ch15. resource requirements planning - mrp & crp

73
1 Resource Requirements Resource Requirements Planning: Planning: MRP and CRP MRP and CRP

Upload: jaishree-panwar

Post on 24-Mar-2015

255 views

Category:

Documents


13 download

TRANSCRIPT

Page 1: Ch15. Resource Requirements Planning - MRP & CRP

1

Resource Requirements Planning:Resource Requirements Planning:

MRP and CRPMRP and CRP

Page 2: Ch15. Resource Requirements Planning - MRP & CRP

2

A

Independent Demand Items

B(4) C(2)

D(2) E(1) D(3) F(2)

Dependent DemandItems

Independent vs. Dependent DemandIndependent vs. Dependent DemandIndependent vs. Dependent DemandIndependent vs. Dependent Demand

Page 3: Ch15. Resource Requirements Planning - MRP & CRP

3

Resource Requirements PlanningResource Requirements PlanningResource Requirements PlanningResource Requirements Planning

Master ProductionMaster ProductionScheduling (MPS)Scheduling (MPS)Master ProductionMaster ProductionScheduling (MPS)Scheduling (MPS)

Material RequirementsMaterial RequirementsPlanning (MRP)Planning (MRP)

Material RequirementsMaterial RequirementsPlanning (MRP)Planning (MRP)

Capacity RequirementsCapacity RequirementsPlanning (CRP)Planning (CRP)

Capacity RequirementsCapacity RequirementsPlanning (CRP)Planning (CRP)

AggregateAggregatePlanningPlanning

AggregateAggregatePlanningPlanning

ResourceResourceRequirementsRequirements

PlanningPlanning

Page 4: Ch15. Resource Requirements Planning - MRP & CRP

4

Production Planning HierarchyProduction Planning HierarchyProduction Planning HierarchyProduction Planning Hierarchy

Firm orders from knowncustomers

Forecast of demand

from random customers

Aggregate Product Plan

Master Production Schedule

(MPS)

Material Requirements

Planning (MRP)

Engineering design changes

Bill of Materials (BOM) file

Inventory transactions

Inventory records

file

Reports

Page 5: Ch15. Resource Requirements Planning - MRP & CRP

5

Materials Requirements Planning (MRP)Materials Requirements Planning (MRP)Materials Requirements Planning (MRP)Materials Requirements Planning (MRP)

Page 6: Ch15. Resource Requirements Planning - MRP & CRP

6

Material Requirements PlanningMaterial Requirements PlanningMaterial Requirements PlanningMaterial Requirements Planning

How muchHow much of an item is needed? of an item is needed?

WhenWhen is an item needed to complete is an item needed to complete a specified number of units...a specified number of units... in a specified period of time?in a specified period of time?

Dependent demand drives MRP Dependent demand drives MRP

Page 7: Ch15. Resource Requirements Planning - MRP & CRP

7

Objectives of MRPObjectives of MRPObjectives of MRPObjectives of MRP

Improve customer serviceImprove customer service Reduce inventory investmentReduce inventory investment Improve plant operating efficiencyImprove plant operating efficiency

Page 8: Ch15. Resource Requirements Planning - MRP & CRP

8

MRP Computer ProgramMRP Computer ProgramMRP Computer ProgramMRP Computer Program

Begins with number of end items neededBegins with number of end items needed Aditional service parts not included in MPSAditional service parts not included in MPS ExplodeExplode MPS into gross requirements by consulting MPS into gross requirements by consulting

bill of materials filebill of materials file Modify gross requirements to get net requirements:Modify gross requirements to get net requirements: NetNet Requirements = Gross Requirements Requirements = Gross Requirements

+ Allocated Inventory+ Allocated Inventory+ Safety Stock+ Safety Stock

-- Inventory On Inventory On HandHand

OffsetOffset orders to allow for lead time orders to allow for lead time

Page 9: Ch15. Resource Requirements Planning - MRP & CRP

9

Bill of Materials (BOM) FileBill of Materials (BOM) FileA Complete Product DescriptionA Complete Product Description

Bill of Materials (BOM) FileBill of Materials (BOM) FileA Complete Product DescriptionA Complete Product Description

Page 10: Ch15. Resource Requirements Planning - MRP & CRP

10

Inventory Records FileInventory Records FileInventory Records FileInventory Records File

Each inventory item carried as a separate fileEach inventory item carried as a separate file Contains inventory positions of each itemContains inventory positions of each item Shows status according to “time buckets”Shows status according to “time buckets”

PeggingPegging Identify each parent item that created demandIdentify each parent item that created demand

Page 11: Ch15. Resource Requirements Planning - MRP & CRP

11

MRP TerminologyMRP TerminologyMRP TerminologyMRP Terminology

Planned order schedulePlanned order schedule - quantity of material to be - quantity of material to be ordered in each time periodordered in each time period

Changes to planned ordersChanges to planned orders - modifications to - modifications to previous planned ordersprevious planned orders

Page 12: Ch15. Resource Requirements Planning - MRP & CRP

12

MRP TerminologyMRP TerminologyMRP TerminologyMRP Terminology

Gross RequirementsGross Requirements

These requirements are typically forecast for These requirements are typically forecast for independent demand itemsindependent demand items

On-hand inventoryOn-hand inventory

The inventory physically present in the facilityThe inventory physically present in the facility

Allocated inventoryAllocated inventory

The inventory physically present in the facility but The inventory physically present in the facility but allocated to a particular work order or purchase allocated to a particular work order or purchase order order

Page 13: Ch15. Resource Requirements Planning - MRP & CRP

13

More MRP TerminologyMore MRP TerminologyMore MRP TerminologyMore MRP Terminology

Net requirementsNet requirements A quantity of an item that must be purchased or A quantity of an item that must be purchased or

manufactured in order to be able to manufactured in order to be able to fullyfully deliver deliver independent demand requirements in a independent demand requirements in a timelytimely fashion fashion

Presence of positive net requirements signals that an Presence of positive net requirements signals that an order must be planned to be received in a given period order must be planned to be received in a given period

Net requirement quantities are subject to adjustments Net requirement quantities are subject to adjustments due to lot sizes considerations. This may lead to some due to lot sizes considerations. This may lead to some orders being received early (inventory is held) or late orders being received early (inventory is held) or late (order backlog)(order backlog)

Page 14: Ch15. Resource Requirements Planning - MRP & CRP

14

More MRP TerminologyMore MRP TerminologyMore MRP TerminologyMore MRP Terminology

Planned order receiptsPlanned order receipts

Quantities that must be planned to be Quantities that must be planned to be receivedreceived in in some future periods in order to meet the some future periods in order to meet the requirements requirements

Planned order releasedPlanned order released

Quantities that must be planned to be Quantities that must be planned to be releasedreleased in in some future periods in order to meet the some future periods in order to meet the requirements requirements

Page 15: Ch15. Resource Requirements Planning - MRP & CRP

15

More MRP TerminologyMore MRP TerminologyMore MRP TerminologyMore MRP Terminology

Scheduled receiptsScheduled receipts

Quantities that will be Quantities that will be receivedreceived in some future in some future periods as their corresponding orders periods as their corresponding orders have been have been releasedreleased in the past in the past

Planned order receipts become scheduled Planned order receipts become scheduled receipts at the time when they are released to receipts at the time when they are released to the shop or to suppliers the shop or to suppliers

Page 16: Ch15. Resource Requirements Planning - MRP & CRP

16

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

LocoMopeds is a manufacturer of off-road LocoMopeds is a manufacturer of off-road mopeds. The following product structure diagram mopeds. The following product structure diagram represents the bill of materials for its dual-carburetor represents the bill of materials for its dual-carburetor Model 442 moped.Model 442 moped.

MOPEDMOPEDMOPEDMOPED

ENGINEENGINEASSEMBLYASSEMBLY

ENGINEENGINEASSEMBLYASSEMBLY

MOTORMOTORMOTORMOTOR CARBURETORCARBURETOR(2)(2)

CARBURETORCARBURETOR(2)(2)

GASGASTANKTANKGASGASTANKTANK

WHEELWHEELASSEMBLYASSEMBLY

(2)(2)

WHEELWHEELASSEMBLYASSEMBLY

(2)(2)

HUB HUB ASSEMBLYASSEMBLY

HUB HUB ASSEMBLYASSEMBLY TIRETIRETIRETIRE

FRAMEFRAMEFRAMEFRAME

Level 0Level 0

Level 1Level 1

Level 2Level 2

Page 17: Ch15. Resource Requirements Planning - MRP & CRP

17

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

Bill of MaterialBill of MaterialParentParent ComponentComponent LevelLevel

Compon.Compon.CodeCode CodeCode CodeCode DescriptionDescription Req’dReq’d

442442 00 #442 Moped#442 Moped

442442 EAEA 11 Engine Assem.Engine Assem. 11GTGT 11 Gas TankGas Tank 11WAWA 11 Wheel Assem.Wheel Assem. 22

FF 11 FrameFrame 11

EAEA MM 22 MotorMotor 11CC 22 CarburetorCarburetor 22

WAWA HAHA 22 Hub Assem.Hub Assem. 11TT 22 TireTire 11

Page 18: Ch15. Resource Requirements Planning - MRP & CRP

18

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

Inventory Status ReportInventory Status Report

ItemItemCodeCode

On-On-HandHand

SafetySafetyStockStock

LotLotSizeSize

LeadLeadTimeTime

Sched. ReceiptsSched. ReceiptsQnty. WeekQnty. Week

442442 500500 200200 LFLLFL 11 ---- ----

EAEA 300300 100100 500500 11 10001000 1010

GTGT 600600 200200 LFLLFL 22 900900 1010

WAWA 500500 400400 500500 11 20002000 1010

FF 600600 00 20002000 33 20002000 1010

MM 250250 00 LFLLFL 11 ---- ----

CC 150150 100100 2000+2000+ 22 ---- ----

HAHA 100100 00 LFLLFL 11 24002400 1111

TT 500500 500500 10001000 33 3000,20003000,2000 11,1211,12

Page 19: Ch15. Resource Requirements Planning - MRP & CRP

19

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

The company is currently planning production The company is currently planning production for weeks 10 through 16. Based on existing orders for weeks 10 through 16. Based on existing orders and demand forecasts, the master production schedule and demand forecasts, the master production schedule is as follows:is as follows:

Master Production Schedule: #442 MopedMaster Production Schedule: #442 Moped

Determine the MRP schedule required to Determine the MRP schedule required to support the master production schedule for the Model support the master production schedule for the Model 442 moped in weeks 10-16.442 moped in weeks 10-16.

1111

13001300 800800 12001200 14001400

1010 16161515141413131212

00 13001300 00

WEEKWEEK

QUANTITYQUANTITY

Page 20: Ch15. Resource Requirements Planning - MRP & CRP

20

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for #442 Mopeds for Weeks 10 - 16, MRP Schedule for #442 Mopeds for Weeks 10 - 16, considering that:considering that: Gross Requirements come from the moped MPSGross Requirements come from the moped MPS There is an On-Hand balance of 500 mopeds at the There is an On-Hand balance of 500 mopeds at the

end of week 9end of week 9 There are no Scheduled Receipts for mopeds There are no Scheduled Receipts for mopeds A lot-for-lot rule is used for ordering mopedsA lot-for-lot rule is used for ordering mopeds Safety stock of 200 mopeds is desiredSafety stock of 200 mopeds is desired Lead time for mopeds is one weekLead time for mopeds is one week

Page 21: Ch15. Resource Requirements Planning - MRP & CRP

21

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for #442 Mopeds . . . InitiallyMRP Schedule for #442 Mopeds . . . Initially

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 500) AVAILABLE (ON-HAND = 500)

NET REQUIREMENTSNET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: 442 MOPED LT: 1 ITEM: 442 MOPED LT: 1 LOT SIZE: LFL SS: 200 LOT SIZE: LFL SS: 200

00

1010

13001300 00

1111 1212 1313

13001300 800800

15151414

1400140012001200

1616

WEEKWEEK

Page 22: Ch15. Resource Requirements Planning - MRP & CRP

22

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for #442 Mopeds . . . CompletedMRP Schedule for #442 Mopeds . . . Completed

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 500)AVAILABLE (ON-HAND = 500)

NET REQUIREMENTSNET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: 442 MOPED LT: 1 ITEM: 442 MOPED LT: 1 LOT SIZE: LFL SS: 200 LOT SIZE: LFL SS: 200

00

300300

10001000

1010

10001000

10001000

300300

13001300

13001300

00

00

1111 1212 1313

13001300

12001200800800

12001200800800

1400140012001200

13001300

13001300

800800

000000 00

14001400

800800

1515

14001400

1414

1400140012001200

1616

WEEKWEEK

Page 23: Ch15. Resource Requirements Planning - MRP & CRP

23

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Gas Tanks for Weeks 10 - 16, MRP Schedule for Gas Tanks for Weeks 10 - 16, considering that:considering that: Gross Requirements come from moped Planned-Gross Requirements come from moped Planned-

Order-ReleasesOrder-Releases There is an On-Hand balance of 600 gas tanks at There is an On-Hand balance of 600 gas tanks at

the end of week 9the end of week 9 There is a Scheduled Receipt for 900 tanks in There is a Scheduled Receipt for 900 tanks in

week 10 week 10 A lot-for-lot rule is used for ordering gas tanksA lot-for-lot rule is used for ordering gas tanks Safety stock of 200 gas tanks is desiredSafety stock of 200 gas tanks is desired Lead time for gas tanks is two weeksLead time for gas tanks is two weeks

Page 24: Ch15. Resource Requirements Planning - MRP & CRP

24

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Gas Tanks . . . InitiallyMRP Schedule for Gas Tanks . . . Initially

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 600)AVAILABLE (ON-HAND = 600)

NET REQUIREMENTSNET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: GAS TANK LT: 2 ITEM: GAS TANK LT: 2 LOT SIZE: LFL SS: 200LOT SIZE: LFL SS: 200

10001000

900900

1010

00 13001300

1111 1212 1313

800800 12001200

15151414

0014001400

1616

WEEKWEEK

Page 25: Ch15. Resource Requirements Planning - MRP & CRP

25

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Gas Tanks . . . CompletedMRP Schedule for Gas Tanks . . . Completed

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE AVAILABLE (ON-HAND = 600) (ON-HAND = 600)

NET REQUIREMENTS NET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: GAS TANK LT: 2 ITEM: GAS TANK LT: 2 LOT SIZE: LFL SS: 200 LOT SIZE: LFL SS: 200

10001000

900900

13001300

10001000

1010

800800

00

12001200

300300

13001300

1111 1212 1313

800800

12001200

14001400

12001200

15151414

0014001400

1616

WEEKWEEK

300300 000000

10001000

10001000 800800

800800

14001400

1400140012001200

00

Page 26: Ch15. Resource Requirements Planning - MRP & CRP

26

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Frames for Weeks 10 - 16, MRP Schedule for Frames for Weeks 10 - 16, considering that:considering that: Gross Requirements come from moped Planned-Gross Requirements come from moped Planned-

Order-ReleasesOrder-Releases There is an On-Hand balance of 600 frames at the There is an On-Hand balance of 600 frames at the

end of week 9end of week 9 There is a Scheduled Receipt for 2000 frames in There is a Scheduled Receipt for 2000 frames in

week 10week 10 The firm uses a Lot Size (multiple) of 2000 for The firm uses a Lot Size (multiple) of 2000 for

ordering framesordering frames No safety stock of frames is desiredNo safety stock of frames is desired Lead time for frames is 3 weeksLead time for frames is 3 weeks

Page 27: Ch15. Resource Requirements Planning - MRP & CRP

27

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Frames . . . InitiallyMRP Schedule for Frames . . . Initially

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE AVAILABLE

NET REQUIREMENTSNET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: FRAME LT: 3 ITEM: FRAME LT: 3 LOT SIZE: 2000 SS: 0LOT SIZE: 2000 SS: 0

10001000

20002000

1010

00 13001300

1111 1212 1313

800800 12001200

15151414

0014001400

1616

WEEKWEEK

600600

Page 28: Ch15. Resource Requirements Planning - MRP & CRP

28

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Frames . . . CompletedMRP Schedule for Frames . . . Completed

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 600) AVAILABLE (ON-HAND = 600)

NET REQUIREMENTSNET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: FRAME LT: 3 ITEM: FRAME LT: 3 LOT SIZE: 2000 SS: 0 LOT SIZE: 2000 SS: 0

10001000

20002000

16001600

00

20002000

1010

16001600

00

20002000

16001600

13001300

1111 1212 1313

800800

20002000

500500

20002000

300300300300 900900

00

12001200

15151414

0014001400

1616

WEEKWEEK

00 00

15001500

00 11001100

Page 29: Ch15. Resource Requirements Planning - MRP & CRP

29

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Engine Assemblies for Weeks 10 - MRP Schedule for Engine Assemblies for Weeks 10 - 16, considering that:16, considering that: Gross Requirements come from moped Planned-Gross Requirements come from moped Planned-

Order-ReleasesOrder-Releases There is an On-Hand balance of 300 engine There is an On-Hand balance of 300 engine

assemblies at the end of week 9assemblies at the end of week 9 There is a Scheduled Receipt for 1000 engine There is a Scheduled Receipt for 1000 engine

assemblies in week 10assemblies in week 10 The firm uses a Lot Size (multiple) of 500 for The firm uses a Lot Size (multiple) of 500 for

ordering engine assembliesordering engine assemblies Safety Stock of 100 engine assemblies is desiredSafety Stock of 100 engine assemblies is desired Lead time for engine assemblies is 1 weekLead time for engine assemblies is 1 week

Page 30: Ch15. Resource Requirements Planning - MRP & CRP

30

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Engine Assemblies . . . InitiallyMRP Schedule for Engine Assemblies . . . Initially

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 300) AVAILABLE (ON-HAND = 300)

NET REQUIREMENTS NET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: ENGINE ASSEM. LT: 1 ITEM: ENGINE ASSEM. LT: 1 LOT SIZE: 500 SS: 100 LOT SIZE: 500 SS: 100

10001000

10001000

1010

00

13001300

1111 1212 1313

800800 12001200

15151414

0014001400

1616

WEEKWEEK

Page 31: Ch15. Resource Requirements Planning - MRP & CRP

31

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Engine Assemblies . . . CompletedMRP Schedule for Engine Assemblies . . . Completed

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 300) AVAILABLE (ON-HAND = 300)

NET REQUIREMENTS NET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: ENGINE ASSEM. LT: 1 ITEM: ENGINE ASSEM. LT: 1 LOT SIZE: 500 SS: 100 LOT SIZE: 500 SS: 100

10001000

10001000

200200

1010

15001500

200 200

00

500500

15001500

11001100

200200

13001300

1111 1212 1313

800800

1000100011001100

1000100015001500

10001000

400400

500500

15001500

400400100100400400 00

12001200

15151414

0014001400

1616

WEEKWEEK

Page 32: Ch15. Resource Requirements Planning - MRP & CRP

32

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Motors for Weeks 10 - 16, MRP Schedule for Motors for Weeks 10 - 16, considering that:considering that: Gross Requirements come from engine assembly Gross Requirements come from engine assembly

Planned-Order-ReleasesPlanned-Order-Releases There is an On-Hand balance of 250 motors at the There is an On-Hand balance of 250 motors at the

end of week 9end of week 9 There are no Scheduled Receipts for motorsThere are no Scheduled Receipts for motors A lot-for-lot rule is used for ordering motorsA lot-for-lot rule is used for ordering motors No Safety Stock of motors is desiredNo Safety Stock of motors is desired Lead time for motors is 1 weekLead time for motors is 1 week

Page 33: Ch15. Resource Requirements Planning - MRP & CRP

33

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Motors . . . InitiallyMRP Schedule for Motors . . . Initially

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTS SCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 250) AVAILABLE (ON-HAND = 250)

NET REQUIREMENTSNET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: MOTOR LT: 1 ITEM: MOTOR LT: 1 LOT SIZE: LFL SS: 0 LOT SIZE: LFL SS: 0 1010

15001500

500500

1111 1212 1313

15001500

10001000

15151414 1616

WEEKWEEK

Page 34: Ch15. Resource Requirements Planning - MRP & CRP

34

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Motors . . . CompletedMRP Schedule for Motors . . . Completed

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTS SCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 250) AVAILABLE (ON-HAND = 250)

NET REQUIREMENTSNET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: MOTOR LT: 1 ITEM: MOTOR LT: 1 LOT SIZE: LFL SS: 0 LOT SIZE: LFL SS: 0

250250

12501250

1010

12501250

500500

12501250

250250

15001500

15001500

500500

500500

00

500500

1111 1212 1313

15001500

10001000

10001000

15001500

15001500

10001000

000000 00

10001000

15151414 1616

WEEKWEEK

Page 35: Ch15. Resource Requirements Planning - MRP & CRP

35

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Carburetors for Weeks 10 - 16, MRP Schedule for Carburetors for Weeks 10 - 16, considering that:considering that: Gross Requirements come from engine assembly Gross Requirements come from engine assembly

Planned-Order-Releases (times 2)Planned-Order-Releases (times 2) There is an On-Hand balance of 150 carburetors at There is an On-Hand balance of 150 carburetors at

the end of week 9the end of week 9 There are no Scheduled Receipts for carburetorsThere are no Scheduled Receipts for carburetors A Lot Size of 200+ is used for ordering carburetorsA Lot Size of 200+ is used for ordering carburetors Safety Stock of 100 carburetors is desiredSafety Stock of 100 carburetors is desired Lead time for carburetors is 2 weeksLead time for carburetors is 2 weeks

Page 36: Ch15. Resource Requirements Planning - MRP & CRP

36

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Carburetors . . . InitiallyMRP Schedule for Carburetors . . . Initially

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTS SCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 150) AVAILABLE (ON-HAND = 150)

NET REQUIREMENTSNET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASES PLANNED ORDER RELEASES

ITEM: CARBURETOR LT: 2 ITEM: CARBURETOR LT: 2 LOT SIZE: 2000+ SS: 100LOT SIZE: 2000+ SS: 100 1010

30003000 10001000

1111 1212 1313

30003000 20002000

15151414 1616

WEEKWEEK

Page 37: Ch15. Resource Requirements Planning - MRP & CRP

37

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Carburetors . . . CompletedMRP Schedule for Carburetors . . . Completed

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTS SCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 150) AVAILABLE (ON-HAND = 150)

NET REQUIREMENTSNET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASES PLANNED ORDER RELEASES

ITEM: CARBURETOR LT: 2 ITEM: CARBURETOR LT: 2 LOT SIZE: 2500+ SS: 100LOT SIZE: 2500+ SS: 100

5050

25002500

1010

25002500

30503050

30003000

30003000

25002500

25002500

950950

5050

10001000

1111 1212 1313

30003000

950950

25002500

14501450

25002500

155015501050105015501550 15501550

20002000

15151414 1616

WEEKWEEK

Page 38: Ch15. Resource Requirements Planning - MRP & CRP

38

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Wheel Assemblies for Weeks 10 - MRP Schedule for Wheel Assemblies for Weeks 10 - 16, considering that:16, considering that: Gross Requirements come from moped Planned-Gross Requirements come from moped Planned-

Order-Releases (times 2)Order-Releases (times 2) There is an On-Hand balance of 500 wheel There is an On-Hand balance of 500 wheel

assemblies at the end of week 9assemblies at the end of week 9 There is a Scheduled Receipt for 2000 wheel There is a Scheduled Receipt for 2000 wheel

assemblies in week 10assemblies in week 10 A Lot Size (multiple) of 500 is used for ordering A Lot Size (multiple) of 500 is used for ordering

wheel assemblieswheel assemblies Safety Stock of 400 wheel assemblies is desiredSafety Stock of 400 wheel assemblies is desired Lead time for wheel assemblies is 1 weekLead time for wheel assemblies is 1 week

Page 39: Ch15. Resource Requirements Planning - MRP & CRP

39

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Wheel Assemblies . . . InitiallyMRP Schedule for Wheel Assemblies . . . Initially

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 500) AVAILABLE (ON-HAND = 500)

NET REQUIREMENTS NET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: WHEEL ASSEM. LT: 1 ITEM: WHEEL ASSEM. LT: 1 LOT SIZE: 500 SS: 400 LOT SIZE: 500 SS: 400

20002000

20002000

1010

00

26002600

1111 1212 1313

16001600 24002400

15151414

0028002800

1616

WEEKWEEK

Page 40: Ch15. Resource Requirements Planning - MRP & CRP

40

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Wheel Assemblies . . . CompletedMRP Schedule for Wheel Assemblies . . . Completed

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 500) AVAILABLE (ON-HAND = 500)

NET REQUIREMENTS NET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: WHEEL ASSEM. LT: 1 ITEM: WHEEL ASSEM. LT: 1 LOT SIZE: 500 SS: 400 LOT SIZE: 500 SS: 400

20002000

20002000

21002100

1010

25002500

100100

00

20002000

25002500

25002500

100100

26002600

1111 1212 1313

16001600

2800280020002000

3000300020002000

30003000

16001600

20002000

20002000

0040040000 200200

24002400

15151414

0028002800

1616

WEEKWEEK

Page 41: Ch15. Resource Requirements Planning - MRP & CRP

41

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Hub Assemblies for Weeks 10 - 16, MRP Schedule for Hub Assemblies for Weeks 10 - 16, considering that:considering that: Gross Requirements come from wheel assembly Gross Requirements come from wheel assembly

Planned-Order-ReleasesPlanned-Order-Releases There is an On-Hand balance of 100 hub assemblies There is an On-Hand balance of 100 hub assemblies

at the end of week 9at the end of week 9 There is a Scheduled Receipt of 2400 hub There is a Scheduled Receipt of 2400 hub

assemblies in week 11assemblies in week 11 A lot-for-lot rule is used for ordering hub assembliesA lot-for-lot rule is used for ordering hub assemblies No Safety Stock of hub assemblies is desiredNo Safety Stock of hub assemblies is desired Lead time for hub assemblies is 1 weekLead time for hub assemblies is 1 week

Page 42: Ch15. Resource Requirements Planning - MRP & CRP

42

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Hub Assemblies . . . InitiallyMRP Schedule for Hub Assemblies . . . Initially

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 100) AVAILABLE (ON-HAND = 100)

NET REQUIREMENTS NET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: HUB ASSEM. LT: 1 ITEM: HUB ASSEM. LT: 1 LOT SIZE: LFL SS: 0 LOT SIZE: LFL SS: 0

00

1010

24002400

25002500

20002000

1111 1212 1313

20002000

30003000

15151414

0000

1616

WEEKWEEK

Page 43: Ch15. Resource Requirements Planning - MRP & CRP

43

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Hub Assemblies . . . CompletedMRP Schedule for Hub Assemblies . . . Completed

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 100) AVAILABLE (ON-HAND = 100)

NET REQUIREMENTS NET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: HUB ASSEM. LT: 1 ITEM: HUB ASSEM. LT: 1 LOT SIZE: LFL SS: 0 LOT SIZE: LFL SS: 0

00

100100

1010

20002000

25002500

24002400

25002500

20002000

20002000

20002000

00

20002000

1111 1212 1313

20002000

30003000

30003000

20002000

20002000

30003000

000000 00

30003000

15151414

0000

1616

WEEKWEEK

Page 44: Ch15. Resource Requirements Planning - MRP & CRP

44

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Tires for Weeks 10 - 16, MRP Schedule for Tires for Weeks 10 - 16, considering that:considering that: Gross Requirements come from wheel assembly Gross Requirements come from wheel assembly

Planned-Order-ReleasesPlanned-Order-Releases There is an On-Hand balance of 500 tires at the There is an On-Hand balance of 500 tires at the

end of week 9end of week 9 There are Scheduled Receipts for 3000 and 2000 There are Scheduled Receipts for 3000 and 2000

tires weeks 11 and 12, respectivelytires weeks 11 and 12, respectively A Lot Size (multiple) of 1000 is used for ordering A Lot Size (multiple) of 1000 is used for ordering

tirestires Safety Stock of 500 tires is desiredSafety Stock of 500 tires is desired Lead time for tires is 3 weeksLead time for tires is 3 weeks

Page 45: Ch15. Resource Requirements Planning - MRP & CRP

45

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Tires . . . InitiallyMRP Schedule for Tires . . . Initially

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 500) AVAILABLE (ON-HAND = 500)

NET REQUIREMENTS NET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: TIRE LT: 3 ITEM: TIRE LT: 3 LOT SIZE: 1000 SS: 500 LOT SIZE: 1000 SS: 500

00

1010

30003000

25002500 20002000

20002000

1111 1212 1313

20002000

30003000

15151414

0000

1616

WEEKWEEK

Page 46: Ch15. Resource Requirements Planning - MRP & CRP

46

Example: MRP ScheduleExample: MRP ScheduleExample: MRP ScheduleExample: MRP Schedule

MRP Schedule for Tires . . . CompletedMRP Schedule for Tires . . . Completed

GROSS REQUIREMENTSGROSS REQUIREMENTS

SCHEDULED RECEIPTSSCHEDULED RECEIPTS

AVAILABLE (ON-HAND = 500) AVAILABLE (ON-HAND = 500)

NET REQUIREMENTS NET REQUIREMENTS

PLANNED ORDER RECEIPTSPLANNED ORDER RECEIPTS

PLANNED ORDER RELEASESPLANNED ORDER RELEASES

ITEM: TIRE LT: 3 ITEM: TIRE LT: 3 LOT SIZE: 1000 SS: 500 LOT SIZE: 1000 SS: 500

00

0 0

20002000

1010

30003000

30003000

30003000

25002500

25002500

20002000

20002000

1111 1212 1313

20002000

25002500

30003000

15001500

20002000

500500 500500500 500 500 500

30003000

15151414

0000

1616

WEEKWEEK

Page 47: Ch15. Resource Requirements Planning - MRP & CRP

47

Issues in MRPIssues in MRPIssues in MRPIssues in MRP

Lot-SizingLot-Sizing Useful at lower levels but may drive excess Useful at lower levels but may drive excess

inventory when applied at higher levelsinventory when applied at higher levels Net Change versus Regenerative MRPNet Change versus Regenerative MRP

Net change may generate too many action noticesNet change may generate too many action notices Regenerative more costly to run but appears to be Regenerative more costly to run but appears to be

easier to manageeasier to manage . . . more. . . more

Page 48: Ch15. Resource Requirements Planning - MRP & CRP

48

Issues in MRPIssues in MRPIssues in MRPIssues in MRP

Safety StockSafety Stock Use depends on uncertainty of demand..... more Use depends on uncertainty of demand..... more

uncertain the greater the need for safety stockuncertain the greater the need for safety stock Assemble-to-Order FirmsAssemble-to-Order Firms

MPS and MRP treated separately from Final MPS and MRP treated separately from Final Assembly Schedule(FAS)Assembly Schedule(FAS)

Use Modular Bill of MaterialUse Modular Bill of Material

Page 49: Ch15. Resource Requirements Planning - MRP & CRP

49

Lot-Sizing in MRPLot-Sizing in MRPLot-Sizing in MRPLot-Sizing in MRP

Lot-sizeLot-size is the quantity ordered/produced at one time is the quantity ordered/produced at one time Large lots are preferred because:Large lots are preferred because:

Changeovers cost less and capacity greaterChangeovers cost less and capacity greater Annual cost of purchase orders lessAnnual cost of purchase orders less Price breaks and transportation breaks can be Price breaks and transportation breaks can be

utilizedutilized Small lots are preferred because:Small lots are preferred because:

Lower inventory carrying costLower inventory carrying cost Reduced risk of obsolescenceReduced risk of obsolescence Shorter cycle time to produce customer orderShorter cycle time to produce customer order

Page 50: Ch15. Resource Requirements Planning - MRP & CRP

50

Lot-Sizing Methods in MRPLot-Sizing Methods in MRPLot-Sizing Methods in MRPLot-Sizing Methods in MRP

Economic Order Quantity (EOQ)Economic Order Quantity (EOQ) does not consider quantity discountsdoes not consider quantity discounts does not always provide the most economical does not always provide the most economical

approach with lumpy demandsapproach with lumpy demands Lot-for-Lot (LFL)Lot-for-Lot (LFL)

accommodates lumpy demandaccommodates lumpy demand Period Order Quantity (POQ)Period Order Quantity (POQ) Many othersMany others

Page 51: Ch15. Resource Requirements Planning - MRP & CRP

51

Lot-Sizing Methods in MRPLot-Sizing Methods in MRPLot-Sizing Methods in MRPLot-Sizing Methods in MRP

The best lot-sizing method, The best lot-sizing method, resulting in least cost,resulting in least cost,

depends on cost depends on cost and demand patternsand demand patterns

Page 52: Ch15. Resource Requirements Planning - MRP & CRP

52

Lot-Sizing in MRPLot-Sizing in MRPLot-Sizing in MRPLot-Sizing in MRP

Lot-sizeLot-size is the quantity ordered/produced at one time is the quantity ordered/produced at one time Large lots are preferred because:Large lots are preferred because:

Changeovers cost less and capacity greaterChangeovers cost less and capacity greater Annual cost of purchase orders lessAnnual cost of purchase orders less Price breaks and transportation breaks can be Price breaks and transportation breaks can be

utilizedutilized Small lots are preferred because:Small lots are preferred because:

Lower inventory carrying costLower inventory carrying cost Reduced risk of obsolescenceReduced risk of obsolescence Shorter cycle time to produce customer orderShorter cycle time to produce customer order

Page 53: Ch15. Resource Requirements Planning - MRP & CRP

53

The best method, resulting in least cost,The best method, resulting in least cost,depends on cost and demand patterns.depends on cost and demand patterns.

Lot-Sizing MethodsLot-Sizing MethodsLot-Sizing MethodsLot-Sizing Methods

Economic Order Quantity (EOQ)Economic Order Quantity (EOQ) does not consider quantity discountsdoes not consider quantity discounts does not always provide the most economical does not always provide the most economical

approach with lumpy demandapproach with lumpy demand Lot-for-Lot (LFL)Lot-for-Lot (LFL)

accommodates lumpy demandaccommodates lumpy demand Period Order Quantity (POQ)Period Order Quantity (POQ)

Page 54: Ch15. Resource Requirements Planning - MRP & CRP

54

Example: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing Decision

The net requirements for a material from an The net requirements for a material from an MRP schedule are:MRP schedule are:

It costs $400 to change over the machines for It costs $400 to change over the machines for this material in the affected work center. It costs this material in the affected work center. It costs $0.40 per unit when one unit of this material must be $0.40 per unit when one unit of this material must be carried in inventory from one week to the next.carried in inventory from one week to the next.

Identify the lot-sizing method that results in the Identify the lot-sizing method that results in the least carrying and changeover costs for the 8-week least carrying and changeover costs for the 8-week schedule.schedule.

NET REQUIREMENTS NET REQUIREMENTS 10001000

11

00 13001300

22 33 44

800800 12001200

6655

0013001300

77

WEEKWEEK

800800

88

Page 55: Ch15. Resource Requirements Planning - MRP & CRP

55

Example: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing Decision

Lot-for-Lot MethodLot-for-Lot Method

Carrying Cost Carrying Cost = 0($.40) = $0 = 0($.40) = $0

Changeover Cost = 6($400) = Changeover Cost = 6($400) = $2,400$2,400

Total = $2,400Total = $2,400

NET REQUIREMENTS NET REQUIREMENTS

BEGINNING INVENTORY BEGINNING INVENTORY

PRODUCTION LOTS PRODUCTION LOTS

ENDING INVENTORYENDING INVENTORY

10001000

00

10001000

00

11

00

00

00

00

00

13001300

13001300

00

22 33 44

800800

000000

0000

1300130012001200800800 00

00

12001200

6655

0013001300

0000

77

WEEKWEEK

800800

00

800800

00

88

Page 56: Ch15. Resource Requirements Planning - MRP & CRP

56

Evaluation of MRPEvaluation of MRPEvaluation of MRPEvaluation of MRP

Most beneficial to process-focused systems that have Most beneficial to process-focused systems that have long processing times and complex multistage long processing times and complex multistage production stepsproduction steps

Lead times must be reliableLead times must be reliable Must freeze MPS for some time before actual Must freeze MPS for some time before actual

production... certain demandproduction... certain demand Difficult to implementDifficult to implement

Page 57: Ch15. Resource Requirements Planning - MRP & CRP

57

Closed Loop MRPClosed Loop MRPClosed Loop MRPClosed Loop MRP

Production PlanningMaster Production Scheduling

Material Requirements PlanningCapacity Requirements Planning

Realistic?

No

Feedback

Execute:Capacity PlansMaterial Plans

Yes

Feedback

Page 58: Ch15. Resource Requirements Planning - MRP & CRP

58

Closed Loop MRPClosed Loop MRPClosed Loop MRPClosed Loop MRP

Materials Management at Washburn Guitar, Inc.Materials Management at Washburn Guitar, Inc.

Page 59: Ch15. Resource Requirements Planning - MRP & CRP

59

Manufacturing Resource Planning (MRP II)Manufacturing Resource Planning (MRP II)Manufacturing Resource Planning (MRP II)Manufacturing Resource Planning (MRP II)

Goal: Plan and monitor Goal: Plan and monitor allall resources of a resources of a manufacturing firm (closed loop):manufacturing firm (closed loop):

Manufacturing Manufacturing Marketing Marketing Finance Finance EngineeringEngineeringShop-floor controlShop-floor control

Simulation capability of the manufacturing systemSimulation capability of the manufacturing system

Page 60: Ch15. Resource Requirements Planning - MRP & CRP

60

Enterprise Resource Planning (ERP)Enterprise Resource Planning (ERP)Enterprise Resource Planning (ERP)Enterprise Resource Planning (ERP)

ERP systems available today integrate ERP systems available today integrate manufacturing with other functional areas in an manufacturing with other functional areas in an organization organization

ERP systems make it easier for management to ERP systems make it easier for management to obtain local information about performance of obtain local information about performance of specific processes, bottlenecks resources, and specific processes, bottlenecks resources, and products (or product groups), etc.products (or product groups), etc.

Class I ERP software packages (for large Class I ERP software packages (for large companies) include BAAN, SAP, and Oraclecompanies) include BAAN, SAP, and Oracle

Page 61: Ch15. Resource Requirements Planning - MRP & CRP

61

Example: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing Decision

Economic Order Quantity (EOQ) MethodEconomic Order Quantity (EOQ) Method

S = $400.00S = $400.00

D = [(Net Req. for 8 wks)/8 weeks)](50 weeks/year)D = [(Net Req. for 8 wks)/8 weeks)](50 weeks/year)

= (6400/8)(50) = 40,000= (6400/8)(50) = 40,000

C = ($0.40 per week)(50 weeks/year)C = ($0.40 per week)(50 weeks/year)

= $20.00= $20.00

2DS 2(40,000)(400)EOQ = = = 1265

C 20

2DS 2(40,000)(400)EOQ = = = 1265

C 20

Page 62: Ch15. Resource Requirements Planning - MRP & CRP

62

Example: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing Decision

Economic Order Quantity (EOQ) MethodEconomic Order Quantity (EOQ) Method

Carrying Cost = 4855($.40) = $1,942Carrying Cost = 4855($.40) = $1,942

Changeover Cost = 6($400) = Changeover Cost = 6($400) = $2,400$2,400

Total = $4,342Total = $4,342

NET REQUIREMENTS NET REQUIREMENTS

BEGINNING INVENTORY BEGINNING INVENTORY

PRODUCTION LOTS PRODUCTION LOTS

ENDING INVENTORYENDING INVENTORY

10001000

00

12651265

265265

11

265265

00

265265

00

230230

12651265

13001300

265265

22 33 44

800800

725725760760695695

695695230230

126512651265126512651265 00

725725

12001200

6655

0013001300

725725760760

77

WEEKWEEK

12651265

11901190

800800

725725

88

Page 63: Ch15. Resource Requirements Planning - MRP & CRP

63

Example: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing Decision

Period Order Quantity (POQ) MethodPeriod Order Quantity (POQ) Method

POQ = (# Weeks/year)/(# Orders/year)POQ = (# Weeks/year)/(# Orders/year)

= 50/(D/EOQ)= 50/(D/EOQ)

= 50/(40,000/1,265)= 50/(40,000/1,265)

= 1.58 or 2 weeks= 1.58 or 2 weeks

Page 64: Ch15. Resource Requirements Planning - MRP & CRP

64

Example: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing Decision

Period Order Quantity (POQ) MethodPeriod Order Quantity (POQ) Method

Carrying Cost = 2900($.40) = $1,160Carrying Cost = 2900($.40) = $1,160

Changeover Cost = 4($400) = Changeover Cost = 4($400) = $1,600$1,600

Total = $2,760Total = $2,760

NET REQUIREMENTS NET REQUIREMENTS

BEGINNING INVENTORY BEGINNING INVENTORY

PRODUCTION LOTS PRODUCTION LOTS

ENDING INVENTORYENDING INVENTORY

10001000

00

10001000

00

11

00

00

00

00

800800

21002100

13001300

00

22 33 44

800800

001300130000

00800800

002500250000 800800

800800

12001200

6655

0013001300

0013001300

77

WEEKWEEK

00

00

800800

800800

88

Page 65: Ch15. Resource Requirements Planning - MRP & CRP

65

Example: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing DecisionExample: Lot-Sizing Decision

SummarySummary

CarryingCarrying Chg.Ovr.Chg.Ovr. TotalTotalMethodMethod CostCost CostCost CostCost

LFLLFL 00 2,4002,400 2,4002,400

EOQEOQ 1,9421,942 2,4002,400 4,3424,342

POQPOQ 1,1601,160 1,6001,600 2,7602,760

Page 66: Ch15. Resource Requirements Planning - MRP & CRP

66

Issues in MRPIssues in MRPIssues in MRPIssues in MRP

Lot-SizingLot-Sizing Useful at lower levels but may drive excess Useful at lower levels but may drive excess

inventory when applied at higher levelsinventory when applied at higher levels Net Change versus Regenerative MRPNet Change versus Regenerative MRP

Net change may generate too many action noticesNet change may generate too many action notices Regenerative more costly to run but appears to be Regenerative more costly to run but appears to be

easier to manageeasier to manage . . . more. . . more

Page 67: Ch15. Resource Requirements Planning - MRP & CRP

67

Issues in MRPIssues in MRPIssues in MRPIssues in MRP

Safety StockSafety Stock Use depends on uncertainty of demand..... more Use depends on uncertainty of demand..... more

uncertain the greater the need for safety stockuncertain the greater the need for safety stock Assemble-to-Order FirmsAssemble-to-Order Firms

MPS and MRP treated separately from Final MPS and MRP treated separately from Final Assembly Schedule(FAS)Assembly Schedule(FAS)

Use Modular Bill of MaterialUse Modular Bill of Material

Page 68: Ch15. Resource Requirements Planning - MRP & CRP

68

MRP II SystemMRP II SystemMRP II SystemMRP II System

MRP II SystemMRP II System

Page 69: Ch15. Resource Requirements Planning - MRP & CRP

69

MRP I to MRP IIMRP I to MRP IIMRP I to MRP IIMRP I to MRP II

MRP I simply exploded demand (MPS) into required MRP I simply exploded demand (MPS) into required materialsmaterials

MRP II became MRP II became Manufacturing Resource PlanningManufacturing Resource Planning which provides a closed-loop business management which provides a closed-loop business management systemsystem Financial managementFinancial management Shop floor controlShop floor control Operations managementOperations management Simulation capabilitySimulation capability

Page 70: Ch15. Resource Requirements Planning - MRP & CRP

70

Evaluation of MRPEvaluation of MRPEvaluation of MRPEvaluation of MRP

Most beneficial to process-focused systems that have Most beneficial to process-focused systems that have long processing times and complex multistage long processing times and complex multistage production stepsproduction steps

Lead times must be reliableLead times must be reliable Must freeze MPS for some time before actual Must freeze MPS for some time before actual

production... certain demandproduction... certain demand Difficult to implementDifficult to implement

Page 71: Ch15. Resource Requirements Planning - MRP & CRP

71

Capacity Requirements Planning (CRP)

Page 72: Ch15. Resource Requirements Planning - MRP & CRP

72

Capacity Requirements Planning (CRP)Capacity Requirements Planning (CRP)Capacity Requirements Planning (CRP)Capacity Requirements Planning (CRP)

Tests MPS for feasibilityTests MPS for feasibility Utilizes routings to determine labor/machine loadsUtilizes routings to determine labor/machine loads If schedule feasible, recommends freezingIf schedule feasible, recommends freezing If schedule overloads resources, points out processes If schedule overloads resources, points out processes

that are overscheduledthat are overscheduled

Page 73: Ch15. Resource Requirements Planning - MRP & CRP

73

Load SchedulesLoad SchedulesLoad SchedulesLoad Schedules

Compares actual labor and machine hours against Compares actual labor and machine hours against available hoursavailable hours

Offsets schedules between successive stages of Offsets schedules between successive stages of production by lead timesproduction by lead times

Provides feasible MPS and economically loaded work Provides feasible MPS and economically loaded work centerscenters

Promotes system operating efficiency ... lowers costs!Promotes system operating efficiency ... lowers costs!