ce electric seminar
TRANSCRIPT
-
8/6/2019 CE Electric Seminar
1/65
Connectingmicrogeneration:welcome & introductionJohn Ba
Director of Customer Operat
28 June 2
-
8/6/2019 CE Electric Seminar
2/65
Who are CE Electric UK? We are an electricity distribution busines
transporting electricity from the nationaltransmission system, and local generatioto 3.8 million domestic and businesscustomers.
Our network covers an area of 25,000
square kilometres, consisting of more th31,000 substations and around 91,000 kof overhead lines and underground cable
Our role is to ensure a reliable, consisten
and safe supply of electricity. We own and rent electricity meters. Other than to meet our own needs, we d
buy or sell electricity. We operate our service territory 24/7
through five delivery zones, with teamsbased at 14 local service centres.
2
-
8/6/2019 CE Electric Seminar
3/65
Our network operates from 132,000 Volts to 230 Volts - designedoriginally to transport electricity from the national grid to wherever
power is needed.
The move to locally connected generation presents new opportunitand challenges.
3
-
8/6/2019 CE Electric Seminar
4/65
We operate in one of the UKs most active regions for distributed
generation enquiries and projects
Source: Ofgem 2009/10 Connections Industry Review
4
-
8/6/2019 CE Electric Seminar
5/65
The generation connected to our network has been growing
CE Electric UK - Generation MW's Connected
0
20
4060
80
100
120
140
160
2005/06 2006/07 2007/08 2008/09 2009/10 2010/11
MW
5
-
8/6/2019 CE Electric Seminar
6/65
whilst the Feed In Tariff, launched in 2010, has contributed to a
significant increase in microgeneration installations
Notified microgeneration installations (CE Electric UK network)
0200400600800
100012001400
2009Q1
2009Q2
2009Q3
2009Q4
2010Q1
2010Q2
2010Q3
2010Q4
2011Q1
2011Q2
6
-
8/6/2019 CE Electric Seminar
7/65
We are aware that local authorities have ambitious plans
Leedssolarpowerpilotschemegetsgo-
aheadSheffieldaim
stobeUK
sfirstgr
eenener
gycity
Solarenergyschemecouldprovidefree
electricityforYorkcounciltenants
PV solar panels eyed up by North Tyneside Counc
7
-
8/6/2019 CE Electric Seminar
8/65
The market is relatively new and developing UK government
published its microgeneration strategy last week
This included:
a government keen to encourage dialogue
between network companies and the
microgeneration industry on connection
issues
Ofgem, the industry regulator, continuing to
work with network companies to improve the
connection process
8
-
8/6/2019 CE Electric Seminar
9/65
Why are we holding todays event?
In direct response to clear stakeholder interest at our Have Your Say eventsheld earlier in 2011, in Gateshead and Leeds
To help businesses and organisations understand the end-to-end process foconnecting microgeneration and, how to take advantage of feed in tariffs
To help raise awareness of what is involved which can reduce overall costs;avoid unexpected delays; and, ensure projects run smoothly
To promote the competitive market for new connections
A significant opportunity for us to learn from you, build great relationships, anuse your feedback to further improve our service
We look forward to assisting with the connection of more of your generation tour network
We see ourselves as partners with our customers and the communities we ser
9
-
8/6/2019 CE Electric Seminar
10/65
Together, we represent a tremendous level of knowledge and skills
Sector Organisations AttendingMicrogeneration Manufacturers and Installers 17
Local Authorities 12
Independent Connections Providers (ICPs) 8
House Builders 6
Consultancies 6
Electricity Suppliers 3
Housing Associations 3Education and Training 3
Development Agencies 2
Independent Distribution Network Operators (IDNOs) 1
Real Estate Services 1
Industry Regulator - Ofgem 1
Total 63
10
-
8/6/2019 CE Electric Seminar
11/65
Todays schedule is designed to be interactiveStart Finish Topic Speaker
10.00 10.15 Welcome and introduction CE Electric
10.15 10:35 Design standards and technical issues why they are necessary andwhat issues can arise
CE Electric
10:35 11.00 The connections process what is involved and how do I apply? CE Electric
11.00 11.15 Questions
11.15 11.30 Break
11.30 11:55 Competition in connections, promoting choice for customers - theindependent connections provider process
GTC & Power OnConnections
11:55 12:15 Feed-in tariffs what are the rewards? British Gas
12.15 12.30 Questions
12.30 13.30 Lunch and opportunity to visit the display stands
13.30 14.45 Introduction to renewable technologies, financial incentives andpayback periods
CO2 Sense
14.45 15.00 Questions and close CE Electric
15:00 16:30 Further networking opportunity / visit the display stands
11
-
8/6/2019 CE Electric Seminar
12/65
Electricity Network IssuIain MHead of System De
-
8/6/2019 CE Electric Seminar
13/65
2
DNO business has been about establishing and maintaining connectio
to people first load, more recently generation
2
Period EraPost war Wiring Britain
2010 - 2020 Enabling smart grids
2020 on Smart grids go live
1960 - 1980 Catering for demand growth
1980 - 2000 Birth of distributed generation (DG)
2000 - 2010 Site-specific DG issues
-
8/6/2019 CE Electric Seminar
14/65
3
There are no technical blockages to connecting DG
Point of Connection Some challenges are easier than others Resources are an issue across the industry
changing connection skills as sector expands
development of new distribution service offerings
DG can improve losses & defer
reinforcement
when located in the right place
planning standards need to recognise DG
NGET
DNO
1000MW
500MW
100MW
50MW
1MW
4kW
Beware: The solutions of the past may be the problems of the future
-
8/6/2019 CE Electric Seminar
15/65
4
What is G83 generation?
G83 is an industry standard for Small Scale Embedded Generators (SSEGs)
Energy Networks Association Engineering Recommendation G83/1-1
Recommendations for the Connection of Smallscale Embedded Generators (Up to
16A per Phase) in Parallel with Public Low-Voltage Distribution Networks
Stage 1 a single unit within a single customers installation
Stage 2 multiple units in a close geographic region, under a planned programme o
work
The stage 2 definition is being clarified in the next issue of G83
Small Scale Embedded Generator (SSEG)
A source of electrical energy and all associated interface equipment, rated up to an
including 16 A per phase, single or multi phase 230/400 V ac and designed to opera
in parallel with a public low voltage distribution Network. 16A at 230V is 3.68kW
Note that with this definition it would be the output of the system after powering the
inverter not the (slightly higher) output of the solar panels that would be relevant.
-
8/6/2019 CE Electric Seminar
16/65
5
Why 16A per phase?
The 16A requirement is from the Electricity Safety, Quality and Continuity Regulations Regulation 22
22.(1) Without prejudice to regulation 21, no person shall install or operate a source of energwhich may be connected in parallel with a distributors network unless he
(a)has the necessary and appropriate equipment to prevent danger or interference with tha
network or with the supply to consumers so far as is reasonably practicable; (b)has the necessary and appropriate personnel and procedures to prevent danger so far areasonably practicable;
(c)where the source of energy is part of a low voltage consumers installation, complies witBritish Standard requirements; and
(d)agrees specific requirements with the distributor who owns or operates the network.
(2) Sub-paragraphs (b) and (d) of paragraph (1) shall not apply to a person who installs or operaa source of energy which may be connected in parallel with a distributors network provided thsub-paragraphs (a) and (c) of paragraph (1) are complied with; and
(a)the source of energy does not produce an electrical output exceeding 16 amperes perphase at low voltage;
(b)the source of energy is configured to disconnect itself electrically from the parallelconnection when the distributors equipment disconnects the supply of electricity to thepersons installation; and
(c)the person installing the source of energy ensures that the distributor is advised of theintention to use the source of energy in parallel with the network before, or at the time of,commissioning the source.
-
8/6/2019 CE Electric Seminar
17/65
6
Why 16A per phase?
The 16A requirement is from the Electricity Safety, Quality and Continuity Regulations Regulation 22
22.(1) Without prejudice to regulation 21, no person shall install or operate a source of energwhich may be connected in parallel with a distributors network unless he
(a)has the necessary and appropriate equipment to prevent danger or interference with tha
network or with the supply to consumers so far as is reasonably practicable; (b)has the necessary and appropriate personnel and procedures to prevent danger so far areasonably practicable;
(c)where the source of energy is part of a low voltage consumers installation, complies witBritish Standard requirements; and
(d)agrees specific requirements with the distributor who owns or operates the network.
(2) Sub-paragraphs (b) and (d) of paragraph (1) shall not apply to a person who installs or operaa source of energy which may be connected in parallel with a distributors network provided thsub-paragraphs (a) and (c) of paragraph (1) are complied with; and
(a)the source of energy does not produce an electrical output exceeding 16 amperes perphase at low voltage;
(b)the source of energy is configured to disconnect itself electrically from the parallelconnection when the distributors equipment disconnects the supply of electricity to thepersons installation; and
(c)the person installing the source of energy ensures that the distributor is advised of theintention to use the source of energy in parallel with the network before, or at the time of,commissioning the source.
-
8/6/2019 CE Electric Seminar
18/65
7
There are a number of basic issues associated with connecting
distributed generation to the wider electricity network
Electrical Issues Contextual IssuesVoltage
Rise & Step
Protection G83 protection is not sufficient to prevent overvoltages
it should protect the generator.
RoCoF can not always discriminate between loss of
mains and system disturbances. For safety it should be
slightly trip happy. This becomes an issue with
increasing generation penetration.
Fault level Varies by technology and location, but customer has a
high degree of control over their contribution to the
issue
Reverse power flow
Thermal ratings We are now seeing 11kV connected generation
exporting to NGET.
Clustering Where it is good to develop one renewable gene
due to resources, ease of planning etc, it is norm
good to develop others. Generator applications cluster, overloading one a
leaving others untouched and leading to comme
queuing issues.
Planning consents
Particularly for overhead lines but also for connecpoint substations
Land rights Wayleaves, easements and statutory rights
Existing network Single phase lines may not be suitable for yourgenerator
-
8/6/2019 CE Electric Seminar
19/65
8
There are a number of basic issues associated with connecting
distributed generation to the wider electricity network
Electrical Issues Contextual IssuesVoltage
Rise & Step
Protection G83 protection is not sufficient to prevent overvoltages
it should protect the generator.
RoCoF can not always discriminate between loss of
mains and system disturbances. For safety it should be
slightly trip happy. This becomes an issue with
increasing generation penetration.
Fault level Varies by technology and location, but customer has a
high degree of control over their contribution to the
issue
Reverse power flow
Thermal ratings We are now seeing 11kV connected generation
exporting to NGET.
Clustering Where it is good to develop one renewable gene
due to resources, ease of planning etc, it is norm
good to develop others. Generator applications cluster, overloading one a
leaving others untouched and leading to comme
queuing issues.
Planning consents
Particularly for overhead lines but also for connecpoint substations
Land rights Wayleaves, easements and statutory rights
Existing network Single phase lines may not be suitable for yourgenerator
-
8/6/2019 CE Electric Seminar
20/65
9
The LV system was designed for a thermal rating and voltage drop ca
by a domestic load of 2kVA ADMD (after diversity maximum demand
One house mighttake up to around18kVA; a hundredhouses would onlytake a maximum ofaround 200kVA.
Costs to customers,were traditionallyminimised bydesigning thesystem so that themaximum length of
cable and theminimum crosssection wereutilised.
To optimise this theno-load voltage
was set as high aspossible within thestatutory limits.
3kVA electric
vehiclecharger
Cleaner energy is pushing our system towards four times what it wasdesigned for. It was not designed for any voltage rise
3kVA of heat
pumps
2kVA oftraditional
load
1kW DG
Voltage Rise
Voltage Drop
Distance from source
-
8/6/2019 CE Electric Seminar
21/65
10
DNOs are involved in a wide range of projects from testing of new
product applications to design of innovative networks
Orkney registered power zone Project to create and test thelogic and control systems required for automatic management
of a constrained distribution network with large volumes of
distributed generation.
Flexnet Major project to explore the commercial, technicaland consumer issues around the development of flexiblenetworks and to develop solutions to the barriers to
implementation.
Energy innovation centre Collaborative, mentoredprogramme to bring new innovations into the distributionindustry from, primarily, SMEs.
Loss of mains A series of projects designed to mitigate anderadicate distributed generation problems such as islanding
and generation protection.
Superconducting fault limiter The development of improvednetwork equipment based on state of the art materials
technology. This will improve network resilience in conditions
caused by an increased volume of distributed generation and
avoid the need to replace assets.
10
-
8/6/2019 CE Electric Seminar
22/65
Connection
Process for SmallScale Embedded
Generation
Chris Moody
Commercial Manager
1
-
8/6/2019 CE Electric Seminar
23/65
Connecting Distributed Generation (DG)
More generation is being connectednow than ever before all over the UK
A consistent approach was needed for
the benefit of all concerned
Three guides developed by a panel ofexperts from network operators and the
generation industry The guides approved by OFGEM and
published by the Energy NetworksAssociation
G83/1-1 Stage 1, Stage 2 and G59/2
www.ce-electricuk.com
2
-
8/6/2019 CE Electric Seminar
24/65
Which Connection Guide?
What size is thegenerator?
Low Voltage?
More than one?
Number ofPremises?
= Which connectionguide to use
3
-
8/6/2019 CE Electric Seminar
25/65
Getting Connected - 1
Action SSEG G83/1-1 Stage 1
SSEG G83/1-1 Stage 2
G59/2
Find and Appoint a
qualified installerwww.microgenerationcertification.org
A competent installer
who is usingapproved equipmentmust be used
As SSEG G83/1-1
Stage 1
As SSEG G83/1-1
Stage 2
Notify us of theconnection
Within 28 Days ofCommissioning
You need approvalfrom us before
connection
As SSEG G83/1-1Stage 2
Communication Information viaCommissioning Pro -forma
Discuss plans withus before startingthe work
As SSEG G83/1-1Stage 2
Submit anapplication form
Not required Submit anapplication form withall details beforestarting the work CEwebsite
As SSEG G83/1-1Stage 2
-
8/6/2019 CE Electric Seminar
26/65
Getting Connected - 2
Action SSEG G83/1-1 Stage 1
SSEG G83/1-1 Stage 2
G59/2
Provide details to usof -
Connection site
Owner of the unitTechnical data
The installer, theiraccreditation andqualifications
Signed declarationof compliance withG83/1-1 and BS7671(IEE)
Using Pro-formaand within 30 daysof commissioning
In addition
System diagrams,site plans andearthingarrangements
As SSEG G83/1-1Stage 2 plus moredetail of thegenerating unit
-
8/6/2019 CE Electric Seminar
27/65
Getting Connected - 3
Action SSEG G83/1-1 Stage 1
SSEG G83/1-1 Stage 2
G59/2
Next Stage Not Applicable We respond within45 working daysadvising if networkre-inforcement isrequired.
As SSEG G83/1-1Stage 2 but 65working days forHigh and Extra HighVoltage.
Connection Charge? No Possibly if network
re-inforcement.required
As SSEG G83/1-1
Stage 2
Next Stage Not Applicable Our quotation for thecharge is acceptedand any necessaryworks completedbefore energisationof the equipment
As SSEG G83/1-1Stage 2
-
8/6/2019 CE Electric Seminar
28/65
Getting Connected - 4
Action SSEG G83/1-1 Stage 1
SSEG G83/1-1 Stage 2
G59/2
Final Stage Not Applicable The generationequipmentinstallation can becompleted and theinstaller must providethe commissioning
confirmationinformation to us.
As SSEG G83/1-1Stage 2 but we maywish to witness thecommissioning testsso must be notified15 working days
beforehand.
In Summary Fit and Inform Inform us beforefitting. There may bea charge. Re-
inforcement workmust be completedbefore energisationof the equipment
As SSEG G83/1-1Stage 2 but wemay wish to witness
the commissioningtests so must benotified 15 workingdays beforehand.
-
8/6/2019 CE Electric Seminar
29/65
How we use the information provided
Used to manage our network safely and efficiently.
Used for reporting required by the regulator
Also need to know if generation is disconnected
Appendix 5: SSEG Decommissioning Confirmationprovides all the information we need. None received
to date.
8
C G C
-
8/6/2019 CE Electric Seminar
30/65
Charge Range for Generation Connections
Work Required GuaranteedStandard
Estimate ofcharge (Excl VAT)
5m extension to the Low Voltagenetwork
45 Working days 600 - 3,000
Transformer change 65 Working days 5,500 - 17,000
100m extension of High Voltagenetwork
65 Working days 9,500 - 25,000
Installation of new ground mounted
transformer
65 Working days 25,000 - 40,000
K C P i
-
8/6/2019 CE Electric Seminar
31/65
Key Contact Points
Website
www.ce-electricuk.com
Contact Address Cargo Fleet Lane, Middlesbrough TS3 8DG
E-mail Address
Connections Enquiry Management Centre
0845 0702703
10
CE Electric UK Website
-
8/6/2019 CE Electric Seminar
32/65
CE Electric UK Website
Connecting people will take you to theconnections page
11
-
8/6/2019 CE Electric Seminar
33/65
SeminarCompetition in Connections
Tom Brough
Head of Sales
28th June 2011
GTC Company Overview
-
8/6/2019 CE Electric Seminar
34/65
GTC Company Overview
GTC is an independent gas transporter (IGT) and independent distribution networkoperator (IDNO).
Design, build, adopt, own and operate high quality gas and electricity networks for thenew build market throughout mainland UK.
Deliver market leading construction of gas, electricity, dual fuel and multi utilityservices to all the leading UK house builders differentiated market.
GTC has continued strong growth in the last 12 months.
Provides customers with choice, improved services, competitive prices and innovative
solutions. GTCs sister company Power On Connections offers leading electricity network
solutions for major industrial, commercial and high rise, inner city developments.
IGT Licence since 1996
IDNO Licence since 2006
-
8/6/2019 CE Electric Seminar
35/65
IEG has 5 main businesses: GTC Power On Connections Manx Gas (Isle of Man / NG & LPG) Jersey Gas (LPG) Guernsey Gas (LPG)
Owner of key utility, energy and transportassets in North and South America, Australasia andEurope
National Coverage
-
8/6/2019 CE Electric Seminar
36/65
National Coverage
Gas NetworksElectricity Networks GTC
Operates > 14,500 networks
across mainland UK, most aretypically in the range of 20-100properties but can be up to 5,000properties.
About 3,000 of these networksare still being built and currentlycirca 1,000 new connections areadded each week as developerscomplete houses ready for sale.
Transports energy to around450,000 properties. Holdcontracts for more than another200,000 connections to be built.
Competition in Connections
-
8/6/2019 CE Electric Seminar
37/65
p
Market is competitive and increasing proportion of connectionscompleted by independent providers
Increasing breadth of sites being supported particularly in electricity
However, competition in electricity lags some way behind that of gas
Why the Discrepancy?
-
8/6/2019 CE Electric Seminar
38/65
y p y
DNO CiC processes characterised by: Application process for point of Connection.
Lengthy and complex DNO connections process.
Protracted process on agreeing connection arrangements. Excessive requirements for land rights.
Delays and conflict in design approval.
Delays in getting DNO staff booked for work.
DNO failure to turn up when promised. DNO reasons to abort work.
Delays in inspection regimes.
Previously DNOs Have No Incentive: To develop services that improve the customer experience.
To engage with ICPs/IDNOs with a genuine view/ intent to deliversolutions
Why the Discrepancy?
-
8/6/2019 CE Electric Seminar
39/65
y p y
Customers want / deserve competitive prices and exemplary servicedelivery
GTC Staff are highly qualified and competent Design, build, own and operate high quality industry standard networks
at competitive prices GTC invest in these networks Construction carried out at cost Gas competition well established and characterised by:
Self determination of point of connection Self connection to upstream network No onerous authorisation or administration associated with
connection Connections carried out within 8 to 10 weeks
Key Areas To Increase Competition
-
8/6/2019 CE Electric Seminar
40/65
y p
Facilitate connection within 8 10 weeks
Actions Required:
Self determination of Point of Connection
Self connection to upstream network
Remove / streamline design approval process
Remove / streamline the audit process
Reduce the number of inerface
GTC working with all DNOs to effect change and develop improvedservice and choice for customers
CE proactively working with GTC to bring about change and prepare forcompetition test
Continuing Process
-
8/6/2019 CE Electric Seminar
41/65
Successes and improvements are being made:
Removal of boundary metering and feeder pillar
Removal for need of dual substation
GTC successful and significantly increasing market share
Developing strong relationships with DNOs
Feeder PillarLink Box
GTC Growing Share of Electric Connections
-
8/6/2019 CE Electric Seminar
42/65
Despite these third party interfaces
GTC has been successful in growing its market share through bothdirect build and adoption from partners
Competitive offers Customer focused approach
Increasing use of in-house teams on site
Speed and flexibility of delivery Commitment to agreed service standards
GTC Currently has over 750 stand alone networks and in excess of70,000 domestic plots contracted to be connected
CE NEDL 36 Networks
CE YEDL 48 Networks
GTC Sister company Power On Connections market leading ICPspecialising in commercial, industrial, embedded generation, high riseand residential development
-
8/6/2019 CE Electric Seminar
43/65
Customer frustrationsthroughtraditionalDistributionNetworkOperator[DNO]practices
the alternative to the host DNO Power Onconnections
Practices
Delaysinprovidingquotations,andadequateinformationtosubstantiatethem.
Nocommercialalternatives. Processeswhichwereunnecessarilycomplex. Lackofcustomerfocus.Impacts
Clienthadnopriceandprogrammecertainty. ClientswastedtimemanagingtheDNO. Clientprojectswereoftendeliveredlate.Response
Ofgemcreatecompetitiveframeworkin2003 Clarificationofcompetitiveelements
Whatiscontestable?
-
8/6/2019 CE Electric Seminar
44/65
DeterminingPointofConnection No
Design Yes
Offsite(Highway)works YesEquipmentprocurement Yes
CableLay&substationInstallation Yes
Inspection,Testing&Records Yes
FinalConnection(closing joints) No
Power Onconnectionsthe alternative to the host DNO
OurCoreValues.Servicing:
-
8/6/2019 CE Electric Seminar
45/65
Servicing: Developers,LocalAuthority,MainContractors,
ConsultingEngineersSpeedofResponse
Speedyquoteturnaround
Wellworkwithyourinformation noforms
No
call
centre
staffProgrammeCertainty
GuaranteedpowerOndate
Constructionprogrammeindicatingallparties
responsibilities
FullyfamiliarwithallDNOprocesses,specificationsand
requirements
CostCertainty
Fixedquotes Ourphilosophyissimpleifyou
StagedPayments paymentsarephasedoverproject
milestones
Competitiveness
Wealwaysdesignthemostcosteffectiveoption
Power Onconnectionsthe alternative to the host DNO
Move to Zero Carbon Homes
-
8/6/2019 CE Electric Seminar
46/65
Increasing number of renewable technologies supported on IDNO networks
GSHP / ASHP
Solar Thermal
Photovoltaic cells
Developers provide details of generation type
Gov Zero Carbon target from 2016 set in 2006 allow time to develop cost effectivetechnologies to replace / reduce traditional fossil fuels.
House building remains at its lowest peacetime levels since 1924 (Source: UK Gov March
2011).
Government announce drive for simplification in construction standards and codes.
The Plan for Growth house builders accountable only for those carbon dioxide emissionsthat are covered by Building Regulations, and will provide cost effective means through whichthey can do this.
Emissions from energy use from cooking and plug in appliances not covered.
Focus on affordability, deliverability, practicality and extension of Green Deal to new homes.
Implication for network owners long term future for gas networks, important role in future fuelmix solutions alongside a range of renewable alternatives.
House builders face Code 6 affordability issues currently gas fundamental element for mostnew build homes.
SMART Metering
-
8/6/2019 CE Electric Seminar
47/65
GTC is supporting house builders by providing SMART enabled gasmeters in new homes today.
Install, own and manage gas meter based on supplier requirements.
In house display with realtime data.
Benefits home owners,house builders &
suppliers.
GTC started installing Smartmeters in January 2011.
Within weeks GTC aquiredorders for over 1,000 plots.
Summary
-
8/6/2019 CE Electric Seminar
48/65
Competitive market house builders seek increasing choices forutilities and in turn their demand pushes growth in market.
The electricity regime is currently failing customers
Government move to a more cost efficient definition of Zero Carbonsignals support for long term future of gas.
SMART metering available now.
GTC continues as the long term partner to house builders, developers,ICPs and UIPs.
-
8/6/2019 CE Electric Seminar
49/65
Feed In Tariffs,
What are the rewards?
Tim BarrsBusiness Development Manager.07957 [email protected]
Agenda
mailto:[email protected]:[email protected] -
8/6/2019 CE Electric Seminar
50/65
Introduction to the feed in tariff.
Who can benefit?
Why?
Summary.
Slide 2
Introduction to the feed in tariff (FiT)
-
8/6/2019 CE Electric Seminar
51/65
2006 Kyoto & 2008 Energy Act
Slide 3
Policy changes creates opportunity
-
8/6/2019 CE Electric Seminar
52/65
FIT fast track review
Early FIT review announced on 7th February.
Full review brought forward to 2011 Fast track review for
-
8/6/2019 CE Electric Seminar
53/65
Slide 5
Who can benefit?
-
8/6/2019 CE Electric Seminar
54/65
Slide 6
Who can benefit?
-
8/6/2019 CE Electric Seminar
55/65
Slide 7
Who can benefit?
-
8/6/2019 CE Electric Seminar
56/65
Slide 8
Who can benefit?
-
8/6/2019 CE Electric Seminar
57/65
Slide 9
Why?The home owner
-
8/6/2019 CE Electric Seminar
58/65
The home owner.
Limit energy price risk,Offset entire energy billFinancial reward , safe risk
Slide 10
Why?LAHAs
-
8/6/2019 CE Electric Seminar
59/65
LAHAs
Fuel poverty obligationCarbon creditsSafe revenue stream
Slide 11
Why?SMEs
-
8/6/2019 CE Electric Seminar
60/65
SME s
Safe financial
InvestmentImageBuildingcompliance
Slide 12
Why?Blue chip companies
-
8/6/2019 CE Electric Seminar
61/65
Blue chip companies
CSR
Commercial incentives
Slide 13
Why?The Church
-
8/6/2019 CE Electric Seminar
62/65
The Church
The church are
a business in thesame sense asany otheropportunity.
Slide 14
Why?All sectors
-
8/6/2019 CE Electric Seminar
63/65
All sectors
Slide 15
Summary
-
8/6/2019 CE Electric Seminar
64/65
The FiT provides;A commercially viable solution forPV installationsStructured to deliver 7-9% return
Additional fuel saving costsincrease the yield closer to 12%Index linked
25 year termPV Life cycle 40yrs +
Slide 16
British Gas SolarAny Questions?
-
8/6/2019 CE Electric Seminar
65/65
Any Questions?
BG Solar HQ City Hall London Social Housing
G8 Summit 1998Canary Warf St Silas Church London
Slide 17
17