challenges of dms control centers in the smart grid
TRANSCRIPT
Gary Ockwell
Efacec Advanced Control Systems
Chief Technology Officer
Challenges of DMS
Control Centers in the
Smart Grid
June 5, 2013
Affected:
• 30 Million Inhabitants
• 800,000 in trapped subways
• 250 Flights at JFK
• 150 Hospitals
Utilities had minimal information and
control capability to monitor and restore
service … led to the creation of SCADA /
EMS ... DMS and to the formation of NERC in
1968
Aug 14 / 03 Blackout
NERC Report:
Root Cause 1: FE Situational Awareness
Root Cause 2: Vegetation Management
Root Cause 3: Reliability Coordinator Ineffective Diagnostics
90% of outages and
disturbances originate in the distribution system
Our Challenges
“Experts say the cascading blackout that put millions of Westerners in
the dark last week was no surprise: Major power outages have more than
doubled in the last decade.”
The largest power failure in California
history left nearly seven million people
without power, affecting :
• San Diego Gas & Electric,
• Imperial Irrigation District
• Comisión Federal de Electricidad, Mexico
• Arizona Public Service
• Western Area Power Administration
Recent Blackout Highlights Nation's Rickety Power Grid
Sep 16, 2011 … In a July interview with ProPublica, FERC
Chairman Jon Wellinghoff said that while the electric grid is
reliable, it is degrading. "It's not getting better," he said. "It's
getting worse."Last week, for example, a mishap involving a
single worker doing repairs on a power station near Yuma,
Ariz., led to rolling blackouts over parts of Arizona, Southern
California and Northern Mexico.
Blackouts disrupt power to at least a third of U.S. homes each
year, and studies show the number of outages is rising.
June 4, 2012
Google search “September 2011 Southwest Blackout”
2.4M hits. #1 hit:……
Hurricanes Irene and Sandy
Created > 85% outages to Long Island and Jersey
Work force grew > 6,000 field crews per utility
“LIPA Customer Bill of Rights”
Assemb. Charles Lavine Nov 20, 2012
1. Establish an Emergency Management
Plan with Poles and Wires Reporting
2. Sufficient customer service
representatives available by phone and
3. Regional Restoration Timetable
4. Communication of the Number of Crews
in each Region
5. Critical Infrastructure Identification
for Gas Stations
6. Emergency Management Plan
7. Customer Complaint Feedback
“LIPA Customer Bill of Rights”
… Con’t
What is lacking?
substation
SCADA
substation
SCADA
Classical OMS’ do not meet the demands of the Smart Grid.
Hurricane Isabel was the costliest and deadliest hurricane in the 2003 Atlantic hurricane season. • Winds reached: 165 mph (270 km/h) • Damage: $3.6 billion (2003 USD) • Dead: 16 direct, 35 indirect
“Pepco identified a problem with the link between the Energy Management System and the OMS in major events with an excessively high number of breaker lockouts and momentary interruptions. Specifically, when a breaker would trip in the Energy Management System, the information would be passed to the OMS, which would then perform the appropriate circuit analysis as if the breaker had locked out.
…“there was concern over the validity of the Outage Management System algorithm in the early stages of the restoration, and there was uncertainty about the stability of the Outage Management System based on problems experienced in the late August thunderstorms.”
Classical OMS’ do not meet the demands of the Smart Grid environment.
“Pepco identified this problem and broke the link between the two systems during the outage, creating the breaker lockout notification in the OMS manually.”
* Bridge Energy Group 2013 DistribuTech
*14,000 utilities surveyed in
2013 53% will replace OMS
64 % said “ restoration
management a top priority”
Smart Grid Integration SCADA,
VVC, auto feeder switching
Knowledgeable staff
DMS OMS
Graphic Data Base
Model Interfaces
100 dynamic objects
100K RT Points for large
No model Only SCADA
Usually ICCP
100 dynamic objects
100K RT Points for large
1000 bus LF model is large
Usually ICCP
1M + objects
10K Real time points
1M+ Connectivity model
IVR, CIS, GIS, AMI, etc
1M+ dynamic objects
200K-2M+ Real time points
Connectivity & LF model
IVR CIS GIS AMI RTUs, IEDs
Slope approx 2.57
Slope approx 3.22
“The time has come to abolish LIPA period
Cuomo said, “We want to privatize the Long
Island service.”
Control Center Requirements:
Media Management System
1st
Group Topics
• new technologies, tools, techniques, and
methods for “proof of concept,” pilots ..
• managing fluctuations of renewable
generation through RT volt/var control
• To shift the peak demand and save energy,
using electrical energy storage units
• New techniques in self-healing control in
smart distribution network
2nd Group Topics
• impacts of operating vehicles in G2V and V2G
and V2B
• PMU solutions for distribution automation
systems
• keeping the system stable with large impact load
• CDPF for optimal DER planning, modeling and
coordination
• implementation of CHANGSHA DMS