cerc final rec ammendment 27-9-2010

Upload: nunna123nath

Post on 05-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    1/25

    TheCentralElectricityRegulatoryCommission

    (TermsandConditionsforrecognitionandissuanceofRenewableEnergyCertificateforRenewableEnergy

    Generation)(FirstAmendment)Regulations,2010.

    StatementofObjectsandReasons

    INTRODUCTION

    1. The Commission had notified the CERC (Terms and Conditions for recognition and issuance ofRenewableEnergyCertificateforRenewableEnergyGeneration)Regulations,2010(hereinafter

    CERC REC Regulations) vide notification dated 14th January, 2010. The concept of renewable

    energy

    certificate

    seeks

    to

    address

    the

    mismatch

    between

    availability

    of

    renewable

    energysourcesandtherequirementofobligatedentitiestomeettheirrenewablepurchaseobligations.

    TheRECmechanismmainlyaimsatpromotinginvestmentintherenewableenergyprojectsand

    toprovideanalternativemodetotheREgeneratorsforrecoveryoftheircosts.

    2. Regulation5oftheCERCRECRegulationsspecifieseligibilitycriteriaforanREgeneratorunderRECframework.Thesaidprovisionisreproducedbelow:

    Agenerating

    company

    engaged

    in

    generation

    of

    electricity

    from

    renewable

    energy

    sources shall be eligible to apply for registration for issuance of and dealing in

    Certificatesifitfulfillsthefollowingcondition:

    a.IthasobtainedaccreditationfromtheStateAgency;

    b.Itdoesnothaveanypowerpurchaseagreementforthecapacityrelatedtosuch

    generation to sell electricityata preferential tariff determined by the Appropriate

    Commission;

    and

    c.Itsellstheelectricitygeneratedeither

    (i)tothedistribution licenseeoftheareainwhichtheeligibleentityislocated,ata

    pricenotexceedingthepooledcostofpowerpurchaseofsuchdistributionlicensee,

    or

    (ii)toanyotherlicenseeortoanopenaccessconsumeratamutuallyagreedprice,

    orthrough

    power

    exchange

    at

    market

    determined

    price.

    3. Concernswereraised fromvariousquartersthattherenewablegeneratorshavinganexistingPPAwithdistributionutilitiesforsaleofelectricityatpreferential(costplus)tariffmightattemptto

    breachtheexistingcontractswiththesoleobjectiveofmakingprofitsthroughRECmechanism.It

    wasalsoarguedthatRECmechanismshouldnotencouragebreachoftheexistingcontracts.

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    2/25

    eligibleforparticipating inRECmechanismsubjecttotheconditionsasapplicabletoanyother

    generatingcompany.Thesecondcomponentisthecaptiveconsumptionorselfconsumption.It

    wasarguedthatsuchaselfconsumptionofelectricitygeneratedfromrenewableenergyshould

    alsobe

    made

    eligible

    for

    REC

    mechanism

    because

    such

    self

    consumption

    actually

    replaces

    the

    demand from the grid power and the entity having such self consumption in effect incurs

    comparativelyhighercostsvisvisthecostofthepowerobtainedfromgrid.Itwas;however,

    felt that the cardinal principle that a renewable energy generator cannotparticipate in RECmechanism if it has availedpromotional benefits (preferential tariff in case of RE generators)shouldbeborne inmindwhileconsideringeligibilityforCPPs.Inotherwords,CPPsshouldalso

    beexcludedfromparticipatinginRECmechanismiftheyhaveavailedpromotional/concessional

    benefitsfromtheutilities.

    5. ToaddresstheseissuespertainingtotheeligibilityconditionsoftheRECRegulation,itwasproposedto amend the REC Regulation. The Commission vide its public notice No. L1/12/2010CERC

    Dated:27th

    August,2010 issueddraftCERC(TermsandConditionsforrecognitionand issuance

    of Renewable Energy Certificate for Renewable Energy Generation) (First Amendment)

    Regulations,2010andinvitedcommentsfromthevariousstakeholders.

    6. In the draft Regulation, the following provisos were proposed to be added at the end of theSubclause(c)ofClause(1)ofRegulation5oftheprincipalregulationsasunder:

    Provided that such a generating company having entered into a power purchase

    agreement for sale of electricity at a preferential tariff shall not, in case of

    premature termination of the agreement, be eligible for participating in the REC

    schemeforaperiodofthreeyearsfromthedateofterminationofsuchagreement

    ortillthescheduleddateofexpiryofpowerpurchaseagreementwhicheverisearlier

    ,ifanyorderorrulingisfoundtohavebeenpassedbyanAppropriateCommissionor

    acompetentcourtagainstthegeneratingcompanyformaterialbreachoftheterms

    andconditions

    of

    the

    said

    power

    purchase

    agreement.

    Provided further that aCaptive PowerProducer (CPP) based on renewableenergy

    sources shall beeligible for theentireenergygenerated fromsuchplant including

    selfconsumption forparticipating in theRECschemesubject to thecondition that

    such CPP has not availed or does not propose to avail any benefit in the form of

    concessional/promotionaltransmissionorwheelingcharges,bankingfacilitybenefit

    andwaiverofelectricitydutyetc.

    Provided

    also

    that

    if

    such

    a

    CPP

    forgoes

    on

    its

    own,

    the

    benefits

    of

    concessional

    transmission or wheeling charges, banking facility benefit and waiver of electricity

    duty etc., it shall become eligible for participating in the REC scheme only after a

    periodofthreeyearshaselapsedfromthedateofforgoingsuchbenefits.

    Provided also that the abovementioned condition for CPPs for participating in the

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    3/25

    7. Last date of submission of comments/suggestion was on 17th September, 2010. A statementindicating list of various stakeholders who have submitted their comments is enclosed in

    Annexure1.

    CONSIDERATION OF THE VIEWS OF THE STAKEHOLDERS AND ANALYSIS AND FINDINGS OF THE

    COMMISSIONONIMPORTANTISSUES

    8. TheCommissionconsideredthecommentsofthestakeholdersonthedraftamendmentregulations.The amendment regulations have been finalized after due consideration of the various issues

    raised. The examination of the major issues and findings of the Commission thereon are

    discussedin

    the

    subsequent

    paragraphs.

    Other

    comments

    of

    the

    stakeholders

    and

    observations

    thereonareenclosedasAnnexure2.

    PRELIMINARYOBJECTIONSTOTHEREGULATIONSANDFINDINGSOFTHECOMMISSION

    I. ValidityofPPAandEligibilityforREC:CommentsofStakeholdersIndianSugarMillsAssociationhasraisedtheconcernthatageneratorcouldbreachexistingPPAand

    enterRECmechanismwithsoleobjectiveofprofit ismisplaced.Association isoftheviewthat the

    profitpotential, ifany,underRECmechanism issame irrespectiveofwhetherthegeneratorcame

    intoitafterexistingPPAordonot havePPAtostartwith.Further,ifageneratorisreadytobearany

    contractual consequences of exiting PPA, it should not be debarred from REC mechanism. Some

    stakeholders (Indian Acrylics Limited etc.)have submitted that the RE generator having long term

    Power PurchaseAgreement (PPA) shouldalsobe madeeligible for REC mechanism,particularly in

    Biomass

    based

    power

    project

    due

    to

    unviable

    preferential

    tariff

    (lower

    than

    CERC

    determined

    tariff)

    andriseincostofbiomass.TVSEnergyLimitedhassubmittedthattheproposedamendmentshould

    not be made applicable upon termination of PPA by an RE Generators which commissioned their

    plantsafter1stApril,2010andentered intoPPAwithutilityatpreferentialrateduetoabsenceof

    RECRegulations.

    FindingsoftheCommissionTheCommissionhascarefullyconsideredthesecommentsanddecidedthatRECmechanismshould

    not

    encourage

    breach

    of

    existing

    contract.

    In

    fact,

    various

    deterrents

    have

    been

    provided

    in

    the

    amendment to dissuade perverse incentive to breach and dishonour the existing contract. The

    existingcontractentered intowithmutualconsentbytwopartiesatapointoftimebasedonthe

    prevailing terms and conditions should be honoured unless both the parties mutually agree to

    terminate the contract. The main objective of REC mechanism is to encourage new capacities

    addition.

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    4/25

    toclarify thathowtodealwiththesituationwheretheStateRegulationsareatvariancewiththe

    CERCRegulations.

    FindingsoftheCommissionTheCommissionhasnotedtheobservationandwouldliketoclarifythattheRECschemeasevolved

    clearlydemarcatestheresponsibilityofCERCandSERC in linewiththeprovisionsoftheElectricity

    Act,2003.Giventhe fact thatREC isanational level framework,jurisdiction in termsof eligibility

    criteria for participation in REC scheme, registration of RE generators, issuance of REC, and

    transactions in PXs etc., clearly vests with CERC. The role of SERC is in recognizing REC as a valid

    instrumentformeetingRPO.

    III. SwitchoverfromRECoptiononceexercisedCommentsofStakeholders

    GujaratEnergyTransmissionCorporationLtd(GETCO)submittedthattheoncetheoptionofREChas

    beenexercisedbyanREGenerator,itshouldnotbeallowedtoswitchoverforSaletoLicenseeorfor

    selfconsumptioninfuture.

    FindingsoftheCommissionTheCommission would like toclarify that the Regulationdoesntenvisage any restriction foraRE

    generator insofarasexerciseof itschoicetooptforRECschemeorpreferentialtariffatanytime

    during the life of the project is concerned. Whenever a generator opts for preferential applicable

    tariffasdeterminedbyAppropriateCommissionforsuchclassofgeneratorswillapply.

    IV. EligibilityofREgeneratorsupplying colocatedloadCommentsofStakeholders

    Thefollowingmajorcommentshavebeenreceivedfromthestakeholders:

    a. M/sGENSOLhasrequestedthatthe Commissionto clarifyeligibilityofnongrid interactiveREprojectsunderRECmechanismwhicharesellingpowerbythirdpartysalewithout injectingto

    thegrid.

    It

    has

    also

    been

    requested

    that

    the

    eligibility

    of

    off

    grid

    RE

    generator

    under

    REC

    scheme

    shouldbeclarified.

    b. AREgeneratorwhere its load iscolocatedwithgeneratingunitandnotavailingconcessionaltransmission/wheeling and banking facility on a part of energy utilized for self consumption

    shouldbeeligibleunderRECscheme. (SudhaAgroOilandChemicalIndustriesLimited)

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    5/25

    V. ConsequentialChangeCommentsofStakeholdersPOSOCOhasproposedtoamendsubRegulation4and7oftheRegulation7oftheRECRegulations

    that onDenominationandissuanceofCertificatesasunder:

    (4)TheCertificatesshallbeissuedtotheeligibleentityonthebasisoftheunitsof

    electricitygeneratedfromrenewableenergysourcesand injected intotheGridor

    deemed to be injected (in case of self consumption by eligible captive power

    producer),anddulyaccounted intheEnergyAccountingSystemasperthe Indian

    ElectricityGrid

    Code

    or

    the

    State

    Grid

    Code

    as

    the

    case

    may

    be,

    and

    the

    directions

    oftheauthoritiesconstitutedundertheActtooverseeschedulinganddispatchand

    energyaccounting,orbasedonwrittencommunicationofdistribution licenseeto

    the concerned State Load Dispatch Centre with regard to the energy input by

    renewableenergygeneratorswhicharenotcoveredundertheexistingscheduling

    anddispatchprocedures.

    (6) Each Certificate issued shall represent one Megawatt hour of electricity

    generatedfromrenewableenergysourceandinjectedordeemedtobeinjected(in

    caseof

    self

    consumption

    by

    eligible

    captive

    power

    producer)

    into

    the

    grid.

    FindingsoftheCommissionThe Commission has noted the suggestion and incorporated in the final amendment as a

    consequentialchange.

    VI. EligibilityofageneratorforactivitiesotherthanRECaftertermination:CommentsofStakeholdersM/s A to Z Group has requested to clarify as to whether after termination of an Agreement, the

    optionofpowersaleorselfconsumptionwouldbeavailableornot.

    FindingsoftheCommissionThe Commission would like to clarify that the generator will be governed in accordance with the

    relevant provisions of the Electricity Act, 2003 and the proposed amendment only deals with the

    limitedissueofeligibilityofaREgeneratorunderRECframework.

    VII Eligibility of CPP under REC framework:

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    6/25

    FindingsoftheCommissionTheCommissionwould liketoclarifythattheREProjectwhichhasoptedforselfconsumptionand

    sale

    of

    surplus

    power

    to

    distribution

    licensee,

    shall

    be

    eligible

    for

    REC

    in

    accordance

    with

    the

    eligibilitycriteriaasspecifiedintheprincipalRECRegulationandinthedraftamendmentofthesaid

    Regulations.Forexample, ifaCPPhasgenerationcapacityof10MWandhasentered intoPPAfor

    saleofonly4MWtolocalDISCOMatpreferentialtariff,itwillnotbeeligibleforRECforthis4MW.

    Itwill,however,beeligibleforRECforthebalance6MWsubjecttoitsfulfillmentofeligibilityasin

    theamendment.

    However, generation and self consumption in a CPP should be separately identifiable and have

    propermeteringsystemasmaybeapprovedbytheconcernedDISCOM/STUandStateAgencies.

    VIII. EligibilityofREgeneratorsellingpowertothirdparty:CommentsofStakeholders

    Someofthestakeholders(likeM/sBetawindFarm,M/sGammaGreenpowerandM/sClarionWind

    Farmhavesubmittedthatthough inTamilNadustatesaleofpowertothirdparty isnotpermitted

    but

    they

    under

    IPP

    status

    are

    supplying

    power

    to

    consumers

    in

    the

    market

    through

    a

    closed

    circuit

    mechanism under group captive scheme as recognized by TNEB. Such projects should be made

    eligibleforRECscheme.

    FindingsoftheCommissionTheCommissionwould liketoreiteratethataslongassuchgeneratorsarecomplyingtheeligibility

    criteriaasspecified intheprincipalRegulationsandamendmentRegulationstheywouldbeeligible

    fortheRECmechanism.

    IX. TreatmentofselfconsumptionbyCPPbasedonrenewable:

    CommentsofStakeholdersThefollowingcommentshavebeenreceivedfromthestakeholders:

    a. RECshouldnotbeissuedforenergywhichgoesintomeetingtheirownRenewablePurchaseObligation(RPO)obligations.(GujaratUrjaVikasNigamLtd,GETCO)

    b. CPPshouldbeeligibleforRECforwholegenerationandretainthenumberofRECsrequired

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    7/25

    for self consumption) would be eligible for REC. The consumption of CPP (which could include

    consumption of electricity generated from its own plant and/or the electricity supplied by the

    DISCOM) would be accounted for separately and RPO would be applicable as % of the energy

    equivalentto

    self

    consumption.

    The

    CPP

    can

    meet

    its

    RPO

    (part

    or

    full)

    out

    of

    the

    REC

    issued

    to

    it

    on

    account of the electricity generated from its plant. The commission is in agreement with the

    suggestion of IWPA that the CPP should be eligible for REC for whole generation and retain the

    numberofREC,srequiredforfulfillmentofhisownRPO.

    Forexample,aneligibleCPPbasedonnonsolarbasedrenewablesourcesgeneratesand inject110

    MWhduringthemonth.Therefore,itisentitledto110nonsolarRECs.Ittransmits/wheelsthesame

    generatedunitsthroughthetransmissionanddistributionsystemuptoitsmanufacturingunitforself

    consumption.Afterdeducting10%lossofthesystem,itgets100MWhfromrenewableenergy. His

    totalconsumption atmfg.unit is200 MWh. Itmeans that theunitpurchases100 MWh from the

    local distribution licensee at the appropriate tariff for category in which it belongs. On such

    consumption,noRPOisapplicable.However,onthebalance100MWhconsumedfromtheCPP,RPO

    isapplicable.Letusassume that theRPO fixedby theSERC for thatyear is6% including1%Solar

    RPO.

    Accordingly, such CPP consumer has to purchase nonsolar renewable energy or nonsolar REC

    equivalentto5MWhandalsohavetopurchase1MWhfromSolarbasedgenerationorSolarREC.

    CPPeligiblefor110nonsolarRECforwholegenerationmayretainthe5RECsrequiredforfulfillmentofhisownnonsolarRPOandpurchase1solarRECfromthepowerexchange.

    X. ConcessionalBenefitsFollowingcommentshavebeenreceivedfromthevariousstakeholders.

    CERC

    Jurisdiction

    a. It is beyond thejurisdiction of CERC to suggest that CPP is eligible for REC if they foregocertain benefit conferred by the State /ERCs and any changes to the availing of such

    concessioncanbemadeonlybytherespectiveauthorities.IfCERCdesiresthataCPPopting

    forRECshouldnotavailconcessionalchargesetc.,CERCcanadviseStateGovernment/SERC

    to incorporate the same in their Orders. Further, there is no procedures /process for

    voluntary withdrawal. (Chhattisgarh Biomass Energy Developers Associations, Emergent

    VenturesPvt.Limited)

    FindingsoftheCommissionThe Commission would like to clarify that the REC scheme as evolved clearly demarcates the

    responsibilitiesofCERCandSERCinlinewiththeprovisionsoftheElectricityAct,2003.Giventhe

    fact that REC is a national level framework, jurisdiction in terms of eligibility criteria for

    participation inRECscheme,registrationofREgenerators, issuanceofREC,andtransactions in

    PXs etc clearly vests with CERC The role of SERC is in recognizing REC as a valid instrument for

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    8/25

    FindingsoftheCommissionAccording to the Commission, It would not amount to Promissory Estoppels as it does not apply

    againstlegislative

    action.

    c. The word etc at the end of the first Para in this amendment to be deleted and specificbenefit to becovered for this purpose should be clearlyspecified.So thatmeaningof the

    provisionmaynotbeopentodifferentinterpretation.(KSKwindEnergyPrivateLimited)

    FindingsoftheCommissionThe

    Commission

    has

    considered

    the

    above

    suggestion

    and

    decided

    to

    delete

    the

    word

    etc.

    from

    thephraseconcessional/promotionaltransmissionorwheelingcharges,bankingfacilitybenefitand

    waiverofelectricitydutyetc.asproposedinthedraftamendmentRegulation.

    GBI/AD:PromotionalbenefitunderRECscheme?

    d. M/s IWPA, Karnataka Council has requested to clarify that whether GBI/AD also beconsideredaspromotionalbenefitandinvestorwhoavailedcannotgoforRECmechanism?

    FindingsoftheCommissionTheCommissionwouldliketoclarifythatGBI/ADwouldnotbeconsideredaspromotionalbenefitas

    faraseligibility forRECmechanism isconcernedbecausethesehavenotbeenobtainedfrom local

    licensees.

    DefinitionofConcessional/promotionaltransmissioncharges

    e. One of the stakeholder M/s A to Z Group suggested that the phraseConcessional/promotionaltransmissionchargesshouldbedefinedintheRegulations.

    FindingsoftheCommissionThe Commission would like to clarify that the expression Concessional/promotionaltransmission/wheeling charges in the amendment Regulation means levy of transmission/wheelingchargesataratelowerthantherateasapplicabletoanormalopenaccesscustomer.

    Restrictionof3yearspostforegoingofconcessionalbenefitsbyCPPs

    f. Eligibility of CPPs based on renewable fuels should be without the preconditions ofconcessionalwheeling,bankingandwaiverofelectricityDuty.Further,Thethreeyearsterm

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    9/25

    afterterminationforbeingeligibleunderRECframeworkiskept withtheintentionthatitwouldactasdeterrenttotheexistingCPPsgettingconcessionalbenefitsandREGeneratorsagainstsuchearlyterminationofPPA.Moreover,themainobjectiveofRECmechanism istoencouragenewcapacityadditioninREsegment.

    Bankingfacility

    CommentsofStakeholders g. CPPwhobanksomepercentageoftheirelectricityshouldbeallowedtoparticipate inREC

    mechanism

    or

    they

    should

    be

    allowed

    to

    avail

    REC

    to

    the

    extent

    of

    number

    of

    units

    that

    are

    notbanked.(GENSOL)

    h. AvailingBankingfacilityshouldnotbereasonfordisqualificationunderRECframework.(AtoZGroup,GujaratFlurochemicalsLimited)

    i. Banking permitted to day is account rather than a benefit as the banking is allowed onlyduringcertainhours&withdrawalofbankedpower isnotpermittedduringcertainhours.

    Furtherbankingchargesalsohavetobeborne.Thecostofbankedenergyismorethanthe

    costof

    power

    under

    open

    access.

    (Indian

    Sugar

    Mills

    Association)

    FindingsoftheCommissionTheCommissionwould liketomentionthatbanking facility isgenerallyextendedtotheplantasa

    whole as incentive. Therefore, the proposed amendment debars a CPP availing such incentive.

    BankingfacilityisgenerallyanadditionalincentiveavailabletothecaptiveREgeneratorespeciallyin

    caseswheretheREgeneratorgetsthebenefitofutilizingthebankedenergyatanytime(including

    peakhours)

    even

    when

    it

    has

    injected

    into

    grid

    during

    off

    peak

    hours.

    If

    banking

    was

    availed

    for

    a

    clearlyindentifiedpartcapacity,samewouldbeconsideredforineligibility.

    TheCommissionhasalsoclarifiedtheexpression banking in the finalamendmentto includeonly

    suchbanking facilitywherebythegeneratorgetsthebenefitofutilizingthebankedenergyatany

    time (including peak hours) even when it has injected into grid during offpeak hours. In other

    words,thebankingfacilitywhereintheCPPisentitledtodrawpowerfromtheutilitybasedonand

    correspondingtothetimeperiod(peakoroffpeakperiod)of injectionofpowerbysuchCPP,shall

    notbe

    considered

    as

    concessional

    /promotional

    benefit

    for

    the

    purpose

    of

    this

    regulation.

    9. We direct that the regulations published in draft form be published in the official Gazette afterincorporatingthechangesasdecidedintheforgoingparagraphs.

    Sd/ Sd/ Sd/ Sd/

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    10/25

    Annexure1

    Sr.

    No.

    NameofStakeholderssubmittedtheircomments

    1 ChhattisgarhBiomassEnergyDevelopersAssociations,

    2 GujaratUrjaVikasNigamLtd.(GUVNL)

    3 IndianWindPowerAssociation(IWPA)

    4 IndianWindPowerAssociation(IWPA),KarnatakaCouncil

    5 IndianWindEnergyAssociation(InWEA)

    6 SudhaAgroOilandChemicalIndustriesLimited

    7 REConnectEnergy

    8

    PriceWaterhouse

    Coopers

    (PWC)

    9 GujaratFlurochemicalsLtd.(GFL)

    10 GENSOL

    11 RanaSugarsLimited

    12 EmergentVenturesIndiaLimited

    13 SimranJeetSingh

    14 U.P.SugarMillsLimited

    15 AtoZGroup

    16 KSKwindEnergyPrivateLimited

    16 IndianAcrylicsLimited

    17 TVSEnergyLimited

    18 IndianSugarMillsAssociation

    19 BetawindFarm,

    20 GammaGreenpower

    21 ClarionWindFarm

    22 GujaratEnergyTransmissionCorporation(GETCO)

    23 PadmajaFinancial Services

    24

    IndependentPower

    Producers

    Association

    of

    India

    (IPPAI)

    25 IndianWindTurbineManufacturersAssociation(IWTMA)

    26 JKSugarLtd.

    27 GujaratElectricityRegulatoryCommission

    28 IndianEnergyExchange

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    11/25

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    12/25

    12

    AtoZGroup After termination of Agreement, whether power sell option or

    selfconsumptionoptionavailableornot?

    TheCommissionwouldliketoclarifythatthe

    generator will be governed in accordance

    withtherelevantprovisionsoftheElectricity

    Act,2003

    and

    the

    proposed

    amendment

    only

    dealswith the limited issueofeligibility ofa

    REgeneratorunderRECframework.

    B Variance in

    Regulation

    SERC and

    CERC on

    termination

    KSKwindEnergy

    PrivateLimited

    MERC in itsrelevant regulationspecified thatprior termination

    shall not entitle existing RE projects to participate in REC

    mechanism.CERCtoclarifythathow todealwith thesituation

    where the State Regulations are at variance with the CERC

    Regulations.

    The Commission has noted the observation

    andwouldliketoclarifythattheRECscheme

    as evolved clearly demarcates the

    responsibility of CERC and SERC in line with

    theprovisions

    of

    the

    Electricity

    Act,

    2003.

    Given the fact that REC is a national level

    framework,jurisdiction intermsofeligibility

    criteria for participation in REC scheme,

    registration of RE generators, issuance of

    REC,andtransactionsinPXsetc.,clearlyvests

    with

    CERC.

    The

    role

    of

    SERC

    is

    crucial

    in

    recognizing REC as a valid instrument for

    meetingRPO.

    C Sale ofpower

    tothirdparty

    M/s Beta wind

    Farm,

    M/s

    Gamma

    Greenpower

    M/s Clarion

    WindFarm

    InTamilNadustatesaleofpowertothirdpartyisnotpermitted.

    ObjectorsareREgeneratorsinIPPstatusandsupplyingpowerto

    consumers in the market through a closed circuit mechanism

    undergroupcaptiveschemeasrecognizedbyTNEB,shouldbe

    madeeligible

    for

    REC

    scheme.

    The eligibility criteria as specified in the

    principal REC Regulations as well as in the

    amendment Regulation required to be

    followed.

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    13/25

    13

    D 3 years lock

    period for

    PPA

    PWC The 3 years time lag should not be made applicable to RE

    generator who have to enter in to PPA at preferential tariff in

    the absence of state level REC regulatory framework and now

    willingto

    move

    to

    APPC

    based

    PPAs

    within

    3months

    of

    the

    state

    levelframework.

    REC mechanismcannot encouragebreachof

    existingcontract.

    The

    existing

    contract

    entered

    into

    with

    mutual consent by two parties at a point of

    time based on the prevailing terms and

    conditions should be honoured unless both

    the parties mutually agree to terminate the

    contract.

    The provision of three years term after

    termination

    for

    being

    eligible

    under

    REC

    framework iskeptwiththe intention that it

    would act as deterrent to the existing RE

    GeneratorsforsuchearlyterminationofPPA.

    Moreover, the major objective of REC

    mechanism is to encourage new capacity

    additioninREsegment.

    IWTMA ThreeyearsperiodmaybedetrimentaltoRECmechanismsince

    thereisexpectedtobeinitialshortfallofREsandifmarketdoes

    not take off due to lack of liquidity , no new plants will be

    commissionedunderRECmechanism.

    IWPA

    Periodof

    3years

    is

    too

    long

    and

    no

    justification

    given

    for

    such

    highperiod.Itshouldbereducedto6months.(IWPA)

    Rana Sugars

    Limited

    Eligibility of CPPs based on renewable fuels should be without

    thepreconditionsofconcessionalwheeling,bankingandwaiver

    ofelectricityDuty.Further,Thethreeyearstermfixedforbeing

    eligible to get REC is arbitrary and withoutjustification same

    shouldbewithdrawnforexistingCPPs.

    E CPPeligibility PWC Regulation5(1)ofprincipalRegulationproposedtobeamended

    to incorporatethatthesurpluspowerofCPPwillbeeligiblefor

    RECifsoldatAPPC.

    This aspect was already clarified in the

    statement of reasons while issuing Principal

    RECRegulations.

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    14/25

    14

    Indian Acrylics

    Limited

    CPP based on RE should not be denied eligibility for REC for

    entiregeneration ifonlypartof itsgeneration istiedup inPPA

    atpreferentialtariff.

    TheCommissionwouldliketoclarifythatthe

    RE Project which has opted for self

    consumption and sale of surplus power to

    distributionlicensee,

    shall

    be

    eligible

    for

    REC

    in accordance with the eligibility criteria as

    specified intheprincipalRECRegulationand

    in the draft amendment of the said

    Regulations.

    Forexample,ifaCPPhasgenerationcapacity

    of10MWandhasentered intoPPA forsale

    ofonly

    4MW

    to

    local

    DISCOM

    at

    preferential

    tariff, itwillnotbeeligible forREC forthis4

    MW. It will, however, be eligible for REC for

    thebalance6MWsubjectto itsfulfilmentof

    eligibilityasintheamendment.

    However,generationandselfconsumptionin

    a CPP should be separately identifiable and

    have

    proper

    metering

    system

    as

    may

    be

    approvedbytheconcernedDISCOM/STUand

    StateAgencies.

    IWPA,

    Karnataka

    Council

    WhetherCPPscanavailRECforgenerationoverandaboveself

    consumptionwithavailingconcessional/promotionalbenefitsor

    not?

    As per the proposed amendment a CPP

    availing concessional benefits shall not be

    eligibleforREC.

    IWPA,

    Karnataka

    Council

    CPPshould

    be

    eligible

    for

    REC

    for

    whole

    generation

    and

    retain

    thenumberofREC,srequiredforfulfilmentofhisownRPO.The

    Commission

    is

    in

    agreement

    with

    the

    suggestionofIWPA.

    Gujarat Urja

    VikasNigamLtd

    REC should not be issued for energy which goes into meeting

    theirownRenewablePurchaseObligation(RPO)obligations.

    The Commission would like to clarify that

    subject to the eligibility for participation

    under REC mechanism, REC would be issued

    on the electricity generated (including

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    15/25

    15

    CPPEligibility

    Gujarat Energy

    Transmission

    Corporation

    Limited(GETCO)

    clearly identifiable self consumption) and

    injectedintothegrid,whereasRPOwouldbe

    applicableonconsumptionofelectricity.As

    such,the

    entire

    generation

    from

    aCPP

    based

    on renewable (including generation used for

    self consumption) would be eligible for REC.

    TheconsumptionofCPP(whichcouldinclude

    consumptionofelectricitygeneratedfromits

    own plant and/or the electricity supplied by

    the DISCOM) would be accounted for

    separatelyandRPOwouldbeapplicableas%

    ofthe

    energy

    equivalent

    to

    self

    consumption.

    TheCPPcanmeetitsRPO(partorfull)outof

    the REC issued to it on account of the

    electricity generated from its plant. The

    commission is in agreement with the

    suggestion of IWPA that the CPP should be

    eligible

    for

    REC

    for

    whole

    generation

    and

    retain the number of REC,s required for

    fulfilmentofhisownRPO.

    GETCO TheOptionofREConceexercisedbyaREGeneratorshouldnot

    be allowed to switch over for Sell to Licensee or for self

    consumption in future. Rationale behind above suggestion is

    that according to GERC order prevailing preferential tariff is

    applicableto

    generator

    having

    commissioned

    new

    machine

    only.

    ThereforeonceRECexercised itwouldbedifficult forUtility to

    fixthetariffforsuchgenerator

    TheCommissionwouldliketoclarifythatthe

    Regulation doesnt envisage any restriction

    foraREgenerator inso farasexerciseof its

    choicetooptforRECschemeorpreferential

    tariffat

    any

    time

    during

    the

    life

    of

    the

    project

    isconcerned.

    Whenever a generator opts for preferential

    tariff, applicable tariff as determined by

    Appropriate Commission for such class of

    generatorswillapply.

    IWTMA Commission should also give the investors an option of an

    conditional switch back to preferential tariff in case they find

    RECunviablewithasimilar12yearwaitingperiod.

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    16/25

    16

    CPPEligibility

    GENSOL Clarify theeligibilityofanongrid interactiveREprojectsunder

    REC mechanism selling power by third party sale without

    injectingtothegrid.

    TheCommissionwouldliketoclarifythatthe

    existing REC regulation makes only grid

    connectedREgeneratoreligibleforREC.

    However, in future the Commission would

    explorethepossibilityof inclusionofoffgrid

    RE generators in the ambit of REC

    mechanism.

    Sudha

    Agro

    Oil

    and Chemical

    Industries

    Limited

    ARE

    generator

    where

    its

    load

    is

    co

    located

    with

    generating

    unit

    and not availing concessional transmission/wheeling and

    bankingfacilityonapartofenergyutilizedforselfconsumption

    shouldbeeligibleunderRECscheme.

    POSOCO POSOCOhasproposedtoamendsubRegulation4and7ofthe

    Regulation7oftheRECRegulationsthat onDenominationand

    issuanceof

    Certificates

    as

    under:

    (4)TheCertificatesshallbeissuedtotheeligibleentityonthe basis of the units of electricity generatedfrom renewableenergy sources and injected into the Grid or deemed to beinjected (incaseofselfconsumptionbyeligiblecaptivepowerproducer),anddulyaccounted intheEnergyAccountingSystemasperthe IndianElectricityGridCodeortheStateGridCodeasthecasemaybe,andthedirectionsoftheauthoritiesconstitutedunder theAct to oversee scheduling and dispatch and energyaccounting, or based on written communication of distributionlicenseetotheconcernedStateLoadDispatchCentrewithregardto the energy input by renewable energy generators which arenot covered under the existing scheduling and dispatchprocedures.

    (6) Each Certificate issued shall represent one Megawatthourofelectricitygeneratedfromrenewableenergysourceandinjectedordeemedtobe injected (incaseofselfconsumptionbyeligiblecaptivepowerproducer)intothegrid.

    The Commission has noted the suggestion

    andincorporatedinthefinalamendmentasa

    consequentialchange.

    IEX To create liquid market, the entry barriers for CPPs may be

    totally removed. If no adequate liquidity in the initial months,

    thenpricediscoverywillnotbeefficientandthemarketwillnot

    getconfidenceinthepricediscoveredontheexchanges.

    The Commission has already explained the

    rationalebehindtheproposedamendmentin

    theExplanatoryMemorandum.

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    17/25

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    18/25

    18

    G Existing CPP

    will flood the

    market

    Rana Sugars

    Limited

    IEX

    Reason given for denying RECs to existing CPPs that these will

    flood the market with low priced REC is also notjustified. This

    should lefttomarketforces.IftherearemoreRECsthenSERCs

    will

    raise

    RPO.

    Issuance

    and

    non

    issuance

    should

    be

    on

    soundenvironment and financial principle for maximizing green

    energy. Proposedqualifyingcriteriawilltendtodiscouragethe

    settingupofmoresuchplants.

    The Commission has already explained the

    rationalebehindtheproposedamendmentin

    theExplanatoryMemorandum.

    IEX Net benefit to the CPP has also to be compared with the risks

    being faced by CPP developer and financials of similar project

    developedasIPPandabintioeligibleforREC.Sudha Agro Oil

    and Chemical

    Industries

    Limited

    Excluding RE generator availing concessional benefit from REC

    mechanism tantamount to withdrawal of the promotional

    benefitoncegiventothem(PromissoryEstoppels).

    According to the Commission, It would not

    amount to Promissory Estoppels as it does

    notapplyagainstlegislativeaction.

    KSKwindEnergy

    PrivateLimited

    ThewordetcattheendofthefirstParainthisamendmentto

    be deleted and specific benefit to be covered for this purpose

    shouldbeclearlyspecified.Sothatmeaningoftheprovisionmay

    notbe

    open

    to

    different

    interpretation.

    The Commission agreed to delete the word

    etc.

    Rana Sugars

    Limited

    Duetomanifoldincreaseininputcostofbiomass, basedpower

    plantasagainstincreaseintariffislimitedto3to5%,itiswrong

    to presume that the CPPs have recovered their cost with

    concessionalwheelingbankingandwaiverofED.

    LikelyRECpricewillbemanytimesthenetvalueofconcession

    and denying REC to captive power plant due to these

    concessionswill

    be

    totally

    unjustified

    and

    discriminatory.

    Theassumptionsaremisplaced.

    H Concessional

    benefits

    PWC Draft Regulation 6 C: If any state Commission withdraws the

    concessions to existing CPPs than such CPP would be eligible

    under REC mechanism immediately and REC market will be

    floodedwithsuchplantsofferinglowpriceRECs. Withdrawalof

    concessionshouldbeexplainedinmoredetail.

    Theprovision intheproposedamendment is

    consideredadequate.

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    19/25

    19

    Concessional

    benefits

    Gujarat

    Electricity

    Regulatory

    Commission

    Suggestedtomakefollowingchangesinthethirdprovisoofthe

    proposeddraftamendment:

    ProvidedalsothatifsuchaCPPforgoesonitsown,the benefits of concessional transmission orwheeling charges, banking facility benefit andwaiver of electricity duty etc., and benefit availedare paid back to the licensee concerned, it shallbecomeeligibleforparticipating intheRECschemeonlyafteraperiodofthreeyearshaselapsedfromthedateofforgoingsuchbenefits.

    Rationalgiven

    is

    that

    the

    benefit

    availed

    by

    such

    CPPs

    were

    bornebytheotherconsumersofconcernedlicensee.

    The provision of three years term after

    foregoing the concessional/promotional

    benefits for being eligible under REC

    frameworkis

    considered

    adequate

    deterrent

    andalsotakescareoftheconcernraised.

    AtoZGroup

    Chhattisgarh

    Biomass Energy

    Developers

    Associations,

    Concessional/promotional transmission charges should be

    definedintheRegulations.

    In most of the states no concession is offered in transmission

    charges.Concessionalwheelingisapplicableonlytolessthan66

    kV.

    TheCommissionwouldliketoclarifythatthe

    expression Concessional/promotional

    transmission charges in the amendment

    Regulation means levy of transmission

    /wheeling charges at a rate lower than the

    rate

    as

    applicable

    to

    a

    normal

    open

    access

    customer.

    IWPA,

    Karnataka

    Council

    IWTMA

    IEX

    IWPA

    IWTMA

    What are benefits considered under the central and state

    concessional/promotionalbenefitsforRECscheme?

    Thetermslikeconcessional/promotionalwillneedbeexplicitly

    definedsotoavoiditopentovariousinterpretation.

    AsperCERCRegulationitisstatedthatnotransmissioncharges

    and losseshavetobepaidbysolargenerators inthiscasesolar

    captivepowerproducercannotgoforRECmechanism?

    The wheeling and banking should not be treated as

    concessional/promotionalbenefit

    Concessional benefits are clearly mentioned

    intheamendment.

    TheCommissionwouldliketoclarifythatthe

    sole purpose of benefit given to solar

    generators

    are

    only

    for

    limited

    projects

    coming under first phase of JNNSM scheme

    wherein NVVN is buying solar power and

    wouldbundlethesametosaletodistribution

    licensee.

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    20/25

    20

    KSKwindEnergy

    PrivateLimited

    IEX

    Will GBI/AD also be considered as promotional benefit and

    investorwhoavailedcannotgoforRECmechanism

    Generator

    having

    concessional

    benefits

    needs

    to

    be

    separatedfor the status of CPP and RE based. Amendment may be

    modified such that RE based CPPs need to forgo only such

    benefits/ concessions which are granted as RE benefits to be

    eligibletoparticipateintheRECscheme.

    It will be wrong to presume that the biomass captive power

    plants have recovered their cost with concessional wheeling,

    bankingand

    waiver

    of

    Electricity

    Duty.

    When a project is eligible for CDM benefits with these minor

    concessions,itshouldbeeligibleforRECaswell.

    The Commission would like to clarify that

    GBI/AD would not be considered as

    promotional benefit as far as eligibility for

    REC

    mechanism

    is

    concerned

    because

    thesehavenotbeenobtainedfromlocallicensees.

    I Banking

    facility

    Chhattisgarh

    Biomass Energy

    Devel. Asso.,

    Rana Sugars

    limited

    Emergent

    VenturesPvt.

    AtoZGroup,

    Gujarat

    Flurochemicals

    Bankingfacilityofferedisnotaconcessionatall.

    Concessionalbankingismisnomer.

    Such facilities given to RE generators are far less than what

    offeredtothermalpowerproducers.

    SameshouldbecontinuedwithoutlinkingwithRECeligibility.

    Availing Banking facility should not be reason for dis

    qualificationunderRECframework.

    The Commission would like to mention that

    banking facility is generally extended to the

    plantasawholeas incentive.Therefore,the

    proposed

    amendment

    debars

    a

    CPP

    availingsuchincentive.Bankingfacilityisgenerallyan

    additional incentive available to the captive

    REgeneratorespeciallyincaseswheretheRE

    generator gets the benefit of utilizing the

    banked energy at any time (including peak

    hours) even when it has injected into grid

    duringoffpeakhours. Ifbankingwasavailed

    for

    a

    clearly

    indentified

    part

    capacity,

    samewouldbeconsideredforineligibility.

    The Commission has also clarified the

    expression banking in the final amendment

    toincludeonlysuchbankingfacilitywhereby

    IPPAI Wind energy is infirm and thus it cannot function without the

    provision of banking. The condition prescribed can never be

    technically availed by a wind energy project and places such

    projectsatacleardisadvantage.

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    21/25

    21

    Indian Sugar

    Mills

    Association

    Bankingpermittedtodayisaccountratherthanabenefitasthe

    banking is allowed only during certain hours & withdrawal of

    banked power is not permitted during certain hours. Further

    banking

    charges

    also

    have

    to

    be

    borne.

    The

    cost

    of

    bankedenergyismorethanthecostofpowerunderopenaccess.

    thegeneratorgetsthebenefitofutilizingthe

    banked energy at any time (including peak

    hours) even when it has injected into grid

    during

    offpeak

    hours.

    In

    other

    words,

    the

    bankingfacilitywhereintheCPPisentitledto

    draw power from the utility based on and

    corresponding to the time period (peak or

    offpeakperiod)ofinjectionofpowerbysuch

    CPP,shallnotbeconsideredasconcessional/

    promotional benefit for the purpose of this

    regulation.

    U.P. Sugar Mills

    Limited

    JKSugarLtd.

    GENSOL

    Padmaja

    FinancialServices Pvt.

    Ltd.

    Banking as permitted today is a cost rather than a benefit

    therefore,bankingandwithdrawalofbankedenergyshouldnot

    betreatedasaconcessiontotheCogenerator.

    JK Sugar submitted that they banked 4.2% of electricity

    generated at the additional charge of 12.5% of electricity that

    they

    banked

    and

    also

    if

    the

    banked

    electricity

    is

    withdrawnbetween17:00and22:00hours,thesugarmillhastopayheavy

    peakhourcharges.

    CPP who bank some percentage of their electricity should be

    allowed to participate in REC mechanism or they should be

    allowed to avail REC to the extent of number of units that are

    notbanked.

    Banking is a facility required to regulate the imbalances in

    generation and consumption so banking charges shall be

    removedfromtheamendment.

    IWPA,

    Karnataka

    Council

    Wheeling and banking facility is provided by DISCOM after

    levyingcertaincharges(incashandkind)thereforeitshouldnot

    beconsideredasconcessionalbenefits.

    Theassumptionsaremisplaced.

    Sudha Agro Oil

    and

    Chemical

    Industries

    Limited

    Benefitbeingenjoyedbyusofconcessionalwheelingcharges is

    @26paise/unit

    (concessional

    and

    normal

    wheeling

    charges

    are

    8

    paiseand34paiseperunit.)asagainstaveragevalueofREC is

    270paise/unitandquantumofbankedenergy isvery lowand

    for that 2% charges we are Paying. Instead of completely

    eliminating existing RE generator from the preview of REC

    mechanism, they should allowed @ 80% of from REC

    mechanism.

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    22/25

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    23/25

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    24/25

    24

    P Miscellaneous Sudha Agro Oil

    and Chemical

    Industries

    Limited

    Whether Auxiliary Consumption energy will also be made

    eligible along with self consumption while calculating energy

    entitlementforgettingRECbenefit.

    The Commission would like to clarify that

    Auxiliary Consumption energy consumption

    of generator and same shall not be

    consideredfor

    REC.

    Only

    net

    energy

    shall

    be

    consideredforREC.RE Connect

    Energy

    ThebenefitofaccessingRECmarketsshouldalsobeavailableto

    those RE power producers who have a PPA under preferential

    tariff, to the extent of their selfconsumption/ auxiliary

    consumptionofREpower.

    PWC AmendmentshouldspecifythatwithinthreemonthsSERCsshall

    establish a framework to respond the request of existing CPPs

    whoarewillingtoforegoconcessions.Furthersuggestedthatin

    casesuch

    framework

    doesnt

    exist,

    CCPs

    should

    be

    given

    right

    to

    participateintheRECmarket.

    Theprovision intheproposedamendment is

    consideredadequate

    PWC Commission should address the issue of restriction in some

    statesonthirdpartysalethroughrenewabletechnologyhaving

    nonfirmpower.(PWC)

    This is beyond the scope of the present

    proposedamendmentintheRegulation.

    GFL Since, PLF of Wind Farm is in the range of 20 25% full

    transmissionchargesinRs./MW/Daywouldbeveryexpensive.

    Since it is under thejurisdiction of the State

    Electricity Regulatory Commission (SERC),

    above aspect can be settled by the

    developers

    with

    SERC

    only.

    For

    the

    purpose

    of this regulation Concessional/promotional

    transmissionorwheelingchargesmeans levyof transmission /wheeling charges at a rate

    lowerthantherateasapplicabletoanormal

    openaccesscustomer.

    IWTMA PLF of RE sources is very low comparative to conventional

    energy sources an because of inherent phenomenon, levying

    uniformwheeling

    charges

    will

    have

    higher

    impact

    on

    renewable

    energygenerators.

    Since it is under thejurisdiction of the State

    Electricity Regulatory Commission (SERC),

    above

    aspect

    can

    be

    settled

    by

    the

    developerswithSERConly.

    Suggestions are beyond the scope of the

    present proposed amendment in the

    Regulation.

    GFL Sell of Electricity component to other licensees should include

    distributionlicenseeofotherstates.

    GFL Quarterly RPO fulfillment by obligated entity should be

    incorporated.

    GENSOL Eligibilityof offgridRE generatorunderRECschemeshouldbe

  • 7/31/2019 Cerc Final Rec Ammendment 27-9-2010

    25/25

    25

    clarified.

    Rana Sugars

    Limited

    PPAofsugarmills inUPprovidesthat10%ofpowergenerated

    canbesoldthroughopenaccess. Sameshouldbe increasedto

    50%.Emergent

    Ventures India

    Limited

    Life time of REC needs to be increased to 2 3 years this will

    smoothen demand supply balance and create a long term

    marketforRECs

    Longevity of REC scheme: In the long run REC Should

    becomethesolebasisforREsupportreplacingtheFITscheme.

    This mechanism need to manage well to ensure FIT can be

    successfullyreplaced.

    Ensuringstable

    price:

    We

    need

    amarket

    mechanism

    for

    ensuring that the REC floor price is supported. This could be

    achieved by market maker entity run by CERC which buys and

    sellsRECs usingspecificfundallocatedbyGOI.andkeepprices

    atminimumlevel

    Simran Jeet

    Singh

    DecentralizedREplantsareconsideredunderRECmechanism