central ephrata substation incident root cause analysis

30
Central Ephrata Substation Incident Root Cause Analysis Results May 2, 2017 Ty Ehrman Jeff Shupe Angel Barahona-Sanchez Darrell Hahn

Upload: others

Post on 07-Apr-2022

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Central Ephrata Substation Incident Root Cause Analysis

Central Ephrata Substation IncidentRoot Cause Analysis Results

May 2, 2017

Ty EhrmanJeff ShupeAngel Barahona-SanchezDarrell Hahn

Page 2: Central Ephrata Substation Incident Root Cause Analysis

Roadmap• Discuss the event• Introduce the investigative team• Describe the distribution system: how should it have worked vs. how

did it work• Damage and safety potential• What else happened and contributed to the problem• Root cause• How to keep it from happening again• Major conclusions and take-aways

Page 3: Central Ephrata Substation Incident Root Cause Analysis

Event and Response• February 15, 2017 – 3 minute electrical fault occurred in the

distribution lines fed by, and near, the Central Ephrata Substation

• Root cause analysis was performed

• Corrective actions have been identified to prevent recurrence

Page 4: Central Ephrata Substation Incident Root Cause Analysis

Root Cause Analysis Team• Root Cause Analysis (“RCA”) requested by Executive Management

• A diverse team of District employees was formed: – Ty Ehrman– Jeff Shupe– Angel Barahona-Sanchez– Scott Smith– Darrell Hahn– Randy Hovland– LeRoy Patterson– Karrie Buescher

• Contracted with Pilot Advisors, Andrew Bielat, to provide RCA expertise

Page 5: Central Ephrata Substation Incident Root Cause Analysis

RCA Process

• The RCA team conducted interviews with employees and witnesses from the public

• A third-party contractor was retained by the District to provide failure mode testing

• A formal RCA methodology was applied and followed

Page 6: Central Ephrata Substation Incident Root Cause Analysis

Central Ephrata Substation Layout

This design is similar to many other existing District distribution substations.

Page 7: Central Ephrata Substation Incident Root Cause Analysis

How the Substation Protection Works

• Fault is detected by relays• Circuit breaker operates

Page 8: Central Ephrata Substation Incident Root Cause Analysis

How the Substation Protection Works

• Fault is detected by relays• Circuit breaker operates• If the fault is still present, the circuit breaker operates to lock-out, clearing

the fault

Page 9: Central Ephrata Substation Incident Root Cause Analysis

How the Substation Protection Works

• If the fault is still present during a breaker failure scenario, the second layer of protection operates

Page 10: Central Ephrata Substation Incident Root Cause Analysis

How the Substation Protection Works

• If the fault is still present during a breaker failure scenario, the second layer of protection operates

• The circuit switcher operates, extinguishing the fault

Page 11: Central Ephrata Substation Incident Root Cause Analysis

How the Central Ephrata Substation Protection System Failed to Operate Correctly

• Fault is detected by relays• Circuit breaker operates opens and closes once• Circuit breaker fails to open again• Fault continues for approximately three minutes, until the

transmission protection system clears the fault

Page 12: Central Ephrata Substation Incident Root Cause Analysis

Consequences

• Safety– On the distribution line: arcing lines burned and came down, presenting a hazard

to the public– Substation: If occupied, employees could have been severely injured

• Disruption to service and damage to customer equipment and property

– Outage affecting up to 8,000 customers in the Ephrata, Quincy, and Soap Lake areas

• Estimated cost to repair District damages: $4.5 – $7.5M

Page 13: Central Ephrata Substation Incident Root Cause Analysis

Original Fault

Page 14: Central Ephrata Substation Incident Root Cause Analysis

Original Fault Location

Page 15: Central Ephrata Substation Incident Root Cause Analysis

Damage to Switchgear

Damage to Truck Near Switchgear

Page 16: Central Ephrata Substation Incident Root Cause Analysis

Damage to Main & Auxiliary Bus

Page 17: Central Ephrata Substation Incident Root Cause Analysis

Damage to CE6 Breaker

Page 18: Central Ephrata Substation Incident Root Cause Analysis

Damage to Transformer

Page 19: Central Ephrata Substation Incident Root Cause Analysis

Damage to Facilities Building

Page 20: Central Ephrata Substation Incident Root Cause Analysis

Central Ephrata Substation DC Battery System

• Purpose: operate the protection systems within the substation• The battery charger helps maintain the battery bank at full charge

and ensure operation during loss of A/C

Page 21: Central Ephrata Substation Incident Root Cause Analysis

Battery Transfer Switch

Interior of Battery Transfer Switch

Page 22: Central Ephrata Substation Incident Root Cause Analysis

1986

Substation Commissioned

2005

Battery TransferSwitch Installed

InadequateDesign Review

For AddedRisk

Safety of Maintenance

“Battery Transfer Switch” Event

SuspectedDistribution

Breaker Failed toOperate

TransmissionBreaker Prevented

More Damage

Suspected Loss of Control Of DC Supply

2013

Replace Battery Transfer Switch

Single-point Failure Known

InadequateMonitoring

Known

2013

RCA Initiated

Unfinished RCA

InadequateCorrective ActionProgram/Preventive Action

CE 6 Protection

FailureFebruary 15, 2017

CE6 Protection

Failure

Battery TransferSwitch “OFF”

Loss of Control of DC Power

Human Error

Establishment of Control of Critical

SystemsInadequate

Establishment of Control of Critical

Systems

/

November 16,2013 February 15, 2017

Inadequate Work/Configuration

Control

Original Design

:InadequatePositive Control

InadequateMod/ Design

Program

Page 23: Central Ephrata Substation Incident Root Cause Analysis

Root Cause

The failure of executive management to establish control

of critical systems

Page 24: Central Ephrata Substation Incident Root Cause Analysis

Corrective Action 1

• Establish and manage a “critical systems” program that includes:

1. Identifying the criticality of systems with respect to safety and asset protection;

2. Establishing appropriate levels of criticality;

3. Establishing and verifying appropriate programmatic control based upon the level of criticality.

Page 25: Central Ephrata Substation Incident Root Cause Analysis

Corrective Action 2• Establish a Programmatic Approach to Operations

A. Programmatically manage the mission-critical business functions, including the critical systems program recommended in Corrective Action 1.

B. Evaluate the processes/programs that should have prevented this event and other unwanted events. Executive level responsibility should include necessary elements of:

I. SafetyII. Risk ManagementIII. Design/Design ModificationsIV. Corrective ActionsV. Work/Configuration ControlVI. Craft Certification and System Training

Page 26: Central Ephrata Substation Incident Root Cause Analysis

Corrective Action 3

• Establish ownership to enhance the awareness and control of critical areas and events

Commonly accepted industrial practice to improve safety, reliability, and performance of equipment and systems is to establish singular authority and ownership of area, systems, and activities.

Page 27: Central Ephrata Substation Incident Root Cause Analysis

Corrective Action 4

• Implementation Team

Establish a cross-disciplinary Implementation Team with the responsibility and authority to ensure the successful implementation of the actions included in the previous three slides.

Page 28: Central Ephrata Substation Incident Root Cause Analysis

Compensatory Actions (Short-Term)• Ensure safe operations of substations

A. Establish entry protocol; B. Improve control of safety zones outside the substations related

to shock risk; C. Create a plan to evaluate integrity and adequacy of existing

substation ground grids.

• DC Power ControlA. Establish positive control of the DC power systems; B. Multidisciplinary review of any design changes or modification.

Page 29: Central Ephrata Substation Incident Root Cause Analysis

Conclusion• Past practice shows that safety is not the primary consideration in

design and operations.– Have made progress on improving safety culture– Safety culture is not yet where it needs to be

• A programmatic approach to define and control the most important elements of safe, effective operations is needed.

• Root cause responsibility has been placed at a high level, but for culture change to take place and a new programmatic approach to be effective, support is needed at all levels of the organization.

Page 30: Central Ephrata Substation Incident Root Cause Analysis

Thank you.Questions?