ce electric seminar

Upload: mtheobald2

Post on 07-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 CE Electric Seminar

    1/65

    Connectingmicrogeneration:welcome & introductionJohn Ba

    Director of Customer Operat

    28 June 2

  • 8/6/2019 CE Electric Seminar

    2/65

    Who are CE Electric UK? We are an electricity distribution busines

    transporting electricity from the nationaltransmission system, and local generatioto 3.8 million domestic and businesscustomers.

    Our network covers an area of 25,000

    square kilometres, consisting of more th31,000 substations and around 91,000 kof overhead lines and underground cable

    Our role is to ensure a reliable, consisten

    and safe supply of electricity. We own and rent electricity meters. Other than to meet our own needs, we d

    buy or sell electricity. We operate our service territory 24/7

    through five delivery zones, with teamsbased at 14 local service centres.

    2

  • 8/6/2019 CE Electric Seminar

    3/65

    Our network operates from 132,000 Volts to 230 Volts - designedoriginally to transport electricity from the national grid to wherever

    power is needed.

    The move to locally connected generation presents new opportunitand challenges.

    3

  • 8/6/2019 CE Electric Seminar

    4/65

    We operate in one of the UKs most active regions for distributed

    generation enquiries and projects

    Source: Ofgem 2009/10 Connections Industry Review

    4

  • 8/6/2019 CE Electric Seminar

    5/65

    The generation connected to our network has been growing

    CE Electric UK - Generation MW's Connected

    0

    20

    4060

    80

    100

    120

    140

    160

    2005/06 2006/07 2007/08 2008/09 2009/10 2010/11

    MW

    5

  • 8/6/2019 CE Electric Seminar

    6/65

    whilst the Feed In Tariff, launched in 2010, has contributed to a

    significant increase in microgeneration installations

    Notified microgeneration installations (CE Electric UK network)

    0200400600800

    100012001400

    2009Q1

    2009Q2

    2009Q3

    2009Q4

    2010Q1

    2010Q2

    2010Q3

    2010Q4

    2011Q1

    2011Q2

    6

  • 8/6/2019 CE Electric Seminar

    7/65

    We are aware that local authorities have ambitious plans

    Leedssolarpowerpilotschemegetsgo-

    aheadSheffieldaim

    stobeUK

    sfirstgr

    eenener

    gycity

    Solarenergyschemecouldprovidefree

    electricityforYorkcounciltenants

    PV solar panels eyed up by North Tyneside Counc

    7

  • 8/6/2019 CE Electric Seminar

    8/65

    The market is relatively new and developing UK government

    published its microgeneration strategy last week

    This included:

    a government keen to encourage dialogue

    between network companies and the

    microgeneration industry on connection

    issues

    Ofgem, the industry regulator, continuing to

    work with network companies to improve the

    connection process

    8

  • 8/6/2019 CE Electric Seminar

    9/65

    Why are we holding todays event?

    In direct response to clear stakeholder interest at our Have Your Say eventsheld earlier in 2011, in Gateshead and Leeds

    To help businesses and organisations understand the end-to-end process foconnecting microgeneration and, how to take advantage of feed in tariffs

    To help raise awareness of what is involved which can reduce overall costs;avoid unexpected delays; and, ensure projects run smoothly

    To promote the competitive market for new connections

    A significant opportunity for us to learn from you, build great relationships, anuse your feedback to further improve our service

    We look forward to assisting with the connection of more of your generation tour network

    We see ourselves as partners with our customers and the communities we ser

    9

  • 8/6/2019 CE Electric Seminar

    10/65

    Together, we represent a tremendous level of knowledge and skills

    Sector Organisations AttendingMicrogeneration Manufacturers and Installers 17

    Local Authorities 12

    Independent Connections Providers (ICPs) 8

    House Builders 6

    Consultancies 6

    Electricity Suppliers 3

    Housing Associations 3Education and Training 3

    Development Agencies 2

    Independent Distribution Network Operators (IDNOs) 1

    Real Estate Services 1

    Industry Regulator - Ofgem 1

    Total 63

    10

  • 8/6/2019 CE Electric Seminar

    11/65

    Todays schedule is designed to be interactiveStart Finish Topic Speaker

    10.00 10.15 Welcome and introduction CE Electric

    10.15 10:35 Design standards and technical issues why they are necessary andwhat issues can arise

    CE Electric

    10:35 11.00 The connections process what is involved and how do I apply? CE Electric

    11.00 11.15 Questions

    11.15 11.30 Break

    11.30 11:55 Competition in connections, promoting choice for customers - theindependent connections provider process

    GTC & Power OnConnections

    11:55 12:15 Feed-in tariffs what are the rewards? British Gas

    12.15 12.30 Questions

    12.30 13.30 Lunch and opportunity to visit the display stands

    13.30 14.45 Introduction to renewable technologies, financial incentives andpayback periods

    CO2 Sense

    14.45 15.00 Questions and close CE Electric

    15:00 16:30 Further networking opportunity / visit the display stands

    11

  • 8/6/2019 CE Electric Seminar

    12/65

    Electricity Network IssuIain MHead of System De

  • 8/6/2019 CE Electric Seminar

    13/65

    2

    DNO business has been about establishing and maintaining connectio

    to people first load, more recently generation

    2

    Period EraPost war Wiring Britain

    2010 - 2020 Enabling smart grids

    2020 on Smart grids go live

    1960 - 1980 Catering for demand growth

    1980 - 2000 Birth of distributed generation (DG)

    2000 - 2010 Site-specific DG issues

  • 8/6/2019 CE Electric Seminar

    14/65

    3

    There are no technical blockages to connecting DG

    Point of Connection Some challenges are easier than others Resources are an issue across the industry

    changing connection skills as sector expands

    development of new distribution service offerings

    DG can improve losses & defer

    reinforcement

    when located in the right place

    planning standards need to recognise DG

    NGET

    DNO

    1000MW

    500MW

    100MW

    50MW

    1MW

    4kW

    Beware: The solutions of the past may be the problems of the future

  • 8/6/2019 CE Electric Seminar

    15/65

    4

    What is G83 generation?

    G83 is an industry standard for Small Scale Embedded Generators (SSEGs)

    Energy Networks Association Engineering Recommendation G83/1-1

    Recommendations for the Connection of Smallscale Embedded Generators (Up to

    16A per Phase) in Parallel with Public Low-Voltage Distribution Networks

    Stage 1 a single unit within a single customers installation

    Stage 2 multiple units in a close geographic region, under a planned programme o

    work

    The stage 2 definition is being clarified in the next issue of G83

    Small Scale Embedded Generator (SSEG)

    A source of electrical energy and all associated interface equipment, rated up to an

    including 16 A per phase, single or multi phase 230/400 V ac and designed to opera

    in parallel with a public low voltage distribution Network. 16A at 230V is 3.68kW

    Note that with this definition it would be the output of the system after powering the

    inverter not the (slightly higher) output of the solar panels that would be relevant.

  • 8/6/2019 CE Electric Seminar

    16/65

    5

    Why 16A per phase?

    The 16A requirement is from the Electricity Safety, Quality and Continuity Regulations Regulation 22

    22.(1) Without prejudice to regulation 21, no person shall install or operate a source of energwhich may be connected in parallel with a distributors network unless he

    (a)has the necessary and appropriate equipment to prevent danger or interference with tha

    network or with the supply to consumers so far as is reasonably practicable; (b)has the necessary and appropriate personnel and procedures to prevent danger so far areasonably practicable;

    (c)where the source of energy is part of a low voltage consumers installation, complies witBritish Standard requirements; and

    (d)agrees specific requirements with the distributor who owns or operates the network.

    (2) Sub-paragraphs (b) and (d) of paragraph (1) shall not apply to a person who installs or operaa source of energy which may be connected in parallel with a distributors network provided thsub-paragraphs (a) and (c) of paragraph (1) are complied with; and

    (a)the source of energy does not produce an electrical output exceeding 16 amperes perphase at low voltage;

    (b)the source of energy is configured to disconnect itself electrically from the parallelconnection when the distributors equipment disconnects the supply of electricity to thepersons installation; and

    (c)the person installing the source of energy ensures that the distributor is advised of theintention to use the source of energy in parallel with the network before, or at the time of,commissioning the source.

  • 8/6/2019 CE Electric Seminar

    17/65

    6

    Why 16A per phase?

    The 16A requirement is from the Electricity Safety, Quality and Continuity Regulations Regulation 22

    22.(1) Without prejudice to regulation 21, no person shall install or operate a source of energwhich may be connected in parallel with a distributors network unless he

    (a)has the necessary and appropriate equipment to prevent danger or interference with tha

    network or with the supply to consumers so far as is reasonably practicable; (b)has the necessary and appropriate personnel and procedures to prevent danger so far areasonably practicable;

    (c)where the source of energy is part of a low voltage consumers installation, complies witBritish Standard requirements; and

    (d)agrees specific requirements with the distributor who owns or operates the network.

    (2) Sub-paragraphs (b) and (d) of paragraph (1) shall not apply to a person who installs or operaa source of energy which may be connected in parallel with a distributors network provided thsub-paragraphs (a) and (c) of paragraph (1) are complied with; and

    (a)the source of energy does not produce an electrical output exceeding 16 amperes perphase at low voltage;

    (b)the source of energy is configured to disconnect itself electrically from the parallelconnection when the distributors equipment disconnects the supply of electricity to thepersons installation; and

    (c)the person installing the source of energy ensures that the distributor is advised of theintention to use the source of energy in parallel with the network before, or at the time of,commissioning the source.

  • 8/6/2019 CE Electric Seminar

    18/65

    7

    There are a number of basic issues associated with connecting

    distributed generation to the wider electricity network

    Electrical Issues Contextual IssuesVoltage

    Rise & Step

    Protection G83 protection is not sufficient to prevent overvoltages

    it should protect the generator.

    RoCoF can not always discriminate between loss of

    mains and system disturbances. For safety it should be

    slightly trip happy. This becomes an issue with

    increasing generation penetration.

    Fault level Varies by technology and location, but customer has a

    high degree of control over their contribution to the

    issue

    Reverse power flow

    Thermal ratings We are now seeing 11kV connected generation

    exporting to NGET.

    Clustering Where it is good to develop one renewable gene

    due to resources, ease of planning etc, it is norm

    good to develop others. Generator applications cluster, overloading one a

    leaving others untouched and leading to comme

    queuing issues.

    Planning consents

    Particularly for overhead lines but also for connecpoint substations

    Land rights Wayleaves, easements and statutory rights

    Existing network Single phase lines may not be suitable for yourgenerator

  • 8/6/2019 CE Electric Seminar

    19/65

    8

    There are a number of basic issues associated with connecting

    distributed generation to the wider electricity network

    Electrical Issues Contextual IssuesVoltage

    Rise & Step

    Protection G83 protection is not sufficient to prevent overvoltages

    it should protect the generator.

    RoCoF can not always discriminate between loss of

    mains and system disturbances. For safety it should be

    slightly trip happy. This becomes an issue with

    increasing generation penetration.

    Fault level Varies by technology and location, but customer has a

    high degree of control over their contribution to the

    issue

    Reverse power flow

    Thermal ratings We are now seeing 11kV connected generation

    exporting to NGET.

    Clustering Where it is good to develop one renewable gene

    due to resources, ease of planning etc, it is norm

    good to develop others. Generator applications cluster, overloading one a

    leaving others untouched and leading to comme

    queuing issues.

    Planning consents

    Particularly for overhead lines but also for connecpoint substations

    Land rights Wayleaves, easements and statutory rights

    Existing network Single phase lines may not be suitable for yourgenerator

  • 8/6/2019 CE Electric Seminar

    20/65

    9

    The LV system was designed for a thermal rating and voltage drop ca

    by a domestic load of 2kVA ADMD (after diversity maximum demand

    One house mighttake up to around18kVA; a hundredhouses would onlytake a maximum ofaround 200kVA.

    Costs to customers,were traditionallyminimised bydesigning thesystem so that themaximum length of

    cable and theminimum crosssection wereutilised.

    To optimise this theno-load voltage

    was set as high aspossible within thestatutory limits.

    3kVA electric

    vehiclecharger

    Cleaner energy is pushing our system towards four times what it wasdesigned for. It was not designed for any voltage rise

    3kVA of heat

    pumps

    2kVA oftraditional

    load

    1kW DG

    Voltage Rise

    Voltage Drop

    Distance from source

  • 8/6/2019 CE Electric Seminar

    21/65

    10

    DNOs are involved in a wide range of projects from testing of new

    product applications to design of innovative networks

    Orkney registered power zone Project to create and test thelogic and control systems required for automatic management

    of a constrained distribution network with large volumes of

    distributed generation.

    Flexnet Major project to explore the commercial, technicaland consumer issues around the development of flexiblenetworks and to develop solutions to the barriers to

    implementation.

    Energy innovation centre Collaborative, mentoredprogramme to bring new innovations into the distributionindustry from, primarily, SMEs.

    Loss of mains A series of projects designed to mitigate anderadicate distributed generation problems such as islanding

    and generation protection.

    Superconducting fault limiter The development of improvednetwork equipment based on state of the art materials

    technology. This will improve network resilience in conditions

    caused by an increased volume of distributed generation and

    avoid the need to replace assets.

    10

  • 8/6/2019 CE Electric Seminar

    22/65

    Connection

    Process for SmallScale Embedded

    Generation

    Chris Moody

    Commercial Manager

    1

  • 8/6/2019 CE Electric Seminar

    23/65

    Connecting Distributed Generation (DG)

    More generation is being connectednow than ever before all over the UK

    A consistent approach was needed for

    the benefit of all concerned

    Three guides developed by a panel ofexperts from network operators and the

    generation industry The guides approved by OFGEM and

    published by the Energy NetworksAssociation

    G83/1-1 Stage 1, Stage 2 and G59/2

    www.ce-electricuk.com

    2

  • 8/6/2019 CE Electric Seminar

    24/65

    Which Connection Guide?

    What size is thegenerator?

    Low Voltage?

    More than one?

    Number ofPremises?

    = Which connectionguide to use

    3

  • 8/6/2019 CE Electric Seminar

    25/65

    Getting Connected - 1

    Action SSEG G83/1-1 Stage 1

    SSEG G83/1-1 Stage 2

    G59/2

    Find and Appoint a

    qualified installerwww.microgenerationcertification.org

    A competent installer

    who is usingapproved equipmentmust be used

    As SSEG G83/1-1

    Stage 1

    As SSEG G83/1-1

    Stage 2

    Notify us of theconnection

    Within 28 Days ofCommissioning

    You need approvalfrom us before

    connection

    As SSEG G83/1-1Stage 2

    Communication Information viaCommissioning Pro -forma

    Discuss plans withus before startingthe work

    As SSEG G83/1-1Stage 2

    Submit anapplication form

    Not required Submit anapplication form withall details beforestarting the work CEwebsite

    As SSEG G83/1-1Stage 2

  • 8/6/2019 CE Electric Seminar

    26/65

    Getting Connected - 2

    Action SSEG G83/1-1 Stage 1

    SSEG G83/1-1 Stage 2

    G59/2

    Provide details to usof -

    Connection site

    Owner of the unitTechnical data

    The installer, theiraccreditation andqualifications

    Signed declarationof compliance withG83/1-1 and BS7671(IEE)

    Using Pro-formaand within 30 daysof commissioning

    In addition

    System diagrams,site plans andearthingarrangements

    As SSEG G83/1-1Stage 2 plus moredetail of thegenerating unit

  • 8/6/2019 CE Electric Seminar

    27/65

    Getting Connected - 3

    Action SSEG G83/1-1 Stage 1

    SSEG G83/1-1 Stage 2

    G59/2

    Next Stage Not Applicable We respond within45 working daysadvising if networkre-inforcement isrequired.

    As SSEG G83/1-1Stage 2 but 65working days forHigh and Extra HighVoltage.

    Connection Charge? No Possibly if network

    re-inforcement.required

    As SSEG G83/1-1

    Stage 2

    Next Stage Not Applicable Our quotation for thecharge is acceptedand any necessaryworks completedbefore energisationof the equipment

    As SSEG G83/1-1Stage 2

  • 8/6/2019 CE Electric Seminar

    28/65

    Getting Connected - 4

    Action SSEG G83/1-1 Stage 1

    SSEG G83/1-1 Stage 2

    G59/2

    Final Stage Not Applicable The generationequipmentinstallation can becompleted and theinstaller must providethe commissioning

    confirmationinformation to us.

    As SSEG G83/1-1Stage 2 but we maywish to witness thecommissioning testsso must be notified15 working days

    beforehand.

    In Summary Fit and Inform Inform us beforefitting. There may bea charge. Re-

    inforcement workmust be completedbefore energisationof the equipment

    As SSEG G83/1-1Stage 2 but wemay wish to witness

    the commissioningtests so must benotified 15 workingdays beforehand.

  • 8/6/2019 CE Electric Seminar

    29/65

    How we use the information provided

    Used to manage our network safely and efficiently.

    Used for reporting required by the regulator

    Also need to know if generation is disconnected

    Appendix 5: SSEG Decommissioning Confirmationprovides all the information we need. None received

    to date.

    8

    C G C

  • 8/6/2019 CE Electric Seminar

    30/65

    Charge Range for Generation Connections

    Work Required GuaranteedStandard

    Estimate ofcharge (Excl VAT)

    5m extension to the Low Voltagenetwork

    45 Working days 600 - 3,000

    Transformer change 65 Working days 5,500 - 17,000

    100m extension of High Voltagenetwork

    65 Working days 9,500 - 25,000

    Installation of new ground mounted

    transformer

    65 Working days 25,000 - 40,000

    K C P i

  • 8/6/2019 CE Electric Seminar

    31/65

    Key Contact Points

    Website

    www.ce-electricuk.com

    Contact Address Cargo Fleet Lane, Middlesbrough TS3 8DG

    E-mail Address

    [email protected]

    Connections Enquiry Management Centre

    0845 0702703

    10

    CE Electric UK Website

  • 8/6/2019 CE Electric Seminar

    32/65

    CE Electric UK Website

    Connecting people will take you to theconnections page

    11

  • 8/6/2019 CE Electric Seminar

    33/65

    SeminarCompetition in Connections

    Tom Brough

    Head of Sales

    28th June 2011

    GTC Company Overview

  • 8/6/2019 CE Electric Seminar

    34/65

    GTC Company Overview

    GTC is an independent gas transporter (IGT) and independent distribution networkoperator (IDNO).

    Design, build, adopt, own and operate high quality gas and electricity networks for thenew build market throughout mainland UK.

    Deliver market leading construction of gas, electricity, dual fuel and multi utilityservices to all the leading UK house builders differentiated market.

    GTC has continued strong growth in the last 12 months.

    Provides customers with choice, improved services, competitive prices and innovative

    solutions. GTCs sister company Power On Connections offers leading electricity network

    solutions for major industrial, commercial and high rise, inner city developments.

    IGT Licence since 1996

    IDNO Licence since 2006

  • 8/6/2019 CE Electric Seminar

    35/65

    IEG has 5 main businesses: GTC Power On Connections Manx Gas (Isle of Man / NG & LPG) Jersey Gas (LPG) Guernsey Gas (LPG)

    Owner of key utility, energy and transportassets in North and South America, Australasia andEurope

    National Coverage

  • 8/6/2019 CE Electric Seminar

    36/65

    National Coverage

    Gas NetworksElectricity Networks GTC

    Operates > 14,500 networks

    across mainland UK, most aretypically in the range of 20-100properties but can be up to 5,000properties.

    About 3,000 of these networksare still being built and currentlycirca 1,000 new connections areadded each week as developerscomplete houses ready for sale.

    Transports energy to around450,000 properties. Holdcontracts for more than another200,000 connections to be built.

    Competition in Connections

  • 8/6/2019 CE Electric Seminar

    37/65

    p

    Market is competitive and increasing proportion of connectionscompleted by independent providers

    Increasing breadth of sites being supported particularly in electricity

    However, competition in electricity lags some way behind that of gas

    Why the Discrepancy?

  • 8/6/2019 CE Electric Seminar

    38/65

    y p y

    DNO CiC processes characterised by: Application process for point of Connection.

    Lengthy and complex DNO connections process.

    Protracted process on agreeing connection arrangements. Excessive requirements for land rights.

    Delays and conflict in design approval.

    Delays in getting DNO staff booked for work.

    DNO failure to turn up when promised. DNO reasons to abort work.

    Delays in inspection regimes.

    Previously DNOs Have No Incentive: To develop services that improve the customer experience.

    To engage with ICPs/IDNOs with a genuine view/ intent to deliversolutions

    Why the Discrepancy?

  • 8/6/2019 CE Electric Seminar

    39/65

    y p y

    Customers want / deserve competitive prices and exemplary servicedelivery

    GTC Staff are highly qualified and competent Design, build, own and operate high quality industry standard networks

    at competitive prices GTC invest in these networks Construction carried out at cost Gas competition well established and characterised by:

    Self determination of point of connection Self connection to upstream network No onerous authorisation or administration associated with

    connection Connections carried out within 8 to 10 weeks

    Key Areas To Increase Competition

  • 8/6/2019 CE Electric Seminar

    40/65

    y p

    Facilitate connection within 8 10 weeks

    Actions Required:

    Self determination of Point of Connection

    Self connection to upstream network

    Remove / streamline design approval process

    Remove / streamline the audit process

    Reduce the number of inerface

    GTC working with all DNOs to effect change and develop improvedservice and choice for customers

    CE proactively working with GTC to bring about change and prepare forcompetition test

    Continuing Process

  • 8/6/2019 CE Electric Seminar

    41/65

    Successes and improvements are being made:

    Removal of boundary metering and feeder pillar

    Removal for need of dual substation

    GTC successful and significantly increasing market share

    Developing strong relationships with DNOs

    Feeder PillarLink Box

    GTC Growing Share of Electric Connections

  • 8/6/2019 CE Electric Seminar

    42/65

    Despite these third party interfaces

    GTC has been successful in growing its market share through bothdirect build and adoption from partners

    Competitive offers Customer focused approach

    Increasing use of in-house teams on site

    Speed and flexibility of delivery Commitment to agreed service standards

    GTC Currently has over 750 stand alone networks and in excess of70,000 domestic plots contracted to be connected

    CE NEDL 36 Networks

    CE YEDL 48 Networks

    GTC Sister company Power On Connections market leading ICPspecialising in commercial, industrial, embedded generation, high riseand residential development

  • 8/6/2019 CE Electric Seminar

    43/65

    Customer frustrationsthroughtraditionalDistributionNetworkOperator[DNO]practices

    the alternative to the host DNO Power Onconnections

    Practices

    Delaysinprovidingquotations,andadequateinformationtosubstantiatethem.

    Nocommercialalternatives. Processeswhichwereunnecessarilycomplex. Lackofcustomerfocus.Impacts

    Clienthadnopriceandprogrammecertainty. ClientswastedtimemanagingtheDNO. Clientprojectswereoftendeliveredlate.Response

    Ofgemcreatecompetitiveframeworkin2003 Clarificationofcompetitiveelements

    Whatiscontestable?

  • 8/6/2019 CE Electric Seminar

    44/65

    DeterminingPointofConnection No

    Design Yes

    Offsite(Highway)works YesEquipmentprocurement Yes

    CableLay&substationInstallation Yes

    Inspection,Testing&Records Yes

    FinalConnection(closing joints) No

    Power Onconnectionsthe alternative to the host DNO

    OurCoreValues.Servicing:

  • 8/6/2019 CE Electric Seminar

    45/65

    Servicing: Developers,LocalAuthority,MainContractors,

    ConsultingEngineersSpeedofResponse

    Speedyquoteturnaround

    Wellworkwithyourinformation noforms

    No

    call

    centre

    staffProgrammeCertainty

    GuaranteedpowerOndate

    Constructionprogrammeindicatingallparties

    responsibilities

    FullyfamiliarwithallDNOprocesses,specificationsand

    requirements

    CostCertainty

    Fixedquotes Ourphilosophyissimpleifyou

    StagedPayments paymentsarephasedoverproject

    milestones

    Competitiveness

    Wealwaysdesignthemostcosteffectiveoption

    Power Onconnectionsthe alternative to the host DNO

    Move to Zero Carbon Homes

  • 8/6/2019 CE Electric Seminar

    46/65

    Increasing number of renewable technologies supported on IDNO networks

    GSHP / ASHP

    Solar Thermal

    Photovoltaic cells

    Developers provide details of generation type

    Gov Zero Carbon target from 2016 set in 2006 allow time to develop cost effectivetechnologies to replace / reduce traditional fossil fuels.

    House building remains at its lowest peacetime levels since 1924 (Source: UK Gov March

    2011).

    Government announce drive for simplification in construction standards and codes.

    The Plan for Growth house builders accountable only for those carbon dioxide emissionsthat are covered by Building Regulations, and will provide cost effective means through whichthey can do this.

    Emissions from energy use from cooking and plug in appliances not covered.

    Focus on affordability, deliverability, practicality and extension of Green Deal to new homes.

    Implication for network owners long term future for gas networks, important role in future fuelmix solutions alongside a range of renewable alternatives.

    House builders face Code 6 affordability issues currently gas fundamental element for mostnew build homes.

    SMART Metering

  • 8/6/2019 CE Electric Seminar

    47/65

    GTC is supporting house builders by providing SMART enabled gasmeters in new homes today.

    Install, own and manage gas meter based on supplier requirements.

    In house display with realtime data.

    Benefits home owners,house builders &

    suppliers.

    GTC started installing Smartmeters in January 2011.

    Within weeks GTC aquiredorders for over 1,000 plots.

    Summary

  • 8/6/2019 CE Electric Seminar

    48/65

    Competitive market house builders seek increasing choices forutilities and in turn their demand pushes growth in market.

    The electricity regime is currently failing customers

    Government move to a more cost efficient definition of Zero Carbonsignals support for long term future of gas.

    SMART metering available now.

    GTC continues as the long term partner to house builders, developers,ICPs and UIPs.

  • 8/6/2019 CE Electric Seminar

    49/65

    Feed In Tariffs,

    What are the rewards?

    Tim BarrsBusiness Development Manager.07957 [email protected]

    Agenda

    mailto:[email protected]:[email protected]
  • 8/6/2019 CE Electric Seminar

    50/65

    Introduction to the feed in tariff.

    Who can benefit?

    Why?

    Summary.

    Slide 2

    Introduction to the feed in tariff (FiT)

  • 8/6/2019 CE Electric Seminar

    51/65

    2006 Kyoto & 2008 Energy Act

    Slide 3

    Policy changes creates opportunity

  • 8/6/2019 CE Electric Seminar

    52/65

    FIT fast track review

    Early FIT review announced on 7th February.

    Full review brought forward to 2011 Fast track review for

  • 8/6/2019 CE Electric Seminar

    53/65

    Slide 5

    Who can benefit?

  • 8/6/2019 CE Electric Seminar

    54/65

    Slide 6

    Who can benefit?

  • 8/6/2019 CE Electric Seminar

    55/65

    Slide 7

    Who can benefit?

  • 8/6/2019 CE Electric Seminar

    56/65

    Slide 8

    Who can benefit?

  • 8/6/2019 CE Electric Seminar

    57/65

    Slide 9

    Why?The home owner

  • 8/6/2019 CE Electric Seminar

    58/65

    The home owner.

    Limit energy price risk,Offset entire energy billFinancial reward , safe risk

    Slide 10

    Why?LAHAs

  • 8/6/2019 CE Electric Seminar

    59/65

    LAHAs

    Fuel poverty obligationCarbon creditsSafe revenue stream

    Slide 11

    Why?SMEs

  • 8/6/2019 CE Electric Seminar

    60/65

    SME s

    Safe financial

    InvestmentImageBuildingcompliance

    Slide 12

    Why?Blue chip companies

  • 8/6/2019 CE Electric Seminar

    61/65

    Blue chip companies

    CSR

    Commercial incentives

    Slide 13

    Why?The Church

  • 8/6/2019 CE Electric Seminar

    62/65

    The Church

    The church are

    a business in thesame sense asany otheropportunity.

    Slide 14

    Why?All sectors

  • 8/6/2019 CE Electric Seminar

    63/65

    All sectors

    Slide 15

    Summary

  • 8/6/2019 CE Electric Seminar

    64/65

    The FiT provides;A commercially viable solution forPV installationsStructured to deliver 7-9% return

    Additional fuel saving costsincrease the yield closer to 12%Index linked

    25 year termPV Life cycle 40yrs +

    Slide 16

    British Gas SolarAny Questions?

  • 8/6/2019 CE Electric Seminar

    65/65

    Any Questions?

    BG Solar HQ City Hall London Social Housing

    G8 Summit 1998Canary Warf St Silas Church London

    Slide 17

    17