  • 7/23/2019 CH4 2 Welding Joint Preparation

    1/46

    Weld Joint Preparation

    (ISO 9692)

  • 7/23/2019 CH4 2 Welding Joint Preparation

    2/46

    Edge Preparation - NeedPoor penetration

    Poor strength

    Good penetration

    Good strength

    (100% jointefficiency)

  • 7/23/2019 CH4 2 Welding Joint Preparation

    3/46

    Edge PreparationFactors which influence choice of edge preparation

    - Thickness

    - Material

    - Welding process

    - Extent of penetration required

    - Welding distortion

    - Cost

  • 7/23/2019 CH4 2 Welding Joint Preparation

    4/46

    Basic Joint Types

    butt

    tee

    lap

    corner

    edge

  • 7/23/2019 CH4 2 Welding Joint Preparation

    5/46

    Basic Weld TypesGroove welds

    Fillet weldPlug / slot weld

    Spot / seam weld

  • 7/23/2019 CH4 2 Welding Joint Preparation

    6/46

    Applicable Welds for Butt jointSquare Groove weld V Groove weld

    U Groove weldBevel Groove weld

    J Groove weld

  • 7/23/2019 CH4 2 Welding Joint Preparation

    7/46

    Applicable Welds for Butt joint

    Double V Groove weld

    Double U Groove weld

    Double Bevel Groove weld

    Double J Groove weld

  • 7/23/2019 CH4 2 Welding Joint Preparation

    8/46

    Applicable Welds for Tee joint

  • 7/23/2019 CH4 2 Welding Joint Preparation

    9/46

    Applicable Welds for Lap joint

    Plug / slot weldSpot / seam weld

    Fillet weld

  • 7/23/2019 CH4 2 Welding Joint Preparation

    10/46

    Applicable Welds for Corner Joint

  • 7/23/2019 CH4 2 Welding Joint Preparation

    11/46

    Applicable Welds for Edge Joint

    Edge weld

  • 7/23/2019 CH4 2 Welding Joint Preparation

    12/46

    Butt jointSquare Groove weld

    Root gap

  • 7/23/2019 CH4 2 Welding Joint Preparation

    13/46

    Butt jointSingle V Groove weldGroove angle

    Root face

    Root gap

  • 7/23/2019 CH4 2 Welding Joint Preparation

    14/46

    Weld Reinforcement

    Correct

    reinforcement

    Minimum cost

    Good joint

    strength

    Excess

    reinforcement

    High cost

    Poor joint strength

    Under

    reinforcement

    Poor joint strength

  • 7/23/2019 CH4 2 Welding Joint Preparation

    15/46

    Butt joint Complete Joint penetration

    Weld from face side

    Back gouging

    Back weld

  • 7/23/2019 CH4 2 Welding Joint Preparation

    16/46

    Butt joint Complete Joint penetration

    Backing weld

    Back gouging

  • 7/23/2019 CH4 2 Welding Joint Preparation

    17/46

    Butt joint Complete Joint penetration(welding from one side)

    TIG / SMAW

    welding

    Consumableguide

  • 7/23/2019 CH4 2 Welding Joint Preparation

    18/46

    Butt Joint Double V grooveLess weld metal

    Less distortionHigher edge preparation cost

    Better for thickness > 20 mm

    More weld metal

    More distortion

    Lower edge preparation cost

    Better for thickness < 20 mm

    Double V groove

    Single V groove

  • 7/23/2019 CH4 2 Welding Joint Preparation

    19/46

    Butt Joint U groove

    Good access at the root

    Less weld metal

    Higher edge preparation cost

    Better for thickness > 40 mm

    Groove angle

    Root face

    Root gap

    Root radius

  • 7/23/2019 CH4 2 Welding Joint Preparation

    20/46

    Butt Joint Bevel groove

    Double bevel groove

    Single bevel grooveBevel angle 40 to 50

    Difficult to approach

    the root

    Weld defects

    Back gouging toremove root defects

    Good weld quality

  • 7/23/2019 CH4 2 Welding Joint Preparation

    21/46

    Butt Joint J groove

    Good access at the root

    Back gouging and back welding to get good weld quality

    Less weld metal

    Higher edge preparation cost

    Better for thickness > 40 mm

  • 7/23/2019 CH4 2 Welding Joint Preparation

    22/46

    Tee Joint Full strength joint

    leg

    leg throat

    throat = 0.707 x legleg = 1.414 x throat

    In a full strength

    joint, leg = 0.75 x

    thickness

  • 7/23/2019 CH4 2 Welding Joint Preparation

    23/46

    Tee Joint Full penetration joint

    leg = throat leg = throat

    45 or 60

  • 7/23/2019 CH4 2 Welding Joint Preparation

    24/46

    Tee Joint

    Theoretical throat

    Actual throat

    AWS D 1.1 recommendation when gap > 1.6 mm

    to increase leg size of fillet by the amount of gap

  • 7/23/2019 CH4 2 Welding Joint Preparation

    25/46

    Lap Joint

    AWS D 1.1 recommendation

    Overlap = 5 x thickness (1 inch minimum)

    Gap between mating faces = 1.6 mm max

    overlap

  • 7/23/2019 CH4 2 Welding Joint Preparation

    26/46

    Welding Position Groove

    1 G

    2 G

    3 G

    4 G

  • 7/23/2019 CH4 2 Welding Joint Preparation

    27/46

    Welding Position Groove

    1 G 2 G

    5 G 6 G

    45

  • 7/23/2019 CH4 2 Welding Joint Preparation

    28/46

    Welding Position Fillet

    1F

    2F

    3F

    4F

  • 7/23/2019 CH4 2 Welding Joint Preparation

    29/46

    Welding Position Fillet

    1F

    2F

    5F

  • 7/23/2019 CH4 2 Welding Joint Preparation

    30/46

    Welding Positions Groove

    Position Inclination of axis Rotation of face

    Flat 0 to 15 150 to 210

    Horizontal 0 to 15 80 to 150

    210 to 280

    Overhead 0 to 80 0 to 80

    280 to 360Vertical 15 to 80 80 to 280

    80 to 90 0 to 360

  • 7/23/2019 CH4 2 Welding Joint Preparation

    31/46

    Welding Positions Fillet

    Position Inclination of axis Rotation of face

    Flat 0 to 15 150 to 210

    Horizontal 0 to 15 125 to 150

    210 to 235

    Overhead 0 to 80 0 to 125

    235 to 360Vertical 15 to 80 125 to 235

    80 to 90 0 to 360

  • 7/23/2019 CH4 2 Welding Joint Preparation

    32/46

    Joint preparation

    According to I SO 9692

    Welding and allied processes -Recommendations for joint preparation

    Part 1:Manual metal-arc welding, gas shielded metal-arc welding, gas

    welding, TIG welding and beam welding of steels

  • 7/23/2019 CH4 2 Welding Joint Preparation

    33/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    34/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    35/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    36/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    37/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    38/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    39/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    40/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    41/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    42/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    43/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    44/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    45/46

  • 7/23/2019 CH4 2 Welding Joint Preparation

    46/46