chapter 05 n

Upload: florensia-restian

Post on 02-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Chapter 05 n

    1/52

    Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    Chapter 5

    Activity-BasedCosting and

    Management

  • 8/10/2019 Chapter 05 n

    2/52

    Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    LearningObjective

    1

  • 8/10/2019 Chapter 05 n

    3/52

    Traditional, Volume-BasedProduct-Costing System

    1-3

    Aerotech produces three complex printed circuitboards referred to as Mode I, Mode II, and ModeIII.

    The following information is obtained fromcompany records:

    Mode I Mode II Mode II I

    Production:

    Units 10,000 20,000 4,000

    Runs 1 run of 10,000

    units

    4 runs of

    5,000 units

    10 runs of

    400 units

  • 8/10/2019 Chapter 05 n

    4/52

    Traditional, Volume-BasedProduct-Costing System

    1-4

    Additional information includes:Mode I Mode I I Mode I I I

    Direct materials 50.00$ 90.00$ 20.00$

    Direct labor (hr/board) 3 4 2Setup time (hr/run) 10 10 10

    Machine time (hr/board) 1 1.25 2

    Mode I Mode I I Mode I I I

    Direct materials 50.00$ 90.00$ 20.00$Direct labor 60.00 80.00 40.00

    Manufacturing overhead 99.00 132.00 66.00Total 209.00$ 302.00$ 126.00$

    Manufacturing overhead is determined as follows

  • 8/10/2019 Chapter 05 n

    5/52

    Traditional, Volume-BasedProduct-Costing System

    1-5

    Mode I Mode II Mode I II

    Units produced 10,000 20,000 4,000

    Direct labor (hr/unit) 3 4 2

    Total hours 30,000 80,000 8,000

    Total hours required 118,000

    Budgeted manufacturing overhead $3,894,000

    Budgeted direct-labor hours 118,000

    = $33 per hour

    Mode I Mode I I Mode I II

    Direct labor (hr/unit) 3 4 2

    Overhead rate per hour 33$ 33$ 33$

    Overhead per unit 99$ 132$ 66$

  • 8/10/2019 Chapter 05 n

    6/52

    Traditional, Volume-BasedProduct-Costing System

    1-6

    With these product costs, Aerotech establishedtarget selling prices (Cost125%).

    Mode I Mode I I Mode I I I

    Direct materials 50.00$ 90.00$ 20.00$

    Direct labor 60.00 80.00 40.00

    Manufacturing overhead 99.00 132.00 66.00

    Total 209.00$ 302.00$ 126.00$

    Mode I Mode II Mode II I

    Cost per unit 209.00$ 302.00$ 126.00$

    Target selling price 261.25 377.50 157.50

    209.00 x 1.25

  • 8/10/2019 Chapter 05 n

    7/52Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    LearningObjective

    2

  • 8/10/2019 Chapter 05 n

    8/52

    Activity Based Costing System(ABC)

    1-8

    ABC systems follow a two-stage procedureto assign overhead costs to products.

    Stage OneIdentify significant activities and assign overhead coststo each activity in proportion to resources used.

    Stage TwoIdentify cost drivers appropriate to each activity andallocate overhead to the products.

  • 8/10/2019 Chapter 05 n

    9/52Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    LearningObjective

    3

  • 8/10/2019 Chapter 05 n

    10/521-10

    Overhead CostsTotal budgeted cost = $3,894,000

    ActivityCostPools

    Machinerycost pool

    $1,212,600

    Setupcost pool$3,000

    Engineeringcost pool$700,000

    Facilitycost pool$507,400

    Unit

    Level

    Batch

    Level

    Product-

    Sustaining

    Level

    Facility

    Level

    Identificationof Activity

    Cost Pools

    Activitymust be

    done oneach unitproduced.

    Activityperformedon each

    batchproduced.

    Activities needed to supportan entire product line

    Activity required in orderfor the productionprocess to occur.

  • 8/10/2019 Chapter 05 n

    11/521-11

    Receiving/Inspectioncost pool $200,000

    Material-Handlingcost pool $600,000

    Quality-Assurancecost pool $421,000

    Packaging/Shippingcost pool $250,000

    Machinery

    cost pool$1,212,600

    Setup

    cost pool$3,000

    Engineering

    cost pool$700,000

    Facility

    cost pool$507,400

    Unit

    Level

    Batch

    Level

    Product-

    Sustaining

    Level

    Facility

    Level

  • 8/10/2019 Chapter 05 n

    12/52Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    LearningObjectives

    3 & 4

  • 8/10/2019 Chapter 05 n

    13/52

    STAGE ONE

    1-13

    Machinery Cost PoolTotal budgeted cost = $1,212,600

    Maintenance

    Depreciation

    Computer Support

    Lubrication

    Electricity

    Calibration

    Activitycostpool

    Various overheadcosts relatedto machinery

  • 8/10/2019 Chapter 05 n

    14/52

    STAGE TWO

    1-14

    Calculatethe pool

    rate

    Budgeted Machinery Costs $1,212,600Budgeted Machine Hours 43,000

    $28.20/hour

    CostAssignment

    ==

    Mode I:

    $28.20 per hr.

    1 hr. per unit

    $28.20 per unit

    Mode II:

    $28.20 per hr.

    1.25 hr. per unit

    $35.25 per unit

    Mode III:

    $28.20 per hr.

    2 hr. per unit

    $56.40 per unit

  • 8/10/2019 Chapter 05 n

    15/52

    STAGE ONE

    1-15

    Calculation oftotal setup cost

    Setup Cost PoolTotal budgeted cost = $3,000

    Activitycostpool

    Total budgeted setup cost

    $20 per hour

    10 hr. per setup

    $200 cost per setup

    15 production runs3,000$ Total

  • 8/10/2019 Chapter 05 n

    16/52

    STAGE TWO

    1-16

    Calculatethe pool

    rate

    Budgeted Setup Costs $3,000Planned Production Runs 15 runs

    $200 per run

    CostAssignment

    =

    =

    Mode I: (1 Run)

    = $.02 per unit

    $200 per run

    10,000 units per run

    Mode II: (4 Runs)

    = $.04 per unit

    $200 per run

    5,000 units per run

    Mode III: (10 Runs)

    = $.50 per unit

    $200 per run

    400 units per run

  • 8/10/2019 Chapter 05 n

    17/52

    STAGE ONE

    1-17

    Various overheadcosts related

    to engineering

    Engineering salaries

    Engineering supplies

    Engineering software

    Depreciation

    Engineering Cost PoolTotal budgeted cost = $700,000

    Activitycostpool

  • 8/10/2019 Chapter 05 n

    18/52

    STAGE TWO

    1-18

    Allocate basedon engineering

    transactions

    CostAssignment

    Engineering Cost PoolTotal budgeted cost = $700,000

    Mode I:

    = $17.50 per unit

    25% $700,000

    10,000 units

    Mode II:

    = $15.75 per unit

    45% $700,000

    20,000 units

    Mode III:

    = $52.50 per unit

    30% $700,000

    4,000 units

  • 8/10/2019 Chapter 05 n

    19/52

    STAGE ONE

    1-19

    Various overheadcosts related

    to generaloperations

    Plant depr.

    Plant mgmt.

    Plant maint.

    Property taxes

    Insurance

    Security

    Facility Cost PoolTotal budgeted cost = $507,400

    Activitycostpool

  • 8/10/2019 Chapter 05 n

    20/52

    STAGE TWO

    1-20

    Budgeted Facilities Cost $507,400Budgeted Direct-Labor Hours 118,000

    $4.30/hour

    CostAssignment

    =

    =

    Mode I:

    $4.30 per hr.

    3 hr. per unit

    $12.90 per unit

    Mode II:

    $4.30 per hr.

    4 hr. per unit

    $17.20 per unit

    Mode III:

    $4.30 per hr.

    2 hr. per unit

    $8.60 per unit

    Calculatethe pool

    rate

  • 8/10/2019 Chapter 05 n

    21/52

    Other Overhead Costs

    1-21

    Board Ove rh e ad % Un its = Cos t/Un it

    Mode I 200,000$ 6% 10,000 = 1.20$

    Mode II 200,000 24% 20,000 = 2.40

    Mode III 200,000 70% 4,000 = 35.00

    Receiving and Inspect ion Cost Pool

    Board Ove rh e ad % Un its = Cos t/Un it

    Mode I 600,000$ 7% 10,000 = 4.20$

    Mode II 600,000 30% 20,000 = 9.00

    Mode III 600,000 63% 4,000 = 94.50

    Material-Handling Cos t P ool

    Board Ove rh e ad % Un its = Cos t/Un it

    Mode I 421,000$ 20% 10,000 = 8.42$

    Mode II 421,000 40% 20,000 = 8.42Mode III 421,000 40% 4,000 = 42.10

    Quality-Assu rance Cost P ool

    Board Ove rh e ad % Un its = Cos t/Un it

    Mode I 250,000$ 4% 10,000 = 1.00$

    Mode II 250,000 30% 20,000 = 3.75

    Mode III 250,000 66% 4,000 = 41.25

    Packaging and Sh ipping Cost Pool

  • 8/10/2019 Chapter 05 n

    22/52

    Other Overhead Costs

    1-22

    Board Ove rh e ad % Un its = Cos t/Un it

    Mode I 250,000$ 4% 10,000 = 1.00$

    Mode II 250,000 30% 20,000 = 3.75

    Mode III 250,000 66% 4,000 = 41.25

    Packaging and Sh ipping Cost Pool

    Board Ove rh e ad % Un its = Cos t/Un it

    Mode I 421,000$ 20% 10,000 = 8.42$

    Mode II 421,000 40% 20,000 = 8.42Mode III 421,000 40% 4,000 = 42.10

    Quality-Assu rance Cost P ool

    Board Ove rh e ad % Un its = Cos t/Un it

    Mode I 200,000$ 6% 10,000 = 1.20$

    Mode II 200,000 24% 20,000 = 2.40

    Mode III 200,000 70% 4,000 = 35.00

    Receiving and Inspect ion Cost Pool

    Board Ove rh e ad % Un its = Cos t/Un it

    Mode I 600,000$ 7% 10,000 = 4.20$

    Mode II 600,000 30% 20,000 = 9.00

    Mode III 600,000 63% 4,000 = 94.50

    Material-Handling Cos t P ool

    $14.82

  • 8/10/2019 Chapter 05 n

    23/52

    Product Cost from ABC

    1-23

    These are the new product costs when Aerotechuses ABC.Mode I Mode II Mode III

    Direct materials 50.00$ 90.00$ 20.00$

    Direct labor 60.00 80.00 40.00

    Machinery 28.20 35.25 56.40

    Setup 0.02 0.04 0.50

    Engineering 17.50 15.75 52.50Facilities 12.90 17.20 8.60

    Other 14.82 23.57 212.85

    Total 183.44$ 261.81$ 390.85$

  • 8/10/2019 Chapter 05 n

    24/52

    Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    Learning

    Objective5

  • 8/10/2019 Chapter 05 n

    25/52

    Distorted Product Costs

    1-25

    Both original and ABC target selling prices are basedon (Cost125%).

    Mode I Mode II Mode III

    Tradition al cos tin g 209.00$ 302.00$ 126.00$

    ABC cos tin g 183.44 261.81 390.85

    Origin al targe t s e llin g price 261.25 377.50 157.50

    ABC targe t s e llin g price 229.30 327.26 488.56

    [$209.001.25] [$183.44 1.25]

    The selling price of Mode I and II are reducedand the selling price for Mode III is increased.

  • 8/10/2019 Chapter 05 n

    26/52

    Distorted Product Costs

    1-26

    Can you identify any problems Aerotech is likely toface as a result of this distortion?

    Mode I Mode II Mode III

    Tradition al cos tin g 209.00$ 302.00$ 126.00$ABC cos tin g 183.44 261.81 390.85

    Cos t dis tortion pe r u n it 25.56 40.19 (264.85)

    Un its produ ce d 10,000 20,000 4,000

    Total cos t dis tortion 255,600 803,800 (1,059,400)

    Traditional costing understates the costof complex, low volume products.

  • 8/10/2019 Chapter 05 n

    27/52

    Two Key Points

    1-27

    A large propor t ion of non -

    un it- level activ i t ies

    A unit-level cost driver,

    such as direct labor,machine hours, orthroughput, will not beable to assign the costsof non-unit-level activities

    accurately.

    Product d ivers i ty

    When the

    consumption ratiosdiffer widely betweenactivities, no singlecost driver will

    accurately assign theresulting overheadcosts.

  • 8/10/2019 Chapter 05 n

    28/52

    Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    Learning

    Objective6

  • 8/10/2019 Chapter 05 n

    29/52

    Cost Drivers

    1-29

    A characteristic of an event or activity that resultsin the incurrence of costs. In selecting a cost

    driver, we must consider . . .

    Degree ofCorrelation

    Cost ofMeasurement

    BehavioralEffects

  • 8/10/2019 Chapter 05 n

    30/52

    Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    Learning

    Objective7

  • 8/10/2019 Chapter 05 n

    31/52

    COLLECTING ABC DATA

    1-31

    INTERVIEWS AND PAPER TRAILS - The informationfor ABC systems initially comes from interviews withemployees in the support departments and a review of eachdepartments records.

    STORYBOARDING -A procedure used to develop adetailed process flow chart, which visually represents activitiesand the relationships among activities.

    MULTIDISCIPLINARY ABC PROJECT TEAMSTo

    gather information from all facets of an organizationsoperations, it is essential to involve personnel from a variety offunctional areas. A typical ABC project team includesACCOUNTING, FINANCE, PRODUCTION, OPERATIONS,ENGINEERS, MARKETINGetc.

  • 8/10/2019 Chapter 05 n

    32/52

    Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    Learning

    Objective8

  • 8/10/2019 Chapter 05 n

    33/52

    Activity-Based Management

    1-33

    The use ofABC costing

    informationto help

    managementmake decisions

  • 8/10/2019 Chapter 05 n

    34/52

    Activity-Based Management

    1-34

    Activity-based costingestablishes relationshipsbetween overhead costs and activities so that

    we can better allocate overhead costs.

    Activity-based managementfocuseson managing activities to reduce costs.

    T Di i l ABC d

  • 8/10/2019 Chapter 05 n

    35/52

    Two-Dimensional ABC andActivity-Based Management

    1-35

    Activities

    T Di i l ABC d

  • 8/10/2019 Chapter 05 n

    36/52

    Two-Dimensional ABC andActivity-Based Management

    1-36

    Cost Objects

    Activities

    Resource costs

    Cost Assignment View

    T Di i l ABC d

  • 8/10/2019 Chapter 05 n

    37/52

    Two-Dimensional ABC andActivity-Based Management

    1-37

    Activity

    Triggers

    Cost Objects

    Activities

    Root

    Causes

    Process ViewActivity Analysis

    Resource costs

    Cost Assignment View

    Performance

    Measures

    Activity Evaluation

    Eli i ti f N V l Add d

  • 8/10/2019 Chapter 05 n

    38/52

    Elimination of Non-Value-AddedCosts

    1-38

    Nonvalue-added

    activities

    NecessaryUnnecessary

    Activities

    Reduce orEliminate

    Continually Evaluateand Improve

    U i ABM t Eli i t N

  • 8/10/2019 Chapter 05 n

    39/52

    Using ABM to Eliminate Non-Value-Added Activities and Costs

    1-39

    1. Identify Activities.

    2. Identify Non-Value-Added Activities.

    3. Understand Activity Linkages, Root Causes,

    and Triggers.

    4. Establish Performance Measures.

    5. Report Non-Value-Added Costs.

    Specifyparts

    Selectvendor

    Receiveparts

    Producegoods

    Inspectfinishedgoods

    Reworkdefectiveproducts

    U i ABM t Eli i t N

  • 8/10/2019 Chapter 05 n

    40/52

    Using ABM to Eliminate Non-Value-Added Activities and Costs

    1-40

    Inspection time

    Process time

    Storage time

    Move time Waiting time

  • 8/10/2019 Chapter 05 n

    41/52

    Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    Learning

    Objective9

  • 8/10/2019 Chapter 05 n

    42/52

    1-42

    Customer Profitability Analysis

    Customer profitability analysis usesactivity-based costing to determine

    the activities, costs, and profit associated

    with serving particular customers.

  • 8/10/2019 Chapter 05 n

    43/52

    1-43

    Customer Profitability Analysis

    Orderssmall

    quantities.

    Orders

    frequently.

    Oftenchanges

    orders.

    Requiredspecial

    packaging.

    Demandfast

    service.

    costly customer

  • 8/10/2019 Chapter 05 n

    44/52

    1-44

    Customer Profitability Analysis

    Customer-Related Activities Cost Driver Base

    Cost Drive

    Rate

    Order processing Purchase orders 150$

    Sales contacts (phone calls, faxes, etc.) Contacts 100

    Sales visits Visits 1,000

    Shipment processing Shipments 200

    Billing and collection Invoices 160Design/engineering change orders Design changes 4,000

    Special packaging Units packaged 40

    Special handling Units handled 60

    A company may use these customerrelated costs to help determine the

    profitability of each customer.

  • 8/10/2019 Chapter 05 n

    45/52

    1-45

    Customer Profitability Analysis

    Customer Profitability

    0.0%

    25.0%

    50.0%

    75.0%

    100.0%

    125.0%

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20CumulativeOperatingIncome

    asa%ofTotal

    OperatingIncome

    75% of actual operating income

    50% of actual operating income

    25% of actual operating income

  • 8/10/2019 Chapter 05 n

    46/52

    Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    Learning

    Objective10

    Acti it Based Management in the

  • 8/10/2019 Chapter 05 n

    47/52

    1-47

    Activity-Based Management in theService Industry

    ActivityAnalysis

    CustomerProfitability

    Analysis

  • 8/10/2019 Chapter 05 n

    48/52

    Copyright

    2011 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

    Learning

    Objective11

    Just in Time Inventory and

  • 8/10/2019 Chapter 05 n

    49/52

    Just-in-Time Inventory andProduction Management

    1-49

    No materials are purchased and no productsare manufactured until they are needed.

    The primary goal of aJIT production system is

    to reduce or eliminate

    inventories at everystage of production.

    Key Features of the JIT

  • 8/10/2019 Chapter 05 n

    50/52

    Key Features of the JITApproach

    1-50

    Smooth, uniform production rate

    Pull method of production

    Purchase is small lot sizes

    Quick, inexpensive setups

    High quality materials

    Effective preventive maintenanceTeamwork

    Multiskilled workers

  • 8/10/2019 Chapter 05 n

    51/52

    JIT Purchasing

    1-51

    Long-termcontracts with

    suppliers.

    Only a fewsuppliers.

    Parts deliveredin small lots.

    Minimalinspection of

    materials.

    Groupedpayments to

    vendor.

  • 8/10/2019 Chapter 05 n

    52/52

    End of Chapter 5This is

    my kind of costpool!