cec 105 theory
DESCRIPTION
This course consist on the process of building or constructionTRANSCRIPT
-
UNESCO-NIGERIA TECHNICAL &
VOCATIONAL EDUCATION REVITALISATION
PROJECT-PHASE II
YEAR I- SEMESTER I
THEORY Version 1: December 2008
NATIONAL DIPLOMA IN
CIVIL ENGINEERING
TECHNOLOGY
CIVIL ENGINEERING CONSTRUCTION I
COURSE CODE: CEC105
-
TABLE OF CONTENTS
Week 1 Building Component
Week 2 Site Preparation
Week 3 Method of Setting Out
Wee 4 Excavations
Week 5 Foundations
Week 6 Damp Proofing, Sub-Structural Works, Rising and seepage of ground
and underground water
Week 7 Floors
Week 8 Walls
Week 9 Brick Bonding
Week 10 Partition Walling
Week 11 Stairs/Staircase
Week 12 Roofs
Week 13 Flat Roofs
Week 14 Slates
Week 15 Suspended Ceilings System
-
WEEK 1
COURSE: CIVIL ENGINEERING CONSTRUCTION 1
1.0 BUILDING COMPONENTS
1.1 Explain the term Building Component
To understand and to be able to explain the term building component.
It will be necessary to take cognizance of the following definitions:
BUILD – This is to make by putting elements, parts or materials
together to form something.
CONSTRUCTION – This is the putting together and assembling of
elements and material in other to erect or build a structure.
BUILDING – This is the act of constructing houses.
COMPONENT – This is a word that describes an element, part or
materials that contribute to the formation of a structure.
From the above definitions, it could be stated that Building
Components are structural elements or materials that can be
assembled, by the following approved construction procedures and
rules, to make up or form a building. The components to be used
depend largely on the purpose of the building (i.e. residential, factory
or recreations, etc.). high-rise building. Examples of building
-
components are foundation floor, wall ceiling, roof, doors, windows,
etc.
A building is so called because of the assemblage of most of these
components. Absence of some of these component parts depending
on the purpose of the building, will render it incomplete, structurally
waste and inhabitable. E.g. imagine a building without a foundation,
walls or roof, will be as good as piece of land with first farmers a tree
without root, man with
1.2 Enumerate the building components, e.g. foundation, floor, wall,
ceiling, roof, fenestration, doors, windows, stairs, etc.
Foundation Columns
Floor Slabs
Wall
Ceiling
Roof
Fenestration
Doors
Windows
Stairs
Chimney
-
1.3 Identify the different functional requirements of building
components
The component parts or materials that make up or forms a building
are normally designed to perform some specific function or for a
specific purpose in the building. Part from the beautification of the
structure, building components should perform some certain
functional requirements as identified below:
1. Foundation: To safety its objectives, foundation must be
designed to satisfy certain requirements as to provide suitable
support and stability for the structure.
To safety sustain and transmit to the combined deal, imposed
and wind loads in such a manner as not to cause any
settlement or other movement which would impair (weaken) the
stability or cause damage which or any part of the building or
any adjourning building.
- It must be taken down to such a depth as to safeguard the
building against the swelling shrinkage and or freezing of the
subsoil (especially on clay soil).
-
- It must be constructed to be capable of resisting any sulphates
attack and any deteriorate (harmful) matter present in the
subsoil.
2. Floor: The floor structure must fulfill several functions and
design considerations as follows:
- Provision of a uniform level surface; except in specified cases
for drainage purposes, floors are normally designed and
constructed to serve as a horizontal surface to support people
and their furniture, equipment and machinery.
- Sufficient strength and stability: The floor structure must be
strong enough to safety support the lead load of the floor and
its finishes, fixtures, parathions and services and the
anticipated imposed loads. This is largely dependent on the
characteristic of the materials used for the floor structure such
as timber, steel or concrete. It is also expected that the floor
should be stiff and remain stable and horizontal under the dead
half of the floor structure and the imposed loads. For stability
there should be adequate vertical support for the floor structure
and the floor should have adequate stiffness against gross
-
deflection under load. Providing reinforcement where
necessary.
- Exclusion of Dampness from the inside of a building
(Ground floor),
There is usually an appreciable transfer of moisture from the
ground to the floor. To prevent this depends on the nature of
the subsoil. A concrete slab could be used on a gravel coarse
grained sand base where the water table is relatively below the
surface. A water concrete slab, where the subsoil is clay base.
- Thermal insulation (properties): The ground floor should be
constructed to minimize the transfer of heat from the building to
the ground or the ground to the building. The hand core and
the damp proof membranes will assist in preventing the floor
being damp and feeling cold and so reduce the transfer of heat.
In some cases the floor could be insulated against excessive
transfer of heat.
- Resistance to sound transmission and absorption (sound
insulation), Timber floors will more readily transmit sound than
a mass concrete floor, so the floors between dwellings (upper
floors) are generally constructed of concrete. The reduction of
-
impact sound is best affected by a floor covering sound as
carpet that readers the sound of footsteps on either a timber or
a concrete floor sound absorption of floor can also be improved
by carpet.
- Resistance to fire:- Timber floor provides lesser period of
resistance to fire than a reinforced concrete floor. Upper floor
should be constructed to provide resistance to fire for a period
adequate for the escape of the occupants from the building
(normally 1 to 6 hours).
3. Wall: Classification and design conveniently divide into two
categories; external and internal construction. Most external
walls support the upper floors and roof and most external wall
are self-supporting only functioning as a means of dividing
space for the building into rooms and coo pertinent it must also
fulfill other design consideration as:
Strength and stability, the wall should sagged by carrying its
own weight and the structural loads placed upon it. The
strength of the wall will depend on the strength of the material
of the wall and the thickness it can carry. The stability of a wall
may affect by foundation movement, eccentric loads
-
(floors/roof) acting on the centre of the wall the thickness,
lateral forces (wind), and expansion due to temperature and
moisture changes.
To assist weather, particularly during cold and the
exclusion of rain
This depends on the exposure of the wall to wind. The
behaviour of a wall excluding wind and rain will depend on the
type of material used in the construction of the wall and how
they are bonded. This wall must be designed so that the rain is
not absorbed to the inside force of the wall, by making the wall
of sufficient thickness, and by applying an external facing of
rendering, or by building cavity wall.
Resistance to sound transmission and sound abortion, the wall
should be designed to resist the impact of noise. Sound is
transmitted as airborne sound and impact sound. Example of
airborne sound from radio and voices. Example of impact
sound is slamming of a door or footsteps on a floor. The
heavier and more degree the material of the wall, the more
effective it is reducing sound. Insulation against impact sound
-
consists of some absorbent materials that cushion the impact of
carpet on a floor.
Durability: The wall is designed with due regards to the
exposure of the wall to driving rain and with sensible….. it
should be durable for the anticipated life of the building and
should require little or no maintenance repair.
Fire Resistance and thermal properties: The wall should be
resistance to collapse, flame penetration and heat transmission
during a fire (normally 1 – 6 hrs). to maintain reasonable and
economical conditions of thermal comfort in building, walls
should provide adequate insulation against excessive loss or
gain of heat, have adequate thermal storage capacity –
lightweight materials are used where loss of heat will be
encountered. While dense materials are used in continually
heated buildings.
Roof: The structure is designed principally to prevent
penetration of inclement (severe) weather and to provide and
adequate barrier against heat loss. Other considerations
include an adequate appearance, the facility to absorb thermal
-
and moisture strength and stability to accommodate
maintenance and rain loads expatriate.
Door: the Fundamental purpose of a door is to provide access
into or out of a building and between the various compartments
within a building. Additionally, the following functions are to be
fulfilled, the extend depending on the building type and
purpose; the door should be designed to have sufficient
strength, shape and stability so as to provide adequate security
and privacy. A door should also function in excluding weather
(wind and rain), containing some waterproofing properties. Door
also act as barriers against fire, sound and thermal movement.
Window: The functions of a window are to admit daylight,
provide natural ventilation and to exclude wind and rainwater. It
also acts as thermal and sound insulators. In some
circumstances, the view from a window provides an important
function as relief and pleasant relaxation from daily internal
routine (view). It contains some fire resistance properties and
can act as a means of escape in case of fire outbreak.
Stairs: A stairway is initially designed to provide an effective
means of access between different floor levels. A secondary
-
function of considerable importance to provide a practical
escape route in the event of fire.
-
WEEK 2
SITE PREPARATION
Before the commencement of actual building construction, there is the
need to conduct certain preliminary site activities. This is to enable the
building team have foreknowledge of a site. Some activities which
preceded the actual building construction are
Site investigation ( ) and organization (layout)
Site welfare facilities
Storage and protection of materials
Site fencing and hoarding
Site clearance and excavation
Leveling and setting out
Ground water control.
1. Site Investigation and Organization – A preliminary examination or
survey of the job is made during the designing and post-designing
stages of a project. The survey enables the contractor or the engineer
to precisely have an idea about the site and assess if there are
peculiar problems to the proposed contract. It is this initial
understanding of these problems that the engineer will use to design
the building to suite the site. Similarly, the contractor could plan and
-
organize his activities, sufficiently to achieve success and minimize
time. This is done by producing a site layout plan and placing
equipment and materials in specific positions for easy reach, handling
and utilization.
Provision of services during site organization to a building site maybe
temporary where the work is transient (short period), e.g. construction
of highways. Elsewhere the services will be a permanent necessity
and should be installed accordingly to avoid repeating the work, e.g.
building construction. It is often advantageous to the contractor to
provide these services particularly electricity and water, from where
permanent installation could be mace. Other temporary services may
include access to site, watchman services, dust control (by watering
ground area), site clean (debris clearance), etc.
-
Some considerations to be given by the contractor during
reconnaissance and layout prior to constructional works are
(a) Availability and means of access to the site whether by road,
rail or waterway.
(b) Availability of suitable materials/equipment and spare available
for erecting plant and or storing materials around the site.
(c) Availability of space to erect temporary site offices and welfare
facilities.
(d) The effect of vibration on adjacent structure when the
construction involves using heavy/massive equipment (e.g. in
piling) should be considered.
Sub
-Roa
d
Acce
ss R
oad
SITE LAYOUT PLAN Existing Building
Main Road
Store and
Storage
Watchmen
PROJECT men
Mixer
Crane
Dumper
Ag
gre
gate
an
d S
an
d
Bu
sh
Toilet
Ca
nte
en
Watchmen
Dressing
Room Tech. Room
Engineering
Room Clinic
-
(e) The availability of water and power supply should be
ascertained and the rate of payment investigated.
(f) Knowledge of the nature and type of soil, and the level of water
table is important as the way necessitate subsoil drainage and
cause flooding.
(g) The local planning authorities should be approached to
ascertain whether there is any special or significant restriction
which could adversely affect the development of site (e.g.
underground cables).
(h) Valuable information can be obtained by talking with the local
inhabitants of the area.
(i) Any special condition that may limit work in anyway should be
noted and taken care of e.g. weather or climatic condition.
2. Subsoil Exploration (Trial boreholes) – Trial boreholes to determined
the nature of a subsoil is an important part of an early site
investigation. The building design and structural loading can be
related to the detailed and thorough examination of the subsoil bearing
potential (ability to withstand load). Preliminary examination may be
with trial pits excavated by spade or a hand anger. When more
detailed information is required, a powered anger is more effective.
-
The depth of boreholes can be several meters deep for high rise
buildings, and boring can be at random or regular intervals. Samples of
subsoil can be extracted loose or distorted, or undisturbed in steel
tubes. They are recorded on a borehole log, and samples are then
taken for laboratory analysis to establish the moisture content, bearing
capacity and chemical composition.
3. Site Welfare Facilities – The provision of shelter and accommodation
for taking meals and deposition of clothes is a basic requirement on
all sites. The builder should provide a hut for workmen so that meals
and short rest can be taken, and also for storage of clothing not
required for work during the day and protective clothing at night. The
mass room or canteen should be convenient for washing facilities.
Adequate wash basins, troughs and showers with soaps and towels
are required. (an isolated sanitary facility with water closets is also
required). Provision for first aid is also very important, and every
contractor must provide first-aid accommodation to include a couch,
stretchers, bandages, blankets, equipment, etc a trained person in
first-aid treatment is to be available on site during working hours.
4. storage and Protection of Materials – Materials such as cement,
timbers, bricks and blocks should be protected from weather by
-
storing in a shed or well stacked in a suitable position on the site,
where they will not be liable to damage and are adequately protected.
Electrical and plumbing (sanitary) fittings should be kept in a locked
shed to avoid theft or breakage. Proper storage is necessary
because saturated cement with time sets and becomes hardened
resulting to wastage. Saturation also affects the mortar or concrete
strength. Water is readily absorbed by timber causing deformation
and rot, this should be avoided. A saturated brisk or block will be very
difficult to handle. They should be well protected.
5. Site Fencing and Hoardings – A permanent fence or a temporary
hoardings will be required around the site. This is a barrier made of
block wall, wooden or mental stalk or rail or wire in some cases used
old zinc to provide security and protect equipment and materials, and
to keep out intruders. It also protections the ugly sight of construction
and preserves the beauty till completion. The hoardings are removed
after the completion of the project. The hoardings should be well
erected and in sage order so as not to cause injury to workers or
passé.
6. Site Clearance excavation to soil – The site should be cleared of the
bushes, shrubs, trees, etc. which are on the building position and
-
around the storage and temporary facilities area. The roads should
be grubbed up and completely removed.
Before any building is erected, it is essential that the area to be
occupied by the building has the vegetable top soil removed from site
completely or placed on one side, and spread level over areas after
completion of the project to provide gardens. The organic content of
the vegetable soil may be injurious to concrete, and so it should
never be used for backfilling, or making up levels under the building.
The path of excavation of topsoil is normally 150mm.
Leveling, land clearance and stripping of the topsoil are all easily
achieved with a bulldozer.
7. Ground Water Control: - Excavation and sample boreholes frequently
reveal and locate a level of saturation within a few meters below the
surface. This is known as the water table and it varies with season.
Excavation below the water table will be difficult and the strength of
any concrete placed in water will be seriously affected. A pre-
knowledge of this fact helps the contractor to be equipped and
prepare with his diesel powered water pump for the temporary
removal of water during excavation and concreting.
-
8. Setting Out and Leveling – After the stripping of the topsoil and
general site leveling, it is important that the structure is built in the
correct position as shown on the architect’s drawings. The position of
a building is marked out with string lines and pegs to indicate
foundation trenches and walls. The frontage line (building line) is an
imaginary line shown on the site plan, or determined by the local
authority, set back from the centre line of the road way.
-
WEEK 3
METHOD OF SETTING OUT
There are three main methods of setting out
345 method
Builder’s square and
Theodolite methods
(a) 345 Method - This is based on the mathematical principle
that any triangle with the sides in the ration of 345 is a right
angle. The method is as follows first you determine the building
line and established one corner of the building by driving a peg
at that point. A tape is used to measure a distance of 3m along
the building lien and a second peg is established with a nail on
top. The ring of the tape is held over the second peg with the
12m mark of the tape. With an assistant and with the 3m mark
of the tape around the corner peg, the tap is then stretched out
to give the position of the third peg at 7m mark. Now a line can
then be extended through third peg to give the width of the
building. The line extended should be perpendicular or 900 to
the building line. The above procedure is also carried out for
the rest corners and any possible intersection within the
-
building. To check the accuracy of the four-sided figure formed,
the diagonals should be measured to be equal in length.
(b) Builder’s Square Method This is similar to the 345 method, but in
this case instead of using a tape a steel builder’s square or a large
timber square and a line are used to establish the squareness of the
corners. Two pegs (P1,P2) with nails at their tops are driven along the
building line. One at the corner. A line is then held along the two
pegs tied at P1 going round the corner peg P2, the building’s square is
then held with its external angle point at nail of the corner peg, while
the line on P1, P2 is touching one entire side of the square. This line
is then pulled round P2 to touch the other entire side of the builder’s
square. Holding the line firm a third peg is the driven down where the
line touches the top of nail of P3.
The diagonals (a)(a) should be equal in length to ascertain the accuracy of the setting out operation.
Building line
a
a P2 P1
P3 7m
3m 0.12m
-
(c) Theodolite Method This is the most accurate method of setting out
of buildings. It involves using a surveying instrument called the
Theodolite. The theodolite is equipped with a telescope and cross
STEEL SQUARE
Ranging line
TIMBER SQUARE
String line
Nail
Builder’s Square
P3
P2 P1 P1 3 P2
4
P3 5
Building line
Timber peg
Diagonal should be equal
-
hair for sighting and ranging, with an internal graduated readings in
degrees for establishing bearings (horizontal and vertical angles).
The method is as follows
I. Mount and set the instrument at point A, sight the telescope, range
and peg out E and B to establish the building line.
ii. Turn the theodolite screws and adjust the degree readings to 0.00.
Turn the telescope of the instrument on the tripod stand towards the
right axis until you can sight 900 00” wide. The instrument clamp sight
the telescope and range to established and peg out points F and C.
iii. Transfer the instrument to point C, and follow the same procedure at
A, range A and F, set the angle 0.00”, turn towards the right axis to
sight and obtain 900 and to establish points G and D.
iv. Point H could be established by using a measuring tape.
B
H
E A
F
C G
Building line
-
WEEK 4
EXCAVATION
Excavation in building construction is simply the act of removing or digging
out earth (soil) from the ground for the purpose of laying foundation,
construction of floor, basements, etc. The earth is originally dug up to
specified depth, width and length.
The technique of excavation is largely determined by sensitivity of the site
to vibration, intensity of work, availability of plant and the subsoil
composition.
There are basically two methods of excavation, the manual method and the
mechanical method.
The manual method involves the use of hand tools such as spades
diggers, hand augers, pickers (rakes) and other manual implements for the
purpose of excavation. The manual method is regarded as a cheap means
of excavation, it is virtually obsolete and time consuming. The method can
be used only in very small buildings, e.g. garages or house extension,
where the site is inaccessible to excavating plant, and where archeological
remains are discovered and particular care is necessary. The method is
also used for trimming excavations by mechanically means where outward
projections and deviations are specified.
-
The mechanical method is a process of using mechanical plant and
equipment for excavation. This use of mechanical plant and equipment
saves considerable man-hours, and are standard features on all sites. The
type of plant varies with the nature of work and the different construction
stages. Plant can commonly be used for
a. Striping clearance and light demolition
b. Striping of top soil
c. Trench excavation
d. Basement excavation
The principal types of plant machine used for excavation are
a. Bulldozer
b. Loader/backhoe
-
b. Loader/Backhoe (Backacter) – The backachter/loader has on one
end a toothed bucket and hydraulic boom which extend out and
excavate towards the cab. This end is used mainly for excavation of
trenches, basement and ditches. The other is equipped with a
faceshovel loader for loading excavated loose earth into a dumper, a
tipper or lorry.
c. Scrapper – The scrapper contains a larger bowl with covered cutting
edge for stripping soil. It is used in very large sties, airfield of
highway.
Bowl Drop d.p.r
Cutting edge
-
d. Dragline/Grab Crane – Where the volume of excavation is large, the
crane- mounted dragline is preferred. The bucket is swinging forward
to penetrate the subsoil and dragged back towards the cab. Deep
excavation into granular soils is more effective with a grab or
„clamshell‟.
EARTHWORK SUPPORT
When excavations (trench) are dug in water saturated soils, it is important
to provide supports to the side of the excavation. This is done to prevent
the walls from caving-in (collapse) causing severe injury or death to those
required to work inside the trench. Apart from causing injury and death, it
will be additional cost to the builder to re-excavate and renew the damaged
work in the trench. Should the sides support collapse, timber and steel are
-
normally used for trench. The process of supporting trenches is generally
termed “planking and strutting”. The amount of support, side and system of
arrangement of the various timers depends on
a. The type and nature of subsoil to be supported
b. The depth of excavation.
c. The length of time the trench is to remain open
d. The time of year or climatic conditions prevailing when the trench
is excavated.
Timber is often the most convenient material for shallow trenches. Steel
interlocking polings are often used for deep water-logged subsoil.
Adjustable steel struts are also more convenient and have considerable re-
use value for all depths of excavation.
The timbering members used in trench support are as follows
i. Poling board – There are of 1.0 to 1.5m in length to suit the trench
depth, and they vary in cross-section fro 175 by 35mm to 225 by
50mm. They are placed vertically and against the soil of all the sides
of excavation.
ii. Wallings – These are longitudinal members running the length of the
trench and supporting the poling boards. They vary in sizes from 175
by 50mm to 225 by 75mm.
-
iii. Struts – These are usually squared timbers, either 100 by 100mm or
150 by 150mm in sizes. They are used to support the wallings, which
in turn holds the poling boards in position. Adjustable steel struts are
also in great use.
iv. Sheeting – These consist of horizontal boards abutting one another
to provide continuous barrier when excavating in loose soils and
common size for the sheeting is 175 x 75mm and there is overlap of
about 150mm at the point of connection between two stages.
Alternatively, steel interlocking poling with adjustable steep struts are
used.
Timbering in loose subsoil
Sheeting
Strut
Wedge Poling
-
Adjustable Steel Strut
In moderately firm ground, the timbering consists of a series of poling
boards which are widely spaced at about 60mm centres, supported by
wallings and struts. In shallow trenches, the poling boards would probably
only be needed at the about 1.8m centres with each pair of poling board
strutted individually with a single strut and no walling.
Timbering in Moderately Form Soil
In loose or saturated soil, a continuous horizontal sheeting supported by
pairs of poling boards and struts about 1.8m may be used. Alternatively, a
Walling
Poling Board
Strut
-
continuous length of poling boards or runners supported by walling and
struts may be used. If the trench exceed more than 1.5m in depth, it is
necessary to step up the timbering so that the lower stage fits inside the
upper section.
CONTROL OF GROUND WATER IN AN EXCAVATION
There are several methods available for controlling ground water during
excavation work. Some of the methods deals with lowering, while others
involves water exclusion from the site. Some of the methods employed in
the control of ground water during excavation work include
i. Plumbing Method ii. Dewatering
iii. Electro osmosis iv. Grouting
v. Soil stabilization
1. PUMPING FROM WELL OR (SUMP)
Pumping from sump is the most used for used of ground water
control since it is economical to install and maintain and can be
applied to all types of ground conditions.
The only problem is of the movement of the soil due to settlement
and there is also the risk of instability at the formation level of the
excavation. Where the excavation goes through permeable soil and
continued into impermeable soil, it is better to form a drain at the line
-
of interception to carry water in the sump. With this system a sump is
constructed at one corner of the site which forms a well point
continuous pumping of water.
The pump which is mounted on the ground level has one
disadvantage due to imitation in the design of suction lift to some
types of pumps. The suction lift of most pumps is at 7.5m – 9m. For
deep excavation where the depth exceeds 9m, the pump will have to
be placed in the excavation or on a level suitable for the suction lift.
2. DEWATERING
This consists of lowering the water table over the area of the site and
is satisfactory for depths up to 16m, it is particularly suitable where
running sand is encountered for once the water has been removed in
the ground, the sand become relatively stable. The equipments used
for the separation comprises of
i. Jetting pump, for driving down the well points
ii. Suction pump iii. Header pipe and
iv. Rises pipe.
The operation of dewatering is carried out by first jetting the well
points into the ground, this is done by securing each well points to
-
38mm diameter riser pipe at the top of which there is a connection by
a hose to the jetting pump. The assembled well points are held on
the ground and the pump operator delivers water under pressure until
the point penetrates the ground. The well points on reaching the
desired depths, the points are “sounded in” the hose of the top of the
well point is determined from the jetting point and attached to 150mm
diameter header pipe has coupling joint at 760mm 1m intervals so
that rises can be jointed at this spacing. For dealing with large volume
of water in loose ground or lose sand. The equipment can be used
for 2 main types of work.
i. The ringing system ii. The progressive system for
trenching.
i. Ringing System – In this system, the building site is encircled
with needle points and for single stage work, until permit
building work to be done at depth up to 6.5m where excavation
of 9m – 12m are required 2 stage work is adopted. For this, the
top are in dewatered and excavated first, the area is then
ringed at this intermediate stage for dewatering the corner
depth.
-
ii. Progressive System – This is suitable for dewatering along
the line of trenches before excavation. The wall points are with
draw when work is completed and filled in dead of the work.
The header pipe in laid along the ink of the proposed trench as
near as practicable. In different ground the pipe is placed in the
trench and supported on struts.
-
WEEK 5
FOUNDATIONS
A foundation is defined as, that part of a structure which is in direct contact
with the ground to which super imposed loads and dead loads are
transmitted or received. It is also an integral part of a building which
transfers the structural load from a building safely to the ground. Many at
times, during the construction of a building, the load on the foundation
gradually increases and eventually, this will result in settlement if the
settlement is slight and uniform throughout the area of the building, no
damage will occur to the building.
But if the settlement is extensive and unequal, serious damage may result
in the form of cracked walls, distorted doors and windows and in some
cases failure may be completed by the collapse of the building.
Selection of foundation types and design depends on the total building load
and the nature and quality of the subsoil. It is essential to achieve a
satisfactory balance between the building load and subsoil characteristics,
otherwise overstressing of the subsoil will lead to excessive building
settlement and serious structural defeats.
The purpose (importance) of foundation is to distribute the weight of the
structure to be carried over a sufficient area of bearing surface, so as to
-
prevent the subsoil from spreading and to avoid settlement of the structure.
A foundation should safety sustain (Carry) and transmit to the ground the
combined dead load, imposed load and wind load, without impairing the
stability of any part of the building.
A foundation is designed to support a number of different kinds of loads.
(a) The DEAD LOAD of the building, which is the sum of the weight of
the frame, the floors, roofs, and walls, electrical and mechanical
equipment and the foundation itself.
(b) The LIVE (IMPOSED) LOAD, which is the sum of the weights of
people in the building, the furnishings, sanitary fixtures and the
equipment they use, snow, ice and rain load on the roof.
(c) The WIND LOAD, which can apply literal, downward, and uplift load
to a foundation.
All foundation settle to some extent as the soil around and beneath them
adjust itself to the loads. Foundation settlement in most buildings is
measured in millimeters. If the total settlement occurs roughly at the same
rate from one side of the foundation to the other, no harm is likely to be
done to the building. This is because all parts of the building rest on the
same kind of soil. But if differential settlement occur (when the building
occupies a piece of land that is underlain by two or more areas of different
-
types of soil with very different load bearing capacities) in which the various
columns and load bearing walls of the building settle by substantial different
amounts, the frames of the building become distorted, floors may stapes,
walls and glass may crack, doors and windows may be difficult to open,
etc. the primary objective of foundation design is to minimize differential
settlement by loading the soil in such a way that equal settlement occur
under the various parts of the building.
SOILS IN FOUNDATION
Where the foundation of a building is on rock, no measurable settlement
will occur, whereas the building on soil will suffer settlement into the ground
by the compression of the soil under the foundation load. Some settlement
on soil foundation cannot be avoided, because as the building is erected,
the load on the foundation increases and compresses the soil. This
settlement must be limited to avoid damage. Bearing capacities for various
rocks and soils determined and should not be exceeded in the design of
the foundation to limit the settlement.
Soils are classified with regards to their size, density and nature of the
particles. Soil can be classified into three broad groups namely coarse
grained non-cohesive, fine grained cohesive and organic soils.
-
Coarse grained non-cohesive soil – This consist of coarse and larger
siliceous product under pressure from the loads on foundation. The soil in
this group compresses and consolidates rapidly by some rearrangement of
the particles and expulsion of water.
A foundation on this type of soil settles rapidly by consolidation of the soil,
as the building is erected, so that there is no further settlement once
building is completed.
Fine grained cohesive soils – This consists of natural deposits of the
finest siliceous and aluminous product or rock weathering such as clay.
Clay is smooth and greasy to touch, it shows high plasticity, dries slowly
and shrinks appreciably on drying. Under pressure of load on foundations,
clay soils are gradually compressed by the expulsion of water from the soil
so that the buildings settle gradually during building work and this
settlement may continue for some years after the building is completed.
Firm shrinkable clays suffer appreciable shrinkage on drying and expansion
of firm clay under grass extends to about 1 metre below the surface and up
to 4m or more below large trees. Building on shallow foundations should
not be close to trees, shrubs and trees should be removed to clear a site
for building on firm clay subsoil. This is because gradual expansion or
contraction (shrinkage) of the soil will cause damage to the building by
-
differential movement. This is as a result of the intake of subsoil water by
the tree roots.
Organic soils – Such as peat are not generally suitable foundation for
buildings. Foundation of this type soil are normally carried down to a
reliable bearing stratum.
TYPES OF FOUNDATIONS
There are four principal types of foundation strip, pad, raft and pile
foundations.
1. STRIP FOUNDATION
This type of foundation is a continuous level support for load bearing
walls. It is usually made of a continuous strip of concrete of 136 mix,
and may be reinforced (126) mix for poor subsoil or high loading.
The continuous strip serves as a level base on which the wall in built
and should be of such width as to spread the load on the foundation
to an area of subsoil capable of supporting the load without stress.
The width of a concrete strip foundation depends on the bearing
capacity of the subsoil, the less the width of the foundation for the
same load. The minimum width of a strip foundation is 450mm and
least thickness is 150mm. they are suitable for low-rise construction.
-
SECTION THROUGH A STRIP FOUNDATION
(a) Wide Strip Foundation
This type of foundation is used where the structural loading is very
high or relative to the subsoil bearing capacity. It is generally
cheaper to reinforce the concrete strip to reduce the equivalent
strength thickness to carry and spread the load.
2P + W
P x P
G.L.
Solid brick wall
-
(b) Deep Strip Foundation
This type of foundation has two applications
i. Narrow strip or trench fill
ii. Reinforced deep strip
The Narrow strip (trench fill) is designed to save considerable
structural construction time and where the nature of the subsoil such
as clay requires a considerable depth of 900mm, it is used to
excavate foundation trenches and fill them with concrete up to just
below the ground level say 2 brick coarse before the finished ground
level.
Wall G.L.
150m
1.2m
Reinforcement
-
Reinforce deep strip are acceptable alternative to wide strip
foundation for soft clay subsoil conditions. The depth should be at
least 900mm to avoid effect of shrinkage and swelling and about
400mm wide to provide sufficient support for the wall. Reinforcement
is required to take care of compressive stress as subsoil may develop
voids in long periods of dry weather due to volume change.
400
900
P
G.L.
-
2. PAD FOUNDATION
These are isolated pairs or column of brick, masonry or reinforced
concrete often in the form of a square or rectangle pad of concrete for
supporting ground beans, and in turn supporting walls. It is very
economical to use pad foundation where the subsoil has poor bearing
capacity for some depth below the surface, rather than excavating
deep trenches and raising wall in strip foundations. It is also used
where isolated columns are specified, especially in framed buildings.
The spread of area of this type of foundation depends on the load on
the soil and the bearing capacity of the subsoil.
400
900
G.L. Wall
Reinforcement
-
FOUNDATION PLAN SHOWING EXCAVATION WORK FOR PAD
CONSTRUCTION
SECTION THROUGH A PAD FOUNDATION
A B C
A 2
3
Reinforcement
column
Reinforcement
Pad foundation
-
3. RAFT FOUNDATION
In soft compressible subsoil, such as soft clay or peat subsoil. It is
necessary to form a raft foundation to spread over the whole base of
the building. Raft foundation consists of a raft of reinforce concrete
under the whole of the building design to transmit the load of the
building to the subsoil below the raft. Relative settlement between the
foundations of columns is avoided by the use of a raft foundation.
The two types of raft commonly used are the flat raft (solid slab raft)
foundation and wide toe raft (beam and slab raft) foundation.
Mat Reinforcement for pad foundation
building
Ground beam
Four members of starter bar
G.L.
-
(a) Flat Raft (solid slab raft) Foundation
This comprises of a reinforced concrete slab of uniform
thickness cast on a bred of blinding concrete and a deny proof
membrane, under the whole area of the building. This type of
foundation is used on loose subsoil with reasonable bearing
capacities for small buildings, such as houses. The slab
normally reinforced top and bottom.
(b) Wide Toe Raft Beam and slab rift ) Foundation
50 Blinding Damp proofing
membrane
Reinforcement
G.L.
Cavity wall
Floor finish
50 spread (cement
& sand)
100 mass concrete
floor
150 reinforced
concrete raft
-
This is like a reinforced concrete floor with down stand beams
called toe. It is used when the ground has poor compressibility.
The reinforced concrete edge beam is designed to support the
outer skin of the brick work or columns. The strengthened
beam collect loads from the walls or columns and transmit
these loads to the slab cast integrally with the beam, and the
slab in turn spread the loads over the whole area of subsoil
below the building.
Reinforcement
Damp proof membrane
100 hardcore
Blinding
Reinforced concrete raft
Screen
Floor finish
Cavity wall
G.L.
-
4. PILE FOUNDATION
Pile foundations are used where the subsoil has poor and uncertain
bearing capacity and in poor drained area where the water table is
high and there is appreciable ground movement. Piles are usually
employed because in these types of subsoil, it might be necessary to
excavate beyond 2m to meet a stable stratum. And it is uneconomical
to consider normal excavation beyond about 2m below the ground
level. The pile column of concrete either cast insitu or precast driven
into the ground to transfer the loads through the poor bearing soil to a
more stable stratum. Boring is undertaken by a powered auger. The
pile foundations are normally employed in the construction of bridges
and oil platforms on seas.
Short Bored Piles - These are used for small buildings on shrinkage
clays where adjacent trees could appreciate volume change in the
subsoil. Short bored (short length) piles are cast in holes by hand or
machine auger. The piles support reinforced concrete ground beams
on which wall are raised.
-
Reinforced
Concrete beam
Building
Poor grade
subsoil Piles
G.L. Sound bearing strata
Depth up
to 4m
G.L.
Reinforced
concrete beam
Concrete pile
Hardcore
Sand blinding
Ground floor slab
-
FOUNDATION ON SLOPING SITES
Walls foundation on sloping sites are normally constructed at one level or
stepped. Where the slope is slight the foundation may be at one level with
floor raised above the highest ground level. Where there is a greater slope,
it is usual to cut and fill so that the wall at the highest point does not act as
a retaining wall and there is no need to raise the ground floor above the
highest point of the site. The process of “cut and fill” is normally practiced
when providing foundation for walls on sloping sites. This is the operation
of cutting into part of the higher part of the site and filling the remaining
lower part with the excavated material or with the imported materials (for
Depth determined by resistance to
driving
G.L.
Reinforced
concrete beam
Steel sleeve
Hardcore
Sand blinding
Ground floor slab
Hollow fibre reinforced concrete shell
Solid concrete shoe
280
-
fill). It should be noted that cutting extends beyond the wall at the highest
point to provide a drained dry area behind it.
Where a building extend some distance up an appreciable slope, it is usual
to use stepped foundation to economize in excavation and foundation
walling.
Foundation at one level
Stepped Foundation
G.L.
Consolidated fill
under solid floor
Consolidated fill
under solid floor
Steeper slope
Ground
Shallow slope
-
STEPPED FOUNDATION
METHODS OF REINFORCEMENT IN FOUNDATIONS
1. GROUND BEAMS
Reinforced concrete
building slab
Ground
bearing slab
Selected soil
fill
Compacted
hardcore Existing G.L.
Top soil removed
Slab of raft reinforced top
and bottom
Section through reinforced concrete ground beam and slab raft with upstand
beams
R.C. Beams
Reinforcements
Floor construction with precast R. C. Beams bearing
on upstand beams on raft.
-
Raised timber or concrete floor
formed on raft
Reinforcements
R.C. Slab reinforced
top and bottom R.C. Beams
G.L.
Reinforcements
Helical building
hand
Lifting hole
Press steel forms
Corner for R.C.
Main reinforcement
Stirrups to
Lifting hole
Chilled cast iron
shoe
-
Cover
Forks
Links
Section of a
body of pile
Main reinforcement
Cast iron shoe
Cast iron shoe
End of tube
Cage of reinforcement
Steel
Concrete consolidates as
the tube is withdrawn Finished reinforcement
concrete pile
-
METHODS OF CONSTRUCTION OF VARIOUS FOUNDATIONS
1. STRIP FOUNDATIONS
Construction of strip foundation is carried out by first excavating the
ground to specified volume to remove soil to receive concrete. A
fairly dry weak concrete is the placed to specified depth inside the
foundation already containing a hardcore base (if necessary). This is
to act as a working base and to receive the oversite concrete. Where
a reinforcement or mesh are required, they are placed on mortar
blocks or concrete blocks (biscuit) on the blinding to give the cover for
concrete. A leveling instrument or a building plumb and short iron
pegs (off cuts) are then used to establish the tip level of the
concreting in the trench at intervals throughout the length of the
foundation trench. Concrete is then mixed and is poured into the
trench over the reinforcement until it reaches the established pegs.
As pouring is done a potter vibrator is used to vibrate the concrete to
remove the voids from the concrete. The concrete is then left to set
and harden and cured with water after one day of easting for at least
7 days.
-
2. PAD FOUNDATION
This is similar to the strip foundation construction, except that instead
of excavating in strips, deep hollow square or rectangular trenches
are dug. The provision of reinforcement for the base of the pad
interlock with the vertical reinforcement going up for the columns.
This is to ascertain a continuous interlocking support, strength and
stability between the pad and the concrete column. Where steel
stanchions (columns) would be placed on the pad foundation,
steel/iron bolts or steel plates are embedded in the foundation during
construction, where the stanchions or columns would be placed
(bolted or welded) on the pad foundations.
Concrete is then mixed, poured or placed, vibrated and cured as in
the strip method. In some cases formwork are sometimes used to
protect the sides and give shape to the pad.
3. RAFT FOUNDATION
The raft system involves the excavation of the whole base area of the
building and where ground beams are specified, is further excavated
below the raft slab foundation. Formwork is made to support the sides
of the foundation and insitu slab.
-
The placing of reinforcement for the slab and beam interlock or
overlaps. The placing of concrete and curing is as in the strip
method.
4. PILE FOUNDATION
(a) Bored Piles
This method is an insitu concrete construction. It consists of drilling
or boring a hole by means of earth drills or mechanically operated
augers which withdraws soil from the hole for casting of pile in
position. Usually steel lining tubes are lowered or knocked in as the
soil is taken out, to support the sides of the board pile.
Reinforcement are placed, concrete is then placed and compacted in
stages. As the concrete pile is cast the lining tubes are gradually
withdrawn
The disadvantages of this method are that it is not possible to check if
the concrete is adequately compacted, and there may be no
adequate cover to the concrete reinforcements.
(b) Precast Concrete Piles
As the name implies, these are precast either round, polygonal or
square concrete, steel or timber piles which are driven into the
ground by means of a mechanically operated drop hammer attached
-
to a mobile piling at a calculated predetermined „set‟. The word „set‟ is
used to describe the distance that a pile is driven into the ground by
the force of the hammer.
To concrete the top of the precast piles to the reinforced concrete
foundation at the top, 300mm of the length of reinforcement of the
pile is exposed, to which the reinforcements of the foundation is
connected.
Precast driven piles are not in general use on sites in built up area
(unrestricted area) due to
i. Difficulties in moving them through narrow streets
ii. Nuisance caused by the raise of driving piles and vibration
caused by driving the piles may damage existing adjacent
buildings.
-
WEEK 6
DAMP PROOFING
SUBSTRUCTURAL WORKS
RISING AND SEEPAGE OF GROUND AND UNDERGROUND WATER
If water is to rise of seep in a wall or floor, a constant supply must be
available at the base and side of the floor and wall. Water rise by an
upward capillary pull between the masonry pores. On building sites with
high water table and on slopping sites where water may run down to the
building, site concrete, floors and walls are likely to get damp by the
respective rising and seepage or moisture/water. The obvious indication of
rising damp and seepage is the dark staining above the skirting, bored on
the interior of a wall. This however, should be carefully checked to avoid
misconception of defective plumbing, leaking gutters/down pipes, and
defective chimney. Another indication of rising damp is the appearance of
white salty deposits on both faces of a wall called efflorescence. It is drawn
from the ground as the dampness rises, and they combine with any salt in
the masonry.
Rising and seepage into building is due to the lack of provision of damp
proofing materials, or may also be due to several possible construction
-
faults (i.e., in the cases where damp proofing materials are provided).
Some of these faults may include the following
The arrows ( ) indicate rising and seepage of ground
and underground water
IMPORTANCE OF DAMP PROOFING IN SUBSTRUCTURAL
WORKS
Damp roofing is the principle of preventing moisture entering buildings and
causing dampness which might be as a result of water/moisture rising up
the wall and floor from the ground forced through the structure, or seeping
through the forces of walls.
d.p.c
d.p.c
Bridging though
mortar painting
Paving or drive finished above
d.p.c
Earth stacked
against wall
Rendering
over the d.p.c
-
One chief essential requirement in building construction is to construct a
structure which is habitable and dry to live in. A dry building is unsightly
and causes damages to some components of the structure affected.
Most structural works are intended to be dry habitable. Any moisture
movement upwards from the ground through the substructural works to the
superstructure hampers the functional requirements of the affected building
components, and this reduces the quality of construction. The intended
purpose/use of the structure may also be defeated. Concrete is to some
degree permeable to water and will absorb moisture from the ground. A
damp oversite concrete slab may cause deterioration and damage in
moisture sensitive floor finishes such as timber or P.V.C. A damp oversite
concrete also will be cold and draw appreciable heat from rooms causing
cold.
Damp proofing helps the prevention of moisture rising up the floor or
seeping through walls, causing efflorescence and damage to the walls and
floor finishes.
Generally, damp proofing helps to maintain the quality, strength, stability,
durability and resistance to moisture/water of structures. It also helps to
maintain an appreciable room temperature. And to provide protection to
-
final finishing materials to concrete floors. A damp proofing materials must
be incorporated in concrete floors.
PROCESSES OF DAMP PROOFING
The process of damp proofing involves the provision of a continuous layer
of horizontal damp proof coarse (d.p.c) at about 150mm above finished
ground level in walls whose foundation are below the ground. And the
provision of a damp proof membrane (d.p.m) for the entire area on top is
between or under the oversite concrete slab.
The d.p.c should be impenetrable and continuous for the whole length and
thickness of the wall and be at least 150mm above finished ground level.
This is to prevent or avoid the possibility of a build-up of materials against
the wall acting as a bridge for moisture seeping through the wall.
A d.p.m should be impenetrable to water and touch enough to withstand
possible damage during laying of screeds or floor finishes. Application of
d.p.m. on irregular surfaces tend to puncture the membrane, so the
application of this materials should be done on a bed of sand or ash of
12mm thickness. The d.p.m may be on top, sandiviched in or under the
concrete slab.
All d.p.c, in external walls should unite with d.p.m in, on, or under the
oversite concrete. This may be affected by either laying the membrane in
-
the concrete at the same level as the d.p.c in the wall or by uniting the
membrane and d.p.c, laid at different levels with a vertical d.p.c.
Narrow trench fill foundation
d.p.c and p.p.m at same level
Concrete strip foundation
d.p.c and d.p.m at different level
150 concrete oversite
50 blinding
d.p.m
50 screed
d.p.c
Cavity wall
d.p.c abd d.p.m Overlaps
Hardcore
Hardcore
d.p.c abd d.p.m Overlaps
d.p.c
Cavity wall
Cavity wall
d.p.m
100 concrete oversite
Bed of sand or ash
d.p.m
-
FUNCTION OF A DAMP PROOF COURSE
Damp proof course is a layer of material capable of preventing the
penetration of moisture. It is laid on top of all walls at a distance of 150mm
above the finish ground level.
A d.p.c is an unbroken layer of impenetrable material on most foundation to
prevent the moisture absorbed from the soil rising and causing dampness
in the wall. Moisture penetration and rising dampness constitutes health
risks and cause discomfort to the inhabitants of the building.
Generally, d.p.c helps the preservation of wall finishes especially at the
base of the walls. d.p.c also provides protection against the dampness
arising from during rain. d.p.c reduces the tendency of the moisture to rise
up to the wall finishes, like rendering and painting at crack blister, peel,
flake, slow drying, etc.
TYPES OF DAMP PROOFING MATERIALS
1. Damp proof membrane materials
a. Hot, pitch or bitumen
b. Bitumen sheets/solutions/tar
c. Mastic asphalt
d. Polythene sheet
-
2. Damp Proof course
a. Flexible d.p.c materials
(i) Lead
(ii) Copper
(iii) Bitumen
(iv) Polythene sheet
b. Semi-Rigid d.p.c materials
(i) Slates
(ii) Bricks
BASEMENT CONSTRUCTION
METHOD OF CONSTRUCTION OF BASEMENT PROCEEDS IN
STAGES
1. Excavation begins at ground level and the sides are supported by
timbering.
2. This continues until the required dept is reached.
3. Foundation is cast and walls started. Timbering is removed
progressively and the space backfilled.
4. The wall reaches ground level all around the excavation.
5. The soil inside the walls can then be removed, if necessary.
-
BASEMENT EXCAVATION
The excavation for deep basements started at ground level, as the holes
becomes deeper a decision base to be made about the method to be
employed.
If ramp of earth is left in position, tipper tracks can use it to get into and out
of the hole. This depends on the length of the excavation, as it must be
able to accommodate a ramp of about 200 slope. Weather condition and
type of soil may also be considered as this may affect the use of the ramp
by loaded vehicles.
The ramp may be removed finally. If this is done by an excavator, with the
soil being removed by bucket and crane, the excavator will have to be
hoisted out on completion. If vehicles cannot drive out of the excavation,
the soil will have to be loaded into buckets, hoisted to the surface and
loaded on to trucks. The excavator is finally lifted out by crane. Where
excavation is not very deep, hand excavation may be used.
Various types of earth moving and excavation plant are available for use in
different circumstances, e.g. bulldozer shovel back actions and drag-line
grab crane excavators, loader and truck.
-
PRINCIPLE OF TANKING IN BASEMENT WORKS
Tanking is a system of forming a continuous waterproofing lining usually in
asphalt round the walls and floor of a basement as a barrier to rising and
penetrating dampness. The term tanking can also be used to describe a
continuous waterproofing lining to the walls and floors of substructures (e.g.
basement structures) to act as a tank to exclude water. This principle is
known as Basement taking.
The traditional material for tanking is mastic asphalt which is applied and
spread hot in three coats to a thickness of 20mm for vertical and 30mm for
horizontal work. Joints between each laying of asphalt in each coat should
be staggered at least 75mm for vertical and 150mm for horizontal work with
the joints in succeeding coats. Angles are reinforced with two coats of fillet
of asphalt.
Asphalt is usually applied to the outside face of structural walls and under
structural floors so that the walls and floors provide resistance against
water pressure on the asphalt, and the asphalt keep water away from the
structure.
Where the walls of the structure are on site boundaries and it is not
possible to excavate to provide adequate working space to apply asphalt
externally, a system of internal tanking may be used.
-
An internal lining is rarely used for new buildings because of the additional
floor and wall construction necessary resist water pressure on the asphalt.
Internal asphalt is sometimes used where a substructure to an existing
building is to be water proofed.
HARD CORE
This is an application of suitable material suck as broken bricks, stones and
tiles, clinker, gravel, quarry waste, which are required on the building site to
fill hollow oversite concrete work. On wet sites, it may be used to provide a
firm working surface and to prevent contamination of the lower part of the
wet concrete during compaction.
The particle materials should be hard and durable, not subject to decay or
breakdown by weather or chemical attack, and it should be easily placed
and well compacted. The hardcore should be spread until it is roughly level
and round until it forms a compact bed for the oversite concrete. The
hardcore bed is usually 100 to 300mm thick. It is spread to such thickness
as required to raise the finished surface of the oversite concrete.
Generally, the hardcore bed serves as a solid working base for building and
as a bed to receive oversite.
-
BLINDING
Is a process of providing a layer of dry concrete, coarse clinker or ash over
the hardcore before placing the oversite concrete. Before the concrete is
laid it is usual to blind the top surface of the hardcore. The purpose is to
prevent the wet concrete running down between the lumps of broken brick
or stone, as it would make easier for water to seep through the hardcore
and could be wasteful of concrete. To blind or seal, the top surface of the
hardcore a thin layer of very dry coarse concrete can be spread over it, or a
thin layer of coarse clinker or ash can be used. the blinding layer, or coat,
will be about 50mm thick, and on it the site concrete is spread and finished
with a true level top surface.
USE OF ANTI-TERMITE TREATMENT IN FOUNDATION WORKS
A problem in tropical climates is the possibility that timber maybe attacked
by termites. The common termite or white ant forms colonies in the ground
where a nest housing the queen is found. The termites can enter a building
through the ground looking for timber to consume. The junction of the wall
and floor is a particularly vulnerable point.
There are some precautions which can be taken to reduce the risk of
termite attack.
-
1. The area around the building should be inspected for termite nests,
which should b dug out and treated with insecticide.
2. During excavation work for the foundation and hardcore bed, the
exposed soil should be treated with insecticide, in an anticipation of
termite attack.
3. The ground floor concrete should be raised above the adjourning
ground level and should project beyond the outer wall face.
-
WEEK 7
FLOORS
Floors are structural parts of a building. They are usually designed to be of
either a timber or concrete work. Generally, in building construction floors
are designed and constructed for the flowing primary purposes (function):
a) Provision of a uniform level surface: - Unless otherwise specified,
floors are constructed to provide a uniform level surface, this is done
primarily to sufficiently provide adequate support, comfort, stability
and strength to carry people, their furniture, equipment and materials.
b) Exclusion of Dampness from inside of the building (especially
ground floors): - Floors also function as to prevent the passage of
moisture rising up/surpring through foundations/walls and causing
dampness and discoyort inside the building, this is normally attained
by using a d.p.m.
c) Thermal Insulation: - Floors minimize the transfer of heat from the
building to the ground of the building. A floor also serves to conserve
or reduce heat as the case (situation) may require. In this case
insulations or special finishing materials are used.
d) Sound Insulator: - Floors also serve as a barrios to transmission of
airborne sound and reduce impact sound, (especially upper floors)
normally concrete is preferred to timber because timber readily
transmit sound than concrete where timber are used they are
-
normally insulated with weight material (by filling the spaces between
the timber joists)
e) Fire Resistant: - in addition to the above functions, floors (especially
upper floor) are resistant, to fire to some considerable degree. They
provide resistance adequate for the escape of the occupants from the
building in times of fire outbreak.
f) Compatibility with the Surface Finish: - The purpose of a floor is
also to provide an adequate and acceptable surface finish to meet the
need of the user, with regards to appearance, comfort, cleanliness,
stability and safety.
GROUND FLOORS
There are primarily two types of ground floors solid ground floor and
raised timber ground floor.
A) SOLID GROUND FLOORS
There are normally constructed in-situ concrete. Solid concrete
ground floors have three principal components; hardcore, a damp
roof membrane and a layer of dense concrete. To construct these
types of floors, hardcore is compacted onto the reduced ground level
after excavation.
To prevent cement ground loss from the superimposed concrete
layer, or to protect a damp roof membrane from fracture, the hardcore
is blinded with a 25mm layer of sand.
-
The damp-proof membrane maybe positioned below the concrete
slab, upon the sand blinding polythene, sheet is the most popular
material, although bituminous sheet is acceptable. Alternatively, the
d.p.m. maybe sandwiched between the finishing their screed and the
structural concrete slab. In this particular case, cold or hot application
of bituminous solution in three layers with final layer sprinkled with
sand to bond to the screed overlay.
The concrete slab is of 100 – 150mm in thickness, composed of
cement, fine aggregate and coarse aggregates in the ratio of 1:3:6 to
provide a minimum strength specification of 1hr/mm2 at 28 days with
coarse aggregate of 38mm. A mix of 1:2:4 is preferred when using
coarse aggregate of 19mm size. A tamping bar is used to compact
and level the concrete to the specified depth-provided by short iron
pegs with finishing provided by cement/sand (1:3) screed.
-
B) SUSPENDED (RAISED) TIMBER GROUND FLOORS
This system of providing ground floors in buildings is now virtually
obsolete due to the escalating cost of the materials and skilled labour
required for their installation. Some few centuries ago houses were
constructed with timber ground floors raised 300 or more above the
site concrete or earth. This was done to have the surface of the
ground floor sufficiently above the ground level to prevent them being
cold and damp during winter.
Construction of this type of floor is made up of selected timber
platforms of hardwood floor boards nailed across timber joists, and
the joists in wall plate bearing on ½B thick sleeper walls, built directly
off the site concrete 1.8 apart. Sleeper walls are generally built three
courses of brick high, and are also built honey-combed to allow fire
circulation of air below the floor, to prevent wood decay. Air bricks are
also provided along external wall also to aid the circulation of air.
Component Parts of the raised timber ground floor construction:
a. Honey-comb sleeper wall: - sleeper walls are ½B thick built directly
off the site concrete about 1.8-2.0m apart. These sleeper walls are
generally built at least three courses of brick high and sometimes as
high as upto 600mm. The walls are built honey-combed to allow free
air circulation below the timber floor members.
-
b. D. P. C.: - This is spread and embedded on top of the sleeper walls
to prevent any moisture rising through the site concrete and sleeper
walls to the timber floor.
c. Wall Plate: - This is a continuous length of softwood timber which is
embedded in mortar on the d.p.c. The wall plate is bedded so that its
top surface is level along its length and also level with the top of wall
plates on other sleeper walls. This timber member is usually 100 x
75mm and is laid on one 100 face so that there is 100 surface with on
which the timber joists bear. The function of a wall plate for timber
joists is two-fold: -
(i) It forms a firm level surface on which the timber joists can bear
and to which they can be nailed.
(ii) It spreads the point load from joists uniformly along the length
of the wall below.
d. Floor Joists: - These are rectangular section softwood timbers laid
with their long sectional axis vertical and laid parallel spaced from
400 to 600 apart.
Floor joists are from 38 to 50 thick and 75 to 125 deep timber boards
are laid across the joists and nailed to form a firm level floor surface.
e. Floor Boards: - For timber, floor boards are usually 16,1921 or 28
thick and from 100 to 180mm wide and up to 5.0m in length. The
edges of the board maybe cut square or plain edged, though this
-
being the cheapest of cutting and fixing them, but boards tend to
shrink causing ugly cracks and the edges to open up. The usual way
of cutting the edges of floor boards is by providing a torque on one
edge and a groove on the opposite edge of each board, commonly
termed T and G. The boards are laid across the floor joists, cramped
together and nailed to the joists with two nails to each board bearing
on each joist.
f. Ventilation using air bricks: - In order to avoid deterioration of timber
under the floor board or suspended timber ground floor, there is need
to allow air circulation under the floor system. In order to achieve this
special air bricks must be provide at the external walls of the building
and adequately spaced. The purpose of these air bricks is to cause
air to circulate under the floor and thereby preventing stagnant air
which is likely to induce dry rot fugues to grow and causing word
decay.
In summary therefore, construction of the raised timber ground floor
can be achieved the assemblage of the above conform placed on a
concrete slab on a hardcore based.
-
SUSPENDED (UPPER) FLOORS
There are two main types of upper floors, timber upper floors and
reinforced concrete upper floors. Though timber upper floor
construction is about half the cost of a similar reinforced concrete
floor, concrete floors are still preferred because of their better
resistance to fire and to sound transmission and supports heavier
loads.
1. TIMBER UPPER FLOORS
There is no much difference in construction between the timber upper
floor and suspended timber ground floor. The only noticeable
difference is the elimination of sleeper walls in the upper floors, which
consequently involved the use of layer timber section for the floor
joists.
i. Strutting between Joists: - Timber floor joists spanning more than
3.0m are strutted at mind-span or 15m spacing to resist buckling and
deformity. This is done to safeguard and prevent cracking of the
plastered ceiling work due to excessive shrinkage and movement of
the joist. The herringbone strut arrangement using 50 or 38mm
square softwood struts is most efficient, but solid strutting is often
used for easier and quicker installation. Solid strutting consists of
short lengths of timber of the same section as the joist which are
-
nailed between the joists either in line or staggered. This is not
usually so effective as the herringbone system, because unless the
short solid lengths are cut very accurately to fit to the sides of the
joists they do not firmly strut between the joists. As with herringbone,
between the first and the last joists and adjacent walls folding wedges
are used to firmly locate the strutting.
ii. End Support for Floor Joists: - The floor is normally framed with
softwood timber joists, with maximum economical span of between
3.6 and 4.0.
The required depth of joists depends on the total load. For
stability, the ends of floor joists must have adequate support from
walls or beams. There are various methods of supporting the ends
of joists in order to sustain the imposed loadings.
a) The ends of the joists are treated with preservatives (to avoid
decay) and are built into the brick walls. This method requires
cutting and packing of trick work in order to bring the top of the
joist on the same plane, care must taken to prevent joist
protinding into the cavities of the cavity wall and providing a
bridge for moisture penetration. Alternatively timber floor joists
can be built into wall to bear on a wall plate of timber or metal,
which are along the length of the wall beneath the joists, this
assist in spreading the load from the floor along the length of
-
the wall and also as a level bed on which the joists are placed
and nail in position. The wall is then raised between and above
the floor joists.
b) End support for the joists can also be attained by the use of
galvanized steel floor hangers, which are built into brick or
block courses so that they project and support the ends of the
joists. This is the best method of providing supports to joist
from external walls as it avoids building timber into walls.
As an alternative to hangers, timber floor joist maybe supported by
a timber wall plate carried on iron corbels built into walls, or brick
courses corbelled out from the wall. The disadvantage of these is
that they form a projection below the ceiling.
iii. Floor Boards: - As with timber ground floors, the boards usually
19 or 21 thick have T & G edges core cramped up and nailed
across the floor joists, with the heading joints staggered.
-
(ii) GALVANIZED
STEEL FLOOR
HANGERS
Hangers built into wall
to support joists.
(iii) STEEL CORBELS BUILT
INTO SUPPORT WALL
PLATE
Wall plate
support joists
Corbels built into wall to
support wall plats/joists.
(IV) WALL PLATE SUPPORTED
OR TWO CORBELS OF BRICK
CORBEL WALL PLATE
Two-course brick corbel
brick wall plate
-
2. REINFORCED CONCRETE UPPER FLOORS
Reinforced concrete floors have a better resistance to damage by fire
and can safely support greater super imposed than timber floors of
similar depth.
(a) Monolithic Reinforced Concrete Floors: - As the name
implies a monolithic reinforced concrete floor is an unbroken
solid mass of concrete between 100 and 300 thick, cast in-situ
and reinforced with steel reinforcing bars.
Construction of monolithic reinforced concrete floor consists of
a temporary CONFERRING (consists of timber/steel platforms
erected at ceiling level supported on timber or steel beams and
posts) to support the concrete while it is still wet and plastic for
7 days. The top surface of the platform is then painted with
mould oil to prevent the wet concrete from adhering to the
platform, so that timber platforms can be removed easily. Small
tiles or blocks (biscuit) are then cast 15-25mm thick depending
on the specified concrete cover. These are placed at frequent
centres on the platform. These tiles (specer blocks or biscuits)
are tied to/and support the steel reinforcement, and ensures
that the mesh will have the specified cover for the concrete.
The concrete is the placed of cast on the centering to the
-
required thickness, and it is compacted, vibrated and leveled off
care must be taken that vibration is not overdone so that most
of the cement is hot brought to the surface, thereby reducing
the strength of the mix. The concrete is then cured for 7 days
before the centering is removed.
b) Precast Self-centering Floor System: - centering or formwork used
to support the monolithic reinforced concrete floors tend to obstruct
and delay building operations. So for emergency projects where time
is an important factor, self-centering concrete floors are used. This
1B wall Timber
support
Timber
chartering
½B
partition
Timber
formwork
Main bars with
bent-up ends
Distribution
bars
Biscuit 1B wall
Raised brick work
above floor cast
Concrete floor built in
Concrete floor
cast in-situ
-
type of floor is made of precasted concrete beams which are usually
manufactured in yards and are transported to the site for fixing. They
serve as floors when they are raised and placed in position with their
ends built into brick walls. Once in position they require is support
other than the bearing of their ends on walls or beams. There are a
wide range of precast self-centering floor systems:
i. Rectangular hollow cross-sectional beam floor units, closed
spaced.
ii. Inverted channel sections, closed spaced
iii. Solid precast ‘T’ section beams with hollow lightweight concrete
infilling blocks.
HOLLOW CONC. BEAN FLOOR
-
WEEK 8
WALLS
Walls are vertical and continuous solid structures, usually constructed from
materials such as clay, stone, concrete, timber or metal.
Walls can be classified with respect to their functional requirements as
internal and external walls. They can also be defined as load bearing
(carrying imposed loads from roofs and floors in addition to their own
weight) and non-load bearing (eg portion), non-load bearing is with respect
to the structural requirements. There are variably two types of walls, solid
wall and framed wall. A solid wall (Masonry wall) is constructed either of
blocks of brick, burned clay, stone or concrete.
These are laid in mortar to overlap to form a bond (bonding) or as a
monolithic (eg concrete wall). A frame wall is constructed from a frame of
small sections of timber, concrete or metal joined together to provide
strength and rigidity, and between the members of the frame thin panels of
some material are then fixed to the frames to fulfill the functional
requirements of the particular wall.
THE FUNCTION OF A WALL IS
(1)To enclose and protect a building, and also serve as a means of (2)
dividing space within a building walls serve (3) as protection against wind
and rain, and to (4) support floor and roofs and to some extent to (5)
conserve heat within the building. Walls can (6) serve to protect the
-
building against fire, excessive heat, and to resist or minimize the
transmission and absorption of sound especial solid block walls. Framed
walls usually of less weight than solid block walls are normally used for
partitioning existing structures so as to minimize the total load of the
building. The use of framed walls is preferred where there is little
consideration for sound transmission. Note that no material for wall
concrete fulfils all the functional requirement of a wall with maximum
efficiency.
BRICKS
Bricks are small blocks manufactured from burnt clay that can be handled
with one hand, and its length is twice the width plus one mortar joint. Blocks
made from sand and lime and blocks made of concrete manufactured in
clay brick size are also called bricks.
The standard size is 215mm x 102.5mm x 65mm which with 10mm mortar
joint becomes 225mm x 112.5mm x 75mm.
65
215
102.5
STANDARD
BRICK
FORMAT SIZE
-
There are various types of bricks of the same standard format are classified
with respect to the material used, composition, extent of mixing and curing,
duration and amount of forming applied. Some of these of bricks are:
commons, facings, engineering bricks, semi-engineering bricks,
composition of clay, flattons, stocks, marts, Gautts, clay shale bricks,
calcium silicate bricks, flint-lime bricks, and hollow, perforated and special
bricks.
Some special applications and features work require bricks to be reduced
in size or reshaped. Specials are either cut from a whole brick, or purpose-
made (manufactured) by hand in hardwood moulds.
KING CLOSER
¼ Brick
½ Brick
½ BAT OR SNAP
HEADER
¾ BAT
¾ BAT
½ Brick
1 Brick
BEVELED CLOSER
Queen Closer
¼ Brick
-
Some examples of purpose-made (manufactured) special bricks
Plink Header Plink stretcher
Squint Angle
Angle brick Dogleg brick
Birds month Cant Double Cant
Half round Coping Saddleback coping
Single bull nose
bull nose mitre Double bull nose
Perforated brick Cellular pressed brick
-
WEEK 9
BRICK BONDING
To build or construct a wall of brick or blocks, it is usual to lay the bricks in
some regular pattern. The brick courses or rows in a wall are arranged to
ensure that each brick overlaps or bear upon two or more bricks
immediately below it. The process of laying the bricks across each other
and binding them together is called bonding. The amount of overlap and
the part of the brick used determined the pattern or bond of brickwork.
Bonding of bricks can also be defined as the arrangement of bricks in
which no vertical joint of one course is exactly over the one in