible in the timing to apply the tools described in this manual to meet individual project requirements. The process flexibility enables a project to be entered at the appropriate timing and deliver an environmental response and outcome that is fit-for-purpose to the project.

    Legislative requirements are the basis of the environmental assessment and management processes in the department. The department also sets internal objectives for environmental outcomes. Compliance with processes specified in this manual will provide the basis for implementation of effective environmental outcomes and facilitate legislative compliance for projects.

    1.4 Aims

    The environmental processes described in this manual support:

    the departments general environmental duty to the environment as required by the Environmental Protection Act 1994

    the department to manage the performance of its functions and operations in accordance with the Corporate Governance Framework (2010)

    the strategies of the Transport and Main Roads Corporate Plan 2011 2015, including the Corporate Strategies to:

    Environmental Processes Manual, Transport and Main Roads, August 2013 1

  • Overview

    Reduce the environmental impact of our [departmental] operations and Implement effective business systems, processes and practices.

    1.5 Objectives

    This manual serves as the primary document to establish environmental assessment and management processes for transport infrastructure projects undertaken by the department.

    The objectives of this manual are to:

    Standardise and clarify the process of environmental assessment and management of infrastructure projects across the department.

    Provide easily accessible information and guidance for environmental assessment and environmental management of infrastructure projects (including reference to the departmental EMS) (Section 2.4).

    Provide a framework to manage projects that establishes:

    - distinct environmental assessment and environmental management stages

    - project scale differentiation: High, Medium and Low Level project streams, in terms of project complexity and environmental risk

    - a clear process map (Figure 1.7) to guide the user through the formal project management process

    - internal templates for department staff to perform and manage projects

    - external brief / contract proformas for department staff to engage external consultants to carry out project tasks

    - a streamlined process for environmental assessment and management.

    - external brief / contract proformas for department staff to engage external consultants to carry out project tasks

    - a streamlined process for environmental assessment and management.

    1.6 Manual structure

    Chapters 1 to 4 of this manual provide the background rationale (why) for the manual structure, aim, purpose and requirements.

    Chapters 5-8 of this manual provide the process details (what, when, how and who) for assessing and managing the environmental component of the project.

    Environmental Processes Manual, Transport and Main Roads, August 2013 2

  • Overview

    1.6.1 Environmental processes alignment to the OnQ framework

    The departments OnQ project management framework identifies four project phases as:

    Concept Development Implementation Finalisation

    The OnQ framework also states that projects included in the road program are generally initiated from the Link Study process. Input to this Link Study process occurs at a strategic level before detailed project assessment is required.

    The OnQ framework details a methodology that can be tailored to any size and nature of project, and a framework that plans out the total project life-cycle. It is used to estimate project costs and resources, clarify the roles and responsibilities of project members, and offers tools, techniques and templates to assist with the project management process.

    This manual aligns environmental processes with strategic level assessment, as well as the OnQ project phases, as demonstrated in Table 1.6.1 below.

    The manual alignment with OnQ project phases is expanded in Figure 1.7 to demonstrate the work tasks associated with each OnQ project phase and manual section.

    The key environmental processes and document names are shown in Figure 1.7 of this manual. Templates and associated procedures are supplied by the departmental EMS (Section 2.4).

    Environmental Processes Manual, Transport and Main Roads, August 2013 3

  • Overview

    Environmental Processes Manual, Transport and Main Roads, August 2013 4

    Table 1.6.1 - Alignment of Key Environmental Processes

    OnQ Project Management Phases

    Concept (including Link Study) Development Implementation Finalisation OnQ Project Management

    Phase

    Project Propos

    al

    Options Analysis

    Business

    Case Preliminary

    Design Detailed Design

    Construction Handover

    LOW ** ** EMP* (Construction) Checklist Review

    MED ** EAR* EDR * (Preliminary Design)

    Key documents in Environmental Process

    ESR*

    HIGH REF* EMP* Planning

    EDR* (Preliminary Design)

    ED

    R*

    (Det

    aile

    d D

    esig

    n)

    EM

    P*(

    Con

    stru

    ctio

    n) R

    evie

    w

    Env

    ironm

    enta

    l Site

    Insp

    ectio

    n C

    heck

    list

    Env

    ironm

    enta

    l Com

    plia

    nce

    Aud

    it R

    epor

    t

    Post Implementation Review / Handover Report (Environment)

    Environmental tasks aligned to project phases

    LINK STUDY Typically centred on route or corridor analysis Link study utilises desktop study tools (electronic environmental datasets (GIS)) (Link Studies include environmental input in to Route Constraints Analysis (RCA) & Corridor Development Plans (CDPs))

    CONCEPT PHASE Environmental input to overall project proposal Includes environmental component options analysis and cost estimate which contribute to the overall project Business Case.

    Input to Preliminary and Detailed Design Recommendations for Environmental Management Input to Contract Documentation

    Project EMP*

    Project Maintenance Plans Input to RMPC* Input to RCP*

    *Document acronyms provided in Glossary and also in later manual content with accompanying document / process descriptions.

    ** Content of ESR is considered sufficient for this phase

  • Overview

    1.7 Infrastructure projects environmental processes flow chart

    Figure 1.7 Environmental Processes Flow Chart

    Input to Detailed Design

    Environmental Risk

    Assessment forProject Classification

    Classification Decision

    (Provisional)

    Low LevelMedium Level High Level

    Further assessment & management required before proceeding to Implementation Phase

    Management recommendations provided in Scoping Report.

    Review of Environmental Factors (REF)

    Environmental Management Plan (Planning) EMP(P)

    Environmental Design Report (EDR)

    Input to Business Case

    Preliminary Design Review

    Input to Preliminary Design

    Detailed Design Review

    Input to Tender Documentation

    Development of Scheme Prototype

    Award of Contract

    Confirm In-Scope and Out-of-Scope project requirements

    Scope Communication or Confirmation (including review of Project Classification)

    Review & Reference Existing Project Work (Link Study & Concept phase Scoping Report(s))

    Environmental input to brief to external consultant

    (Provisional)

    Environmental Design Report (EDR)

    EMP(C) Review

    EMP(C) Implementation Audit

    Post Implementation Review

    DEVELOPMENTPHASE

    FINALISATIONPHASE

    IMPLEMENTATIONPHASE

    CONCEPT PHASE

    Surrender of Approvals

    Handover Report

    Maintenance of Infrastructure Network

    EMP (Maintenance) EMP(M) Road Corridor Permits (RCP)Statement of Environmental Effects

    Environmental Scoping ReportMajor Outputs:

    Project ClassificationOptions Analysis

    Cost Estimate

    Environmental Assessment Report (EAR)Includes:

    Review of Environmental Factors (REF)Environmental Management Plan (Planning) EMP(P)

    Review of Environmental Factors (REF)

    Environmental Management Plan (Planning) EMP(P)

    Repeated if required by

    project

    EMP (Construction) EMP(C)

    Site Inspection

    Overall project manager engages Component Manager (Environment) CM(E)

    Overall project manager engages Component Manager (Environment) CM(E)

    Overall project manager engages Component Manager (Environment) CM(E)

    Overall project manager engages Component Manager (Environment) CM(E)

    - Input to Environmental Management Plan (Construction) EMP(C) through Specification Annexures- Input to Principals Erosion and Sediment Control (ESC) Plan

    - Input to Environmental Management Plan (Construction) EMP(C) through Specification Annexures- Input to Principals Erosion and Sediment Control (ESC) Plan

    LEGEND Key Document in

    processProcess Decision

    Nomination of Significant Environmental Areas

    (Provisional)

    Project data entered into Departmental GIS Systems (Environmental Workspace)

    (Provisional)

    Data Provisional ProcessSub-Task /

    Input Process

    No Further Assessment Required

    Environmental Processes Manual, Transport and Main Roads, August 2013 5

    Amendment RegisterContentsTable of Figures1 Overview1.1 Introduction1.2 Previous version1.3 Scope1.4 Aims1.5 Objectives1.6 Manual structure1.6.1 Environmental processes alignment to the OnQ framework1.7 Infrastructure projects environmental processes flow chart