cementing a new · the plant had installed air cannons supplied by 3 different vendors to fight...

2
CASE STUDY CEMENTING A NEW STANDARD OF CLEANING IN A STICKY SITUATION PROBLEM Sticky material fell into the chute in large chunks, blocking the chute. Oftentimes, the plant was forced to stop production and clean this chute every 5 hours. An average of 900 tons of production was lost per day equating to a $54,000 daily loss. SOLUTION As a result of the IGS Big Blue Air Cannon installation, manual cleaning was no longer necessary. The plant is now evaluating further areas, where build up is a problem, for additional air cannon upgrades. Problem | The Failed Trio A cement plant in the Caribbean was experiencing issues in their raw material chute. Buildup occurred in the entire chute, but the principal problem was near the top. Sticky material fell into the chute in large chunks, blocking the chute. The plant had installed air cannons supplied by 3 different vendors to fight this problem. Unfortunately, the air cannons were unable to shift the buildup, requiring manual clean-up. Oftentimes, the plant was forced to stop production and clean this chute every 5 hours. An average of 900 tons of production was lost per day equating to a $54,000 daily loss. Evaluating Alternatives Jeff Shelton, IGS air cannon innovations pioneer, has commented: “Little has changed in the air cannon market over the last two decades, in terms of design of the cannon and its components. All the while, cement industry has continued to innovate, creating new maintenance challenges. It was time that the air cannon technology caught up with the industry.” The plant was made aware of the IGS Big Blue air cannons. Widespread in the Power industry, yet relatively new to Cement. IGS have performed several improvements to the conventional air cannon component designs and cleaning power. integratedglobal.com

Upload: others

Post on 06-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CEMENTING A NEW · The plant had installed air cannons supplied by 3 different vendors to fight this problem. Unfortunately, the air cannons were unable to shift the buildup, requiring

CASE STUDY

CEMENTING A NEW STANDARD OF CLEANING IN A STICKY SITUATION

PROBLEM

Sticky material fell into the chute in large chunks, blocking the chute. Oftentimes,

the plant was forced to stop production and clean this chute every 5 hours. An average of 900 tons of production was lost per day

equating to a $54,000 daily loss.

SOLUTION

As a result of the IGS Big Blue Air Cannon installation, manual cleaning was no longer

necessary. The plant is now evaluating further areas, where build up is a problem, for

additional air cannon upgrades.

Problem | The Failed TrioA cement plant in the Caribbean was experiencing issues in

their raw material chute. Buildup occurred in the entire chute,

but the principal problem was near the top. Sticky material fell

into the chute in large chunks, blocking the chute.

The plant had installed air cannons supplied by 3 different

vendors to fight this problem. Unfortunately, the air cannons

were unable to shift the buildup, requiring manual clean-up.

Oftentimes, the plant was forced to stop production and clean

this chute every 5 hours. An average of 900 tons of production

was lost per day equating to a $54,000 daily loss.

Evaluating AlternativesJeff Shelton, IGS air cannon innovations pioneer, has

commented: “Little has changed in the air cannon market over

the last two decades, in terms of design of the cannon and its

components. All the while, cement industry has continued to

innovate, creating new maintenance challenges. It was time that

the air cannon technology caught up with the industry.”

The plant was made aware of the IGS Big Blue air cannons.

Widespread in the Power industry, yet relatively new to Cement.

IGS have performed several improvements to the conventional

air cannon component designs and cleaning power.

integratedglobal.com

Page 2: CEMENTING A NEW · The plant had installed air cannons supplied by 3 different vendors to fight this problem. Unfortunately, the air cannons were unable to shift the buildup, requiring

Problem Area The Failed Trio Smooth Solution

Cementing a New Standard of Cleaning in a Sticky Situation | CASE STUDY

Smooth SolutionFollowing a through evaluation and multiple consultations with

IGS technical experts, a solution was identified and installed. A

three-port multiplier with high velocity nozzles was fitted.

The high velocity nozzle produces a high energy ball of air,

moving material better than a wide thin blast of air from a

fan jet nozzle. Increased air tank volume would now make the

sticky material easier to move. New discharge locations have

now made it possible to push the material downward, at the

angle of the chute, instead of across the chute. Any working

cannons were relocated.

The IGS Multiplier coupled with a larger 300L air cannon

combined the initial power of the Blaster with the large moving

mass of the Pusher to effectively clean this chute where other

cannons had been ineffective. IGS is the only company that can

offer cannon systems with this mix of blast types allowing to

not only break up hardened buildup, but then shove it out of

the way.

As a result of the IGS Big Blue Air Cannon installation, manual

cleaning was no longer necessary. The plant is now evaluating

further areas, where build up is a problem, for additional air

cannon upgrades.

Cementing a New Standard of Cleaning Efficiency and innovation are major drivers in the current

climate. Cement plant managers, therefore, look for vendors

who are able to fortify their resources by taking traditional

systems and enhancing them for better performance.

Eventually, what may now be considered “new” will become a

new standard of cleaning.

The success of this installation allowed this plant to elect to

purchase 75 additional IGS Big Blue air cannons to install on

their preheat tower. The air cannons are part of a project to

switch fuels. The plant is moving away from the expensive low-

sulfur coal to a high-sulfur pet coke.

It is established this change will create significant buildup

in the preheat tower. The plant worked with IGS to best

determine the location of auxiliary air cannons. Each air cannon

is being supplied with the High Velocity Nozzles.

IGS have unmatched experience in air cannon installations, for

more information contact: [email protected]

Let the Power of Blue work for you!

EXPERT OPINION

Chris Landers, IGS air cannon expert, has commented: “For air cannons to solve buildup issues they must be applied correctly. The air cannons in this application were not applied correctly in our opinion. We felt there were issues with the following; location of nozzle, type of nozzle and the cleaning energy provided by each cannon.”

integratedglobal.com

Sticky material fell into the chute in large chunks, blocking the chute.

The air cannons were unable to shift the buildup, requiring manual clean-up.

IGS Big Blue Air Cannon installation - manual cleaning is no longer necessary.