chapter 05 n
TRANSCRIPT
-
8/10/2019 Chapter 05 n
1/52
Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
Chapter 5
Activity-BasedCosting and
Management
-
8/10/2019 Chapter 05 n
2/52
Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
LearningObjective
1
-
8/10/2019 Chapter 05 n
3/52
Traditional, Volume-BasedProduct-Costing System
1-3
Aerotech produces three complex printed circuitboards referred to as Mode I, Mode II, and ModeIII.
The following information is obtained fromcompany records:
Mode I Mode II Mode II I
Production:
Units 10,000 20,000 4,000
Runs 1 run of 10,000
units
4 runs of
5,000 units
10 runs of
400 units
-
8/10/2019 Chapter 05 n
4/52
Traditional, Volume-BasedProduct-Costing System
1-4
Additional information includes:Mode I Mode I I Mode I I I
Direct materials 50.00$ 90.00$ 20.00$
Direct labor (hr/board) 3 4 2Setup time (hr/run) 10 10 10
Machine time (hr/board) 1 1.25 2
Mode I Mode I I Mode I I I
Direct materials 50.00$ 90.00$ 20.00$Direct labor 60.00 80.00 40.00
Manufacturing overhead 99.00 132.00 66.00Total 209.00$ 302.00$ 126.00$
Manufacturing overhead is determined as follows
-
8/10/2019 Chapter 05 n
5/52
Traditional, Volume-BasedProduct-Costing System
1-5
Mode I Mode II Mode I II
Units produced 10,000 20,000 4,000
Direct labor (hr/unit) 3 4 2
Total hours 30,000 80,000 8,000
Total hours required 118,000
Budgeted manufacturing overhead $3,894,000
Budgeted direct-labor hours 118,000
= $33 per hour
Mode I Mode I I Mode I II
Direct labor (hr/unit) 3 4 2
Overhead rate per hour 33$ 33$ 33$
Overhead per unit 99$ 132$ 66$
-
8/10/2019 Chapter 05 n
6/52
Traditional, Volume-BasedProduct-Costing System
1-6
With these product costs, Aerotech establishedtarget selling prices (Cost125%).
Mode I Mode I I Mode I I I
Direct materials 50.00$ 90.00$ 20.00$
Direct labor 60.00 80.00 40.00
Manufacturing overhead 99.00 132.00 66.00
Total 209.00$ 302.00$ 126.00$
Mode I Mode II Mode II I
Cost per unit 209.00$ 302.00$ 126.00$
Target selling price 261.25 377.50 157.50
209.00 x 1.25
-
8/10/2019 Chapter 05 n
7/52Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
LearningObjective
2
-
8/10/2019 Chapter 05 n
8/52
Activity Based Costing System(ABC)
1-8
ABC systems follow a two-stage procedureto assign overhead costs to products.
Stage OneIdentify significant activities and assign overhead coststo each activity in proportion to resources used.
Stage TwoIdentify cost drivers appropriate to each activity andallocate overhead to the products.
-
8/10/2019 Chapter 05 n
9/52Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
LearningObjective
3
-
8/10/2019 Chapter 05 n
10/521-10
Overhead CostsTotal budgeted cost = $3,894,000
ActivityCostPools
Machinerycost pool
$1,212,600
Setupcost pool$3,000
Engineeringcost pool$700,000
Facilitycost pool$507,400
Unit
Level
Batch
Level
Product-
Sustaining
Level
Facility
Level
Identificationof Activity
Cost Pools
Activitymust be
done oneach unitproduced.
Activityperformedon each
batchproduced.
Activities needed to supportan entire product line
Activity required in orderfor the productionprocess to occur.
-
8/10/2019 Chapter 05 n
11/521-11
Receiving/Inspectioncost pool $200,000
Material-Handlingcost pool $600,000
Quality-Assurancecost pool $421,000
Packaging/Shippingcost pool $250,000
Machinery
cost pool$1,212,600
Setup
cost pool$3,000
Engineering
cost pool$700,000
Facility
cost pool$507,400
Unit
Level
Batch
Level
Product-
Sustaining
Level
Facility
Level
-
8/10/2019 Chapter 05 n
12/52Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
LearningObjectives
3 & 4
-
8/10/2019 Chapter 05 n
13/52
STAGE ONE
1-13
Machinery Cost PoolTotal budgeted cost = $1,212,600
Maintenance
Depreciation
Computer Support
Lubrication
Electricity
Calibration
Activitycostpool
Various overheadcosts relatedto machinery
-
8/10/2019 Chapter 05 n
14/52
STAGE TWO
1-14
Calculatethe pool
rate
Budgeted Machinery Costs $1,212,600Budgeted Machine Hours 43,000
$28.20/hour
CostAssignment
==
Mode I:
$28.20 per hr.
1 hr. per unit
$28.20 per unit
Mode II:
$28.20 per hr.
1.25 hr. per unit
$35.25 per unit
Mode III:
$28.20 per hr.
2 hr. per unit
$56.40 per unit
-
8/10/2019 Chapter 05 n
15/52
STAGE ONE
1-15
Calculation oftotal setup cost
Setup Cost PoolTotal budgeted cost = $3,000
Activitycostpool
Total budgeted setup cost
$20 per hour
10 hr. per setup
$200 cost per setup
15 production runs3,000$ Total
-
8/10/2019 Chapter 05 n
16/52
STAGE TWO
1-16
Calculatethe pool
rate
Budgeted Setup Costs $3,000Planned Production Runs 15 runs
$200 per run
CostAssignment
=
=
Mode I: (1 Run)
= $.02 per unit
$200 per run
10,000 units per run
Mode II: (4 Runs)
= $.04 per unit
$200 per run
5,000 units per run
Mode III: (10 Runs)
= $.50 per unit
$200 per run
400 units per run
-
8/10/2019 Chapter 05 n
17/52
STAGE ONE
1-17
Various overheadcosts related
to engineering
Engineering salaries
Engineering supplies
Engineering software
Depreciation
Engineering Cost PoolTotal budgeted cost = $700,000
Activitycostpool
-
8/10/2019 Chapter 05 n
18/52
STAGE TWO
1-18
Allocate basedon engineering
transactions
CostAssignment
Engineering Cost PoolTotal budgeted cost = $700,000
Mode I:
= $17.50 per unit
25% $700,000
10,000 units
Mode II:
= $15.75 per unit
45% $700,000
20,000 units
Mode III:
= $52.50 per unit
30% $700,000
4,000 units
-
8/10/2019 Chapter 05 n
19/52
STAGE ONE
1-19
Various overheadcosts related
to generaloperations
Plant depr.
Plant mgmt.
Plant maint.
Property taxes
Insurance
Security
Facility Cost PoolTotal budgeted cost = $507,400
Activitycostpool
-
8/10/2019 Chapter 05 n
20/52
STAGE TWO
1-20
Budgeted Facilities Cost $507,400Budgeted Direct-Labor Hours 118,000
$4.30/hour
CostAssignment
=
=
Mode I:
$4.30 per hr.
3 hr. per unit
$12.90 per unit
Mode II:
$4.30 per hr.
4 hr. per unit
$17.20 per unit
Mode III:
$4.30 per hr.
2 hr. per unit
$8.60 per unit
Calculatethe pool
rate
-
8/10/2019 Chapter 05 n
21/52
Other Overhead Costs
1-21
Board Ove rh e ad % Un its = Cos t/Un it
Mode I 200,000$ 6% 10,000 = 1.20$
Mode II 200,000 24% 20,000 = 2.40
Mode III 200,000 70% 4,000 = 35.00
Receiving and Inspect ion Cost Pool
Board Ove rh e ad % Un its = Cos t/Un it
Mode I 600,000$ 7% 10,000 = 4.20$
Mode II 600,000 30% 20,000 = 9.00
Mode III 600,000 63% 4,000 = 94.50
Material-Handling Cos t P ool
Board Ove rh e ad % Un its = Cos t/Un it
Mode I 421,000$ 20% 10,000 = 8.42$
Mode II 421,000 40% 20,000 = 8.42Mode III 421,000 40% 4,000 = 42.10
Quality-Assu rance Cost P ool
Board Ove rh e ad % Un its = Cos t/Un it
Mode I 250,000$ 4% 10,000 = 1.00$
Mode II 250,000 30% 20,000 = 3.75
Mode III 250,000 66% 4,000 = 41.25
Packaging and Sh ipping Cost Pool
-
8/10/2019 Chapter 05 n
22/52
Other Overhead Costs
1-22
Board Ove rh e ad % Un its = Cos t/Un it
Mode I 250,000$ 4% 10,000 = 1.00$
Mode II 250,000 30% 20,000 = 3.75
Mode III 250,000 66% 4,000 = 41.25
Packaging and Sh ipping Cost Pool
Board Ove rh e ad % Un its = Cos t/Un it
Mode I 421,000$ 20% 10,000 = 8.42$
Mode II 421,000 40% 20,000 = 8.42Mode III 421,000 40% 4,000 = 42.10
Quality-Assu rance Cost P ool
Board Ove rh e ad % Un its = Cos t/Un it
Mode I 200,000$ 6% 10,000 = 1.20$
Mode II 200,000 24% 20,000 = 2.40
Mode III 200,000 70% 4,000 = 35.00
Receiving and Inspect ion Cost Pool
Board Ove rh e ad % Un its = Cos t/Un it
Mode I 600,000$ 7% 10,000 = 4.20$
Mode II 600,000 30% 20,000 = 9.00
Mode III 600,000 63% 4,000 = 94.50
Material-Handling Cos t P ool
$14.82
-
8/10/2019 Chapter 05 n
23/52
Product Cost from ABC
1-23
These are the new product costs when Aerotechuses ABC.Mode I Mode II Mode III
Direct materials 50.00$ 90.00$ 20.00$
Direct labor 60.00 80.00 40.00
Machinery 28.20 35.25 56.40
Setup 0.02 0.04 0.50
Engineering 17.50 15.75 52.50Facilities 12.90 17.20 8.60
Other 14.82 23.57 212.85
Total 183.44$ 261.81$ 390.85$
-
8/10/2019 Chapter 05 n
24/52
Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
Learning
Objective5
-
8/10/2019 Chapter 05 n
25/52
Distorted Product Costs
1-25
Both original and ABC target selling prices are basedon (Cost125%).
Mode I Mode II Mode III
Tradition al cos tin g 209.00$ 302.00$ 126.00$
ABC cos tin g 183.44 261.81 390.85
Origin al targe t s e llin g price 261.25 377.50 157.50
ABC targe t s e llin g price 229.30 327.26 488.56
[$209.001.25] [$183.44 1.25]
The selling price of Mode I and II are reducedand the selling price for Mode III is increased.
-
8/10/2019 Chapter 05 n
26/52
Distorted Product Costs
1-26
Can you identify any problems Aerotech is likely toface as a result of this distortion?
Mode I Mode II Mode III
Tradition al cos tin g 209.00$ 302.00$ 126.00$ABC cos tin g 183.44 261.81 390.85
Cos t dis tortion pe r u n it 25.56 40.19 (264.85)
Un its produ ce d 10,000 20,000 4,000
Total cos t dis tortion 255,600 803,800 (1,059,400)
Traditional costing understates the costof complex, low volume products.
-
8/10/2019 Chapter 05 n
27/52
Two Key Points
1-27
A large propor t ion of non -
un it- level activ i t ies
A unit-level cost driver,
such as direct labor,machine hours, orthroughput, will not beable to assign the costsof non-unit-level activities
accurately.
Product d ivers i ty
When the
consumption ratiosdiffer widely betweenactivities, no singlecost driver will
accurately assign theresulting overheadcosts.
-
8/10/2019 Chapter 05 n
28/52
Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
Learning
Objective6
-
8/10/2019 Chapter 05 n
29/52
Cost Drivers
1-29
A characteristic of an event or activity that resultsin the incurrence of costs. In selecting a cost
driver, we must consider . . .
Degree ofCorrelation
Cost ofMeasurement
BehavioralEffects
-
8/10/2019 Chapter 05 n
30/52
Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
Learning
Objective7
-
8/10/2019 Chapter 05 n
31/52
COLLECTING ABC DATA
1-31
INTERVIEWS AND PAPER TRAILS - The informationfor ABC systems initially comes from interviews withemployees in the support departments and a review of eachdepartments records.
STORYBOARDING -A procedure used to develop adetailed process flow chart, which visually represents activitiesand the relationships among activities.
MULTIDISCIPLINARY ABC PROJECT TEAMSTo
gather information from all facets of an organizationsoperations, it is essential to involve personnel from a variety offunctional areas. A typical ABC project team includesACCOUNTING, FINANCE, PRODUCTION, OPERATIONS,ENGINEERS, MARKETINGetc.
-
8/10/2019 Chapter 05 n
32/52
Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
Learning
Objective8
-
8/10/2019 Chapter 05 n
33/52
Activity-Based Management
1-33
The use ofABC costing
informationto help
managementmake decisions
-
8/10/2019 Chapter 05 n
34/52
Activity-Based Management
1-34
Activity-based costingestablishes relationshipsbetween overhead costs and activities so that
we can better allocate overhead costs.
Activity-based managementfocuseson managing activities to reduce costs.
T Di i l ABC d
-
8/10/2019 Chapter 05 n
35/52
Two-Dimensional ABC andActivity-Based Management
1-35
Activities
T Di i l ABC d
-
8/10/2019 Chapter 05 n
36/52
Two-Dimensional ABC andActivity-Based Management
1-36
Cost Objects
Activities
Resource costs
Cost Assignment View
T Di i l ABC d
-
8/10/2019 Chapter 05 n
37/52
Two-Dimensional ABC andActivity-Based Management
1-37
Activity
Triggers
Cost Objects
Activities
Root
Causes
Process ViewActivity Analysis
Resource costs
Cost Assignment View
Performance
Measures
Activity Evaluation
Eli i ti f N V l Add d
-
8/10/2019 Chapter 05 n
38/52
Elimination of Non-Value-AddedCosts
1-38
Nonvalue-added
activities
NecessaryUnnecessary
Activities
Reduce orEliminate
Continually Evaluateand Improve
U i ABM t Eli i t N
-
8/10/2019 Chapter 05 n
39/52
Using ABM to Eliminate Non-Value-Added Activities and Costs
1-39
1. Identify Activities.
2. Identify Non-Value-Added Activities.
3. Understand Activity Linkages, Root Causes,
and Triggers.
4. Establish Performance Measures.
5. Report Non-Value-Added Costs.
Specifyparts
Selectvendor
Receiveparts
Producegoods
Inspectfinishedgoods
Reworkdefectiveproducts
U i ABM t Eli i t N
-
8/10/2019 Chapter 05 n
40/52
Using ABM to Eliminate Non-Value-Added Activities and Costs
1-40
Inspection time
Process time
Storage time
Move time Waiting time
-
8/10/2019 Chapter 05 n
41/52
Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
Learning
Objective9
-
8/10/2019 Chapter 05 n
42/52
1-42
Customer Profitability Analysis
Customer profitability analysis usesactivity-based costing to determine
the activities, costs, and profit associated
with serving particular customers.
-
8/10/2019 Chapter 05 n
43/52
1-43
Customer Profitability Analysis
Orderssmall
quantities.
Orders
frequently.
Oftenchanges
orders.
Requiredspecial
packaging.
Demandfast
service.
costly customer
-
8/10/2019 Chapter 05 n
44/52
1-44
Customer Profitability Analysis
Customer-Related Activities Cost Driver Base
Cost Drive
Rate
Order processing Purchase orders 150$
Sales contacts (phone calls, faxes, etc.) Contacts 100
Sales visits Visits 1,000
Shipment processing Shipments 200
Billing and collection Invoices 160Design/engineering change orders Design changes 4,000
Special packaging Units packaged 40
Special handling Units handled 60
A company may use these customerrelated costs to help determine the
profitability of each customer.
-
8/10/2019 Chapter 05 n
45/52
1-45
Customer Profitability Analysis
Customer Profitability
0.0%
25.0%
50.0%
75.0%
100.0%
125.0%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20CumulativeOperatingIncome
asa%ofTotal
OperatingIncome
75% of actual operating income
50% of actual operating income
25% of actual operating income
-
8/10/2019 Chapter 05 n
46/52
Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
Learning
Objective10
Acti it Based Management in the
-
8/10/2019 Chapter 05 n
47/52
1-47
Activity-Based Management in theService Industry
ActivityAnalysis
CustomerProfitability
Analysis
-
8/10/2019 Chapter 05 n
48/52
Copyright
2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin
Learning
Objective11
Just in Time Inventory and
-
8/10/2019 Chapter 05 n
49/52
Just-in-Time Inventory andProduction Management
1-49
No materials are purchased and no productsare manufactured until they are needed.
The primary goal of aJIT production system is
to reduce or eliminate
inventories at everystage of production.
Key Features of the JIT
-
8/10/2019 Chapter 05 n
50/52
Key Features of the JITApproach
1-50
Smooth, uniform production rate
Pull method of production
Purchase is small lot sizes
Quick, inexpensive setups
High quality materials
Effective preventive maintenanceTeamwork
Multiskilled workers
-
8/10/2019 Chapter 05 n
51/52
JIT Purchasing
1-51
Long-termcontracts with
suppliers.
Only a fewsuppliers.
Parts deliveredin small lots.
Minimalinspection of
materials.
Groupedpayments to
vendor.
-
8/10/2019 Chapter 05 n
52/52
End of Chapter 5This is
my kind of costpool!