ce 462 project

Upload: prc5035

Post on 08-Apr-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 CE 462 Project

    1/28

    Gilkey Creek AnalysisLippincott Blvd, Roat Ct, & Lapeer Rd

    Group 8Paul Christner

    Ryan Kunkel

    Timothy Panzigrau

    Silvia Sutkowski

    4/29/2011

  • 8/7/2019 CE 462 Project

    2/28

    Table of Contents

    Abstract ......................................................................................................................................................... 3

    Introduction .................................................................................................................................................. 4

    Discussion ..................................................................................................................................................... 4

    Methods .................................................................................................................................................... 4

    Findings ..................................................................................................................................................... 5

    Assessment ............................................................................................................................................... 5

    Conclusion and Recommendations .............................................................................................................. 6

    Appendices

    APPENDIX A: Location Maps ......................................................................................................................... 7

    APPENDIX B: Flood Flow Data ..................................................................................................................... 10

    APPENDIX C: Review of As-builts and Engineering Plans ............................................................................ 12

    APPENDIX D: Existing Inundation and Cross Sections................................................................................. 14

    APPENDIX E: Proposed Floodplains and Cross Sections ............................................................................. 21

    APPENDIX F: GIS Table of Contents ............................................................................................................ 27

  • 8/7/2019 CE 462 Project

    3/28

    Abstract

    Due to urbanization, the upper 7.1 miles of Gilkey Creek, located in the City of Burton, Genesee

    County, Michigan, frequently floods. A location map is provided in APPENDIX A. Flow data for the

    project area was used from a previous project that simulated both the 10-year and 100-year flood along

    Gilkey Creek and is attached as APPENDIX B. Engineering plans and as-builts were reviewed and

    APPENDIX C contains the information gathered. A survey crew also gathered information pertaining to

    the existing crossings and typical drain cross sections. The specific crossings studied were Lippincott

    Boulevard, Roat Court, and Lapeer Road. All information was evaluated using ArcMAP, HEC-RAS, and

    HEC-GeoRAS. Existing conditions for the 10-year and 100-year flood events can be found in APPENDIX

    D. Upon analysis it is recommended that the following improvements be made:

    Replace existing structure at each crossing with bridges. Excavate Roat Ct crossing to have new, lower bottom elevation. Institute a maintenance schedule to maintain flow capabilities.

    Resulting outcomes with the above recommendations during the 10-year and 100-year floods for the

    studied crossings can be found in APPENDIX E.

  • 8/7/2019 CE 462 Project

    4/28

    Introduction

    Group 8 was retained by the City of Burton to analyze 3 crossings over Gilkey Creek due to its

    frequent flooding. Gilkey Creek is located in the City of Burton, Genesee County, Michigan. A location

    map can be found in APPENDIX A. Originally the creek and its tributaries served as a drainage route for

    the adjacent farmlands. Urbanization has resulted in significant changes in the 8.7 square mile

    watershed and now contains residential, commercial, industrial, and agricultural land uses. This

    increase in urbanization has resulted in a runoff spike, which needs to be properly modeled to manage

    flood waters. There are 43 total crossings over the main branch of Gilkey Creek. Group 8 was contacted

    to analyze the existing crossings at Lippincott Blvd, Roat Ct, and Lapeer St. The location of this section of

    the creek can be found in APPENDIX A. Flow data for the project area was used from a previous project

    that simulated both the 10-year and 100-year flood along Gilkey Creek and is attached as APPENDIX B.

    From this data, the existing floodplains were created and are depicted in APPENDIX D. All information

    gathered was evaluated and manipulated using ArcMAP, HEC-RAS, and HEC-GeoRAS.

    Discussion

    Methods

    In order to start analysis of the creek, information was gathered from a variety of sources. A

    survey crew was retained to analyze the existing crossings and typical drain cross sections.

    Engineering plans and as-builts were also reviewed. The information gathered from this review

    can be found in APPENDIX C. FEMA flood maps effective September 25, 2009 were studied to

    understand the flood effects on the surrounding area. Existing conditions, such as land use types and

    topographic data, useful in ArcGIS were obtained through Genesee County. APPENDIX F shows a

    screen shot of the GIS Table of Contents with a sample layout. Flow data for the project area was

    used from a previous project that simulated both the 10-year and 100-year flood along Gilkey Creek.

    The flow data is attached as APPENDIX B. Using the GIS data obtained, a concise map was created to

    include only the area of interest. Through HEC-GeoRAS modeling techniques the creek geometry was

    created and imported into HEC-RAS. Effectively, a model of the section of stream being analyzed was

    created. Adding the flood flow data allowed for an existing floodplains map to be created in ArcMAP.

    The existing floodplain maps and cross sections at the crossings can be found in APPENDIX D. Steady

    flow analyses were run. The effects of different structures at the crossings were evaluated and the

    most effective designs were chosen to properly manage the flood flows.

  • 8/7/2019 CE 462 Project

    5/28

    Findings

    For the existing culverts and pipes, both the 10-year flood and 100-year flood overtopped the

    roadways. The resulting floodplain and cross sections of the existing flows can be found in APPENDIX

    D. Several structural options were evaluated. Size increases in the box culverts and pipes were tried

    but no options were viable with the given elevations of the roadway. The only feasible options

    appeared to be the construction of bridges to replace the existing structures. For Lippincott Blvd,

    Roat Ct, Lapeer Rd a bridge effectively managed the flow coming through the crossing. In addition,

    an excavation of the channel bottom at the Roat Ct crossing would improve the flow.

    Assessment

    The mapped inundation using the existing results differed from the provided FEMA floodplain

    data, both in APPENDIX D. The differences mainly exist due to the programs predilection for linearly

    connecting cross-sections. Some of the curvy features of the creek were not correctly depicted in the

    model and therefore allowed for a slightly skewed map of the inundations.

    Comparing the existing conditions to the proposed conditions shows a significant change in the

    management of the flood waters. With existing conditions, each crossing was overtopped during

    both the 10-year and 100-year flood events. By changing the structures at each crossing from box

    culverts and pipes to bridges, the flood flows were adequately managed at all three crossings. The

    effectiveness in managing the 10- and 100- year flows can be seen by comparing the cross-sections in

    APPENDIX D and APPENDIX E.

    The impacts of the proposed changes are social, environmental, and economic. Some of the

    social impacts will occur during construction. Unfortunately many travel routes will be temporarily

    alternated to accommodate for construction at the crossings. The outcome of this construction will

    end up being socially beneficial due to the decrease in flooding. Homes, businesses, and roadways

    will no longer be affected by the overflowing waters and therefore will allow for people to still travel

    and live without worrying about their homes flooding. The reduction in flooding will also be

    economically beneficial. Businesses and roadways will be able to stay open instead of closing due to

    flooding. One downside of the flooding will be the reduction in nutrients provided to surrounding

    farmlands and wetlands. Also, by not allowing the creek to naturally flood, downstream crossings

    may be adversely affected because more flow will go through the studied cross sections.

  • 8/7/2019 CE 462 Project

    6/28

    Environmental impacts can be vast. With the decrease of floods, less loose sediment from

    surrounding lands will be taken downstream and affect other crossings and the creek in general.

    Conclusion and Recommendations

    Upon analysis it is recommended that the following improvements be made:

    Replace existing structures at each crossing with bridges. Excavate Roat Rd crossing to have new, lower bottom elevation. Institute a maintenance schedule to maintain flow capabilities.

    Resulting outcomes with the above recommendations during the 10-year and 100-year floods for the

    studied crossings can be found in APPENDIX E. Flooding conditions for both the 10-year and 100-year

    predictions may be slightly inaccurate due to the cross-sections being drawn somewhat small. This

    eliminated some of the possible flooding that should occur, therefore making it look less expansive.

    Also, more cross sections along the stream would have provided a more accurate map of the inundation

    compared to the actual stream. However, by comparing the flooding extent from before and after

    modifications, it is easy to see that the newly implemented bridges significantly help contain the

    majority of flood water from overtopping the banks and corresponding roadway. The first attempt was

    to increase the dimensions of the culverts, but it was quickly realized for them to accommodate the

    flooding the culverts had to be so large they resembled bridges. For this reason three bridges were

    implemented to solve the flooding problem of the Gilkey Creek over Lapeer, Roat and Lippencott roads.

  • 8/7/2019 CE 462 Project

    7/28

    APPENDIX A: Location Maps

  • 8/7/2019 CE 462 Project

    8/28

    Genessee County, Mighigan

    Approximate Watershed of Gilkey Creek

  • 8/7/2019 CE 462 Project

    9/28

  • 8/7/2019 CE 462 Project

    10/28

    APPENDIX B: Flood Flow Data

  • 8/7/2019 CE 462 Project

    11/28

    STA (ft)

    10-YR

    (cfs)

    100-YR

    (cfs)

    -1+66 866 1256

    0+79 887 1282

    24+39 854 1243

    26+98 854 1243

    37+03 868 1307

    58+38 864 1321

    67+94 689 1043

    112+89 683 1052

    116+29 666 1155

    127+39 670 1159

    148+78 662 1137

    169+44 580 981

    219+39 511 996

    237+54 410 780

    269+81 325 602

    283+25 304 563

    326+48 248 450

    348+77 58 114

    373+21 35 71

    0+00 located 306 ft downstream of Center Road

  • 8/7/2019 CE 462 Project

    12/28

    APPENDIX C: Review of As-builts and Engineering Plans

  • 8/7/2019 CE 462 Project

    13/28

    Crossing Type Surface Structure Type

    Span

    (ft)

    Rise

    (ft)

    # of

    Openings

    Length Parallel to

    Flow (ft) Skew Condition Headwall Type

    Headwall

    Condition

    Sediment in

    Culvert (ft)

    Center

    RoadRoad Bituminous

    Corrugated Metal

    Pipe Arch13 9 1 80 90 Fair 90-deg Concrete Wingwalls Fair 4

    Railroad Rail Rail,Ballast

    Concrete PipeCMP

    CMP

    79.5

    9

    79.5

    9

    3 243 90 Poor d/s - steel and concretewingwalls

    u/s - projecting

    Poor 1.5

    I-69 Highway Bituminous

    Concrete Box

    Concrete Pipe

    Concrete Pipe

    10

    8

    8

    7

    8

    8

    3 262 90 Fair

    90-deg Concrete Wingwalls

    for Box Culvert, Projecting

    for Concrete Pipes

    Fair --

    Lapeer

    RoadRoad Bituminous Concrete Box 13.3 7 1 45 90 Poor 90-deg Concrete Wingwalls Poor --

    Roat Court Road DirtCorrugated Metal

    Pipe7.5 7.5 1 54 90 Good Mitred to Slope Fair --

    LippincottBlvd.

    Road BituminousConcrete BoxConcrete Box

    88

    6.46.4

    2 74 90 Fair Concrete Wingwalls Poor1.51.5

    Atherton

    RoadRoad Bituminous Concrete Box 11.7 6.4 1 46 90 Good Projecting Poor --

    Belsay Road Road Bituminous Concrete Box 14 6 1 60 90 New 45-deg Concrete Wingwalls New --

    Bristol Road Road DirtCorrugated Metal

    Pipe5 5 1 43 90 Poor Concrete Wingwalls Poor 1

  • 8/7/2019 CE 462 Project

    14/28

    APPENDIX D: Existing Inundation and Cross Sections

  • 8/7/2019 CE 462 Project

    15/28

    FEMA Floodplain

  • 8/7/2019 CE 462 Project

    16/28

    Existing Inundation 10 yr Flood

    Existing Inundation 100 yr Flood

  • 8/7/2019 CE 462 Project

    17/28

    Lippincott Blvd 10yr Flood

    Lippincott Blvd 100 yr Flood

    0 10 20 30 40 50760

    762

    764

    766

    768

    770

    772

    GilkeyCrk Plan: Gilkey1 4/28/2011Lippincott Blvd

    Station (ft)

    Elevation(

    ft)

    Legend

    EG 10yr

    WS 10yr

    Crit 10yr

    Ground

    BankSta

    .045 .045 .045

    0 10 20 30 40 50760

    762

    764

    766

    768

    770

    772

    774

    GilkeyCrk Pla n: Gilkey1 4/28/20 11Lippincott Blvd

    Station (ft)

    Elevation(

    ft)

    Legend

    EG 100yr

    WS 100yr

    Cri t 100yr

    Ground

    BankSta

    .045 .045 .045

  • 8/7/2019 CE 462 Project

    18/28

    Roat Ct 10yr Flood

    Roat Ct 100yr Flood

    0 10 20 30 40 50 60761

    762

    763

    764

    765

    766

    767

    768

    769

    770

    GilkeyCrk Plan : Gilkey1 4/28/201 1Roat Ct

    Station (ft)

    Elevation(

    ft)

    Legend

    EG 10yr

    WS 10yr

    Crit 10yr

    Ground

    BankSta

    .045 .045 .045

    0 10 20 30 40 50 60760

    762

    764

    766

    768

    770

    772

    GilkeyCrk Plan : Gilkey1 4/28/2011Roat Ct

    Station ( ft)

    Elevation(

    ft)

    Legend

    EG 100yr

    WS 100yr

    Crit 100yr

    Ground

    BankSta

    .045 .045 .045

  • 8/7/2019 CE 462 Project

    19/28

  • 8/7/2019 CE 462 Project

    20/28

    Existing Section Profile

    0 1000 2000 3000 4000 5000 6000 7000750

    755

    760

    765

    770

    775

    GilkeyCrk Plan : 1) Gilkey1 4/28/2011

    Main Channel Distance (ft)

    Elevation(

    ft)

    Legend

    EG 100yr

    WS 100yr

    EG 10yr

    WS 10yr

    Crit 100yr

    Crit 10yr

    Ground

    GilkeyCreek Group8

  • 8/7/2019 CE 462 Project

    21/28

    APPENDIX E: Proposed Floodplains and Cross Sections

  • 8/7/2019 CE 462 Project

    22/28

    Inundation with Proposed Changes 10 yr Flood

    Inundation with Proposed Changes 100 yr Flood

  • 8/7/2019 CE 462 Project

    23/28

    Lippincott Blvd 10yr Flood

    Lippincott Blvd 100 yr Flood

    0 10 20 30 40 50760

    762

    764

    766

    768

    770

    772

    GilkeyCrk Plan : Gilkey1 4/28/2011Lippincott Blvd

    Station (f t)

    Elevation(

    ft)

    Legend

    EG 10yr

    WS 10yr

    Crit 10yr

    Ground

    BankSta

    .045 .045 .045

    0 10 20 30 40 50760

    762

    764

    766

    768

    770

    772

    774

    GilkeyCrk Plan: Gilkey1 4/28/2011Lippincott Blvd

    Station ( ft)

    Elevation(

    ft)

    Legend

    EG 100yr

    WS 100yr

    Crit 100yr

    Ground

    BankSta

    .045 .045 .045

  • 8/7/2019 CE 462 Project

    24/28

    Roat Ct 10yr Flood

    Roat Ct 100yr Flood

    0 10 20 30 40 50 60762

    764

    766

    768

    770

    GilkeyCrk Plan: Gilkey1 4/28/2011Roat Ct

    Station ( ft)

    Elevation(

    ft)

    Legend

    EG 10yr

    WS 10yr

    Crit 10yr

    Ground

    BankSta

    .045 .045 .045

    0 10 20 30 40 50 60762

    764

    766

    768

    770

    772

    GilkeyCrk Plan: Gilkey1 4/28/201 1Roat Ct

    Station (ft)

    Elevation(

    ft)

    Legend

    EG 100yr

    WS 100yr

    Crit 100yr

    Ground

    BankSta

    .045 .045 .045

  • 8/7/2019 CE 462 Project

    25/28

    Lapeer Rd 10yr Flood

    Lapeer Rd 100 yr Flood

    0 10 20 30 40 50 60756

    758

    760

    762

    764

    766

    768

    770

    GilkeyCrk Pla n: Gilkey1 4/28/2011

    Station ( ft)

    Elevation(

    ft)

    Legend

    EG 10yr

    WS 10yr

    Crit 10yr

    Ground

    BankSta

    .045 .045 .045

    0 10 20 30 40 50 60756

    758

    760

    762

    764

    766

    768

    770

    GilkeyCrk Plan : Gilkey1 4/28/20 11

    Station (ft)

    Elevation(

    ft)

    Legend

    EG 100yr

    WS 100yr

    Cri t100yr

    Ground

    BankSta

    .045 .045 .045

  • 8/7/2019 CE 462 Project

    26/28

    Existing Section Profile

    0 1000 2000 3000 4000 5000 6000 7000750

    755

    760

    765

    770

    775

    GilkeyCrk Plan : Gilkey1 4/28/201 1

    Main Channel Distance (ft)

    Elevation(

    ft)

    Legend

    EG 100yr

    WS 100yr

    EG 10yr

    WS 10yr

    Crit 100yr

    Crit 10yr

    Ground

    GilkeyCreek Group8

  • 8/7/2019 CE 462 Project

    27/28

    APPENDIX F: GIS Table of Contents

  • 8/7/2019 CE 462 Project

    28/28