BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Project Proponent:
BONIFACIO WATER CORPORATION 31st Street, cor. 2nd Ave Bonifacio Global City, BGC Taguig City, Philippines
Project Preparer:
BROADFIELD Engineering Technologies and Integrated Services 4590A Guadal Canal St. Brgy. 587, Sta. Mesa Manila
Centralized sewage treatment plant facility
ENVIRONMENTAL COMPLIANCE
CERTIFICATE
(ECC) AMMENDMENT
PROJECT DESCRIPTION REPORT
50TH
Corner 31st
Street,Pamayanang Diego Silang, Ususan, Taguig City
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
PROJECT DESCRIPTION REPORT
CENTRALIZED SEAWAGE TREATMENT PLANT FACILITY
50TH Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City
BONIFACIO WATER CORPORATION
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
1. BASIC INFORMATION ON PROJECT AND PROPONENT
1.1 Brief Project Description
Table 1: Brief Project Description
Project Title CENTRALIZED SEWAGE TREATMENT PLANT FACILITY
Proponent BONIFACIO WATER CORPORATION
Project Location 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City
Nature of Project Sewage Treatment Plant Facility
Existing Area 23,126 M² / 2.3126Hectares
Gross Floor Area 23,126 M² / 2.3126Hectares
1.2 Proponent Profile
Table 2: Proponent Profile
Company BONIFACIO WATER CORPORATION.
Address 31st Street, cor. 2nd Ave Bonifacio Global City, BGC Taguig City, Philippines
Classification Corporation
SEC Reg. No. A199816979
Landline (632) 8183601 ext 2410
Contact Person/
Authorized
Representative
Allan N. Escobar / Resident Mechanical Engineer
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
1.3 Preparer
Table 3: Preparer
Company BROADFIELD Engineering Technologies &
Integrated Services
Business Address 4590A Guadal Canal St., Barangay 587, Sta. Mesa,
Manila
Contact Details (0917)5550624
Representative JAMES M. AQUENDE CE/EnSE
Designation General Manager
Email Address [email protected]
Details of Data and corresponding information will be discussed in the forgoing
report indicated herein.
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
2. BASIC DESCRIPTION
2.1 Project Information
Project Title CENTRALIZED SEWAGE TREATMENT PLANT FACILITY
Project Location 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City
Nature of Project Sewage Treatment Plant Facility
Existing ECC Number ECC-NCR-1502-0054
Existing Area 23,126 M² / 2.3126Hectares
Gross Floor Area 23,126 M² / 2.3126Hectares
Land Zoning Classification
Socialized Housing Zone
Project Geographical Coordinates:
Point 1:
Latitude: 14°31'29.47"N
Longitude: 121° 3'38.97"E
Point 2:
Latitude: 14°31'31.30"N
Longitude: 121° 3'43.91"E
Point 3:
Latitude: 14°31'20.54"N
Longitude: 121° 3'42.75"E
Components
BONIFACIO WATER CORPORATION is a domestic corporation engaged in the collection, purification of wastewater and distribution of potable water operated by Manila Water Company Inc . Bonifacio Water Corporation is undergoing a complete transformation for human and industrial effluents to be disposed of without danger to human health or unacceptable damage to the natural environment and potable water to its consumer.
BONIFACIO WATER CORPORATION is heavily investing in the
modernization and development of its facilities. Partnering with ARUP
and M.E Sicat Construction, the construction of a world-class
Centralized Sewage Treatment Plant Facility ensure BWC’s continued
ability to provide superior wastewater treatment.
BONIFACIO WATER CORPORATION was previously granted with
Environmental Compliance Certificate by Environmental Management
Bureau. Its existing facility is located at 50th Corner 31st
Street,Pamayanang Diego Silang, Ususan, Taguig City.
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
The firm then decided to Increase the capacity of sewage treatment
plant to cater the growing demand of their customers.
With this, the facility is on the process of amending its existing ECC to
include all the future development in compliance with Philippine
Environmental Impact Assessment (EIA) P.D. 1586.
The location of the project is primarily ideal since facilities discharging wastewater happen to be operating adjacent to the project site.
Waste Streams
Construction/ Development Phase
Dust, Smoke & Noise from Heavy equipment during expansion and
redevelopment of the Bonifacio Water Corporation facility
Domestic Wastewater from expansion and redevelopment of the
Bonifacio Water Corporation
Residuals/ Solid waste generation/ Debris
Scrap/ Reusable waste materials
Operational Phase
Dust, Smoke & Noise
Domestic Wastewater
Waste (Toxic and Hazardous Waste)
Residuals/ Solid waste generation/ Garbage
Scrap/ Reusable waste materials
Domestic Sludge from expansion and redevelopment of the
Bonifacio Water Corporation Septic Tank and waste water treatment
facility
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
BONIFACIO WATER CORPORATION STP
PROCESS FLOW CHART
L
TO EFFLUENT RIVER OUTFALL
SLUDGE CAKE FOR RECYCLING
TO SOLID WASTE DISPOSAL
FINE SCREENING
GRIT & GREASE REMOVAL
Removes Grits and Grease in Wastewater
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
Satellite View of the
Project Site
CENTRALIZED SEWAGE TREATMENT PLANT FACILITY BONIFACIO WATER CORPORATION
Figure 1: Satellite View of the Project Site
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
EXISTING FACILITY
CENTRALIZED SEWAGE TREATMENT PLANT FACILITY BONIFACIO WATER CORPORATION
Figure 2: Existing Facility
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
LOCATION MAP
CENTRALIZED SEWAGE TREATMENT PLANT FACILITY BONIFACIO WATER CORPORATION
Figure 3: Location Map
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
VICINITY MAP
CENTRALIZED SEWAGE TREATMENT PLANT FACILITY BONIFACIO WATER CORPORATION
Figure 4: Vicinity Map
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
SITE DEVELOPMENT
PLAN
CENTRALIZED SEWAGE TREATMENT PLANT FACILITY BONIFACIO WATER CORPORATION
Figure 5: Site Development Plan
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
Figure 6: Comparison of Existing and Proposed Project
NATIONAL CAPITAL
REGION LAND COVER MAP
CENTRALIZED SEWAGE TREATMENT PLANT FACILITY BONIFACIO WATER CORPORATION
Figure 7: NCR Land Cover Map
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
Satellite View of the Project
Impact Areas
Primary – 500 m.
Secondary – 1 km
CENTRALIZED SEWAGE TREATMENT PLANT FACILITY BONIFACIO WATER CORPORATION
Figure 8: Satellite View of the Project Impact Areas
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
ENVIRONMENTAL IMPACT STATEMENT (EIS) WORKSCOPE
1. Methodology for Data Gathering
Primary data (pertinent project information) has been provided by the project proponent while secondary data has been compiled by conducting researches on different government agencies and other resources available. Pertinent project information is gathered by the EIA Team including actual observation on the current operation of the project. In the preparation of this EIS study, both primary and secondary data were used.
2. Secondary Data Gathered & Sources
Secondary data were obtained through extensive research work with different agencies of the government & private including PAGASA, DENR-EMB, and the City Government of Taguig.
3. Primary/ Baseline Data
Primary data were obtained through actual site inspection and data provided by the project proponent. The following are the methodology used in gathering information and data about the environmental setting and receiving environment of the project site:
a. Survey/ ocular inspection of the project site and its surroundings were done to identify the
adjacent industries/ activities within the 100 meter radius and the receiving environment.
b. The proponent was interviewed regarding operation of the project and requested other information/ technical data to complete this study.
c. Conduct research to the different government agencies concerned such as the Department of Environment and Natural Resources/ EMB, CPDO of Taguig and other reference were also used to complete this EIS study.
The EIA process aims to prepare an EIS document and the following scope of work:
Prepare the description of the project;
Prepare a description of existing environmental profile of the project site;
Identify impacts in the activities/ operation of the project;
Evaluate environmental performances in the protection and mitigation measures to eliminate/ minimize adverse impacts of the project and the enhancement to maximize positive impacts; and
Evaluate performance in environmental management and monitoring.
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
General Approach
The EIA study involves four (4) distinct steps:
a. Scoping
The Consultant conducted a scoping meeting with the Proponent to identify environmental issues associated with the project. The project information will be collected and discussed with the Proponent to consider all environmental concerns and project requirements in data collection phase.
b. Data and Reports Collection Phase This involves the collection of primary data and other related secondary information that will be used for the performances evaluation of the past and present mitigation and enhancement measures to address adverse environment impact in the area and will be the key inputs to EIS. Data will be collected using standard methods.
c. Environmental Performances Assessment The impacts of the existing project activities to the environment will be assessed during the Environmental Performances Assessment. Both beneficial and adverse impacts of the project to the environment will be discussed and will assess the efficacy of the current environmental management measures to mitigate significant adverse impacts and enhancement measures.
d. Impact Management Plan The Impact Management Plan (IMP) will be established for the identified performance assessment. Environmental management will be integrated in the over-all project activities consisting of impact management plan, environmental monitoring plan and accountability framework.
Key Activities
The key activities to be conducted in accomplishing the objectives of the EIA study include the following tasks:
Task 1: Data Collection and Characterization of the Existing Environment
All available secondary data which are related to the project will be collected and reviewed. The base map illustrating the location of the project will serve as initial background information on the environmental situation of the existing project. This activity will also involve the characterization of the present environmental condition which will serve as the main input to the impact assessment and preparation of the impact management and monitoring plans.
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
Task 2: Impact Assessment
An essential starting point for proper environmental management of project activities is the fundamental knowledge of environmental consequences of such activities. These consequences can be categorized in terms of environmental pollution, environmental problems due to project location, environmental problems relating to planning and design of facilities and environmental problems relating to installation and operations and etc. Physical pollution problems are normally the negative effects of development projects. These problems stem from its physical properties, such as noise, smoke emissions, dust and suspended solids in water. Physical pollution is the most obvious negative environmental effect of industrial activities that may affect beneficial uses of the resource. Occupational health and safety planning is also of paramount importance in the installation and operation phase of the project.
Task 3: Environmental Management Plan
The environmental management plan (EMP) provides for various measures to ensure that the project will not cause undue adverse impacts on the environment and vice versa and truly contribute to social and economic development of the country. The EMP contains the following:
Impact Management Plan – Measures that would minimize, mitigate or compensate
the adverse impact of major significance and importance and enhance beneficial or positive impacts.
Environmental Monitoring Plan – Deals with monitoring of residual impacts, i.e., those impacts that could not be mitigated or reduced. Contains a discussion of the residual impacts predicted, indicators or parameters for these impacts, methodology for monitoring and guidelines for evaluation of these indicators or parameters.
Task 4: Preparation of the EIS Document
The results of the environmental site characterization, impact assessment and development of mitigating/ enhancement measures will be written into an EIS document. The EIS document will follow the outline prescribed in DENR-EMB’s Revised Procedural Manual (RPM) of Administrative Order (DAO) No. 2003-30 which includes the salient feature of evaluating the impacts of the existing project and considers the significant beneficial impact to the affected areas.
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
2.1 Public Participation
The proponent secured shall Barangay Clearance in accordance with the decision of the Barangay
Council and its constituents. This clearance shall be granted in favour of the proponents proposed
project and that there’s neither objection nor opposing party recorded upon the issuance of
aforementioned subject.
In addition, the project proponent will prepare materials such as brochures/leaflet containing
project description to inform the public on the nature of the on-going project. These materials will
be distributed in coordination with barangay officials and the proponent. An updated signage and
warning signs will be made visible around the project’s premises to inform the public, commuters
and transport groups on the status of the project before, during and after the construction. Traffic
advisory will also be disseminated by the proponent before the commencement of the project
construction, to warn the public possible traffic in the area and suggest alternate routes
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
1) Summary of Baseline Characterization Key Environmental Impacts and Management & Monitoring Plan and EMF & EGF Commitments Several baseline conditions have been considered in the formulation of the environmental management and monitoring plan. These are the following:
Table 4: Baseline Characterization
ECOSYSTEM ENVIRONMENTAL QUALITY STATUS
The Land
Land
The site is located in Barangay Ususan and is 700-meter West of the Taguig River a tributary of Pasig River , and North West of Laguna de Bay . According to Google Earth, the site has an elevation of about 7.62 meter above the ground Presently, the Land use classification of the project site is Specialized Zone based on the City Planning and Development office of Taguig City and with the Comprehensive Land Use Plan of the City of Taguig .The dominant establishments in the barangay include retail stores and groceries, from input stores, business and personal services. The project doesn’t alter the land classification of the area since the Bonifacio Water Corporation is classified as Socialized Housing Zone
The Water
Water Quality
The body of water near the project site is Taguig River East of the Site and on the Laguna de bay West. Significant impact on the quality of water near the project site which will be addressed by proper waste water management and treatment system. The proposed project will not contribute in the flooding of the Barangay because it will be constructed with well-engineered drainage system which will allow normal flow of flood/ storm water during rainy days. Bonifacio Water Corporation expected discharge will come from domestic sources only. However, the company will construct its own Sewage Treatment Plant (STP) to treat wastewater which will be discharge in Taguig River.
The Air
Air Quality
No major source emission within the area aside from the few vehicles passing along 50th street . For the proposed expansion project, projected impact on the quality of air will be mitigated by proper maintenance of generator set. Regular maintenance of clients vehicles and trucks within the project site shall also be required and monitored regularly Regular Emission testing and Ambient Air Monitoring be required to monitor the condition of the air quality within the project site.
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
ECOSYSTEM ENVIRONMENTAL QUALITY STATUS
Noise
DENR Standard for Noise Quality ranges from 50 to 75 dBa depending on the classification of the area. Typical sources of noise emission are the vehicles coming in and out of the facility. No major source of noise emitting equipment that will be used in project operation. Work hour during construction will be limited during the daytime.
The People
Employment
Bonifacio Water Corporation project enhances the waste management system in Taguig City. It will also contributes to the income of the city by paying regular taxes. The proponent also solve problem such as unemployment in the host area.
Tax Revenue Increase economic growth in local government of Taguig
Impacts Management Plan focuses on the identified and possible impacts of the project throughout its
implementation.
Impacts of the project will be mainly on:
1. Land
2. Water
3. Air
4. Socio – Economic
The impacts could be temporary or permanent, significant or not significant depending on the nature of the existing quality of receptors. Such impacts could include: high level of suspended particulates, noise associated with loading, unloading and drilling operations and negative aesthetic impacts. Project Impacts are classified into the three stages:
1. Pre-Construction Phase 2. Construction Phase 3. Operational Phase
Studies showed comparison between no–project and with project has formed a Summary matrix of Environmental Issues and Impacts, to enable the EIA team conclude and analyze environmental degradation and/or improvements. The analysis briefly presents the main environmental issues and possible impacts scenarios. Ratings of Impacts are qualitative only.
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared by: BROADFIELD Engineering Technologies & Integrated Services
SUMMARY OF MATRIX OF ENVIRONMENTAL ISSUES / IMPACTS Table 5: Summary Matrix of Environmental Issues/ Impacts
Phase Environmental Parameter Without Project
Scenario With Project
Scenario
Pre-Construction
Reliability of Water availability N N
Reliability of Water Quality M M
Land acquisition and resettlement N N
Disturbance of economic activities N N
Construction
Disturbance of land use N M
Loss of Natural Vegetation M M
Disturbance of stream channels, aquatic plant and animal habitats N M
Soil and Water Contamination N M
Hindrance (noise, air, traffic, etc) due to construction activities N N
Operation
Public Health N N
Sufficient Water Supply M M
Contamination of steam channels M M
Water Logging and Sanitation N M
Water supply competition M M
Legend: S – Significant Impact M – Moderate Impact N – No impact B – Beneficial
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Table 6: Summary Impact Management Plan
Project Phase / Environmental
Aspect
(Project Activity Which Will Likely
Impact the Environmental
Component)
Environmental
Component
Likely to be Affected
Potential Impact Option for Prevention or
mitigation or Enhancement Responsible Entity Cost
Guarantee / Financial
Arrangement
I. PRE-CONSTRUCTION &
CONSTRUCTION PHASE/
DEVELOPMENT PHASE
A. The land
Solid waste
generation
Designation of temporary storage area/ MRF prior to collection
Regular collection through a private garbage collector
Proponent/ Contractor P20T/ year Shall be included in the
TOR
Hazardous Waste
Generation
Designation of temporary storage area prior to collection
Registration from EMB as Hazardous & Toxic Waste Generator
Regular collection of an accredited hazardous waste hauler and treater
Proponent/ Contractor P20T/ year Shall be included in the
TOR
Soil contamination
due to oil or
lubricant spills
caused by heavy
equipment
Provide proper construction machines and vehicles and maintain them properly
Proponent/ Contractor Included on the
contractors fee
Shall be included in the
TOR
Soil erosion
Provide buffer zone between the construction site and the receiving body of water
Use silt fences and sediment traps, cover exposed earth especially
Proponent/ Contractor P100T/year Shall be included in the
TOR
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
before heavy rains are expected, benching cuts, use of sediment basins
Provision of surface water runoff drainage systems
Limit height of stockpile Follow schedule of
earthworks activities as recommended by professionals such as engineers and architects
B. The Air
Smoke emission
from vehicles Ensure proper
maintenance of vehicles Proponent/ Contractor P15T/ year
Shall be included in the
TOR
Noise pollution
Installation of control devices such as mufflers and noise suppressor to all construction equipment
Regular maintenance of heavy equipment construction machinery
Provision for temporary noise barriers particularly in noise sensitive areas in the immediate vicinity of the construction area
Proponent/ Contractor P15T/ year Shall be included in the
TOR
Dust generation
during construction
activities
Regular wetting of ground soil in the construction site
Regular preventive maintenance of heavy equipment and service vehicles
Construction site must be fenced for safety reason and security reasons.
Proponent/ Contractor P10T/ year Shall be included in the
TOR
Climate Change Flooding Improvement of current
drainages within the vicinity to be resilient to the effects
Proponent/ Contractor Included on the
contractors fee
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Increase in
structural fatigue
and materials failure
of climate change such as typhoon and flooding
Sufficient and effective drainage systems shall be incorporated in the design. The proponent shall coordinate with DPWH and LGUs how to integrated the drainage systems in to the existing canal/culverts
Consider design of building robust or resilient to the effect of climate change
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
C. The Water
Generation of
domestic
wastewater /
sewage
Provision for portable sanitary facilities (portalets) to collect dometic waste water which will be collected and disposed by accredited waste haulers
Proponent/ Contractor P15T/ year Shall be included in the
TOR
Flooding
Sufficient and effective drainage systems shall be incorporated in the design. The proponent shall coordinate with DPWH and LGUs how to integrated the drainage systems in to the existing canal/culverts
Proponent/ Contractor Included on the
contractors fee
Siltation
Provide buffer zone between the construction site and the receiving body of water
Regular hauling of construction debris such as excess sand and cement
Implementation of appropriate erosion control measures particularly during rainy season
Proponent/ Contractor P100T/year
D. The People
Occupational health
and safety
Proper orientation during pre-employment
Enforce wearing of appropriate working attire
Provision for PPE
Proponent/ Contractor P20T/ year Shall be included in the
TOR
Fire and natural
hazards
Fire extinguishers are strategically located throughout the facility.
Formulation of Emergency Preparedness and Response Program.
Proponent/ Contractor P15T/ year Shall be included in the
TOR
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Sanitation Enforce wearing of
appropriate working attire Regular housekeeping
Proponent/ Contractor P10T/ year Shall be included in the
TOR
Employment Priority given to qualified local residents
Proponent/ Contractor Shall be included in the
TOR
Traffic
Limit delivery of materials during night time
Provide security guard to assist traffic flow during construction
Strict implementation of traffic management plan
Proponent/ Contractor P15/month Shall be included in the
TOR
III. OPERATION PHASE A. The land
Solid waste generation Proper storage to the allotted
area/MRF prior to collection Regular collection through City
Garbage collector
Proponent/
Management P20T/ year
Included in the operational
cost
Residual wastes
generation and Scrap
materials
Regular collection through City Garbage collector
Collection/ buying of scrap/ reusable materials by Scrap trading company
Proponent/
Management P20T/ year
Included in the operational
cost
Toxic and Hazardous
Waste
Registration from EMB as toxic and hazardous waste generator
Collection of waste and stored temporarily in a designated storage to be treated by accredited third party hazwaste hauler and treater
Proponent/
Management
Accredited Third party
Haz Waste hauler and
Treater
P20T/ year
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
B. The Air Air pollution emissions
Application for Permit to Operate for APS/CF
Clients/ Visitor’s vehicles not under the control of the proponent
Ensure proper maintenance standby generator set
Public announcement of keeping your vehicles running in good condition to avoid emission of harmful smoke.
Proponent/
Management
Included in the operational
cost
C. Climate Change
Flooding
Increase in
structural fatigue
and materials failure
Maintenance of current drainages within the vicinity to be resilient to the effects of climate change such as typhoon and flooding
Regular checkup and maintenance of building structure
Proponent/ Contractor Included on the
contractors fee
Included in the operational
cost
D. The Water Generation of
domestic wastewater Securing Discharge Permit
from EMB Provision for STP/WTP
Proponent/
Management
Included in the operational
cost
E. The People Solid waste generation Proper storage to the allotted
area/MRF prior to collection Regular collection through City
Garbage collector
Proponent/
Management
Included in the operational
cost
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Residual wastes
generation and Scrap
materials
Regular collection through City Garbage collector
Collection/ buying of scrap/ reusable materials by Scrap trading company
Proponent/
Management
Included in the operational
cost
Employment Priority given to qualified local residents
Proponent/
Management
Included in the operational
cost
Traffic
Provide security personnel assisting vehicles going in and out the building
Provide enough parking to avoid cars parking on Radial Road 10
Proper implementation of Traffic Management Plan
Designate loading and unloading area for commuters.
Proponent/
Management P20T/month
Included in the operational
cost
IV. ABANDONMENT PHASE
A. The land Solid waste
generation
Proper storage to the allotted area
Regular collection through a private garbage collector contracted by the company
Management Unable to
determine yet
Will be included in the
contractor’s scope of work
B. The Water Debris Ensure that debris are
confined within the site All workers involved shall
be provided with PPEs
Management Unable to
determine yet
Will be included in the
contractor’s scope of work
C. The Air
Generation of
domestic
wastewater
Coursed through the existing WTP
Management Unable to
determine yet
Will be included in the
contractor’s scope of work
D. The People Unemployment Compensate based on
tenure Referral and endorsement
based on performance
HRD / Management Unable to
determine yet
Will be included in the
contractor’s scope of work
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Table 7: Summary Environmental Monitoring Plan
Key Environmental
Aspects per Project
Phase
Potential
Impacts Per
Env’tl Sector
Parameter to
be Monitored
Sampling & Measurement Plan
Lead
Person
Annual
Estimate
d Cost
EQPL MANAGEMENT SCHEME
Method Frequency Location EQPL RANGE
MANAGEMENT
MEASURE
Alert Action Limit Alert Action Limit
I. CONSTRUCTION
PHASE/
DEVELOPMENT
PHASE
A. The land Solid waste
generation Weighing Daily
Storage Area
within the
project site
Proponent P10T/
month
uncollected
within a day
uncollected
within 2 days
Uncollected
within a week
provide
temporary
storage
area
Coordinate
with local
hauling
collector for
regular
hauling
Buy own hauling
equipment to
transfer waste to
temporary
dumping site
B. The Air
Smoke emission
from Generator
(CO, NO x)
Emission
testing Annually
Within the
Project site Proponent P15T/ year
NOx = 1,200
mg/NCM
CO = 300
mg/NCM
NOx = 1,600
mg/NCM
CO = 400
mg/NCM
NOx = 2,000
mg/NCM
CO = 500
mg/NCM
Regular
maintenanc
e of genset
Check-up &
replacement
of defective
parts
Complete repair of
the unit and
consider buying a
replacement
Dust generation
during
construction/
Development
activities
Visual Daily Within the
Project site Proponent P10T/ year
Within the
project site
Outside the
project site
Neighboring
establishmen
t/ residents
continuous
wetting
Provide net
buffer zone for
dust
generation
Buy dust collection
system
C. The
People
And Water
Solid waste
generation Weighing Daily
Within the
Project site Proponent
P10T/
month
uncollected
within a day
uncollected
within 2 days
Uncollected
within a week
provide
temporary
storage
area
Coordinate
with local
hauling
collector for
regular
hauling
Buy own hauling
equipment to
transfer waste to
temporary
dumping site
Generation of
domestic
wastewater /
sewage
Grab
sampling Semi annual
Within the
Project site Proponent P20T/ year
BOD =
30mg/L
COD =
60mg-O2/L
TSS =42mg/L
O&G =
3.0mg/L
pH =7 & 8.5
Color =90CU
Coliforn
=6,000
BOD =
40mg/L
COD =
80mg-O2/L
TSS =56mg/L
O&G =
4.0mg/L
pH =6.8& 8.8
Color =120CU
Coliforn
=8,000
BOD =
50mg/L
COD = 100mg-O2/L
TSS
=70mg/L
O&G =
5.0mg/L
pH =6.5& 9.0
Color
=150CU
Coliforn
=10,000
Regular
maintenanc
e of STP
Check-up &
replacement
of defective
parts
Increase capacity
or consider
redesign of the
STP
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
II. OPERATION PHASE
A. The Land
Solid waste
generation Weighing Daily
Storage Area
within the
project site
Proponent P20T/ year uncollected
within a day
uncollected
within 2 days
Uncollected
within a week
provide
temporary
storage
area
Coordinate
with local
hauling
collector for
regular
hauling
Buy own hauling
equipment to
transfer waste to
temporary
dumping site
Toxic and
Hazardous
Waste
Collection
of waste
and stored
temporarily
in a
designated
storage to
be treated
by
accredited
3rd party
hazwaste
treater
quarterly
Storage Area
within the
project site
Proponent P50T/ year Uncollected
monthly
Uncollected
quarterly
Uncollected
within a year
provide
temporary
storage
area
Coordinate
with
accredited 3rd
party haz
waste hauler
Change or get
another qualified
and responsible 3rd
party hauler
B. The Air
Air pollution
emissions/
Smoke emission
from genset
(CO, NO x)
emission
testing Annually
Within the
Project site Proponent P20T/ year
NOx = 1,200
mg/NCM
CO = 300
mg/NCM
NOx = 1,600
mg/NCM
CO = 400
mg/NCM
NOx = 2,000
mg/NCM
CO = 500
mg/NCM
Regular
maintenanc
e of genset
Check-up &
replacement
of defective
parts
Complete repair of
the unit and
consider buying a
replacement
C. The
Water
Generation of
domestic
wastewater/
sewage
(Ph, BOD, COD,
TSS, Coliform &
Color)
Grab
Sampling Quarterly
Within the
Project site Proponent
P15T/
month
BOD =
30mg/L
COD =
60mg-O2/L
TSS =42mg/L
O&G =
3.0mg/L
pH =7 & 8.5
Color =90CU
Coliforn
=6,000
BOD =
40mg/L
COD =
80mg-O2/L
TSS =56mg/L
O&G =
4.0mg/L
pH =6.8& 8.8
Color =120CU
Coliforn
=8,000
BOD =
50mg/L
COD = 100mg-O2/L
TSS
=70mg/L
O&G =
5.0mg/L
pH =6.5& 9.0
Color
=150CU
Coliforn
=10,000
Regular
maintenanc
e of STP
Check-up &
replacement
of defective
parts
Increase capacity
or consider
redesign of the
STP
D. The
People
Solid waste
generation Weighing Daily
Storage Area
within the
project site
Proponent P20T/ year uncollected
within a day
uncollected
within 2 days
Uncollected
within a week
provide
temporary
storage
area
Coordinate
with local
hauling
collector for
regular
hauling
Buy own hauling
equipment to
transfer waste to
temporary
dumping site
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Generation of
domestic
wastewater/
sewage
Grab
Sampling
Quarterly Within the
Project site Proponent
P20T/
month
BOD =
30mg/L
COD =
60mg-O2/L
TSS =42mg/L
O&G =
3.0mg/L
pH =7 & 8.5
Color =90CU
Coliforn
=6,000
BOD =
40mg/L
COD =
80mg-O2/L
TSS =56mg/L
O&G =
4.0mg/L
pH =6.8& 8.8
Color =120CU
Coliforn
=8,000
BOD =
50mg/L
COD = 100mg-O2/L
TSS
=70mg/L
O&G =
5.0mg/L
pH =6.5& 9.0
Color
=150CU
Coliforn
=10,000
Regular
maintenanc
e of STP
Check-up &
replacement
of defective
parts
Increase capacity
or consider
redesign of the
STP
III. ABANDONMENT
PHASE
A. The land Solid waste
generation Weighing Daily
Collection by
Third party
hauler
Proponent Included in the abandonment program and will apply for separate ECC for the implementation of the abandonment program.
B. The
Water Debris Weighing Daily
Collection by
Third party
hauler
Proponent Included in the abandonment program and will apply for separate ECC for the implementation of the abandonment program.
C. The Air Generation of
domestic
wastewater
Grab
Sampling Quarterly
Collection by
Third party
hauler
Proponent
Included in the abandonment program during and will apply for separate ECC for the implementation of the abandonment
program.
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Social Development Program (SDP)
Concern
Responsible
Community Member/
Beneficiary
Government Agency /Non-
government Agency and
Services
Proponent Indicative
Timeline Source of Fund
1. Health and Safety
Blood Drive/Donation
Donation of Medicine
Relief good for calamity victims
Barangay Chairman and
Kagawad for Health
-Project Affected
Community
-City Health Office
-Barangay health Centers
-Barangay Disaster Management
Community
Relations Officer
-Pre-construction
-Construction
-Operation
LGU Health Office/
Proponent
2. Education and Recreation
Book Drive
Barangay Kagawad for
Education
-Project Affected Families
-DepED Community
Relations Officer
-Pre-construction
-Construction
-Operation
LGU TESDA/
Proponent
3. Environment and Sanitation
Barangay Clean Up
Cleaning of Estero
Tree Planting
Barangay Kagawad for
Environment
-Project Affected
Community
-CENRO
-CHO
Community
Relations Officer
-Pre-construction
-Construction
-Operation
LGU CENRO/
Proponent
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Information, Education and Communication (IEC) Plan
Target Sector Identified as Needing Project IEC
Major Topic/s of concern in Relation to
Project
IEC Scheme/ Strategy/ Method
Information Medium Indicative Timeline
and Frequency Indicative Cost
1. LGU/ Barangay Presentation of
Project Description Technical Meeting
Project Description
Report (Ring Bind)
Before Construction
During Construction
Operation
P50,000.00
2. Construction Worker Presentation of
EMP/IMP/DRRMP Technical Meeting
Structural and
Architectural Plans
Before Construction
During Construction P50,000.00
3. Building Tenants and Employees
Presentation of EMP/IMP/
DRRMP/TMP
Public Information
Campaign
Flyer/ Project
Information Sheet Operation P50,000.00
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
Prepared By:
JEFFREY TORRES
Consultant IPCO-221
BROADFIELD Engineering Technologies
And Integrated Services
JAMES M. AQUENDE CE/EnSE
General Manager/ Consultant IPCO-220
BROADFIELD Engineering Technologies
And Integrated Services
BONIFACIO WATER CORPORATION. – CENTRALIZED SEWAGE TREATMENT FACILITY 50th Corner 31st Street,Pamayanang Diego Silang, Ususan, Taguig City Project Description Report
ANNEX Information and Education Campaign Report