cec 105 theory

182
UNESCO-NIGERIA TECHNICAL & VOCATIONAL EDUCATION REVITALISATION PROJECT-PHASE II YEAR I- SEMESTER I THEORY Version 1: December 2008 NATIONAL DIPLOMA IN CIVIL ENGINEERING CIVIL ENGINEERING CONSTRUCTION I COURSE CODE: CEC105

Upload: mathewniyi4

Post on 24-Jun-2021

278 views

Category:

Engineering


159 download

DESCRIPTION

This course consist on the process of building or construction

TRANSCRIPT

  • UNESCO-NIGERIA TECHNICAL &

    VOCATIONAL EDUCATION REVITALISATION

    PROJECT-PHASE II

    YEAR I- SEMESTER I

    THEORY Version 1: December 2008

    NATIONAL DIPLOMA IN

    CIVIL ENGINEERING

    TECHNOLOGY

    CIVIL ENGINEERING CONSTRUCTION I

    COURSE CODE: CEC105

  • TABLE OF CONTENTS

    Week 1 Building Component

    Week 2 Site Preparation

    Week 3 Method of Setting Out

    Wee 4 Excavations

    Week 5 Foundations

    Week 6 Damp Proofing, Sub-Structural Works, Rising and seepage of ground

    and underground water

    Week 7 Floors

    Week 8 Walls

    Week 9 Brick Bonding

    Week 10 Partition Walling

    Week 11 Stairs/Staircase

    Week 12 Roofs

    Week 13 Flat Roofs

    Week 14 Slates

    Week 15 Suspended Ceilings System

  • WEEK 1

    COURSE: CIVIL ENGINEERING CONSTRUCTION 1

    1.0 BUILDING COMPONENTS

    1.1 Explain the term Building Component

    To understand and to be able to explain the term building component.

    It will be necessary to take cognizance of the following definitions:

    BUILD – This is to make by putting elements, parts or materials

    together to form something.

    CONSTRUCTION – This is the putting together and assembling of

    elements and material in other to erect or build a structure.

    BUILDING – This is the act of constructing houses.

    COMPONENT – This is a word that describes an element, part or

    materials that contribute to the formation of a structure.

    From the above definitions, it could be stated that Building

    Components are structural elements or materials that can be

    assembled, by the following approved construction procedures and

    rules, to make up or form a building. The components to be used

    depend largely on the purpose of the building (i.e. residential, factory

    or recreations, etc.). high-rise building. Examples of building

  • components are foundation floor, wall ceiling, roof, doors, windows,

    etc.

    A building is so called because of the assemblage of most of these

    components. Absence of some of these component parts depending

    on the purpose of the building, will render it incomplete, structurally

    waste and inhabitable. E.g. imagine a building without a foundation,

    walls or roof, will be as good as piece of land with first farmers a tree

    without root, man with

    1.2 Enumerate the building components, e.g. foundation, floor, wall,

    ceiling, roof, fenestration, doors, windows, stairs, etc.

    Foundation Columns

    Floor Slabs

    Wall

    Ceiling

    Roof

    Fenestration

    Doors

    Windows

    Stairs

    Chimney

  • 1.3 Identify the different functional requirements of building

    components

    The component parts or materials that make up or forms a building

    are normally designed to perform some specific function or for a

    specific purpose in the building. Part from the beautification of the

    structure, building components should perform some certain

    functional requirements as identified below:

    1. Foundation: To safety its objectives, foundation must be

    designed to satisfy certain requirements as to provide suitable

    support and stability for the structure.

    To safety sustain and transmit to the combined deal, imposed

    and wind loads in such a manner as not to cause any

    settlement or other movement which would impair (weaken) the

    stability or cause damage which or any part of the building or

    any adjourning building.

    - It must be taken down to such a depth as to safeguard the

    building against the swelling shrinkage and or freezing of the

    subsoil (especially on clay soil).

  • - It must be constructed to be capable of resisting any sulphates

    attack and any deteriorate (harmful) matter present in the

    subsoil.

    2. Floor: The floor structure must fulfill several functions and

    design considerations as follows:

    - Provision of a uniform level surface; except in specified cases

    for drainage purposes, floors are normally designed and

    constructed to serve as a horizontal surface to support people

    and their furniture, equipment and machinery.

    - Sufficient strength and stability: The floor structure must be

    strong enough to safety support the lead load of the floor and

    its finishes, fixtures, parathions and services and the

    anticipated imposed loads. This is largely dependent on the

    characteristic of the materials used for the floor structure such

    as timber, steel or concrete. It is also expected that the floor

    should be stiff and remain stable and horizontal under the dead

    half of the floor structure and the imposed loads. For stability

    there should be adequate vertical support for the floor structure

    and the floor should have adequate stiffness against gross

  • deflection under load. Providing reinforcement where

    necessary.

    - Exclusion of Dampness from the inside of a building

    (Ground floor),

    There is usually an appreciable transfer of moisture from the

    ground to the floor. To prevent this depends on the nature of

    the subsoil. A concrete slab could be used on a gravel coarse

    grained sand base where the water table is relatively below the

    surface. A water concrete slab, where the subsoil is clay base.

    - Thermal insulation (properties): The ground floor should be

    constructed to minimize the transfer of heat from the building to

    the ground or the ground to the building. The hand core and

    the damp proof membranes will assist in preventing the floor

    being damp and feeling cold and so reduce the transfer of heat.

    In some cases the floor could be insulated against excessive

    transfer of heat.

    - Resistance to sound transmission and absorption (sound

    insulation), Timber floors will more readily transmit sound than

    a mass concrete floor, so the floors between dwellings (upper

    floors) are generally constructed of concrete. The reduction of

  • impact sound is best affected by a floor covering sound as

    carpet that readers the sound of footsteps on either a timber or

    a concrete floor sound absorption of floor can also be improved

    by carpet.

    - Resistance to fire:- Timber floor provides lesser period of

    resistance to fire than a reinforced concrete floor. Upper floor

    should be constructed to provide resistance to fire for a period

    adequate for the escape of the occupants from the building

    (normally 1 to 6 hours).

    3. Wall: Classification and design conveniently divide into two

    categories; external and internal construction. Most external

    walls support the upper floors and roof and most external wall

    are self-supporting only functioning as a means of dividing

    space for the building into rooms and coo pertinent it must also

    fulfill other design consideration as:

    Strength and stability, the wall should sagged by carrying its

    own weight and the structural loads placed upon it. The

    strength of the wall will depend on the strength of the material

    of the wall and the thickness it can carry. The stability of a wall

    may affect by foundation movement, eccentric loads

  • (floors/roof) acting on the centre of the wall the thickness,

    lateral forces (wind), and expansion due to temperature and

    moisture changes.

    To assist weather, particularly during cold and the

    exclusion of rain

    This depends on the exposure of the wall to wind. The

    behaviour of a wall excluding wind and rain will depend on the

    type of material used in the construction of the wall and how

    they are bonded. This wall must be designed so that the rain is

    not absorbed to the inside force of the wall, by making the wall

    of sufficient thickness, and by applying an external facing of

    rendering, or by building cavity wall.

    Resistance to sound transmission and sound abortion, the wall

    should be designed to resist the impact of noise. Sound is

    transmitted as airborne sound and impact sound. Example of

    airborne sound from radio and voices. Example of impact

    sound is slamming of a door or footsteps on a floor. The

    heavier and more degree the material of the wall, the more

    effective it is reducing sound. Insulation against impact sound

  • consists of some absorbent materials that cushion the impact of

    carpet on a floor.

    Durability: The wall is designed with due regards to the

    exposure of the wall to driving rain and with sensible….. it

    should be durable for the anticipated life of the building and

    should require little or no maintenance repair.

    Fire Resistance and thermal properties: The wall should be

    resistance to collapse, flame penetration and heat transmission

    during a fire (normally 1 – 6 hrs). to maintain reasonable and

    economical conditions of thermal comfort in building, walls

    should provide adequate insulation against excessive loss or

    gain of heat, have adequate thermal storage capacity –

    lightweight materials are used where loss of heat will be

    encountered. While dense materials are used in continually

    heated buildings.

    Roof: The structure is designed principally to prevent

    penetration of inclement (severe) weather and to provide and

    adequate barrier against heat loss. Other considerations

    include an adequate appearance, the facility to absorb thermal

  • and moisture strength and stability to accommodate

    maintenance and rain loads expatriate.

    Door: the Fundamental purpose of a door is to provide access

    into or out of a building and between the various compartments

    within a building. Additionally, the following functions are to be

    fulfilled, the extend depending on the building type and

    purpose; the door should be designed to have sufficient

    strength, shape and stability so as to provide adequate security

    and privacy. A door should also function in excluding weather

    (wind and rain), containing some waterproofing properties. Door

    also act as barriers against fire, sound and thermal movement.

    Window: The functions of a window are to admit daylight,

    provide natural ventilation and to exclude wind and rainwater. It

    also acts as thermal and sound insulators. In some

    circumstances, the view from a window provides an important

    function as relief and pleasant relaxation from daily internal

    routine (view). It contains some fire resistance properties and

    can act as a means of escape in case of fire outbreak.

    Stairs: A stairway is initially designed to provide an effective

    means of access between different floor levels. A secondary

  • function of considerable importance to provide a practical

    escape route in the event of fire.

  • WEEK 2

    SITE PREPARATION

    Before the commencement of actual building construction, there is the

    need to conduct certain preliminary site activities. This is to enable the

    building team have foreknowledge of a site. Some activities which

    preceded the actual building construction are

    Site investigation ( ) and organization (layout)

    Site welfare facilities

    Storage and protection of materials

    Site fencing and hoarding

    Site clearance and excavation

    Leveling and setting out

    Ground water control.

    1. Site Investigation and Organization – A preliminary examination or

    survey of the job is made during the designing and post-designing

    stages of a project. The survey enables the contractor or the engineer

    to precisely have an idea about the site and assess if there are

    peculiar problems to the proposed contract. It is this initial

    understanding of these problems that the engineer will use to design

    the building to suite the site. Similarly, the contractor could plan and

  • organize his activities, sufficiently to achieve success and minimize

    time. This is done by producing a site layout plan and placing

    equipment and materials in specific positions for easy reach, handling

    and utilization.

    Provision of services during site organization to a building site maybe

    temporary where the work is transient (short period), e.g. construction

    of highways. Elsewhere the services will be a permanent necessity

    and should be installed accordingly to avoid repeating the work, e.g.

    building construction. It is often advantageous to the contractor to

    provide these services particularly electricity and water, from where

    permanent installation could be mace. Other temporary services may

    include access to site, watchman services, dust control (by watering

    ground area), site clean (debris clearance), etc.

  • Some considerations to be given by the contractor during

    reconnaissance and layout prior to constructional works are

    (a) Availability and means of access to the site whether by road,

    rail or waterway.

    (b) Availability of suitable materials/equipment and spare available

    for erecting plant and or storing materials around the site.

    (c) Availability of space to erect temporary site offices and welfare

    facilities.

    (d) The effect of vibration on adjacent structure when the

    construction involves using heavy/massive equipment (e.g. in

    piling) should be considered.

    Sub

    -Roa

    d

    Acce

    ss R

    oad

    SITE LAYOUT PLAN Existing Building

    Main Road

    Store and

    Storage

    Watchmen

    PROJECT men

    Mixer

    Crane

    Dumper

    Ag

    gre

    gate

    an

    d S

    an

    d

    Bu

    sh

    Toilet

    Ca

    nte

    en

    Watchmen

    Dressing

    Room Tech. Room

    Engineering

    Room Clinic

  • (e) The availability of water and power supply should be

    ascertained and the rate of payment investigated.

    (f) Knowledge of the nature and type of soil, and the level of water

    table is important as the way necessitate subsoil drainage and

    cause flooding.

    (g) The local planning authorities should be approached to

    ascertain whether there is any special or significant restriction

    which could adversely affect the development of site (e.g.

    underground cables).

    (h) Valuable information can be obtained by talking with the local

    inhabitants of the area.

    (i) Any special condition that may limit work in anyway should be

    noted and taken care of e.g. weather or climatic condition.

    2. Subsoil Exploration (Trial boreholes) – Trial boreholes to determined

    the nature of a subsoil is an important part of an early site

    investigation. The building design and structural loading can be

    related to the detailed and thorough examination of the subsoil bearing

    potential (ability to withstand load). Preliminary examination may be

    with trial pits excavated by spade or a hand anger. When more

    detailed information is required, a powered anger is more effective.

  • The depth of boreholes can be several meters deep for high rise

    buildings, and boring can be at random or regular intervals. Samples of

    subsoil can be extracted loose or distorted, or undisturbed in steel

    tubes. They are recorded on a borehole log, and samples are then

    taken for laboratory analysis to establish the moisture content, bearing

    capacity and chemical composition.

    3. Site Welfare Facilities – The provision of shelter and accommodation

    for taking meals and deposition of clothes is a basic requirement on

    all sites. The builder should provide a hut for workmen so that meals

    and short rest can be taken, and also for storage of clothing not

    required for work during the day and protective clothing at night. The

    mass room or canteen should be convenient for washing facilities.

    Adequate wash basins, troughs and showers with soaps and towels

    are required. (an isolated sanitary facility with water closets is also

    required). Provision for first aid is also very important, and every

    contractor must provide first-aid accommodation to include a couch,

    stretchers, bandages, blankets, equipment, etc a trained person in

    first-aid treatment is to be available on site during working hours.

    4. storage and Protection of Materials – Materials such as cement,

    timbers, bricks and blocks should be protected from weather by

  • storing in a shed or well stacked in a suitable position on the site,

    where they will not be liable to damage and are adequately protected.

    Electrical and plumbing (sanitary) fittings should be kept in a locked

    shed to avoid theft or breakage. Proper storage is necessary

    because saturated cement with time sets and becomes hardened

    resulting to wastage. Saturation also affects the mortar or concrete

    strength. Water is readily absorbed by timber causing deformation

    and rot, this should be avoided. A saturated brisk or block will be very

    difficult to handle. They should be well protected.

    5. Site Fencing and Hoardings – A permanent fence or a temporary

    hoardings will be required around the site. This is a barrier made of

    block wall, wooden or mental stalk or rail or wire in some cases used

    old zinc to provide security and protect equipment and materials, and

    to keep out intruders. It also protections the ugly sight of construction

    and preserves the beauty till completion. The hoardings are removed

    after the completion of the project. The hoardings should be well

    erected and in sage order so as not to cause injury to workers or

    passé.

    6. Site Clearance excavation to soil – The site should be cleared of the

    bushes, shrubs, trees, etc. which are on the building position and

  • around the storage and temporary facilities area. The roads should

    be grubbed up and completely removed.

    Before any building is erected, it is essential that the area to be

    occupied by the building has the vegetable top soil removed from site

    completely or placed on one side, and spread level over areas after

    completion of the project to provide gardens. The organic content of

    the vegetable soil may be injurious to concrete, and so it should

    never be used for backfilling, or making up levels under the building.

    The path of excavation of topsoil is normally 150mm.

    Leveling, land clearance and stripping of the topsoil are all easily

    achieved with a bulldozer.

    7. Ground Water Control: - Excavation and sample boreholes frequently

    reveal and locate a level of saturation within a few meters below the

    surface. This is known as the water table and it varies with season.

    Excavation below the water table will be difficult and the strength of

    any concrete placed in water will be seriously affected. A pre-

    knowledge of this fact helps the contractor to be equipped and

    prepare with his diesel powered water pump for the temporary

    removal of water during excavation and concreting.

  • 8. Setting Out and Leveling – After the stripping of the topsoil and

    general site leveling, it is important that the structure is built in the

    correct position as shown on the architect’s drawings. The position of

    a building is marked out with string lines and pegs to indicate

    foundation trenches and walls. The frontage line (building line) is an

    imaginary line shown on the site plan, or determined by the local

    authority, set back from the centre line of the road way.

  • WEEK 3

    METHOD OF SETTING OUT

    There are three main methods of setting out

    345 method

    Builder’s square and

    Theodolite methods

    (a) 345 Method - This is based on the mathematical principle

    that any triangle with the sides in the ration of 345 is a right

    angle. The method is as follows first you determine the building

    line and established one corner of the building by driving a peg

    at that point. A tape is used to measure a distance of 3m along

    the building lien and a second peg is established with a nail on

    top. The ring of the tape is held over the second peg with the

    12m mark of the tape. With an assistant and with the 3m mark

    of the tape around the corner peg, the tap is then stretched out

    to give the position of the third peg at 7m mark. Now a line can

    then be extended through third peg to give the width of the

    building. The line extended should be perpendicular or 900 to

    the building line. The above procedure is also carried out for

    the rest corners and any possible intersection within the

  • building. To check the accuracy of the four-sided figure formed,

    the diagonals should be measured to be equal in length.

    (b) Builder’s Square Method This is similar to the 345 method, but in

    this case instead of using a tape a steel builder’s square or a large

    timber square and a line are used to establish the squareness of the

    corners. Two pegs (P1,P2) with nails at their tops are driven along the

    building line. One at the corner. A line is then held along the two

    pegs tied at P1 going round the corner peg P2, the building’s square is

    then held with its external angle point at nail of the corner peg, while

    the line on P1, P2 is touching one entire side of the square. This line

    is then pulled round P2 to touch the other entire side of the builder’s

    square. Holding the line firm a third peg is the driven down where the

    line touches the top of nail of P3.

    The diagonals (a)(a) should be equal in length to ascertain the accuracy of the setting out operation.

    Building line

    a

    a P2 P1

    P3 7m

    3m 0.12m

  • (c) Theodolite Method This is the most accurate method of setting out

    of buildings. It involves using a surveying instrument called the

    Theodolite. The theodolite is equipped with a telescope and cross

    STEEL SQUARE

    Ranging line

    TIMBER SQUARE

    String line

    Nail

    Builder’s Square

    P3

    P2 P1 P1 3 P2

    4

    P3 5

    Building line

    Timber peg

    Diagonal should be equal

  • hair for sighting and ranging, with an internal graduated readings in

    degrees for establishing bearings (horizontal and vertical angles).

    The method is as follows

    I. Mount and set the instrument at point A, sight the telescope, range

    and peg out E and B to establish the building line.

    ii. Turn the theodolite screws and adjust the degree readings to 0.00.

    Turn the telescope of the instrument on the tripod stand towards the

    right axis until you can sight 900 00” wide. The instrument clamp sight

    the telescope and range to established and peg out points F and C.

    iii. Transfer the instrument to point C, and follow the same procedure at

    A, range A and F, set the angle 0.00”, turn towards the right axis to

    sight and obtain 900 and to establish points G and D.

    iv. Point H could be established by using a measuring tape.

    B

    H

    E A

    F

    C G

    Building line

  • WEEK 4

    EXCAVATION

    Excavation in building construction is simply the act of removing or digging

    out earth (soil) from the ground for the purpose of laying foundation,

    construction of floor, basements, etc. The earth is originally dug up to

    specified depth, width and length.

    The technique of excavation is largely determined by sensitivity of the site

    to vibration, intensity of work, availability of plant and the subsoil

    composition.

    There are basically two methods of excavation, the manual method and the

    mechanical method.

    The manual method involves the use of hand tools such as spades

    diggers, hand augers, pickers (rakes) and other manual implements for the

    purpose of excavation. The manual method is regarded as a cheap means

    of excavation, it is virtually obsolete and time consuming. The method can

    be used only in very small buildings, e.g. garages or house extension,

    where the site is inaccessible to excavating plant, and where archeological

    remains are discovered and particular care is necessary. The method is

    also used for trimming excavations by mechanically means where outward

    projections and deviations are specified.

  • The mechanical method is a process of using mechanical plant and

    equipment for excavation. This use of mechanical plant and equipment

    saves considerable man-hours, and are standard features on all sites. The

    type of plant varies with the nature of work and the different construction

    stages. Plant can commonly be used for

    a. Striping clearance and light demolition

    b. Striping of top soil

    c. Trench excavation

    d. Basement excavation

    The principal types of plant machine used for excavation are

    a. Bulldozer

    b. Loader/backhoe

  • b. Loader/Backhoe (Backacter) – The backachter/loader has on one

    end a toothed bucket and hydraulic boom which extend out and

    excavate towards the cab. This end is used mainly for excavation of

    trenches, basement and ditches. The other is equipped with a

    faceshovel loader for loading excavated loose earth into a dumper, a

    tipper or lorry.

    c. Scrapper – The scrapper contains a larger bowl with covered cutting

    edge for stripping soil. It is used in very large sties, airfield of

    highway.

    Bowl Drop d.p.r

    Cutting edge

  • d. Dragline/Grab Crane – Where the volume of excavation is large, the

    crane- mounted dragline is preferred. The bucket is swinging forward

    to penetrate the subsoil and dragged back towards the cab. Deep

    excavation into granular soils is more effective with a grab or

    „clamshell‟.

    EARTHWORK SUPPORT

    When excavations (trench) are dug in water saturated soils, it is important

    to provide supports to the side of the excavation. This is done to prevent

    the walls from caving-in (collapse) causing severe injury or death to those

    required to work inside the trench. Apart from causing injury and death, it

    will be additional cost to the builder to re-excavate and renew the damaged

    work in the trench. Should the sides support collapse, timber and steel are

  • normally used for trench. The process of supporting trenches is generally

    termed “planking and strutting”. The amount of support, side and system of

    arrangement of the various timers depends on

    a. The type and nature of subsoil to be supported

    b. The depth of excavation.

    c. The length of time the trench is to remain open

    d. The time of year or climatic conditions prevailing when the trench

    is excavated.

    Timber is often the most convenient material for shallow trenches. Steel

    interlocking polings are often used for deep water-logged subsoil.

    Adjustable steel struts are also more convenient and have considerable re-

    use value for all depths of excavation.

    The timbering members used in trench support are as follows

    i. Poling board – There are of 1.0 to 1.5m in length to suit the trench

    depth, and they vary in cross-section fro 175 by 35mm to 225 by

    50mm. They are placed vertically and against the soil of all the sides

    of excavation.

    ii. Wallings – These are longitudinal members running the length of the

    trench and supporting the poling boards. They vary in sizes from 175

    by 50mm to 225 by 75mm.

  • iii. Struts – These are usually squared timbers, either 100 by 100mm or

    150 by 150mm in sizes. They are used to support the wallings, which

    in turn holds the poling boards in position. Adjustable steel struts are

    also in great use.

    iv. Sheeting – These consist of horizontal boards abutting one another

    to provide continuous barrier when excavating in loose soils and

    common size for the sheeting is 175 x 75mm and there is overlap of

    about 150mm at the point of connection between two stages.

    Alternatively, steel interlocking poling with adjustable steep struts are

    used.

    Timbering in loose subsoil

    Sheeting

    Strut

    Wedge Poling

  • Adjustable Steel Strut

    In moderately firm ground, the timbering consists of a series of poling

    boards which are widely spaced at about 60mm centres, supported by

    wallings and struts. In shallow trenches, the poling boards would probably

    only be needed at the about 1.8m centres with each pair of poling board

    strutted individually with a single strut and no walling.

    Timbering in Moderately Form Soil

    In loose or saturated soil, a continuous horizontal sheeting supported by

    pairs of poling boards and struts about 1.8m may be used. Alternatively, a

    Walling

    Poling Board

    Strut

  • continuous length of poling boards or runners supported by walling and

    struts may be used. If the trench exceed more than 1.5m in depth, it is

    necessary to step up the timbering so that the lower stage fits inside the

    upper section.

    CONTROL OF GROUND WATER IN AN EXCAVATION

    There are several methods available for controlling ground water during

    excavation work. Some of the methods deals with lowering, while others

    involves water exclusion from the site. Some of the methods employed in

    the control of ground water during excavation work include

    i. Plumbing Method ii. Dewatering

    iii. Electro osmosis iv. Grouting

    v. Soil stabilization

    1. PUMPING FROM WELL OR (SUMP)

    Pumping from sump is the most used for used of ground water

    control since it is economical to install and maintain and can be

    applied to all types of ground conditions.

    The only problem is of the movement of the soil due to settlement

    and there is also the risk of instability at the formation level of the

    excavation. Where the excavation goes through permeable soil and

    continued into impermeable soil, it is better to form a drain at the line

  • of interception to carry water in the sump. With this system a sump is

    constructed at one corner of the site which forms a well point

    continuous pumping of water.

    The pump which is mounted on the ground level has one

    disadvantage due to imitation in the design of suction lift to some

    types of pumps. The suction lift of most pumps is at 7.5m – 9m. For

    deep excavation where the depth exceeds 9m, the pump will have to

    be placed in the excavation or on a level suitable for the suction lift.

    2. DEWATERING

    This consists of lowering the water table over the area of the site and

    is satisfactory for depths up to 16m, it is particularly suitable where

    running sand is encountered for once the water has been removed in

    the ground, the sand become relatively stable. The equipments used

    for the separation comprises of

    i. Jetting pump, for driving down the well points

    ii. Suction pump iii. Header pipe and

    iv. Rises pipe.

    The operation of dewatering is carried out by first jetting the well

    points into the ground, this is done by securing each well points to

  • 38mm diameter riser pipe at the top of which there is a connection by

    a hose to the jetting pump. The assembled well points are held on

    the ground and the pump operator delivers water under pressure until

    the point penetrates the ground. The well points on reaching the

    desired depths, the points are “sounded in” the hose of the top of the

    well point is determined from the jetting point and attached to 150mm

    diameter header pipe has coupling joint at 760mm 1m intervals so

    that rises can be jointed at this spacing. For dealing with large volume

    of water in loose ground or lose sand. The equipment can be used

    for 2 main types of work.

    i. The ringing system ii. The progressive system for

    trenching.

    i. Ringing System – In this system, the building site is encircled

    with needle points and for single stage work, until permit

    building work to be done at depth up to 6.5m where excavation

    of 9m – 12m are required 2 stage work is adopted. For this, the

    top are in dewatered and excavated first, the area is then

    ringed at this intermediate stage for dewatering the corner

    depth.

  • ii. Progressive System – This is suitable for dewatering along

    the line of trenches before excavation. The wall points are with

    draw when work is completed and filled in dead of the work.

    The header pipe in laid along the ink of the proposed trench as

    near as practicable. In different ground the pipe is placed in the

    trench and supported on struts.

  • WEEK 5

    FOUNDATIONS

    A foundation is defined as, that part of a structure which is in direct contact

    with the ground to which super imposed loads and dead loads are

    transmitted or received. It is also an integral part of a building which

    transfers the structural load from a building safely to the ground. Many at

    times, during the construction of a building, the load on the foundation

    gradually increases and eventually, this will result in settlement if the

    settlement is slight and uniform throughout the area of the building, no

    damage will occur to the building.

    But if the settlement is extensive and unequal, serious damage may result

    in the form of cracked walls, distorted doors and windows and in some

    cases failure may be completed by the collapse of the building.

    Selection of foundation types and design depends on the total building load

    and the nature and quality of the subsoil. It is essential to achieve a

    satisfactory balance between the building load and subsoil characteristics,

    otherwise overstressing of the subsoil will lead to excessive building

    settlement and serious structural defeats.

    The purpose (importance) of foundation is to distribute the weight of the

    structure to be carried over a sufficient area of bearing surface, so as to

  • prevent the subsoil from spreading and to avoid settlement of the structure.

    A foundation should safety sustain (Carry) and transmit to the ground the

    combined dead load, imposed load and wind load, without impairing the

    stability of any part of the building.

    A foundation is designed to support a number of different kinds of loads.

    (a) The DEAD LOAD of the building, which is the sum of the weight of

    the frame, the floors, roofs, and walls, electrical and mechanical

    equipment and the foundation itself.

    (b) The LIVE (IMPOSED) LOAD, which is the sum of the weights of

    people in the building, the furnishings, sanitary fixtures and the

    equipment they use, snow, ice and rain load on the roof.

    (c) The WIND LOAD, which can apply literal, downward, and uplift load

    to a foundation.

    All foundation settle to some extent as the soil around and beneath them

    adjust itself to the loads. Foundation settlement in most buildings is

    measured in millimeters. If the total settlement occurs roughly at the same

    rate from one side of the foundation to the other, no harm is likely to be

    done to the building. This is because all parts of the building rest on the

    same kind of soil. But if differential settlement occur (when the building

    occupies a piece of land that is underlain by two or more areas of different

  • types of soil with very different load bearing capacities) in which the various

    columns and load bearing walls of the building settle by substantial different

    amounts, the frames of the building become distorted, floors may stapes,

    walls and glass may crack, doors and windows may be difficult to open,

    etc. the primary objective of foundation design is to minimize differential

    settlement by loading the soil in such a way that equal settlement occur

    under the various parts of the building.

    SOILS IN FOUNDATION

    Where the foundation of a building is on rock, no measurable settlement

    will occur, whereas the building on soil will suffer settlement into the ground

    by the compression of the soil under the foundation load. Some settlement

    on soil foundation cannot be avoided, because as the building is erected,

    the load on the foundation increases and compresses the soil. This

    settlement must be limited to avoid damage. Bearing capacities for various

    rocks and soils determined and should not be exceeded in the design of

    the foundation to limit the settlement.

    Soils are classified with regards to their size, density and nature of the

    particles. Soil can be classified into three broad groups namely coarse

    grained non-cohesive, fine grained cohesive and organic soils.

  • Coarse grained non-cohesive soil – This consist of coarse and larger

    siliceous product under pressure from the loads on foundation. The soil in

    this group compresses and consolidates rapidly by some rearrangement of

    the particles and expulsion of water.

    A foundation on this type of soil settles rapidly by consolidation of the soil,

    as the building is erected, so that there is no further settlement once

    building is completed.

    Fine grained cohesive soils – This consists of natural deposits of the

    finest siliceous and aluminous product or rock weathering such as clay.

    Clay is smooth and greasy to touch, it shows high plasticity, dries slowly

    and shrinks appreciably on drying. Under pressure of load on foundations,

    clay soils are gradually compressed by the expulsion of water from the soil

    so that the buildings settle gradually during building work and this

    settlement may continue for some years after the building is completed.

    Firm shrinkable clays suffer appreciable shrinkage on drying and expansion

    of firm clay under grass extends to about 1 metre below the surface and up

    to 4m or more below large trees. Building on shallow foundations should

    not be close to trees, shrubs and trees should be removed to clear a site

    for building on firm clay subsoil. This is because gradual expansion or

    contraction (shrinkage) of the soil will cause damage to the building by

  • differential movement. This is as a result of the intake of subsoil water by

    the tree roots.

    Organic soils – Such as peat are not generally suitable foundation for

    buildings. Foundation of this type soil are normally carried down to a

    reliable bearing stratum.

    TYPES OF FOUNDATIONS

    There are four principal types of foundation strip, pad, raft and pile

    foundations.

    1. STRIP FOUNDATION

    This type of foundation is a continuous level support for load bearing

    walls. It is usually made of a continuous strip of concrete of 136 mix,

    and may be reinforced (126) mix for poor subsoil or high loading.

    The continuous strip serves as a level base on which the wall in built

    and should be of such width as to spread the load on the foundation

    to an area of subsoil capable of supporting the load without stress.

    The width of a concrete strip foundation depends on the bearing

    capacity of the subsoil, the less the width of the foundation for the

    same load. The minimum width of a strip foundation is 450mm and

    least thickness is 150mm. they are suitable for low-rise construction.

  • SECTION THROUGH A STRIP FOUNDATION

    (a) Wide Strip Foundation

    This type of foundation is used where the structural loading is very

    high or relative to the subsoil bearing capacity. It is generally

    cheaper to reinforce the concrete strip to reduce the equivalent

    strength thickness to carry and spread the load.

    2P + W

    P x P

    G.L.

    Solid brick wall

  • (b) Deep Strip Foundation

    This type of foundation has two applications

    i. Narrow strip or trench fill

    ii. Reinforced deep strip

    The Narrow strip (trench fill) is designed to save considerable

    structural construction time and where the nature of the subsoil such

    as clay requires a considerable depth of 900mm, it is used to

    excavate foundation trenches and fill them with concrete up to just

    below the ground level say 2 brick coarse before the finished ground

    level.

    Wall G.L.

    150m

    1.2m

    Reinforcement

  • Reinforce deep strip are acceptable alternative to wide strip

    foundation for soft clay subsoil conditions. The depth should be at

    least 900mm to avoid effect of shrinkage and swelling and about

    400mm wide to provide sufficient support for the wall. Reinforcement

    is required to take care of compressive stress as subsoil may develop

    voids in long periods of dry weather due to volume change.

    400

    900

    P

    G.L.

  • 2. PAD FOUNDATION

    These are isolated pairs or column of brick, masonry or reinforced

    concrete often in the form of a square or rectangle pad of concrete for

    supporting ground beans, and in turn supporting walls. It is very

    economical to use pad foundation where the subsoil has poor bearing

    capacity for some depth below the surface, rather than excavating

    deep trenches and raising wall in strip foundations. It is also used

    where isolated columns are specified, especially in framed buildings.

    The spread of area of this type of foundation depends on the load on

    the soil and the bearing capacity of the subsoil.

    400

    900

    G.L. Wall

    Reinforcement

  • FOUNDATION PLAN SHOWING EXCAVATION WORK FOR PAD

    CONSTRUCTION

    SECTION THROUGH A PAD FOUNDATION

    A B C

    A 2

    3

    Reinforcement

    column

    Reinforcement

    Pad foundation

  • 3. RAFT FOUNDATION

    In soft compressible subsoil, such as soft clay or peat subsoil. It is

    necessary to form a raft foundation to spread over the whole base of

    the building. Raft foundation consists of a raft of reinforce concrete

    under the whole of the building design to transmit the load of the

    building to the subsoil below the raft. Relative settlement between the

    foundations of columns is avoided by the use of a raft foundation.

    The two types of raft commonly used are the flat raft (solid slab raft)

    foundation and wide toe raft (beam and slab raft) foundation.

    Mat Reinforcement for pad foundation

    building

    Ground beam

    Four members of starter bar

    G.L.

  • (a) Flat Raft (solid slab raft) Foundation

    This comprises of a reinforced concrete slab of uniform

    thickness cast on a bred of blinding concrete and a deny proof

    membrane, under the whole area of the building. This type of

    foundation is used on loose subsoil with reasonable bearing

    capacities for small buildings, such as houses. The slab

    normally reinforced top and bottom.

    (b) Wide Toe Raft Beam and slab rift ) Foundation

    50 Blinding Damp proofing

    membrane

    Reinforcement

    G.L.

    Cavity wall

    Floor finish

    50 spread (cement

    & sand)

    100 mass concrete

    floor

    150 reinforced

    concrete raft

  • This is like a reinforced concrete floor with down stand beams

    called toe. It is used when the ground has poor compressibility.

    The reinforced concrete edge beam is designed to support the

    outer skin of the brick work or columns. The strengthened

    beam collect loads from the walls or columns and transmit

    these loads to the slab cast integrally with the beam, and the

    slab in turn spread the loads over the whole area of subsoil

    below the building.

    Reinforcement

    Damp proof membrane

    100 hardcore

    Blinding

    Reinforced concrete raft

    Screen

    Floor finish

    Cavity wall

    G.L.

  • 4. PILE FOUNDATION

    Pile foundations are used where the subsoil has poor and uncertain

    bearing capacity and in poor drained area where the water table is

    high and there is appreciable ground movement. Piles are usually

    employed because in these types of subsoil, it might be necessary to

    excavate beyond 2m to meet a stable stratum. And it is uneconomical

    to consider normal excavation beyond about 2m below the ground

    level. The pile column of concrete either cast insitu or precast driven

    into the ground to transfer the loads through the poor bearing soil to a

    more stable stratum. Boring is undertaken by a powered auger. The

    pile foundations are normally employed in the construction of bridges

    and oil platforms on seas.

    Short Bored Piles - These are used for small buildings on shrinkage

    clays where adjacent trees could appreciate volume change in the

    subsoil. Short bored (short length) piles are cast in holes by hand or

    machine auger. The piles support reinforced concrete ground beams

    on which wall are raised.

  • Reinforced

    Concrete beam

    Building

    Poor grade

    subsoil Piles

    G.L. Sound bearing strata

    Depth up

    to 4m

    G.L.

    Reinforced

    concrete beam

    Concrete pile

    Hardcore

    Sand blinding

    Ground floor slab

  • FOUNDATION ON SLOPING SITES

    Walls foundation on sloping sites are normally constructed at one level or

    stepped. Where the slope is slight the foundation may be at one level with

    floor raised above the highest ground level. Where there is a greater slope,

    it is usual to cut and fill so that the wall at the highest point does not act as

    a retaining wall and there is no need to raise the ground floor above the

    highest point of the site. The process of “cut and fill” is normally practiced

    when providing foundation for walls on sloping sites. This is the operation

    of cutting into part of the higher part of the site and filling the remaining

    lower part with the excavated material or with the imported materials (for

    Depth determined by resistance to

    driving

    G.L.

    Reinforced

    concrete beam

    Steel sleeve

    Hardcore

    Sand blinding

    Ground floor slab

    Hollow fibre reinforced concrete shell

    Solid concrete shoe

    280

  • fill). It should be noted that cutting extends beyond the wall at the highest

    point to provide a drained dry area behind it.

    Where a building extend some distance up an appreciable slope, it is usual

    to use stepped foundation to economize in excavation and foundation

    walling.

    Foundation at one level

    Stepped Foundation

    G.L.

    Consolidated fill

    under solid floor

    Consolidated fill

    under solid floor

    Steeper slope

    Ground

    Shallow slope

  • STEPPED FOUNDATION

    METHODS OF REINFORCEMENT IN FOUNDATIONS

    1. GROUND BEAMS

    Reinforced concrete

    building slab

    Ground

    bearing slab

    Selected soil

    fill

    Compacted

    hardcore Existing G.L.

    Top soil removed

    Slab of raft reinforced top

    and bottom

    Section through reinforced concrete ground beam and slab raft with upstand

    beams

    R.C. Beams

    Reinforcements

    Floor construction with precast R. C. Beams bearing

    on upstand beams on raft.

  • Raised timber or concrete floor

    formed on raft

    Reinforcements

    R.C. Slab reinforced

    top and bottom R.C. Beams

    G.L.

    Reinforcements

    Helical building

    hand

    Lifting hole

    Press steel forms

    Corner for R.C.

    Main reinforcement

    Stirrups to

    Lifting hole

    Chilled cast iron

    shoe

  • Cover

    Forks

    Links

    Section of a

    body of pile

    Main reinforcement

    Cast iron shoe

    Cast iron shoe

    End of tube

    Cage of reinforcement

    Steel

    Concrete consolidates as

    the tube is withdrawn Finished reinforcement

    concrete pile

  • METHODS OF CONSTRUCTION OF VARIOUS FOUNDATIONS

    1. STRIP FOUNDATIONS

    Construction of strip foundation is carried out by first excavating the

    ground to specified volume to remove soil to receive concrete. A

    fairly dry weak concrete is the placed to specified depth inside the

    foundation already containing a hardcore base (if necessary). This is

    to act as a working base and to receive the oversite concrete. Where

    a reinforcement or mesh are required, they are placed on mortar

    blocks or concrete blocks (biscuit) on the blinding to give the cover for

    concrete. A leveling instrument or a building plumb and short iron

    pegs (off cuts) are then used to establish the tip level of the

    concreting in the trench at intervals throughout the length of the

    foundation trench. Concrete is then mixed and is poured into the

    trench over the reinforcement until it reaches the established pegs.

    As pouring is done a potter vibrator is used to vibrate the concrete to

    remove the voids from the concrete. The concrete is then left to set

    and harden and cured with water after one day of easting for at least

    7 days.

  • 2. PAD FOUNDATION

    This is similar to the strip foundation construction, except that instead

    of excavating in strips, deep hollow square or rectangular trenches

    are dug. The provision of reinforcement for the base of the pad

    interlock with the vertical reinforcement going up for the columns.

    This is to ascertain a continuous interlocking support, strength and

    stability between the pad and the concrete column. Where steel

    stanchions (columns) would be placed on the pad foundation,

    steel/iron bolts or steel plates are embedded in the foundation during

    construction, where the stanchions or columns would be placed

    (bolted or welded) on the pad foundations.

    Concrete is then mixed, poured or placed, vibrated and cured as in

    the strip method. In some cases formwork are sometimes used to

    protect the sides and give shape to the pad.

    3. RAFT FOUNDATION

    The raft system involves the excavation of the whole base area of the

    building and where ground beams are specified, is further excavated

    below the raft slab foundation. Formwork is made to support the sides

    of the foundation and insitu slab.

  • The placing of reinforcement for the slab and beam interlock or

    overlaps. The placing of concrete and curing is as in the strip

    method.

    4. PILE FOUNDATION

    (a) Bored Piles

    This method is an insitu concrete construction. It consists of drilling

    or boring a hole by means of earth drills or mechanically operated

    augers which withdraws soil from the hole for casting of pile in

    position. Usually steel lining tubes are lowered or knocked in as the

    soil is taken out, to support the sides of the board pile.

    Reinforcement are placed, concrete is then placed and compacted in

    stages. As the concrete pile is cast the lining tubes are gradually

    withdrawn

    The disadvantages of this method are that it is not possible to check if

    the concrete is adequately compacted, and there may be no

    adequate cover to the concrete reinforcements.

    (b) Precast Concrete Piles

    As the name implies, these are precast either round, polygonal or

    square concrete, steel or timber piles which are driven into the

    ground by means of a mechanically operated drop hammer attached

  • to a mobile piling at a calculated predetermined „set‟. The word „set‟ is

    used to describe the distance that a pile is driven into the ground by

    the force of the hammer.

    To concrete the top of the precast piles to the reinforced concrete

    foundation at the top, 300mm of the length of reinforcement of the

    pile is exposed, to which the reinforcements of the foundation is

    connected.

    Precast driven piles are not in general use on sites in built up area

    (unrestricted area) due to

    i. Difficulties in moving them through narrow streets

    ii. Nuisance caused by the raise of driving piles and vibration

    caused by driving the piles may damage existing adjacent

    buildings.

  • WEEK 6

    DAMP PROOFING

    SUBSTRUCTURAL WORKS

    RISING AND SEEPAGE OF GROUND AND UNDERGROUND WATER

    If water is to rise of seep in a wall or floor, a constant supply must be

    available at the base and side of the floor and wall. Water rise by an

    upward capillary pull between the masonry pores. On building sites with

    high water table and on slopping sites where water may run down to the

    building, site concrete, floors and walls are likely to get damp by the

    respective rising and seepage or moisture/water. The obvious indication of

    rising damp and seepage is the dark staining above the skirting, bored on

    the interior of a wall. This however, should be carefully checked to avoid

    misconception of defective plumbing, leaking gutters/down pipes, and

    defective chimney. Another indication of rising damp is the appearance of

    white salty deposits on both faces of a wall called efflorescence. It is drawn

    from the ground as the dampness rises, and they combine with any salt in

    the masonry.

    Rising and seepage into building is due to the lack of provision of damp

    proofing materials, or may also be due to several possible construction

  • faults (i.e., in the cases where damp proofing materials are provided).

    Some of these faults may include the following

    The arrows ( ) indicate rising and seepage of ground

    and underground water

    IMPORTANCE OF DAMP PROOFING IN SUBSTRUCTURAL

    WORKS

    Damp roofing is the principle of preventing moisture entering buildings and

    causing dampness which might be as a result of water/moisture rising up

    the wall and floor from the ground forced through the structure, or seeping

    through the forces of walls.

    d.p.c

    d.p.c

    Bridging though

    mortar painting

    Paving or drive finished above

    d.p.c

    Earth stacked

    against wall

    Rendering

    over the d.p.c

  • One chief essential requirement in building construction is to construct a

    structure which is habitable and dry to live in. A dry building is unsightly

    and causes damages to some components of the structure affected.

    Most structural works are intended to be dry habitable. Any moisture

    movement upwards from the ground through the substructural works to the

    superstructure hampers the functional requirements of the affected building

    components, and this reduces the quality of construction. The intended

    purpose/use of the structure may also be defeated. Concrete is to some

    degree permeable to water and will absorb moisture from the ground. A

    damp oversite concrete slab may cause deterioration and damage in

    moisture sensitive floor finishes such as timber or P.V.C. A damp oversite

    concrete also will be cold and draw appreciable heat from rooms causing

    cold.

    Damp proofing helps the prevention of moisture rising up the floor or

    seeping through walls, causing efflorescence and damage to the walls and

    floor finishes.

    Generally, damp proofing helps to maintain the quality, strength, stability,

    durability and resistance to moisture/water of structures. It also helps to

    maintain an appreciable room temperature. And to provide protection to

  • final finishing materials to concrete floors. A damp proofing materials must

    be incorporated in concrete floors.

    PROCESSES OF DAMP PROOFING

    The process of damp proofing involves the provision of a continuous layer

    of horizontal damp proof coarse (d.p.c) at about 150mm above finished

    ground level in walls whose foundation are below the ground. And the

    provision of a damp proof membrane (d.p.m) for the entire area on top is

    between or under the oversite concrete slab.

    The d.p.c should be impenetrable and continuous for the whole length and

    thickness of the wall and be at least 150mm above finished ground level.

    This is to prevent or avoid the possibility of a build-up of materials against

    the wall acting as a bridge for moisture seeping through the wall.

    A d.p.m should be impenetrable to water and touch enough to withstand

    possible damage during laying of screeds or floor finishes. Application of

    d.p.m. on irregular surfaces tend to puncture the membrane, so the

    application of this materials should be done on a bed of sand or ash of

    12mm thickness. The d.p.m may be on top, sandiviched in or under the

    concrete slab.

    All d.p.c, in external walls should unite with d.p.m in, on, or under the

    oversite concrete. This may be affected by either laying the membrane in

  • the concrete at the same level as the d.p.c in the wall or by uniting the

    membrane and d.p.c, laid at different levels with a vertical d.p.c.

    Narrow trench fill foundation

    d.p.c and p.p.m at same level

    Concrete strip foundation

    d.p.c and d.p.m at different level

    150 concrete oversite

    50 blinding

    d.p.m

    50 screed

    d.p.c

    Cavity wall

    d.p.c abd d.p.m Overlaps

    Hardcore

    Hardcore

    d.p.c abd d.p.m Overlaps

    d.p.c

    Cavity wall

    Cavity wall

    d.p.m

    100 concrete oversite

    Bed of sand or ash

    d.p.m

  • FUNCTION OF A DAMP PROOF COURSE

    Damp proof course is a layer of material capable of preventing the

    penetration of moisture. It is laid on top of all walls at a distance of 150mm

    above the finish ground level.

    A d.p.c is an unbroken layer of impenetrable material on most foundation to

    prevent the moisture absorbed from the soil rising and causing dampness

    in the wall. Moisture penetration and rising dampness constitutes health

    risks and cause discomfort to the inhabitants of the building.

    Generally, d.p.c helps the preservation of wall finishes especially at the

    base of the walls. d.p.c also provides protection against the dampness

    arising from during rain. d.p.c reduces the tendency of the moisture to rise

    up to the wall finishes, like rendering and painting at crack blister, peel,

    flake, slow drying, etc.

    TYPES OF DAMP PROOFING MATERIALS

    1. Damp proof membrane materials

    a. Hot, pitch or bitumen

    b. Bitumen sheets/solutions/tar

    c. Mastic asphalt

    d. Polythene sheet

  • 2. Damp Proof course

    a. Flexible d.p.c materials

    (i) Lead

    (ii) Copper

    (iii) Bitumen

    (iv) Polythene sheet

    b. Semi-Rigid d.p.c materials

    (i) Slates

    (ii) Bricks

    BASEMENT CONSTRUCTION

    METHOD OF CONSTRUCTION OF BASEMENT PROCEEDS IN

    STAGES

    1. Excavation begins at ground level and the sides are supported by

    timbering.

    2. This continues until the required dept is reached.

    3. Foundation is cast and walls started. Timbering is removed

    progressively and the space backfilled.

    4. The wall reaches ground level all around the excavation.

    5. The soil inside the walls can then be removed, if necessary.

  • BASEMENT EXCAVATION

    The excavation for deep basements started at ground level, as the holes

    becomes deeper a decision base to be made about the method to be

    employed.

    If ramp of earth is left in position, tipper tracks can use it to get into and out

    of the hole. This depends on the length of the excavation, as it must be

    able to accommodate a ramp of about 200 slope. Weather condition and

    type of soil may also be considered as this may affect the use of the ramp

    by loaded vehicles.

    The ramp may be removed finally. If this is done by an excavator, with the

    soil being removed by bucket and crane, the excavator will have to be

    hoisted out on completion. If vehicles cannot drive out of the excavation,

    the soil will have to be loaded into buckets, hoisted to the surface and

    loaded on to trucks. The excavator is finally lifted out by crane. Where

    excavation is not very deep, hand excavation may be used.

    Various types of earth moving and excavation plant are available for use in

    different circumstances, e.g. bulldozer shovel back actions and drag-line

    grab crane excavators, loader and truck.

  • PRINCIPLE OF TANKING IN BASEMENT WORKS

    Tanking is a system of forming a continuous waterproofing lining usually in

    asphalt round the walls and floor of a basement as a barrier to rising and

    penetrating dampness. The term tanking can also be used to describe a

    continuous waterproofing lining to the walls and floors of substructures (e.g.

    basement structures) to act as a tank to exclude water. This principle is

    known as Basement taking.

    The traditional material for tanking is mastic asphalt which is applied and

    spread hot in three coats to a thickness of 20mm for vertical and 30mm for

    horizontal work. Joints between each laying of asphalt in each coat should

    be staggered at least 75mm for vertical and 150mm for horizontal work with

    the joints in succeeding coats. Angles are reinforced with two coats of fillet

    of asphalt.

    Asphalt is usually applied to the outside face of structural walls and under

    structural floors so that the walls and floors provide resistance against

    water pressure on the asphalt, and the asphalt keep water away from the

    structure.

    Where the walls of the structure are on site boundaries and it is not

    possible to excavate to provide adequate working space to apply asphalt

    externally, a system of internal tanking may be used.

  • An internal lining is rarely used for new buildings because of the additional

    floor and wall construction necessary resist water pressure on the asphalt.

    Internal asphalt is sometimes used where a substructure to an existing

    building is to be water proofed.

    HARD CORE

    This is an application of suitable material suck as broken bricks, stones and

    tiles, clinker, gravel, quarry waste, which are required on the building site to

    fill hollow oversite concrete work. On wet sites, it may be used to provide a

    firm working surface and to prevent contamination of the lower part of the

    wet concrete during compaction.

    The particle materials should be hard and durable, not subject to decay or

    breakdown by weather or chemical attack, and it should be easily placed

    and well compacted. The hardcore should be spread until it is roughly level

    and round until it forms a compact bed for the oversite concrete. The

    hardcore bed is usually 100 to 300mm thick. It is spread to such thickness

    as required to raise the finished surface of the oversite concrete.

    Generally, the hardcore bed serves as a solid working base for building and

    as a bed to receive oversite.

  • BLINDING

    Is a process of providing a layer of dry concrete, coarse clinker or ash over

    the hardcore before placing the oversite concrete. Before the concrete is

    laid it is usual to blind the top surface of the hardcore. The purpose is to

    prevent the wet concrete running down between the lumps of broken brick

    or stone, as it would make easier for water to seep through the hardcore

    and could be wasteful of concrete. To blind or seal, the top surface of the

    hardcore a thin layer of very dry coarse concrete can be spread over it, or a

    thin layer of coarse clinker or ash can be used. the blinding layer, or coat,

    will be about 50mm thick, and on it the site concrete is spread and finished

    with a true level top surface.

    USE OF ANTI-TERMITE TREATMENT IN FOUNDATION WORKS

    A problem in tropical climates is the possibility that timber maybe attacked

    by termites. The common termite or white ant forms colonies in the ground

    where a nest housing the queen is found. The termites can enter a building

    through the ground looking for timber to consume. The junction of the wall

    and floor is a particularly vulnerable point.

    There are some precautions which can be taken to reduce the risk of

    termite attack.

  • 1. The area around the building should be inspected for termite nests,

    which should b dug out and treated with insecticide.

    2. During excavation work for the foundation and hardcore bed, the

    exposed soil should be treated with insecticide, in an anticipation of

    termite attack.

    3. The ground floor concrete should be raised above the adjourning

    ground level and should project beyond the outer wall face.

  • WEEK 7

    FLOORS

    Floors are structural parts of a building. They are usually designed to be of

    either a timber or concrete work. Generally, in building construction floors

    are designed and constructed for the flowing primary purposes (function):

    a) Provision of a uniform level surface: - Unless otherwise specified,

    floors are constructed to provide a uniform level surface, this is done

    primarily to sufficiently provide adequate support, comfort, stability

    and strength to carry people, their furniture, equipment and materials.

    b) Exclusion of Dampness from inside of the building (especially

    ground floors): - Floors also function as to prevent the passage of

    moisture rising up/surpring through foundations/walls and causing

    dampness and discoyort inside the building, this is normally attained

    by using a d.p.m.

    c) Thermal Insulation: - Floors minimize the transfer of heat from the

    building to the ground of the building. A floor also serves to conserve

    or reduce heat as the case (situation) may require. In this case

    insulations or special finishing materials are used.

    d) Sound Insulator: - Floors also serve as a barrios to transmission of

    airborne sound and reduce impact sound, (especially upper floors)

    normally concrete is preferred to timber because timber readily

    transmit sound than concrete where timber are used they are

  • normally insulated with weight material (by filling the spaces between

    the timber joists)

    e) Fire Resistant: - in addition to the above functions, floors (especially

    upper floor) are resistant, to fire to some considerable degree. They

    provide resistance adequate for the escape of the occupants from the

    building in times of fire outbreak.

    f) Compatibility with the Surface Finish: - The purpose of a floor is

    also to provide an adequate and acceptable surface finish to meet the

    need of the user, with regards to appearance, comfort, cleanliness,

    stability and safety.

    GROUND FLOORS

    There are primarily two types of ground floors solid ground floor and

    raised timber ground floor.

    A) SOLID GROUND FLOORS

    There are normally constructed in-situ concrete. Solid concrete

    ground floors have three principal components; hardcore, a damp

    roof membrane and a layer of dense concrete. To construct these

    types of floors, hardcore is compacted onto the reduced ground level

    after excavation.

    To prevent cement ground loss from the superimposed concrete

    layer, or to protect a damp roof membrane from fracture, the hardcore

    is blinded with a 25mm layer of sand.

  • The damp-proof membrane maybe positioned below the concrete

    slab, upon the sand blinding polythene, sheet is the most popular

    material, although bituminous sheet is acceptable. Alternatively, the

    d.p.m. maybe sandwiched between the finishing their screed and the

    structural concrete slab. In this particular case, cold or hot application

    of bituminous solution in three layers with final layer sprinkled with

    sand to bond to the screed overlay.

    The concrete slab is of 100 – 150mm in thickness, composed of

    cement, fine aggregate and coarse aggregates in the ratio of 1:3:6 to

    provide a minimum strength specification of 1hr/mm2 at 28 days with

    coarse aggregate of 38mm. A mix of 1:2:4 is preferred when using

    coarse aggregate of 19mm size. A tamping bar is used to compact

    and level the concrete to the specified depth-provided by short iron

    pegs with finishing provided by cement/sand (1:3) screed.

  • B) SUSPENDED (RAISED) TIMBER GROUND FLOORS

    This system of providing ground floors in buildings is now virtually

    obsolete due to the escalating cost of the materials and skilled labour

    required for their installation. Some few centuries ago houses were

    constructed with timber ground floors raised 300 or more above the

    site concrete or earth. This was done to have the surface of the

    ground floor sufficiently above the ground level to prevent them being

    cold and damp during winter.

    Construction of this type of floor is made up of selected timber

    platforms of hardwood floor boards nailed across timber joists, and

    the joists in wall plate bearing on ½B thick sleeper walls, built directly

    off the site concrete 1.8 apart. Sleeper walls are generally built three

    courses of brick high, and are also built honey-combed to allow fire

    circulation of air below the floor, to prevent wood decay. Air bricks are

    also provided along external wall also to aid the circulation of air.

    Component Parts of the raised timber ground floor construction:

    a. Honey-comb sleeper wall: - sleeper walls are ½B thick built directly

    off the site concrete about 1.8-2.0m apart. These sleeper walls are

    generally built at least three courses of brick high and sometimes as

    high as upto 600mm. The walls are built honey-combed to allow free

    air circulation below the timber floor members.

  • b. D. P. C.: - This is spread and embedded on top of the sleeper walls

    to prevent any moisture rising through the site concrete and sleeper

    walls to the timber floor.

    c. Wall Plate: - This is a continuous length of softwood timber which is

    embedded in mortar on the d.p.c. The wall plate is bedded so that its

    top surface is level along its length and also level with the top of wall

    plates on other sleeper walls. This timber member is usually 100 x

    75mm and is laid on one 100 face so that there is 100 surface with on

    which the timber joists bear. The function of a wall plate for timber

    joists is two-fold: -

    (i) It forms a firm level surface on which the timber joists can bear

    and to which they can be nailed.

    (ii) It spreads the point load from joists uniformly along the length

    of the wall below.

    d. Floor Joists: - These are rectangular section softwood timbers laid

    with their long sectional axis vertical and laid parallel spaced from

    400 to 600 apart.

    Floor joists are from 38 to 50 thick and 75 to 125 deep timber boards

    are laid across the joists and nailed to form a firm level floor surface.

    e. Floor Boards: - For timber, floor boards are usually 16,1921 or 28

    thick and from 100 to 180mm wide and up to 5.0m in length. The

    edges of the board maybe cut square or plain edged, though this

  • being the cheapest of cutting and fixing them, but boards tend to

    shrink causing ugly cracks and the edges to open up. The usual way

    of cutting the edges of floor boards is by providing a torque on one

    edge and a groove on the opposite edge of each board, commonly

    termed T and G. The boards are laid across the floor joists, cramped

    together and nailed to the joists with two nails to each board bearing

    on each joist.

    f. Ventilation using air bricks: - In order to avoid deterioration of timber

    under the floor board or suspended timber ground floor, there is need

    to allow air circulation under the floor system. In order to achieve this

    special air bricks must be provide at the external walls of the building

    and adequately spaced. The purpose of these air bricks is to cause

    air to circulate under the floor and thereby preventing stagnant air

    which is likely to induce dry rot fugues to grow and causing word

    decay.

    In summary therefore, construction of the raised timber ground floor

    can be achieved the assemblage of the above conform placed on a

    concrete slab on a hardcore based.

  • SUSPENDED (UPPER) FLOORS

    There are two main types of upper floors, timber upper floors and

    reinforced concrete upper floors. Though timber upper floor

    construction is about half the cost of a similar reinforced concrete

    floor, concrete floors are still preferred because of their better

    resistance to fire and to sound transmission and supports heavier

    loads.

    1. TIMBER UPPER FLOORS

    There is no much difference in construction between the timber upper

    floor and suspended timber ground floor. The only noticeable

    difference is the elimination of sleeper walls in the upper floors, which

    consequently involved the use of layer timber section for the floor

    joists.

    i. Strutting between Joists: - Timber floor joists spanning more than

    3.0m are strutted at mind-span or 15m spacing to resist buckling and

    deformity. This is done to safeguard and prevent cracking of the

    plastered ceiling work due to excessive shrinkage and movement of

    the joist. The herringbone strut arrangement using 50 or 38mm

    square softwood struts is most efficient, but solid strutting is often

    used for easier and quicker installation. Solid strutting consists of

    short lengths of timber of the same section as the joist which are

  • nailed between the joists either in line or staggered. This is not

    usually so effective as the herringbone system, because unless the

    short solid lengths are cut very accurately to fit to the sides of the

    joists they do not firmly strut between the joists. As with herringbone,

    between the first and the last joists and adjacent walls folding wedges

    are used to firmly locate the strutting.

    ii. End Support for Floor Joists: - The floor is normally framed with

    softwood timber joists, with maximum economical span of between

    3.6 and 4.0.

    The required depth of joists depends on the total load. For

    stability, the ends of floor joists must have adequate support from

    walls or beams. There are various methods of supporting the ends

    of joists in order to sustain the imposed loadings.

    a) The ends of the joists are treated with preservatives (to avoid

    decay) and are built into the brick walls. This method requires

    cutting and packing of trick work in order to bring the top of the

    joist on the same plane, care must taken to prevent joist

    protinding into the cavities of the cavity wall and providing a

    bridge for moisture penetration. Alternatively timber floor joists

    can be built into wall to bear on a wall plate of timber or metal,

    which are along the length of the wall beneath the joists, this

    assist in spreading the load from the floor along the length of

  • the wall and also as a level bed on which the joists are placed

    and nail in position. The wall is then raised between and above

    the floor joists.

    b) End support for the joists can also be attained by the use of

    galvanized steel floor hangers, which are built into brick or

    block courses so that they project and support the ends of the

    joists. This is the best method of providing supports to joist

    from external walls as it avoids building timber into walls.

    As an alternative to hangers, timber floor joist maybe supported by

    a timber wall plate carried on iron corbels built into walls, or brick

    courses corbelled out from the wall. The disadvantage of these is

    that they form a projection below the ceiling.

    iii. Floor Boards: - As with timber ground floors, the boards usually

    19 or 21 thick have T & G edges core cramped up and nailed

    across the floor joists, with the heading joints staggered.

  • (ii) GALVANIZED

    STEEL FLOOR

    HANGERS

    Hangers built into wall

    to support joists.

    (iii) STEEL CORBELS BUILT

    INTO SUPPORT WALL

    PLATE

    Wall plate

    support joists

    Corbels built into wall to

    support wall plats/joists.

    (IV) WALL PLATE SUPPORTED

    OR TWO CORBELS OF BRICK

    CORBEL WALL PLATE

    Two-course brick corbel

    brick wall plate

  • 2. REINFORCED CONCRETE UPPER FLOORS

    Reinforced concrete floors have a better resistance to damage by fire

    and can safely support greater super imposed than timber floors of

    similar depth.

    (a) Monolithic Reinforced Concrete Floors: - As the name

    implies a monolithic reinforced concrete floor is an unbroken

    solid mass of concrete between 100 and 300 thick, cast in-situ

    and reinforced with steel reinforcing bars.

    Construction of monolithic reinforced concrete floor consists of

    a temporary CONFERRING (consists of timber/steel platforms

    erected at ceiling level supported on timber or steel beams and

    posts) to support the concrete while it is still wet and plastic for

    7 days. The top surface of the platform is then painted with

    mould oil to prevent the wet concrete from adhering to the

    platform, so that timber platforms can be removed easily. Small

    tiles or blocks (biscuit) are then cast 15-25mm thick depending

    on the specified concrete cover. These are placed at frequent

    centres on the platform. These tiles (specer blocks or biscuits)

    are tied to/and support the steel reinforcement, and ensures

    that the mesh will have the specified cover for the concrete.

    The concrete is the placed of cast on the centering to the

  • required thickness, and it is compacted, vibrated and leveled off

    care must be taken that vibration is not overdone so that most

    of the cement is hot brought to the surface, thereby reducing

    the strength of the mix. The concrete is then cured for 7 days

    before the centering is removed.

    b) Precast Self-centering Floor System: - centering or formwork used

    to support the monolithic reinforced concrete floors tend to obstruct

    and delay building operations. So for emergency projects where time

    is an important factor, self-centering concrete floors are used. This

    1B wall Timber

    support

    Timber

    chartering

    ½B

    partition

    Timber

    formwork

    Main bars with

    bent-up ends

    Distribution

    bars

    Biscuit 1B wall

    Raised brick work

    above floor cast

    Concrete floor built in

    Concrete floor

    cast in-situ

  • type of floor is made of precasted concrete beams which are usually

    manufactured in yards and are transported to the site for fixing. They

    serve as floors when they are raised and placed in position with their

    ends built into brick walls. Once in position they require is support

    other than the bearing of their ends on walls or beams. There are a

    wide range of precast self-centering floor systems:

    i. Rectangular hollow cross-sectional beam floor units, closed

    spaced.

    ii. Inverted channel sections, closed spaced

    iii. Solid precast ‘T’ section beams with hollow lightweight concrete

    infilling blocks.

    HOLLOW CONC. BEAN FLOOR

  • WEEK 8

    WALLS

    Walls are vertical and continuous solid structures, usually constructed from

    materials such as clay, stone, concrete, timber or metal.

    Walls can be classified with respect to their functional requirements as

    internal and external walls. They can also be defined as load bearing

    (carrying imposed loads from roofs and floors in addition to their own

    weight) and non-load bearing (eg portion), non-load bearing is with respect

    to the structural requirements. There are variably two types of walls, solid

    wall and framed wall. A solid wall (Masonry wall) is constructed either of

    blocks of brick, burned clay, stone or concrete.

    These are laid in mortar to overlap to form a bond (bonding) or as a

    monolithic (eg concrete wall). A frame wall is constructed from a frame of

    small sections of timber, concrete or metal joined together to provide

    strength and rigidity, and between the members of the frame thin panels of

    some material are then fixed to the frames to fulfill the functional

    requirements of the particular wall.

    THE FUNCTION OF A WALL IS

    (1)To enclose and protect a building, and also serve as a means of (2)

    dividing space within a building walls serve (3) as protection against wind

    and rain, and to (4) support floor and roofs and to some extent to (5)

    conserve heat within the building. Walls can (6) serve to protect the

  • building against fire, excessive heat, and to resist or minimize the

    transmission and absorption of sound especial solid block walls. Framed

    walls usually of less weight than solid block walls are normally used for

    partitioning existing structures so as to minimize the total load of the

    building. The use of framed walls is preferred where there is little

    consideration for sound transmission. Note that no material for wall

    concrete fulfils all the functional requirement of a wall with maximum

    efficiency.

    BRICKS

    Bricks are small blocks manufactured from burnt clay that can be handled

    with one hand, and its length is twice the width plus one mortar joint. Blocks

    made from sand and lime and blocks made of concrete manufactured in

    clay brick size are also called bricks.

    The standard size is 215mm x 102.5mm x 65mm which with 10mm mortar

    joint becomes 225mm x 112.5mm x 75mm.

    65

    215

    102.5

    STANDARD

    BRICK

    FORMAT SIZE

  • There are various types of bricks of the same standard format are classified

    with respect to the material used, composition, extent of mixing and curing,

    duration and amount of forming applied. Some of these of bricks are:

    commons, facings, engineering bricks, semi-engineering bricks,

    composition of clay, flattons, stocks, marts, Gautts, clay shale bricks,

    calcium silicate bricks, flint-lime bricks, and hollow, perforated and special

    bricks.

    Some special applications and features work require bricks to be reduced

    in size or reshaped. Specials are either cut from a whole brick, or purpose-

    made (manufactured) by hand in hardwood moulds.

    KING CLOSER

    ¼ Brick

    ½ Brick

    ½ BAT OR SNAP

    HEADER

    ¾ BAT

    ¾ BAT

    ½ Brick

    1 Brick

    BEVELED CLOSER

    Queen Closer

    ¼ Brick

  • Some examples of purpose-made (manufactured) special bricks

    Plink Header Plink stretcher

    Squint Angle

    Angle brick Dogleg brick

    Birds month Cant Double Cant

    Half round Coping Saddleback coping

    Single bull nose

    bull nose mitre Double bull nose

    Perforated brick Cellular pressed brick

  • WEEK 9

    BRICK BONDING

    To build or construct a wall of brick or blocks, it is usual to lay the bricks in

    some regular pattern. The brick courses or rows in a wall are arranged to

    ensure that each brick overlaps or bear upon two or more bricks

    immediately below it. The process of laying the bricks across each other

    and binding them together is called bonding. The amount of overlap and

    the part of the brick used determined the pattern or bond of brickwork.

    Bonding of bricks can also be defined as the arrangement of bricks in

    which no vertical joint of one course is exactly over the one in