challenges of the next generation energy market … lmp (nodal price) at bus i can be calculated...
TRANSCRIPT
Sponsored by the IEEE GREECE PES CHAPTER
By
Alex Papalexopoulos, Ph.D. President & CEO, ECCO International, Inc.
October 6, 2011 Athens, Greece
Challenges of the Next Generation Energy Market Design Structures
Copyright 2011, ECCO International, Inc. 2
Outline
Overview of the key competitive energy market models Current status of energy markets Major Challenges Competitive Energy Markets Face Today Capacity Markets Transmission and Infrastructure Investment Issues Renewable Energy Sources Market Issues Demand Response Markets Summary
Exchanges – NordPool, Australia, California (old design), Spain, Poland, Ontario)
Pools – Britain (until 2001), various markets in the USA, Chile, Alberta, Argentina, Columbia, Singapore, Greece
Central Optimization Bilateral 100% – Britain (since 2001) Bifurcated – NY, PJM 60% bilateral Self-Scheduled
40% Dispatched voluntarily Market Clearing, Self-Scheduling
Various Markets for Energy
3 Copyright 2011, ECCO International, Inc.
0
10
20
30
40
50
60
Self-supplied Bilateral transactions
Spot market Imports
Market type
Mar
ket s
hare
(%)
Year 2007 Year 2008
PJM Energy Markets
4 Copyright 2011, ECCO International, Inc.
None – PJM (before 2001) Unit Commitment & Dispatch – California, NE,
NY, PJM, NZ, Greece, etc. TSO procures needs – if not self-provided Daily Procurement Auctions – All U.S. markets TSO controls dispatch of sufficient units
Long-Term Bilateral Contracts – Britain, Sweden, Poland, Cyprus TSO procures needs through annual contracts Reliability-Must-Run: California imposes contracts on these units Annual auctions for fast-start/ramp resources: New England
Markets for Ancillary Services
5 Copyright 2011, ECCO International, Inc.
Transco's (ITCs) – Britain, NordPool, Poland, NZ, Chile
System Operators – Australia, Canada [power pools] U.S.: California, Texas, New England, NY, PJM
Zonal Pricing – NordPool, Australia, California (old model) Texas (old model)
TSO charges marginal cost of inter-zonal congestion Explicit market for adjustments to alleviate congestion
Nodal Pricing – California, NY, PJM, NE, Texas, NZ TSO charges marginal cost at every location
Markets Structure for Transmission
6 Copyright 2011, ECCO International, Inc.
NONE – Some argue that Transmission = Public Good Better reliability, more competitive and liquid energy
markets TSOs can procure adjustment services via long-term
contracts as in Britain, Sweden, if congestion is infrequent ZONAL PRICING – Proponents argue for commercial
simplicity and forward sufficiency – but has been under severe attack – California and Texas have abandoning it Firm and Physical Transmission Rights and hedges remain
controversial The “DEC Game” in California & Texas was fatal; it
resulted in Billions of Dollars of losses to consumers
Key Principles of Various Transmission Markets
7 Copyright 2011, ECCO International, Inc.
LOCATIONAL/NODAL PRICING – Preferred method in the USA Full transmission is part of the market clearing mechanism All resource, system, security and transmission constraints
are priced – thousands of prices are created and used for settlements
Financial Rights (i.e., locational hedges) are required (FTR market) Point-to-Point vs. explicit pricing of flow-gates Formation of secondary markets
Key Principles of Various Transmission Markets
8 Copyright 2011, ECCO International, Inc.
Congestion Management vs Transmission Investments
Fundamental tradeoff: congestion vs. investment costs What’s optimal?
Copyright 2011, ECCO International, Inc. 10
11
Zonal Market Design Flaws
Operationally infeasible plan Reliability problems Socialization of constraint mitigation cost Price reversals in reserve markets due to auction structure Un-priced inter-temporal products and constraints – Need
Unit Commitment Improper price signals for investments Sequential solution of simultaneous problems – Need Co-
optimization of Energy and Ancillary Services One settlement system As-bid pricing It does not support RES and Demand Response
Copyright 2011, ECCO International, Inc.
Why Nodal?
Market efficiency: minimization of production cost System-wide, incentive-compatible
System-wide and local reliability Advanced locational signal for buyers and sellers to match
next day needs and supplies Economic signal (LMP) to Generators and Demand
Response while protecting load Congestion risk management (CRR/FTR/TCC) and
transmission planning
12 Copyright 2011 ECCO International, Inc
Transition from Zonal To Nodal (LMP) Market
• No intra-zonal constraints enforced • Internal Congestion Zones – Constraints enforced between zones
• Full Network Model (All constraints enforced) • Locational Marginal Pricing at each node
North
South
Middle
13 Copyright 2011 ECCO International, Inc
Zonal Model • Few zones; solve inter- zonal congestion via markets • Congestion within the zones small and infrequent • Socialize intra-zonal congestion
Locational Marginal Pricing (LMP) • All nodes are priced (LMPs) • Nodal prices reflect cost of energy, congestion and transmission losses
Nodal Model • Models the entire TSO Grid • Simulates grid operation considering transmission limitations and energy schedules submitted • All scarce resources are priced
Zonal Pricing • Pricing only the zones • Does not address congestion within a zone
Transition from Zonal To Nodal (LMP) Market
Copyright 2011, ECCO International, Inc 14
Transition from Zonal To Nodal (LMP) Market
Physical Transmission Rights • Physical rights across borders only • They are obtained in auctions • They provide scheduling priority
Congestion Revenue Rights (CRRs) or FTRs • Financial rights available between any two points in the network • Annual CRRs • Monthly CRRs • Long Term CRRs • Separate from operations Sequential Markets
• Higher procurement costs • Price reversals • Can lead to scarcity
Integrated Forward Markets • Simultaneous optimization of Energy, Congestion Management and Ancillary Services 15 Copyright 2011, ECCO International, Inc
It is a forward contract in which the holder is entitled to receive the Locational Marginal Price difference (may be negative) between the point of ejection and point of injection, LMPb - LMPa
FTR Payoff (LMPb – LMPa) g
LMPb-LMPa
FTR holder pays TSO
TSO pays FTR holder
FTR – PTP Obligation
16 Copyright 2011, ECCO International, Inc.
It is a forward contract in which the holder has the right (not obligation) to receive the Locational Marginal Price difference (if positive) between the point of ejection and point of injection, LMPb – LMPa
FTR Payoff (LMPb – LMPa) g
LMPb-LMPa FTR holder pays nothing to TSO
TSO pays FTR holder
FTR – PTP Option
17 Copyright 2011, ECCO International, Inc.
The LMP (nodal price) at Bus i can be calculated using the following equation
λi = λref - Li * λref - Σj (μj * SFji) where
λi = Nodal price at bus i λref = Nodal price at the reference bus Li = Marginal loss factor at bus i = (∂Ploss/∂Pi), Pi is injection at bus i and
Ploss is the system losses μ j = Shadow price of constraint j SFji = Shift factor for real load at Bus i (the reference bus (ref) is the
reference bus for this shift factor) on constraint j
LMP Price Determination
. Copyright 2011, ECCO International, Inc 19
Key Elements of an LMP Energy Market Design
Real-Time Markets
Transmission & Ancillary Services Markets
Reliability Unit Commitment (RUC)
Financial Transmission Rights (FTRs)
Forward Energy Markets/Bilateral Markets
Capacity Markets 22 Copyright 2011, ECCO International, Inc.
Virtual Markets
Virtual Markets: Incs (Virtual Supply)
An Increment Offer (INC) or virtual supply offer is an offer to sell a specified MW quantity in the DAM at a designated location (Hub, Zone, Node) if the Day Ahead Market LMP at that location is at or above the offer price
If the INC clears the Day Ahead Market, the Participant is a seller at that location at the Day Ahead LMP
Since the transaction is virtual, the Participant becomes a buyer of that same MW quantity at the Real Time market LMP for that location
23 Copyright 2011, ECCO International, Inc
Virtual Markets: Decs (Virtual Demand)
A Decrement Bid (DEC) or virtual demand bid is a bid to buy a specified MW quantity at a designated location (Hub, Zone, Node) in the Day Ahead Market (DAM) if the DAM LMP at that location is at or below the bid price
If the DEC clears the Day Ahead Market, the Participant is a buyer at that location at the Day Ahead Market LMP
Since the transaction is virtual, the Participant becomes a seller of that same MW quantity at the Real Time market for that location
24 Copyright 2011 ECCO International, Inc
LMPs & Ancillary Services Prices
When the market clears it produces along with the LMPs the Ancillary Services Marginal Prices for each region (RASMPs) and for each service
Energy and energy are coupled through the resource’s Capacity limit constraints
If these constraints are binding the LMPs are impacted The RASMPs for each service is the shadow cost of the AS constraint
for the service at the optimal solution All resources in the region are paid the same regional price (ASMP) Units that belong in more than one region are paid the summation of
the RASMPs of the over-lapping regions
Copyright 2011, ECCO International, Inc 25
Benefits of Energy-AS Co-optimization
Efficient Unit Commitment and Energy/AS schedule Lower overall cost
Efficient allocation of inter-tie transmission capacity Accurate representation of opportunity cost in LMP and AS
Marginal Price (ASMP) ASMP ≥ AS Bid + Opportunity Cost (OC)
Opportunity Cost = |LMP – Energy Bid| If LMP < Energy Bid → OC = 0 If a resource has not submitted an energy bid and is not under an
obligation to offer energy, then OC = 0
Copyright 2011, ECCO International, Inc 26
State of the Art Modeling
Start Up Cost & Unit Start Up Time Functions Forbidden Regions & Ramp Rate Functions Inter-temporal Constraints (Minimum Up/Down Constraints,
Start-Up Time, Maximum number of Daily Start-Ups, Daily Energy Limit, etc.)
Various types of network constraints (Full AC Power Flow Solution, Transmission Constraints, Inter-Tie Energy/AS Constraints, Nomograms, Contingency Constraints, etc.)
MIP based Security Constrained Unit Commitment for the co-optimization of the energy, ancillary services and transmission markets
Copyright 2011, ECCO International, Inc 27
Mixed Integer Linear Programming (MILP) Separate power flows for each time interval Iterate with optimization engine that has a single power balance constraint
and the active inequality constraints for each time interval
Power Flow Power Flow Optimization Engine Power Flow Power Flow Power Flow Power Flow
Schedules
PTDFs Loss marginal rates
Current Dominant Solution Methodology
28 Copyright 2011, ECCO International, Inc.
MILP versus ALR Comparison
Capability MILP ALR Flexibility for adding new constraints and models Yes No Flexibility of modeling a large number of coupling constraints Yes No Dynamic ramp rates & Forbidden regions with crossing rules Yes No Advanced infeasibility detection Heuristics to achieve a feasible solution No Yes Block dispatchable transactions Yes No
Optimal automatic discrete relaxation of infeasible constraints
Yes No
Lower bound on the optimal solution Yes No
Performance fast enough fast
29 Copyright 2011, ECCO International, Inc.
Next Generation of Energy Market Design
Develop Multi-Day Unit Commitment (issues: bid replication, performance)
Co-optimize Energy/AS/FTRs in the DAM to hedge congestion in RTM
Implement Nodal Pricing for Loads (issues: economic hardship on entities located in load pockets)
Co-optimize generation dispatch for congestion management and network reconfiguration, i.e., transmission switching (issue: network reconfiguration solution does not ensure revenue adequacy in the FTR market)
Copyright 2011, ECCO International, Inc 30
Next Generation of Energy Market Design
Co-optimize Markets and Reliability (Co-optimize Energy, AS, Transmission & RUC products)
Develop Functional Capacity Markets Develop Transmission Markets and Policies for
Transmission Investments Develop Market Mechanisms to Manage High Penetration of
Renewable Energy Sources (RES) Develop Demand Respond Market Mechanisms
Copyright 2011, ECCO International, Inc 31
32
DAM-RUC Co-Optimization
One integrated approach Two power balance constraints
Generation Schedule = Load Schedule Generation Schedule + RUC Capacity = Demand Forecast
Pros Only one pass Maximum efficiency Effective mitigation Better manage over-
generation conditions
Cons May be difficult to isolate RUC
commitment cost Congestion costs from RUC
capacity More complex to implement
Copyright 2011, ECCO International, Inc
33
DAM-RUC Co-Optimization
Minimize Start-Up Cost Minimum Load Cost Energy Schedule Cost Ancillary Services Procurement Cost RUC Capacity Procurement Cost
All other constraints similar to DAM and RUC Inter-temporal constraints (MUT, MDT, MDS, ramp rates, energy
limits) Forbidden operating regions AS regional constraints Inter-tie Energy/AS/RUC Capacity constraints
Copyright 2011, ECCO International, Inc
Next Generation of Energy Market Design
Co-optimize Markets and Reliability (Co-optimize Energy, AS, Transmission & RUC products)
Develop Functional Capacity Markets Develop Transmission Markets and Policies for
Transmission Investments Develop Market Mechanisms to Manage High Penetration of
Renewable Energy Sources (RES) Develop Demand Respond Market Mechanisms
Copyright 2011, ECCO International, Inc 34
Capacity Market Design
Capacity markets interact with and are part of organized electricity market design. The details differ in various implementations but there are certain common issues.
Missing Money. The most common justification of the need for capacity markets cites the fact that historically the money earned in “energy only” markets has been too little to justify new entry
Copyright 2011, ECCO International, Inc. 35
PJM data show that a combustion turbine (1999-2010, per MW-Year) would have earned Average Net Energy Revenue = $40,943, versus Average Levelized Fixed Cost = $88,317
Better scarcity pricing design would mitigate the missing money problem and reduce the importance of capacity markets
Transmission Constraints. Locational requirements arise because of transmission constraints; This creates strong interactions across markets and can produce volatile capacity prices
Capacity Market Design
36 Copyright 2011, ECCO International, Inc.
Investment Timing. Transmission expansion, generation capacity expansion and demand response investments are partial substitutes on very different investment horizons. This creates a significant coordination problem
Market Power. The inherent nature of capacity market requirements with explicit and known demand curves and large changes in price for small changes in quantity creates a pervasive and inherent problem of market power and price manipulation
Capacity Market Design
37 Copyright 2011, ECCO International, Inc.
Capacity Market Design
Withholding Supply. If a supplier could reduce net capacity or increase net demand in the formal capacity market, suppliers might profit on higher prices for
remaining sales in capacity market Withholding Demand. If load could reduce net demand or increase net supply, loads could benefit from lower prices on remaining purchases from the capacity markets
Copyright 2011, ECCO International, Inc. 38
Next Generation of Energy Market Design
Co-optimize Markets and Reliability (Co-optimize Energy, AS, Transmission & RUC products)
Develop Functional Capacity Markets Develop Transmission Markets and Policies for
Transmission Investments Develop Market Mechanisms to Manage High Penetration of
Renewable Energy Sources (RES) Develop Demand Respond Market Mechanisms
Copyright 2011, ECCO International, Inc 39
Copyright 2011, ECCO International, Inc. 40
Why Markets Cannot Support All Transmission Investments
North
South
K η0
PS
PN
Price
Quantity K0 K*
A
C
B
Congestion Rent Congestion Cost
No Congestion
Net Supply in North SN
Net Demand in South DS
Congestion Rents vs Congestion Costs
δK
Surplus S1
η0 η1
K1
η0 = shadow price, η0 * K0 = Congestion Rent, Triangle ABC = congestion costs η1 (K1 – K0) = ex-post congestion rents paid to transmission investors , S1 = Social Surplus
Since η1 (K1 – K0) < S1 → Under-incentive to upgrade the line
Lumpiness results in underinvestment in transmission like grid owners rewarded by congestion rents has suboptimal incentives to remove these congestion rents
Competition between transmission and generation projects raises pre-emption issues
Given the drastically different completion schedules, the transmission investor is at a strategic disadvantage
Also complementary transmission investments may give rise to wars of attrition in which no owner wants to move first by fear of being “under-dimensioned” by a rival owner
41 Copyright 2011, ECCO International, Inc.
Why Markets Cannot Support All Transmission Investments
Assume two complementary projects with capacities KNM and KMS
The value of Point to Point Rights are: KNM (PM – PN) & KMS(PS – PM) The incentive for gaming comes for the fact that lower-capacity line grabs the entire rights’ value Suppose that KMS < KNM PM = PN & PS > PM
This gives rise to the game where each would like to have a slightly capacity than the other
42 Copyright 2011, ECCO International, Inc.
Why Markets Cannot Support All Transmission Investments
North
M
South
PN
PN
PM
These detrimental behaviors can be only avoided through a centralized transmission process
The Merchant Transmission model in which investors build for anticipated need and take all the risks appears to have died
The challenge is to ensure a move to low carbon future, sustainable development and security of supply
These objectives require mandated transmission investments or as we call them public-policy driven investments
43 Copyright 2011, ECCO International, Inc.
New Transmission Investments Environment
Implementation of a Hybrid Model Planning Process (allow a regional approach; top down
approach) Transmission Permitting (expand control of Federal
Government) Transmission Financing and Cost Allocation (current cost
allocation methods are inadequate; broad based “postage stamp” or “regionalization” approach is required)
Transmission System Modernization and the Smart Grid 44 Copyright 2011, ECCO International, Inc.
Infrastructure Investments: Road Map for the Future
Copyright 2011, ECCO International, Inc. 45
Implementation of the Hybrid Model
Objective: Preserve the Merchant Transmission Model Principle: Regulated based, mandated transmission investments
should be limited to cases where the investment is inherently large and inherently lumpy
Test 1: Economic Justification. Ensure that the usual social welfare calculation that applies to all regulated investments under traditional regulation (aggregate benefit exceeds aggregate costs) is valid
Test 2: Market Failure Justification. The investment is large and lumpy enough to materially affect market prices, making the ex-post Financial Rights worth less than the cost of the investment
Copyright 2011, ECCO International, Inc. 46
Transmission System
Modernization and the Smart Grid
Apply Smart Grid Concepts to Revolutionize the EHV Grid Increase Congressional Oversight of actual costs, benefits and performance
of smart grid investments A transmission solution for the 21st Century
high capacity transmission high technology platform foundation for an interstate electric high-way system wired to facilitate a highly reliable and smart electric grid wired to expand opportunities for new high technology generation supply and new high technology
demand-side options
Creating a Modern EHV Grid
Broad Grid Planning
Broad Cost Allocation
Federal Siting
Our Energy Future
Technology
Next Generation of Energy Market Design
Co-optimize Markets and Reliability (Co-optimize Energy, AS, Transmission & RUC products)
Develop Functional Capacity Markets Develop Transmission Markets and Policies for
Transmission Investments Develop Market Mechanisms to Manage High
Penetration of Renewable Energy Sources (RES) Develop Demand Respond Market Mechanisms
Copyright 2011, ECCO International, Inc 47
RES Market Issues
Managing renewables today Grid Rule Changes Day Ahead Market Rules Changes Additional Forward Markets Additional Congestion Hedging Mechanisms Integration Costs of RES into the grid
48 Copyright 2011, ECCO International, Inc.
Our Future?
Spanish renewables + Must Run exceed load in many hour
2010: Wind provides 16% of Spanish electricity Wind spillage rapidly growing (from .02% to 0.8% in one year)
Copyright 2011, ECCO International, Inc. 49
Giving Renewables Absolute Priority Makes Neither Economic nor Environmental Sense
Can increase both costs and emissions
Copyright 2011, ECCO International, Inc. 50
Managing Renewables Today
Renewable participation in Day-Ahead Markets is not consistent throughout US markets
Same in Europe: Renewable goals are country by country Renewables may not participate due to forecast uncertainties
and unfavorable market rules This may lead to renewables “showing up” in real-time
markets, causing inconsistencies from the Day-Ahead market Priority access or guaranteed access and dispatch for RES is
required by EU legislation 51 Copyright 2011, ECCO International, Inc.
Managing Renewables Today
But “priority” is interpreted differently: NL: Can’t ramp down, even voluntarily UK: Anyone can participate in balancing market: source blind Germany: Regulator has relieved grid of obligation when prices negative
Key objective: Implement markets rules to provide TSO operational flexibility and incorporate RES in the market process
52 Copyright 2011, ECCO International, Inc.
Grid Rules for Renewables
Ensure that RES provide valuable Ancillary Services Ensure that grid rules require these capabilities from new
RES Promote electricity storage; Pumped-storage and others
(compressed air) A/S products could include: Black Start, Voltage Support,
Primary Governor Response, Load Following, Regulation Reserves, and Spinning Reserves
53 Copyright 2011, ECCO International, Inc.
Day-Ahead Market Rules for Renewables
Day-ahead market rules should not be prejudiced against (or biased towards) any particular resource category; provide economic bids; minimize administrative measures
Economic bids enable the market optimization to efficiently dispatch the fleet, and efficiently curtail when necessary
The market products and rules should support grid reliability and overall economic efficiency of the grid
Production tax credits & other incentives should not adversely impact operation of markets
54 Copyright 2011, ECCO International, Inc.
Day-Ahead Market Rules for Renewables
For example, wind generation often continues to produce at negative prices (e.g. -$30/MWh) because of external incentives
These prices do not reflect the “true” costs of operation (e.g. fuel, maintenance, …)
This behavior can have negative impacts on other resources in the grid
Participation in Day-Ahead Market by renewables is subject to additional uncertainty, due to wind/solar forecasting errors
Additional hedging mechanisms are required 55 Copyright 2011, ECCO International, Inc.
Day-Ahead Market Rules for Renewables
Provide incentives for increased dispatch capability (especially downward dispatchability) such as disallowing netting of deviations
Netting of deviations takes away the incentives for renewable developers to invest in dispatch capability
Substantially reduce energy bid floors to enable LMPs (or MCPs) to go lower, thus incenting resources to submit decremental bids and capturing the RES opportunity costs
Achieve flexible thermal generation
56 Copyright 2011, ECCO International, Inc.
Day-Ahead Market Rules for Renewables
Implement market rules to increase operational flexibility, such as Performance-based Regulation, load following, etc.
Faster ramping resources provide more Area Control Error (ACE) correction than slower ramping resources
Netting regulation energy does not recognize the greater ACE correction faster ramping resources provide
57 Copyright 2011, ECCO International, Inc.
Day-Ahead Market Rules for Renewables
We propose a two-part payment system Capacity Payment
Cross-product opportunity cost (Payment reflects cost of not participating in energy market)
Inter-temporal opportunity cost (The value a resource forfeits to provide regulation due to less flexibility to charge/discharge advantageously through the energy market)
58 Copyright 2011, ECCO International, Inc.
Day-Ahead Market Rules for Renewables
Performance payment Mileage payment
Compensate for the work performed by a regulating unit Absolute value of up and down movement of a regulation resource
multiplied by a $/MW-ACE Correction Price ACE Correction Price: 1) preference is a market bid for ACE
correction; 2) establish admin price if market bid is unworkable Accuracy adjustment
Using telemetry, adjust the mileage payment based on how well a resource tracks the TSO AGC signal
Mileage payment multiplied by accuracy factor
59 Copyright 2011, ECCO International, Inc.
Net Energy Vs. Mileage
Replace net energy payments by a mileage payment for ACE correction provided
Copyright 2011, ECCO International, Inc. 60
Copyright 2011, ECCO International, Inc. 61
RTD Timeline
Dispatch
LMP/MCP
1
T−7.5' RTED
2
T T−5' T+10' T+5' T−10'
T−2.5'
Design of a Flexible Ramping Product
Intemporal optimization of Real-Time Dispatch (RTD) optimizes over time to account for expected future ramp requirements, such as those associated with top of the hour changes in net-interchange, a pump storage unit going on or off-line, or a generation unit going on or off-line
Accommodating RES entails scheduling additional ramping capability to respond to ramp constraints that cannot be projected, but could arise because of unpredictable changes in load or intermittent generation output
62 Copyright 2011, ECCO International, Inc.
Design of a Flexible Ramping Product
Use RTD to create additional upward (or downward) ramp capability. How?
Dispatch down (out of merit) resources whose available upward ramping capability is capacity limited, thus creating additional upward ramping capability (Their output is replaced with the output of higher cost units whose available ramping capability is not capacity constrained)
Conversely, additional downward ramp capability can be created by dispatching up out-of-merit resources whose downward ramping capability is limited by their minimum load
63 Copyright 2011, ECCO International, Inc.
Additional Forward Markets (e.g. Hour Ahead Market)
Significant forecasting errors exist in the Day-Ahead for renewable resources
An additional forward market (e.g. 4-hours into the future) could be very beneficial Renewable resource forecasts become significantly better when the
timeframe becomes shorter Provide a scheduling opportunity to RES to establish a schedule as
the basis for measuring real-time deviations There is still time for other non-renewable resources (e.g. combined-
cycle plants) to respond to changes in RES (and load) forecasts
64 Copyright 2011, ECCO International, Inc.
Additional Congestion Hedging Mechanisms
Energy Markets typically offer Financial Transmission Rights to allow hedging against congestion uncertainty Purchased months/years ahead and settled in the Day-Ahead
Renewable resources have significant uncertainty even after the close of the Day-Ahead Market Additional hedging mechanisms would allow for hedging of
congestion in the 4-Hour Ahead and Real-Time Markets
65 Copyright 2011, ECCO International, Inc.
RES Integration with the Grid Issues
Integrating RES into grid operations is expected to drive several types of cost increases
Increased procurement of regulation Greater operational demands on conventional resources
(more starts, more ramping) Increased need for flexible, dispatchable capacity Potentially higher uplift charges Increased capacity payments to supplement declining
market prices and revenues 66 Copyright 2011, ECCO International, Inc.
Next Generation of Energy Market Design
Co-optimize Markets and Reliability (Co-optimize Energy, AS, Transmission & RUC products)
Develop Functional Capacity Markets Develop Transmission Markets and Policies for
Transmission Investments Develop Market Mechanisms to Manage High Penetration of
Renewable Energy Sources (RES) Develop Demand Respond Market Mechanisms
Copyright 2011, ECCO International, Inc 67
Demand Response: Impact on Cleared Demands
1,500
2,000
2,500
3,000
3,500
0 2 4 6 8 10 12 14 16 18 20 22 24 hour
without DRs with DRs
clea
red
dem
and
(MW
)
Copyright 2011, ECCO International, Inc. 68
Demand Response: Impact on Clearing Prices
hour
30
35
40
45
50
clea
ring
pric
e ($
/MW
h)
0 2 4 6 8 10 12 14 16 18 20 22 24
without DRs with DRs
Copyright 2011, ECCO International, Inc. 69
Demand Response: Existing Products
Typically we have two types of DR products, a) Price DR Products and b) Reliability (emergency) DR Products
Generally, Price DR products are activated when energy procurement prices are high or system resources are constrained
Reliability DR Products are activated programs to respond to severe resource constraints or grid emergencies
DR markets include, a) Capacity Market, b) Reserves & Regulation Market and c) Energy Markets
70 Copyright 2011, ECCO International, Inc.
Copyright 2011, ECCO International, Inc.
Current DR Bidding Modeling
Participating Load (PL) submits a three-part bid that includes the following: a) Load Curtailment Cost, b) Minimum Load Reduction Cost and c) Load Energy Bid
Aggregate PLs are modeled as aggregate controls in the optimization with a fixed distribution to the underlying nodes using LDFs
The Base Load is a Price Taker, i.e., it is charged the relevant aggregate LMP as any non-Participating Load
When the Participating Load is curtailed from the Base Load, it is eligible for recovering its Load Curtailment Cost and its hourly Minimum Load Reduction Cost
When the Participating Load is dispatched it is paid (in addition to the Base Load charge) its LMP for the load reduction
71
Copyright 2011, ECCO International, Inc.
DR Bidding Modeling
Load Curtailment
MW
Base Load Schedule
$/MWh
Minimum Load Reduction
Minimum Load
72
Copyright 2011, ECCO International, Inc.
Major Market Rules Changes are Required
The Current DR market model is not working
73
Copyright 2011, ECCO International, Inc.
DR Market Rules Changes
DR resources can arbitrage low Zonal prices and higher nodal prices; the potential “money pump” in which DR resources can exaggerate the load reduction is substantial
This strategy is likely to be profitable in locations and at times when the LMP is anticipated to be higher than the Zonal price
Define and implement much smaller Zones within which LMPs are fairly uniform
Require that DRs purchase their baseline at the nodal prices where the reductions are to occur
74
Copyright 2011, ECCO International, Inc.
DR Market Rules Changes
Implement Dynamic Pricing rules – Make the default retail price a pass-through of wholesale short-term energy prices
Lack of Dynamic Pricing prevents consumers from benefitting from a lower ANNUAL bill by reducing their consumption during hours of high prices and increasing their consumptions during hours of lower prices
Ensure “symmetric treatment” between generating and load resources
Set a Zero baseline for final consumers, as for suppliers, and charge for each of consumption the hourly price
75
Copyright 2011, ECCO International, Inc.
DR Market Rules Changes Paying for demand reductions is NOT working Paying consumers not to consume faces a serious challenge of
measuring what the consumer would have done without the payment (“baseline problem”)
This approach suffers from two major difficulties: The adverse selection problem (the buyer of the DR does not know
what the seller would have done in the absence of payment) The moral hazard problem (customers have a strong incentive of
inflating the level of baseline) Solution: develop a payment structure to set symmetric prices for
consumption and reductions 76
Copyright 2011, ECCO International, Inc.
Conclusions
Europeans are in denial with respect to LMP markets; they need to move to LMP based energy markets without delays
Integration of markets with reliability is an important requirement Capacity market design needs to be revisited and expanded Markets cannot solve the infrastructure investment problem (Federal
involvement/EU level involvement is required) Deep penetration of RES will come at a high costs and requires
substantial changes of the market design Change the DR market design is necessary with the ultimate objective
to achieve “symmetric treatment “ between generators and loads and between consumption and reductions
77