CF MEP Commissioning. CF Commissioning Plan. Commissioning Plan (CP) developed by Jacobs Facilities (Engineer of Record) Title II project deliverable Reviewed and approved by LCLS CF Eng group leader – Javier Sevilla - PowerPoint PPT PresentationTRANSCRIPT
David Saenz
CF Commissioning [email protected]
Oct 30, 2007 2
CF Commissioning PlanCommissioning Plan (CP) developed by Jacobs Facilities (Engineer of Record)
Title II project deliverableReviewed and approved by LCLS CF Eng group leader – Javier Sevilla
CP includes a comprehensive list of field deliverables and requirements that meet expectations of LCLS
AdministrationDetailed scope of Commissioning workQuality Control PlanTesting and Training Schedule
Field Plumbing and Fire Protection SystemsMechanical SystemsElectrical SystemsElevator and Crane SystemsDemonstration and Testing
CP managed by 3rd party subcontractor, independent of trades and Turner, hired by LCLS
David Saenz
CF Commissioning [email protected]
Oct 30, 2007 3
Beam Transport Hall – Undulator Hall
Far Experimental Hall –
Electron Beam Dump
Front End Enclosure
Near Experimental Hall/Central Utility Plant/12Kv Substation
X-Ray Transport & Diagnostics Tunnel
Commissioning Areas
David Saenz
CF Commissioning [email protected]
Oct 30, 2007 5
BTH Looking East
Drawings
M4201
A2200
SB 2.3
AHU
Storage tank for runoff water from tunnels
Ductwork
David Saenz
CF Commissioning [email protected]
Oct 30, 2007 9
CUP Plan View Drawing M0203
Electrical Rm
Chillers
Boilers
Mech Room-NEH
David Saenz
CF Commissioning [email protected]
Oct 30, 2007 10
CENTRAL UTILITY PLANT (CUP)
Title II-IFCTwo Chillers (425 tons/ea), Primary and Secondary CHW loops and Pumps BTH,UH,EBD,FEE, NEH and FEH
One Boiler (150 BHP/ea) Primary and Secondary HW loops and pumps
DDC Temperature Control System to be connected to SLAC network via Web Control
One Air Compressor (268 SCFM@150psi), Air Dryer and Receiver.Will provide service to: BTH, UH, EBD, FEE, NEH,X-RAY, FEH
Wet Sprinkler System-Ordinary Hazard Group 1
One AHU for electrical room
Mechanical room for NEH HVAC system (MAU)
David Saenz
CF Commissioning [email protected]
Oct 30, 2007 12
CP ProcurementBased on early estimates, budget was established at $350K
Bids were solicited Aug 07 for CxA (Commissioning Agent)
5 CxA bidders invited4 bidders responded and all 4 were within budget!
Technical evaluation by CF group is completeWeighted point score
Awarded to Engineering Economics Inc (EEI) at $229K
David Saenz
CF Commissioning [email protected]
Oct 30, 2007 13
CxAEngineering Economics Inc (EEI)
Offices nationwide and able to shift resources if necessary, although not likely
Commissioned over 33 million sfData centers
Medical research labs
Pharmaceutical labs
Federal facilities LCLS Sector 20 Injector Facilities - successful
LCLS Magnetic Measurement Facilities - successful
David Saenz
CF Commissioning [email protected]
Oct 30, 2007 14
SummaryRoles and responsibilities are clearExpectations are documented and well understoodCxA will be assigned to work with trades, SLAC Facilities maintenance staff and LCLS CF Engineering groupGoal is to deliver a complete and functional project with all MEP systems fully operational, inspected, tested, verified and documented