cdm-pdd-scc-form project design document form for ...cdm-pdd-scc-form version 05.0 page 1 of 45...

45
CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT DESIGN DOCUMENT (PDD) Title of the project activity Nam Long Hydropower Project Version number of the PDD 04 Completion date of the PDD 26/09/2014 Project participant(s) Nam Long Power Co., Ltd. Climate Bridge Ltd. Host Party Lao PDR United Kingdom of Great Britain and Northern Ireland Sectoral scope and selected methodology(ies), and where applicable, selected standardized baseline(s) Sectoral Scope 1: Energy Industries. Baseline methodology: AMS I.D. - Grid Connected Renewable Electricity Generation Estimated amount of annual average GHG emission reductions 24,035 t CO 2 e

Upload: others

Post on 17-Aug-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 1 of 45

Project design document form for

small-scale CDM project activities

(Version 05.0)

PROJECT DESIGN DOCUMENT (PDD)

Title of the project activity Nam Long Hydropower Project

Version number of the PDD 04

Completion date of the PDD 26/09/2014

Project participant(s) Nam Long Power Co., Ltd. Climate Bridge Ltd.

Host Party Lao PDR United Kingdom of Great Britain and Northern Ireland

Sectoral scope and selected

methodology(ies), and where applicable,

selected standardized baseline(s)

Sectoral Scope 1: Energy Industries. Baseline methodology: AMS I.D. - Grid Connected Renewable Electricity Generation

Estimated amount of annual average GHG

emission reductions 24,035 t CO2e

Page 2: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 2 of 45

SECTION A. Description of project activity

A.1. Purpose and general description of project activity

>> Nam Long Hydropower project (hereafter referred to as the “the project”) is located 50 km west of Luang Namtha and 9 km northwest of Long District, Luang Namtha Province, Lao PDR. The project is located on the Nam Long, a tributary of the Nam Ma, which finally discharges into the Mekong River. The scheme is a run-of-river scheme. The installed capacity of the project is 5 MW, with the annually 37 GWh power supplied to the local Luang Namtha grid. Electricite du Laos (EDL) will buy all power produced, with measurement of output at the plant. The power supply in Luang Namtha Province is precarious, till 2011, there was only one 1.5MW hydropower project in the local Luang Namtha grid, most of the electricity is imported from China. The Luang Namtha province is facing a considerable shortage in supply in relation to demand, and load shedding is a frequent phenomenon. The proposed project will result in CO2 emission reduction, as it will displace the power generation that otherwise would be based on a mix of fossil fuels. The reduction in carbon dioxide emissions is estimated to be 24,035 tonnes per year. As a renewable energy project, the project will produce positive environmental and economic benefits and contribute to the local sustainable development in following aspects: During the construction period, plenty of job opportunities were provided to local residents,

and the workers newly coming to the area are bringing local people lots of employment

opportunities that increase the income of the local residents;

The infrastructure has been greatly improved. The enhancement of the transportation and

electricity system brings substantial benefits to local villagers;

The use of firewood will be reduced because of displacement by electricity, this reduces the

damage to the local vegetation;

Provide clean & cheap electricity in this region, promote the sustainable development in this

region and slowing down the increasing trend of GHG emissions

A.2. Location of project activity

A.2.1. Host Party

>> Lao PDR

A.2.2. Region/State/Province etc.

>> Luang Namtha Province

A.2.3. City/Town/Community etc.

>> Long District

A.2.4. Physical/ Geographical location

>> The Project site is located at the Nam Long, a tributary of the Nam Ma, which finally discharges into the Mekong River, 50 km west of Luang Namtha and 9 km northwest of Long District, Luang Namtha Province, Lao PDR. The approximate coordinates of the project site is: 20°55′58″N, 100°55′58″E.

Page 3: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 3 of 45

Figure A.1 Show the location of the project:

Figure A.1. Location of the project

A.3. Technologies and/or measures

>> The total installed capacity of the project is 5 MW. The construction of the project includes fixed weir, a sand f1ush, intake, headrace channel, head tank, penstock, powerhouse with 2 units of turbines (2*2,500 kW), and a tailrace. The baseline scenario is the same as the scenario existing prior to the implementation of the project activity. The baseline scenario is the electricity delivered to the grid by the project activity would have otherwise been generated by the operation of grid-connected power plants and by the addition of new generation sources into the grid. Without the project the existing scenario of imported electricity from China would continue. The table below summarizes the main technical features of the project.

Page 4: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 4 of 45

Table A.1 Main parameters of the project

Parameter Unit Value

Gross head m 254

Rated head m 245

Rated discharge m3/s 2.62

Installed capacity MW 5

Electricity generation MWh 37,000

Plant factor - 84%

G

G Regional Grid

consisting of Luang

Namtha and China

Southern Power

Grid

Transformer G Turbine & Generator Unit

Project site

M Meter

M2

M1

M3

EGoutput,y/EGinput,y

EGinput,y

EGoutput,y/EGinput,y

Facility

power use

Figure A.2. Technical diagram

A.4. Parties and project participants

>>

Party involved (host) indicates host Party

Private and/or public entity(ies) project participants (as applicable)

Indicate if the Party involved wishes to be considered as project participant (Yes/No)

Lao PDR (host) Nam Long Power Co., Ltd.

(Project owner) No

United Kingdom of Great Britain and Northern Ireland

Climate Bridge Ltd. No

A.5. Public funding of project activity

>> The project does not receive any public funding from Parties included in Annex I of the UNFCCC. The project does not use ODA directly or indirectly.

Page 5: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 5 of 45

A.6. Debundling for project activity

>> According to the Guidelines on Assessment of Debundling for SSC Project Activities (Version 03, EB54, Annex 13), a proposed small-scale project activity shall be deemed to be a debundled component of a large project activity if there is a registered small-scale CDM project activity or an application to register another small-scale CDM project activity: (a) With the same project participants; (b) In the same project category and technology/measure; (c) Registered within the previous 2 years; And (d) Whose project boundary is within 1 km of the project boundary of the proposed small-scale

activity at the closest point. The project owner indicates that there is no registered small-scale CDM project activity or an application to register another small-scale CDM project activity in accordance with any condition mentioned above, therefore the project is not a de-bundled component of a large project activity.

SECTION B. Application of selected approved baseline and monitoring

methodology

B.1. Reference of methodology

>>

Baseline methodology:

Baseline methodology: AMS I.D. Grid connected renewable electricity generation (Version 17, EB 61). This methodology draws upon the following tools: Guidelines for demonstrating additionality of microscale project activities (version 05.0, EB 73) and Tool to calculate the emission factor for an electricity system (version 4, EB 75) And the Approved consolidated baseline and monitoring methodology ACM0002 (Version 14, EB 75): Consolidated baseline methodology for grid-connected electricity generation from renewable sources is also a reference according to AMS I.D. Please click following link for more information about the methodology and tool: http://cdm.unfccc.int/methodologies/PAmethodologies/approved.html

B.2. Project activity eligibility

>> The Project is a grid connected renewable electricity generation project which meets all the applicability criteria stated in methodology ASM I.D (version 17): The project makes use of renewable water resources to generate electricity to the local Luang

Namtha grid; The project will install a new power plant at the site where there was no renewable energy

power plant operating prior to the implementation of the project activity (Greenfield plant); The total installed capacity of the project is 5 MW, it satisfies the requirement that the capacity

of the project should be at most 5 MW for a small-scale CDM project. The other criteria stated in the AMS I.D are not applicable to the project; Therefore, the methodology AMS-I.D.-Grid Connected Renewable Electricity Generation is applicable to the Project.

Page 6: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 6 of 45

B.3. Project boundary

>>

Spatial boundary The project located in the north part of Lao PDR, The power generated by the project will be supplied to the local Luang Namtha Power Grid, which is not connected with the main grid of Lao EDL, but connected with China Southern Power Grid (CSPG) through transmission lines.

According to the AMS-I.D., the spatial extent of the project boundary includes the project power plant and all power plants connected physically to the electricity system that the CDM project power plant is connected to.

According to “Tool to calculate the emission factor for an electricity system”, the project

electricity system is defined as the spatial extent of the power plants that are physically connected through transmission and distribution lines to the project activity (i.e. the renewable power plant location) and that can be dispatched without significant transmission constraints. According to the tool mentioned above, there are no transmission constraints if any one of the following criteria is met: i. In case of electricity systems with spot markets for electricity: there are differences in electricity prices (without transmission and distribution costs) of less than five per cent between the two electricity systems during 60 per cent or more of the hours of the year; or ii. The transmission line is operated at 90 per cent or less of its rated capacity at least during 90 per cent of the hours of the year. For transmission lines between China and Lao Power Grid, there is no spot market exists, so the criteria i. list above is not applicable. Furthermore the load of the transmission lines between local grid and China Southern Power Grid is about 36% of its rated capacity

1. So, the electricity system

does not have significant transmission constrain. According to the “Tool to calculate the emission factor for an electricity system”: In addition, in cases involving international interconnection (i.e. transmission line is between different countries and the project electricity system covers national grids of interconnected countries) it should be further verified that there are no legal restrictions for international electricity exchange. As the infrastructure in the North part of Lao PDR is poor, the power use is dependence on the power supplied from China. From Dec 2009 to Mar 2014, there is totally 522 million KWh power supplied from China to Lao

2. During the Neighboring State Electricity Enterprise Summit, 6 country

including Lao and China signed the Memorandum of Understanding on high-level communication mechanism for the transnational Power Grid deep cooperation. Based on the above information, it could be concluded that there are no legal restrictions for international electricity exchange. Based on the reasons listed above, it is shown that the most appropriate definition of the spatial

extension of the project electricity system is a regional grid consisting of regional grid of Luang Namtha Grid and CSPG.

According to “Tool to calculate the emission factor for an electricity system”, the Connected

electricity system is an electricity system that is connected by transmission lines to the project electricity system. As the local Luang Namtha Power Grid is not connected with any other power grid, the connected electricity system is defined according to the definition provided by the

1 According to the statement from local power grid staff, the rated capacity of the 22KV transmission line is 12.75 MW, the normally load is about 4.6 MW, which accounts 36% (4.6/12.75) of its rated capacity.

2 http://www.csg.cn/nwgsxw/2014/gdyw/201404/t20140429_80028.html

Page 7: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 7 of 45

Chinese DNA (NDRC)3. As the Central China Power grid (CCPG) supplied power to CSPG in 2009,

2010, 20114, therefore, CCPG is selected as the connected electricity system.

Geographical site: the area where the project is constructed which includes the dam, the tunnel, the power house and the sub-station.

Physical boundary: This consists of all power plants connected physically to the electricity system, which is defined as the Local Luang Namtha Grid and the China Grid, to which the project is connected (Refer to Section B.4 for details).

Emission sources and gases

The greenhouse gases and emission sources included in or excluded from the project boundary are shown in the table below.

Table B.1. GHG emissions in Project boundary

Source Gas Included?

Justification/Explanatio

n

Ba

se

lin

e CO2 emissions from

electricity generation in fossil fuel fired power plants that are displaced due to the project activity

CO2 Yes Main emission source

CH4 No Minor emission source

N2O No Minor emission source

Pro

ject

Ac

tiv

ity

For geothermal power plants, fugitive emissions of CH4 and CO2 from non condensable gases contained in geothermal steam.

CO2 No

Not applicable to hydro power Project

CH4 No

N2O No

CO2 emissions from combustion of fossil fuels for electricity generation in solar thermal power plants and geothermal power plants.

CO2 No

Not applicable to hydro power Project

CH4 No

N2O No

For hydro power plants, emissions of CH4 from the reservoir.

CO2 No Minor emission source

CH4 No

The project does not create reservoir, thus the emission source from reservoir is excluded

N2O No Minor emission source

A flow diagram of the project boundary is presented in Figure B.1 below. The flow diagram physically delineates the project boundary, includes the flow of electricity and the project electricity system and the GHG emissions.

3 http://cdm.ccchina.gov.cn/Detail.aspx?newsId=41386&TId=3

4 CCPG supplied power to CSPG: 21,852,270 MWh in 2009, 23,423,940 MWh in 2010 and 16,118,680 in 2011, China DNA.

Page 8: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 8 of 45

G

GRegional Grid consisting of

Luang Namtha and China

Southern Power Grid

CO2 emissions

Transformer G Turbine & Generator Unit

Project site

Project boundary

Fossil fuel fired power

plants

M2

M1

M3

EGoutput,y/EGinput,y

EGoutput,y/EGinput,y

M Meter

EGinput,y

Facility

power use

Figure B.1 Flow diagram of the project boundary

B.4. Establishment and description of baseline scenario

>> According to ASM I.D, the baseline scenario is that the electricity delivered to the grid by the project activity would have otherwise been generated by the operation of grid-connected power plants and by the addition of new generation sources into the grid. Long District is not connected to the main power grid in Lao PDR. The map below shows that the grid receives power from the China Southern Power Grid. Power is distributed in the province by EdL.

Page 9: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 9 of 45

Figure B.2 Planned Power System Diagram of Lao In year of 20155

According to the definition of the China Power Grid provided by the Chinese DNA (NDRC)

6, the

China Power Grid consists of six Regional Power Grids which is Northern China Power Grid (NCPG), Northeastern China Power Grid (NECPG), Eastern China Power Grid (ECPG), Central China Power grid (CCPG), Northwestern China Power Grid (NWCPG) and China Southern Power Grid (CSPG). The project is connected physically with the CSPG. CSPG is defined as the project electricity system. The grid consists of independent province-level electricity systems including Guangdong, Guangxi, Yunnan, Guizhou and Hainan province that are physically connected through transmission and

distribution lines. In accordance with the tool, the project electricity system is a regional grid

consisting of regional grid of Luang Namtha Grid and CSPG, and the CCPG as the connected

electricity system. The imported electricity and relevant CO2 emission will be considered in OM calculation. Thus the baseline scenario of the proposed project is delivery of the equivalent amount of annual power from the local Luang Namtha grid and output from the CSPG, to which the proposed project is also connected. To determine the baseline scenario, the information for the Luang Namtha grid is provided by Electricite du Laos (EDL), and the information for the China Southern Power Grid is provided by Chinese DNA.

B.5. Demonstration of additionality

>>

Prior CDM consideration: The Project Owner was aware of CDM incentives following the completion of the Feasibility Study Report (FSR). As the Feasibility Studies had shown that the project would only deliver a marginal revenue for investors, the Project Owner started to obtain quotations from CDM Consultants.

Table B.2. Major milestones in the development of the investment project and CDM

application

Detail Date

FSR Completed February 2008

FSR approved by government of Lao (GoL) 07/04/2008

Initial Environmental Examination (IEE) Completed May 2008

Board meeting decided to carry out the project with CDM assistance 05/06/2008

Civil Work Agreement(Start date) 07/07/2008

Service Agreement of CDM Development with an local Consultant for finding the a buyer

11/11/2008

Signed PPA 11/02/2009

A Japanese CERs buyer sent a Letter of Interest for the project 17/04/2009

Desk Due Diligence Conducted by the Japanese Buyer 12/09/2009

The Japanese buyer issued refusal letter due to failed DD, for there is no regulation for the trans-nation power grid situation

12/10/2009

IEE approved by GOL 07/12/2009

MOU for CERs purchasing was signed with an European Buyer 03/09/2010

The European Buyer carried out an onsite visit for the project April 2011

Equipment Purchase Contract 11/05/2011

Successful Due Diligence letter 04/07/2011

Apply for Lao LoA 06/09/2011

Due to Market Falls, the European buyer decided to withdraw from the project

28/03/2012

5 Date Source: EdL Technical Department Power System Planning Office

6 http://cdm.ccchina.gov.cn/Detail.aspx?newsId=41386&TId=3

Page 10: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 10 of 45

Termination of authorization with the local consultant 10/08/2012

CDM Services Agreement with new consultant Beijing Karbon Energy Consulting Co., Ltd.

12/02/2013

Term sheet with the new buyer Climate Bridge Ltd. 10/04/2013

ERPA signed with Climate Bridge Ltd. 08/10/2013

Updated LoA Application to Lao DNA 25/11/2013

As per the “Guidelines on the Demonstration and assessment of prior consideration of the CDM” (Version 04), the project’s start date is before 02/08/2008, it does not need to inform the Host Country DNA and the UNFCCC secretariat their intention to seek CDM status. The additionality of the Project could be assessed according to the UNFCCC-approved additionality demonstration criteria of “Microscale Project Activity” per Guidelines for demonstrating additionality of microscale project activities (Version 05.0).

According to Paragraph 8(a), Project activities up to five megawatts that employ renewable energy technology are additional if the geographic location of the project activity is in one of the least developed countries or the small island developing States (LDCs/SIDS) or in a special underdeveloped zone (SUZ) of the host country, which can be summarized as follow in accordance with the project situation:

(i) The installed capacity of the project is up to 5 MW The installed capacity of the project is 5 MW, which is no more than 5 MW.

(ii) The project activity is located in LDCs/SIDs

Lao PDR is one of the 49 least developed countries7 published by the Committee for Development

Policy (CDP). Therefore, the condition 8(a) is satisfied. Thus, the project is deemed to be additional.

B.6. Emission reductions

B.6.1. Explanation of methodological choices

>> The Methodology AMS I.D (version 17) is applied in the context of the project in the following four steps:

Step 1, calculate the project emissions;

Step 2, calculate the baseline emissions;

Step 3, calculate the project leakage;

Step 4, calculate the emission reductions.

Calculate the project emissions According to Methodology, the project emissions shall be calculated by the following equation:

y FF,y GP,y HP,yPE =PE PE PE (Equation B.1)

Where:

PEy = Project emissions in year y (tCO2e/yr)

PEFF,y = Project emissions from fossil fuel consumption in year y (tCO2/yr)

PEGP,y = Project emissions from the operation of geothermal power plants due to the release of non-condensable gases in year y (tCO2e/yr)

7 http://www.unohrlls.org/en/ldc/25/

Page 11: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 11 of 45

PEHP,y = Project emissions from water reservoirs of hydro power plants in year y (tCO2e/yr)

This project does not involve fossil fuel consumption and geothermal power, so PEFF,y=0, PEGP,y=0. For hydro power project activities that result in new reservoirs and hydro power project activities that result in the increase of existing reservoirs, project proponents shall account for project emissions, estimated as follows: a) If the power density (PD) of power plant is greater than 4 W/m

2 and less than or equal to 10

W/m2:

Res y

HP, y

EF TEGPE

1000

(Equation B.2)

Where:

PEHP,y = Project emissions from water reservoirs (tCO2e/yr)

EFRes = Default emission factor for emissions from reservoirs, and the default value as per EB 23 is 90 kg CO2e /MWh

TEGy = Total electricity produced by the project activity, including the electricity supplied to the grid and the electricity supplied to internal loads, in year y (MWh)

b) If the power density (PD) of the power plant is greater than 10 W/ m

2

PEHP,y=0 (Equation B.3) The PD of the project activity is calculated as follows:

PJ BL

PJ BL

Cap -CapPD=

A -A (Equation B.4)

Where:

PD = Power density of the project activity (W/ m2)

CapPJ = Installed capacity of the hydro power plant after the implementation of the project activity (W)

CapBL = Installed capacity of the hydro power plant before the implementation of the project activity (W). For new hydro power plants, this value is zero

APJ = Area of the reservoir measured in the surface of the water, after the implementation of the project activity, when the reservoir is full (m

2)

ABL = Area of the reservoir measured in the surface of the water, before the implementation of the project activity, when the reservoir is full (m

2). For new

reservoirs, this value is zero

As the project does not include a reservoir, there is no PD for the project.

Calculate the baseline emissions Baseline emissions include only CO2 emissions from electricity generation in fossil fuel fired power plants that are displaced due to the project activity. The methodology assumes that all project electricity generation above baseline levels would have been generated by existing grid-connected power plants and the addition of new grid-connected power plants. The baseline emissions are to be calculated as follows:

BEy=EGBL,y* EFCO2,grid,y (Equation B.5) Where:

BEy = Baseline Emissions in year y (tCO2/yr)

EGBLy = Quantity of net electricity supplied to the grid as a result of the implementation

of the CDM project activity in year y (MWh/yr)

Page 12: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 12 of 45

EFCO2,grid,y = Combined margin CO2 emission factor for grid connected power generation in

year y

According to Methodology, if the project activity is the installation of a new grid-connected renewable power plant/unit at a site where no renewable power plant was operated prior to the implementation of the project activity, then:

EGBL,y=EGfacility,y (Equation B.6) The emission coefficient (measured in tCO2e/MWh) should be calculated in a transparent and conservative manner according to the procedures prescribed in the “Tool to calculate the emission factor for an electricity system” (Version 4). The data used for calculation are from an official source (where available) and publicly available. The calculation processes are as follows: STEP 1: Identify the relevant electricity system.

STEP 2: Choose whether to include off-grid power plants in the project electricity system.

STEP 3: Select a method to determine the operating margin (OM).

STEP 4: Calculate the operating margin emission factor according to the selected method.

STEP 5: Calculate the build margin (BM) emission factor;

STEP 6: Calculate the combined margin (CM) emissions factor.

STEP 1: Identify the relevant electricity system

As we discussed in section B.3, the project electricity system is defined as a regional grid of Luang Namtha Grid and CSPG.

STEP 2: Choose whether to include off-grid power plants in the project electricity system

(optional) According to “Tool to calculate the emission factor for an electricity system” (Version 4), there are two options to calculate the operating margin and build margin emission factor:

Option I: Only grid power plants are included in the calculation.

Option II: Both grid power plants and off-grid power plants are included in the calculation. Option I is chosen for operating margin and build margin emission factor calculation.

STEP 3: Select a method to determine the operating margin (OM) According to “Tool to calculate the emission factor for an electricity system” (Version 4), there are four methods for calculating the EFgrid, OM, y: (a) Simple OM, or (b) Simple adjusted OM, or (c) Dispatch Data Analysis OM, or (d) Average OM Calculating method (b) simple adjusted OM, would require the annual load duration curve of the grid. However, the relevant information is not publicly available and is difficult to obtain. Therefore, the method (b) is not applicable. The method (c) requires the detailed operation and dispatch data of power plants in the grid. This data is also not publicly available for the China Southern Power Grid. Therefore, the method (c) is not applicable.

Page 13: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 13 of 45

The method (d), average OM, is used when low-cost / must run resources constitute more than 50% of total amount of power generation in the grid. This is not the scenario in the China Southern Power Grid and therefore method (d) is not applicable. The method a), the simple OM is used where low-cost / must run resources constitute less than 50% of the total grid generation in: 1) average of the five most recent years or 2) based on long-term normal for hydroelectricity production. The percentage of low-cost/must run resources in the grid is 26.90% in 2007, 33.76% in 2008,

32.01% in 2009, 30.34% in 2010 and 31.74% in 20118. The low-cost / must run resources

constitute less than 10% of the total grid generation in the recent 5 years and the simple OM (method a) can be used. Thus, method (a) is applicable to calculate EFgrid, OM, y. For the project, EFgrid, OM, simple, y is calculated using ex ante option: a 3-year generation-weighted average, based on the most recent data available at the time of submission of the CDM-PDD to DOE for validation, without requirement to monitor and recalculate the emissions factor during the crediting period.

STEP 4: Calculate the operating margin emission factor according to the selected method The simple OM emission factor is calculated as the generation-weighted average CO2 emissions per unit net electricity generation (tCO2/MWh) of all generating power plants serving the system, not including low-cost/must-run power plants/units. According to “Tool to calculate the emission factor for an electricity system” (Version 4), there are two options based on different data for calculating simple OM: Option A: Based on the net electricity generation and a CO2 emission factor of each power unit; or Option B: Based on the total net electricity generation of all power plants serving the system

and the fuel types and total fuel consumption of the project electricity system. For the project, the necessary data for Option A is not available, so Option B can be used since the quantity of electricity supplied to the grid by low-cost/must-run power sources is known and off-grid power plants are not included in the calculation.. Under this option, the simple OM emission factor is calculated based on the net electricity supplied to the grid by all power plants serving the system, not including low-cost/must-run power plants/units, and based on the fuel type(s) and total fuel consumption of the project electricity system, as follows:

2, ,, ,

, ,

( )i yi y i y CO

igrid OMSimple y

y

FC NCV EF

EFEG

(Equation B.7)

Where:

EFgrid,OMsimple,y = Simple operating margin CO2 emission factor in year y (tCO2/MWh)

FCi, y = Amount of fossil fuel type i consumed in the project electricity system in year y (mass or volume unit)

NCVi,y = Net calorific value (energy content) of fossil fuel type i in year y (GJ / mass or volume unit)

EFCO2,i,y = CO2 emission factor of fossil fuel type i in year y (tCO2/GJ)

EGy = Net electricity generated and delivered to the grid by all power sources serving the system, not including low-cost/must-run power plants/units, in year y (MWh)

8 China Electric Power Yearbook 2008~2012 and Lao EdL Annual Report 2008~2011

Page 14: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 14 of 45

i = All fossil fuel types combusted in power sources in project electricity system in year y

y = The data available in the most recent 3 years

The Operating Margin emission factors for 2009, 2010 and 2011 are calculated. A 3-year generation-weighted average of the emission factors is calculated as the operating margin emission factor of the baseline, which is calculated ex-ante and will not be renewed in the first crediting period.

CSPG EFgrid, OM, y, adopts the calculation process updated by China DNA on Sep. 17th 2013. The

exact calculation process of CSPG EFgrid, OM, y can be found from: http://www.ccchina.gov.cn/archiver/cdmcn/UpFile/Files/Default/201309181742.pdf For the detailed calculating procedures please refer to Appendix 4 of the PDD.

The Operation Margin Emission Factor of CSPG and Luang Namtha Grid is 0.9223 tCO2e/MWh.

Step 5. Calculate the build margin (BM) emission factor In terms of vintage of data, project participants can choose between one of the following two options: Option 1: For the first crediting period, calculate the build margin emission factor ex-ante based on

the most recent information available on units already built for sample group m at the time of CDM-PDD submission to the DOE for validation. For the second crediting period, the build margin emission factor should be updated based on the most recent information available on units already built at the time of submission of the request for renewal of the crediting period to the DOE. For the third crediting period, the build margin emission factor calculated for the second crediting period should be used. This option does not require monitoring the emission factor during the crediting period.

Option 2: For the first crediting period, the build margin emission factor shall be updated annually, ex-post, including those units built up to the year of registration of the project activity or, if information up to the year of registration is not yet available, including those units built up to latest year for which information is available. For the second crediting period, the build margin emissions factor shall be calculated ex-ante, as described in option 1 above. For the third crediting period, the build margin emission factor calculated for the second crediting period should be used.

The Option 1 is chosen to calculate without requirement to monitor and recalculate the emissions factor during the crediting period. According to “Tool to calculate the emission factor for an electricity system”, the sample group of power units m used to calculate the build margin should be determined as per the following procedure, consistent with the data vintage selected above: (a) Identify the set of five power units, excluding power units registered as CDM project

activities, that started to supply electricity to the grid most recently (SET5-units) and determine their annual electricity generation (AEGSET-5-units, in MWh);

(b) Determine the annual electricity generation of the project electricity system, excluding power units registered as CDM project activities (AEGtotal, in MWh). Identify the set of power units, excluding power units registered as CDM project activities, that started to supply electricity to the grid most recently and that comprise 20% of AEGtotal (if 20% falls on part of the generation of a unit, the generation of that unit is fully included in the calculation) (SET≥20%) and determine their annual electricity generation (AEGSET-≥20%, in MWh);

(c) From SET5-units and SET≥20% select the set of power units that comprises the larger annual electricity generation (SETsample);

Page 15: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 15 of 45

The build margin emissions (BM) factor is the generation-weighted average emission factor (tCO2e/MWh) of all power units m during the most recent year y for which power generation data is available, calculated as follow:

m,y EL,m,y

m

grid,BM,y

m,y

m

EG EF

EFEG

(Equation B.8)

Where:

EFgrid,BM,y = Build margin CO2 emission factor in year y (tCO2e/MWh);

EGm,y = Net electricity generated and delivered to the grid by power unit m in year y (MWh);

EFEL,m,y = CO2 emission factor of power unit m in the year y (tCO2e/MWh);

m = Power units included in the build margin;

y = Most recent historical year for which power generation data is available;

In China, EB accepts9 the following deviation in methodology application:

1. The group of power plants to be considered for the determination the BM emission factor can’t

be selected as no plant specific generation data are available. Instead, the capacity addition

from one year to another is used as basis for determining the build margin, i.e. the capacity

addition over 1 - 3 years, whichever results in a capacity addition that is closest to 20% of total

installed capacity.

2. Use proportional weights that correlate to the distribution of installed capacity in place during

the selected period above, using plant efficiencies and emission factors of commercially

available best practice technology in terms of efficiency. It is suggested to use the efficiency

level of the best technology commercially available in the provincial/regional or national grid of

China, as a conservative proxy.

Since there is no way to separate the different generation technology capacities as coal, oil or gas etc from thermal power based on the present statistical data, the following calculating measures will be taken:

Firstly, according to the energy statistical data of most recent one year, determine the ratio of CO2 emissions produced by solid, liquid, and gas fuels consumption for power generation;

Secondly, multiply this ratio by the respective emission factors based on commercially available best practice technology in terms of efficiency;

Finally, this emission factor for thermal power is multiplied with the ratio of thermal power identified within the approximation for the latest 20% installed capacity addition to the grid. The result is the BM emission factor of the grid.

Sub-step a. Calculate the power generation emissions for solid, liquid and gas fuel and each share of total emissions based on the Energy Balance Table of the most recent year.

,

,

2

2

i,j,y i,y CO ,i,j,y

Coal,y

i,j,y i,y CO ,i,j,y

F NCV EF

λF NCV EF

i COAL j

i j

(Equation B.9a)

9 This is in accordance with the “Request for guidance: Application of AM0005 and AMS-I.D in China”, a letter

from DNV to the Executive Board, dated 07/10/2005, available online at: http://cdm.unfccc.int/UserManagement/FileStorage/6POIAMGYOEDOTKW25TA20EHEKPR4DM

This approach has been applied by several registered CDM projects using methodology ACM0002 so far.

Page 16: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 16 of 45

,

,

2

2

i,j,y i,y CO ,i,j,y

Oil,y

i,j,y i,y CO ,i,j,y

F NCV EF

λF NCV EF

i OIL j

i j

(Equation B.9b)

,

,

2

2

i,j,y i,y CO ,i,j,y

Gas,y

i,j,y i,y CO ,i,j,y

F NCV EF

λF NCV EF

i GAS j

i j

(Equation B.9c)

Where,

Fi, j, y = The amount of fuel i (in a mass or volume unit) consumed by power plant/unit j in year(s) y;

NCVi,y = The net calorific value (energy content) of fossil fuel type i (coal, oil and gas) in year y (GJ/Mass or Volume unit);

EFCO2,i, j, y = The CO2 emission factor of fuel type i (coal, oil and gas) in year(s) y (tCO2e/GJ);

Coal, Oil

and Gas

= Solid fuel, liquid fuel and gas fuel respectively;

Sub-step b. Calculate emission factor for thermal power of the grid based on the result of Step a. and the efficiency level of the best technology commercially available in China.

Thermal,y Coal,y Coal,Adv,y Oil,y Oil,Adv,y Gas,y Gas,Adv,yEF =λ ×EF +λ ×EF +λ ×EF (Equation B.10)

Where EFCoal, Adv,y, EFOil, Adv,y and EFGas, Adv,y refer to the emission factors of efficiency level of the best technology commercially utilized in power generation using coal, oil and gas in China.

Sub-step c. Calculate BM of the grid based on the result of Step b and the share of thermal power of recent 20% capacity additions.

Thermal

BM,y Thermal

Total

CAPEF EF

CAP (Equation

B.11)

Where,

CAPTotal = Total capacity additions(MW);

CAPThermal = Capacity additions of thermal power(MW);

As mentioned above, the build margin emission factor of the baseline is calculated ex-ante and will not be renewed in the first crediting period. CSPG EFgrid, BM, y adopts the data updated by China DNA on Sep. 17

th, 2013. The exact calculation

process of EF grid, BM, y can be found at: http://www.ccchina.gov.cn/archiver/cdmcn/UpFile/Files/Default/20130917081706402591.pdf Refer to Appendix 4 of the PDD for more details.

The Build Margin Emission Factor of CSPG & Luang Namtha Grid is 0.3769 tCO2e/MWh.

STEP 6: Calculate the combined margin (CM) emissions factor According to “Tool to calculate the emission factor for an electricity system” (Version 4), the calculation of the combined margin (CM) emission factor (EFgrid, CM, y) is based on one of the following methods: (a) Weighted average CM; or (b) Simplified CM.

Page 17: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 17 of 45

The weighted average CM method (option A) should be used as the preferred option, and therefore adopted in this project.

EFCO2,grid,y = , , , , , ,grid CM y OM grid OM y BM grid BM yEF w EF w EF (Equation B.12)

Where:

wOM = Weighting of operating margin emission factor (%);

wBM = Weighting of build margin emission factor (%).

The Operating Margin Emission Factor (EFgrid, CM, y) is 0.9223 tCO2e/MWh and the Build Margin

Emission Factor (EFgrid, CM, y) is 0.3769 tCO2e/MWh. The defaults weights value for other than wind and solar power generation projects are used as specified in the “Tool to calculate the emission factor for an electricity system” (Version 04) (wOM = 0.5; wBM = 0.5).

Using values mentioned above, the Combined Margin Emission Factor of CSPG& Loung

Namtha Grid (EFgrid, CM, y) corresponds to 0.6496 tCO2e/MWh.

Calculate the project leakage No leakage emissions are considered.

Calculate the emission reductions Emission reductions are calculated as follows:

y y yER =BE -PE (Equation B.13)

Where:

ERy = Emission reduction in year y (t CO2e/yr)

BEy = Baseline emission in year y (t CO2e/yr)

PEy = Project emission in year y (t CO2e/yr)

B.6.2. Data and parameters fixed ex ante

>>

Data / Parameter FCi, y, Fi,j,y

Unit mass or volume unit of the fuel i

Description Amount of fossil fuel type i consumed in the project electricity system in year y (mass or volume unit)

Source of data China Electric Power Yearbook 2010~2012 EdL Annual Report 2008~2011

Value(s) applied See Appendix 4 for details.

Choice of data or Measurement methods and procedures

Data used are from China and Lao DNA.

Purpose of data Baseline emission

Additional comment

Data / Parameter NCVi,y

Unit kJ/kg or kJ/m3

Description The net calorific value (energy content) per mass or volume unit of fuel i in year y.

Page 18: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 18 of 45

Source of data China Electric Power Yearbook 2010~2012 EdL Annual Report 2008~2011

Value(s) applied See Appendix 4 for details.

Choice of data or Measurement methods and procedures

Data used are from China and Lao DNA.

Purpose of data Baseline emission

Additional comment

Data / Parameter EFCO2, i,y, EFCO2, i,j,y

Unit tCO2/TJ

Description The CO2 emission factor per unit of fuel i in year y, or the CO2 emission factor per unit of fuel i by province j in year y

Source of data 2006 IPCC Guidelines for National Greenhouse Gas Inventories, Volume 2 Chapter 1 Table 1.4

Value(s) applied See Appendix 4 for details.

Choice of data or Measurement methods and procedures

No specific local value available, the value form IPCC 2006, Guidelines for National Greenhouse Gas Inventories was adopted.

Purpose of data Baseline emission

Additional comment

Data / Parameter EGy ,EGm,y

Unit MWh

Description Net electricity generated and delivered to the grid by all power sources serving the system, not including low-cost/must-run power plants/units, in year y.

Source of data China Electric Power Yearbook 2010~2012 EdL Annual Report 2008~2011

Value(s) applied See Appendix 4 for details.

Choice of data or Measurement methods and procedures

Data used are from China and Lao DNA.

Purpose of data Baseline emission

Additional comment

Data / Parameter EGimport,y

Unit MWh

Description The electricity(MWh) imported from CCPG in year y.

Source of data China Electric Power Yearbook 2010~2012

Value(s) applied See Appendix 4 for details.

Choice of data or Measurement methods and procedures

Data used are from China DNA.

Purpose of data Baseline emission

Additional comment

Page 19: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 19 of 45

Data / Parameter A BL

Unit m2

Description Area of the reservoir measured in the surface of the water, before the implementation of the project activity, when the reservoir is full

Source of data Project on-site

Value(s) applied 0

Choice of data or Measurement methods and procedures

For new reservoirs, this value is zero.

Purpose of data Project emission

Additional comment

Data / Parameter CAP BL

Unit MW

Description Installed capacity of the hydro power plant before the implementation of the project activity.

Source of data Project on-site

Value(s) applied 0

Choice of data or Measurement methods and procedures

For new hydro power plants, this value is zero

Purpose of data Project emission

Additional comment

Data / Parameter EFRes

Unit kgCO2e/MWh

Description Default emission factor for emissions from reservoirs

Source of data Methodology ACM0002 (Version 14)

Value(s) applied 90 kgCO2e/MWh

Choice of data or Measurement methods and procedures

-

Purpose of data Project emission

Additional comment

Data / Parameter FCBM,i,y

Unit mass or volume unit

Description Amount of fossil fuel type i consumed by the most recently built power plants in year y

Source of data China Electric Power Yearbook 2010~2012 EdL Annual Report 2008~2011

Value(s) applied See Appendix 4 for details.

Choice of data or Measurement methods and procedures

Data used are from China and Lao DNA.

Purpose of data Baseline emission

Additional comment

Page 20: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 20 of 45

B.6.3. Ex ante calculation of emission reductions

>>

Project emission

PEy=0 tCO2e

Baseline emission According to section B.6.1, in first crediting period, the baseline emission factor of the project:

EFCO2, grid, y= , , , , , ,grid CM y OM grid OM y BM grid BM yEF w EF w EF =0.6496 tCO2e/MWh.

The baseline emission of the project:

BEy=EGBL, y×EFCO2, grid, y= 37,000 ×0.6496=24,035 tCO2e

Project leakage No leakage emissions are considered.

Emission reductions

y y yER =BE -PE =24,035 – 0 = 24,035 tCO2e

B.6.4. Summary of ex ante estimates of emission reductions

>>

Year

Baseline

emissions

(tCO2 e)

Project

emissions

(tCO2 e)

Leakage

(tCO2 e)

Emission

reductions

(tCO2 e)

Year 1 24,035 0 0 24,035

Year 2 24,035 0 0 24,035

Year 3 24,035 0 0 24,035

Year 4 24,035 0 0 24,035

Year 5 24,035 0 0 24,035

Year 6 24,035 0 0 24,035

Year 7 24,035 0 0 24,035

Total 168,245 0 0 168,245

Total number

of crediting

years

7

Annual

average over

the crediting

period

24,035 0 0 24,035

Page 21: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 21 of 45

B.7. Monitoring plan

B.7.1. Data and parameters to be monitored

>>

Data / Parameter EGfacility,y

Unit MWh

Description Quantity of net electricity generation supplied by the project plant/unit to the grid in year y

Source of data Calculated value

Value(s) applied EGfacility,y = EGoutput,y- EGinput,y

Measurement methods and procedures

Calculated

Monitoring frequency

QA/QC procedures Please refer to EGoutput,y and EGinput,y

Purpose of data Baseline emission

Additional comment

Data / Parameter EGoutput,y

Unit MWh

Description Electricity supplied by the project to the grid in year y

Source of data Measured by meters.

Value(s) applied 37,000

Measurement methods and procedures

Continuous measurement and monthly recording

Monitoring frequency Monthly

QA/QC procedures According to the recommendation by the manufacturer or the regulations of the grid company, meters will be calibrated periodically. Data measured by meters will be cross-checked with the record document confirmed by EdL.

Purpose of data Baseline emission

Additional comment

Data / Parameter EGinput,y

Unit MWh

Description The electricity used by the project and input from the grid in year y

Source of data Measured by meters.

Value(s) applied Estimated to be 0 MWh for ex-ante calculation

Measurement methods and procedures

Continuous measurement and monthly recording

Monitoring frequency Monthly

QA/QC procedures According to the recommendation by the manufacturer or the regulations by the grid company, meters will be calibrated periodically. Data measured by meters will be cross-checked with the record document confirmed by EdL.

Purpose of data Baseline emission

Additional comment

Data / Parameter CapPJ

Unit MW

Description Installed capacity of the hydro power plant after the implementation of the project activity.

Source of data FSR

Page 22: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 22 of 45

Value(s) applied 5

Measurement methods and procedures

Use the data in the FSR at start of the project. Measure by check the nameplate after operation.

Monitoring frequency Annually

QA/QC procedures -

Purpose of data Project emission

Additional comment -

B.7.2. Sampling plan

>> The purpose of the monitoring plan is to ensure that the monitoring and calculation of emission reductions of the project within the crediting period is complete, consistent, clear and accurate. The plan will be implemented by the project owner with the support of the grid corporation.

1. Monitoring organization

The monitoring process will be carried out under the responsibility of the project owner. A monitoring panel will be established by the plant managers to be in charge of monitoring the data and information relating to the calculation of emission reductions with the cooperation of the Technical and Financial Department. A CDM manager will be assigned full charge the monitoring works. The operation and management structure is shown below:

Figure B.3 Organization structure of the monitoring activity

2. Monitoring apparatus and installation: The meters will be installed in accordance with relevant national or international standard. Before the operation of the project, the metering equipments will be clarified and examined by the project owner and the power grid company according to the above regulation. The M1 and M2 are bidirectional meters. Meter M1 will be the main meter, installed at the grid access points, to monitoring both the input and output electricity. Meter M2 will be the backup meter for M1. The accuracy of M1 and M2 is 0.5s. Meter M3 will be installed also for monitoring the power download for the facility power use. The accuracy of M3 is 1. Therefore, the reading from M1 upload will be recorded for the EGoutput,y, and the sum up of M1 and M3 download will be recorded for EGinput,y.

Monitoring panel

Technical department

Calibrating and maintaining

the meters, and checking,

archiving and managing data.

Financial department

Collecting financial data

required by the checking

activity, including meter

readings and the receipts

of electricity sales Statistician

Measuring and recording the

meter readings, and making a

regular summary according to

requirement of the

monitoring panel.

CDM manager

Supervise the project

operation related to data

monitoring, ensure a smooth

and orderly monitoring

process.

Page 23: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 23 of 45

The power generated will be delivered to the local power grid through a 22kV transmission line.

G

G Regional Grid

consisting of Luang

Namtha and China

Southern Power

Grid

Transformer G Turbine & Generator Unit

Project site

M Meter

M2

M1

M3

EGoutput,y/EGinput,y

EGinput,y

EGoutput,y/EGinput,y

Facility

power use

Figure B.4 Monitoring points of the project

3. Data collection: The specific steps for data collection and reporting are listed below: a) During the crediting period, both the grid company and the project owner will record the values

displayed by the main meter. b) Simultaneously to step a), the project owner will record the values displayed by the backup

meters. c) The meters will be calibrated according to the relevant regulation and request of EdL. d) The main meter’s readings will be cross-checked with the record document confirmed by EdL. e) The project owner and the grid company will record both output and input power readings

from the main meter. These data will be used to calculate the amount of net electricity delivered to the grid.

f) The project owner will be responsible of providing copies of the record document confirmed by EdL to the DOE for verification.

If the reading of the main meter in a certain month is inaccurate and beyond the allowed error or the meter doesn’t work normally, the grid-connected power generation shall be determined by following measures: g) Read the data of the backup meters. h) If the backup meter’s data is not accurate enough to be accepted, or the practice is not

standardized, the project owner and the grid corporation should jointly make a reasonable and conservative estimation method which can be supported by sufficient evidence and proved to be reasonable and conservative when verified by the DOE.

i) If the project owner and the grid corporation don’t agree on an estimated method, arbitration will be conducted according the procedures set by the agreement to work out an estimation method.

4. Calibration

Page 24: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 24 of 45

Calibration of Meters & Metering should be implemented according to relevant standards and rules accepted by the grid company EdL. After the examination, the meters should be sealed. The lift of the seals requires the presence of both the project owner and the grid company. One party must not lift the seals or fiddle with the meters without the presence of the other party. All the meters installed shall be tested by a qualified metering verification institution commissioned jointly by the project owner and the grid company within 10 days after: 1) Detection of a difference larger than the allowed error in the readings of both meters; 2) The repair of all or parts of the meter caused by the failure of one or more parts that do not

operate in accordance with the specifications.

5. Data management system Physical documents such as the plant electrical wiring diagram will be gathered with this monitoring plan in a single place. In order to facilitate auditors’ access to project documents, the project materials and monitoring results will be indexed. All paper-based information will be stored by the technical department of the project owner and all the material will have a copy for backup. All data, including calibration records, will be kept until 2 years after the end of the total crediting period.

6. Monitoring Report During the crediting period, at the end of each year, the monitoring officer shall produce a monitoring report covering the past monitoring period. The report shall be transmitted to the general manager who will check the data and issue a final monitoring report in the name of the project participants. Once the final report is issued, it will be submitted to the DOE for verification.

B.7.3. Date of completion of application of methodology and standardized baseline and

contact information of responsible persons/ entities

>> Date of completion of application of methodology and standardized baseline: 26/09/2014 Responsible persons/ entities: Mr. Lu Yaodong Beijing Karbon Energy Consulting Co., Ltd.

SECTION C. Duration and crediting period

C.1. Duration of project activity

C.1.1. Start date of project activity

>> 07/07/2008 (signature of the civil work agreement)

C.1.2. Expected operational lifetime of project activity

>> 25 years

C.2. Crediting period of project activity

C.2.1. Type of crediting period

>>

Page 25: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 25 of 45

First period of renewable crediting period

C.2.2. Start date of crediting period

>> 20/07/2014

C.2.3. Length of crediting period

>> 7 years of the first crediting period

SECTION D. Environmental impacts

D.1. Analysis of environmental impacts

>> The Initial Environmental Examination with Environmental Management Plan (IEE) for the project was compiled by the qualified institute “National Consulting Group (NCG)”. The IEE has approved by the Water Resources and Environment Administration in 07/12/2009. According to this report, environmental impacts caused by the project and the corresponding measures adopted by the project owner for mitigation are as following:

Construction Phase

Wastewater The waste water is not allowed to be discharged into the river directly in order to protect the water quality. The wastewater generated from disturbed, erosion prone land (i.e. construction camps, quarries, borrow pits and spoil dumps) will be treated employing the following mitigation measures according to the IEE: Dirty water from erosion-prone land will be collected in interception channels and, if necessary,

directed to sedimentation ponds, prior to being released to the environment; Septic sanitation facilities will be provided to construction and camp areas. No untreated

human waste is allowed to enter any watercourse to affect water quality, aquatic environments and human health.

All hydrocarbons (e.g. fuels and lubricants) and chemical reagents will be stored in safe places, fully bundled areas constructed and managed in accordance with relevant International Standards and Material Safety Data Sheets. Oil, fuel and lubricant storage areas should be located apart from any water courses. The project developer will ensure that containers of reagents and drums of used oil or grease are stored under cover at all times;

Potentially oil runoff from areas such as vehicle maintenance bays, equipment lay down areas, or refuelling stations will be contained by perimeter bundling or interception drains. Oil runoff will be directed through oil/water separators prior to discharge to the environment. Oil/water separators will be regularly cleaned and maintained.

Exhaust gases and dust

Exhaust gases resulting from vehicles, construction equipments and the dust generating from the construction activities is the greatest threat of air quality. Dustproof measures are employed including watering and dust collecting, wet construction method will be used to minimize the negative impact and those construction equipment and vehicles in compliance with relevant sanitary regulations will be selected and properly conserved. Furthermore, dustproof respirator will be applied to protect the respiratory tract of the workers on site who are granted to be the main casualties. Attribute to the methods mentioned above, the negative impact on air quality is confined into the construction site during the construction period and can be neglected.

Solid and Liquid Waste

Page 26: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 26 of 45

Waste management procedures will be based on the following hierarchy (in decreasing order of preference): (i) Minimize the waste production and maximize waste recycling and reuse; and (ii) Promote safe waste disposal. To minimize waste production, a lot of mitigation measures will be taken including maximizing the efficiency of all on-site activities, supplying products with less waste produced and using no-hazardous materials. Project owner will educate staff, contractors to minimize litter generation and procedures will be established for segregating different types of waste at the location where they are generated to maximize the recovery of recyclables.

Noise and vibration

The area of construction, including quarries should have restricted working hours, including restricted times for above ground blasting. Construction workers exposed to noise levels of 70-80 dB or more than will be provided with adequate hearing protection, in accordance with the requirements of the health and safety plan. The exhaust and radiator silencers will be fitted to construction equipment, in particular, trucks and loaders. Construction activities and use of heavy vehicles will be minimized during night time. Emissions from reversing alarms may be regulated to reduce intrusiveness, particularly at night.

Impacts on ecosystem Soil and water erosion might be induced attribute to slope exploration, earth-and-rock excavation, and the utilization of dumpsites. Rehabilitation of vegetation and other technique methods will be conducted to minimize the negative impact once the construction activities completed. Lands will be occupied permanently due to the construction of a water retaining dam, an access road, dumpsites and livelihood areas, however, due to the severe vegetation deterioration, the soil is poor with low coverage rate of vegetation. Therefore, the induced ecosystem loss is minimal. No cultural relic, mineral or protected plant were identified during the environment survey, and no extinction of plants will be induced. Hence, the impact to the local ecosystem attributed to the transformation of land use is insignificant. As the construction site is far away from any village, the proposed project will not result in any displacement of residents and inundation of houses.

Operation Phase

Waste water The wastewater mainly generated from the permanent staff during the operation phase is not allowed to be fed into the river directly. It is designed that the domestic sewage should be disposed using the advanced integrated treatment equipment to minimize the impacts on local environment.

Water quality and quantity Due to to the run-of-river type of the hydropower project, the hydrological features such as the precipitation, temperature etc. will not alter. Furthermore, the minimum water flow will be not less than the natural flow in the dry season to maintain the eco-system. In conclusion, environmental impacts arising from the project are considered insignificant.

Page 27: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 27 of 45

SECTION E. Local stakeholder consultation

E.1. Solicitation of comments from local stakeholders

>> Stakeholder comments are collected in a series of ground survey, village profile and household survey with the use of questionnaires and interviews. The participants of the surveys and interviews were from different groups including: all the stakeholders who have concerns about the project, representatives of the Lao Women’s Union at village level, Lao national Old People Union at the village level, and the head of village and the head of household.

In order to consult the public’s opinions and suggestions about the project, stakeholders were invited to carry out a consultation meeting through local government and bulletins. The stakeholder meeting was hold in 19/03/2008, 35 stakeholders including representative of government officials at the Long district, Lao Women’s Union, Lao national front for Construction Youth Union at the village level and representatives of local villagers. The summary of stakeholders is as follow:

Table E.1. Basic information of the comments participants

Item Category Number Percentage

Age

Below 30 8 22.8%

30~40 12 34.3%

40~50 12 34.3%

Above 50 3 8.6%

Gender Male 23 65.7%

Female 12 34.3%

Education

Elementary school 16 45.7%

Junior high school 8 22.9%

Senior high school 9 25.7%

College and above 2 5.7%

E.2. Summary of comments received

>> The comments received from the stakeholders are summary as follows: 1) minimum water flow 2) improve local power supply situation 3) improve the road construction 4) provide working chance to local residents

E.3. Report on consideration of comments received

>> The project does not involve resettlements. Considerations on the comments by the stakeholders are listed as follow: 1) The minimum flow will be always released to maintain the eco-system and meet demand

for irrigation in the downstream. 2) The construction of the project will improve the local electricity transmission system and

promote the electrification progress. 3) During the project construction period, the project owner will improve local road conditions

to transport the equipments, which will greatly improve local transportation condition.

Page 28: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 28 of 45

4) During the project construction period, plenty of working chances will be provided to local residents. And during the operation period, some long-term positions will be provided to local people.

SECTION F. Approval and authorization

>> The Letter of approval from the Lao PDR was issued in 26/03/2014, and the Letter of approval from UK was issued in 01/07/2014.

- - - - -

Page 29: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 29 of 45

Appendix 1: Contact information of project participants and

responsible persons/ entities

Project participant and/or responsible person/ entity

Project participant

Responsible person/ entity for application of the selected methodology

(ies) and, where applicable, the selected standardized baselines to the project activity

Organization Nam Long Power Co., Ltd.

Street/P.O. Box Asean Street, House No. 192, Sidamduane Village, Chanthabouly District

Building

City Vientiane Capital

State/Region

Postcode

Country Lao PDR

Telephone 856-21-213-138

Fax 856-21-213-407

E-mail [email protected]

Website www.lcclao.com

Contact person Bounleuth LUANGPASEUTH

Title

Salutation Mr.

Last name LUANGPASEUTH

Middle name

First name Bounleuth

Department

Mobile 856-20-5551 5194

Direct fax 856-21-213-407

Direct tel. 856-21-213-138

Personal e-mail [email protected]

Page 30: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 30 of 45

Project participant and/or responsible person/ entity

Project participant

Responsible person/ entity for application of the selected methodology

(ies) and, where applicable, the selected standardized baselines to the project activity

Organization Climate Bridge Ltd.

Street/P.O. Box Bluebell Road, Alvington

Building Motivo House

City Yeovil

State/Region Somerset

Postcode BA 20 2FG

Country United Kingdom of Great Britain and Northern Ireland

Telephone +49 89 2351 9320 - 0

Fax

E-mail [email protected]

Website

Contact person Princeton Peng

Title Director

Salutation Mr.

Last name Peng

Middle name

First name Princeton

Department

Mobile

Direct fax

Direct tel.

Personal e-mail

Page 31: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 31 of 45

Appendix 2: Affirmation regarding public funding

No public funding from parties included in UNFCCC Annex I is available to the project activity.

Page 32: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 32 of 45

Appendix 3: Applicability of selected methodology and

standardlized baseline

Please refer to the Section B.1 of the PDD.

Page 33: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 33 of 45

Appendix 4: Further background information on ex ante calculation of emission reductions

Table 1 2009 OM

Fuel

Unit Guangdo

ng Guangxi Guizhou Yunnan Hainan

Luang

Namtha

Total of

Fuel

(FCi,y)

Emission

Factor

(kgCO2/TJ)

Average NCV

(MJ/t,km3)

CO2 emission(tCO2e)

A B C D E F G=A+…+F H I

J=I×H×E/105

(in mass)

L=I×H×E/104(in

volume)

Raw coal 104 t 8,011.98 1,815.41 4,925.23 3,311.44 376.59 18,440.65 87,300 20,908 336,591,357

Cleaned coal 104 t 1.8 1.8 87,300 26,344 41,397

Other washed

coal 10

4 t 11.67 44.92 56.59 87,300 8,363 413,158

Briquette 104 t 195.86 195.86 87,300 20,908 3,574,971

Coke 104 t 4.9 1.6 1.63 8.13 95,700 28,435 221,236

Coke oven gas 108 m

3 2.89 2.02 2.48 7.39 37,300 16,726 461,047

Other coal gas 108 m

3 1.11 20.88 48.61 70.6 37,300 5,227 1,376,468

Crude oil 104 t 0 71,100 41,816 0

Gasoline 104 t 0 67,500 43,070 0

Diesel 104 t 6.46 0.52 0.49 0.12 7.59 72,600 42,652 235,027

Fuel oil 104 t 157.37 0.09 157.46 75,500 41,816 4,971,182

LPG 104 t 0 61,600 50,179 0

Refinery gas 104 t 0.51 0.51 48,200 46,055 11,321

Natural gas 108 m

3 47.21 6.19 53.4 54,300 38,931 11,288,511

Other petroleum

products 10

4 t 45.31 0.83 46.14 72,200 41,816 1,393,020

Other coke

products 10

4 t 0 95,700 28,435 0

Other energy 10

4 t-

tce 152.99 98.56 23.01 49.01 20 343.57 0 0 0

Total 360,578,694

Data source: China Energy Statistical Yearbook 2010; EdL Annual Report 2009

Page 34: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 34 of 45

Note: The electricity import from CCPG in 2009 is 21,852,270 MWh, and the simple OM emission factor of CCPG in 2009 is 0.95455tCO2e/MWh, so the total CO2 emission of CSPG &Luang Namtha Grid in 2009 is 360,578,694 + 0.95455 ×21,852,270 = 381,437,884 tCO2e.

Table 2 2009 Coal Firing Power Generation

Province

Electricity

Generation

Electricity

Generation

Plant own

consumption

Power Supplying

to Grid

(108 kWh) (MWh) (%) (MWh)

Guangdong 2,143 214,300,000 6.16 201,099,120

Guangxi 428 42,800,000 6.69 39,936,680

Guizhou 978 97,800,000 6.68 91,266,960

Yunnan 548 54,800,000 6.52 51,227,040

Hainan 114 11,400,000 8.17 10,468,620

Luang Namtha 0 0 0

Total 393,998,420

Data source: China Electric Power Yearbook 2010, EdL Annual Report 2009

Note: When calculating simple OM emission factor in 2009, the electricity import from CCPG is 21,852,270MWh, so the total thermal power generation of CSPG in 2009 is 393,998,420 +21,852,270 = 415,850,690 MWh.

Page 35: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 35 of 45

Table 3 2010 OM

Fuel

Unit Guangdon

g

Guangx

i

Guizho

u Yunnan

Haina

n

Luang

Namtha

Total of

Fuel

(FCi,y)

Emission

Factor

(kgCO2/TJ)

Average

NCV

(MJ/t,km3)

CO2 emission(tCO2e)

A B C D E F G=A+…+F H I

J=I×H×E/105

(in mass)

L=I×H×E/104(in

volume)

Raw coal 104 t 9,758.45 2,330.59 4,876.8

3,345.11

471.84 20,782.79 87,300 20,908 379,341,699

Cleaned coal 104 t 1.03 0.39 1.42 87,300 26,344 32,658

Other washed coal 104 t 11.24 39.08 50.32 87,300 8,363 367,381

Briquette 104 t 179.27 179.27 87,300 20,908 3,272,159

Coke 104 t 0 95,700 28,435 0

Gangue 104 t 301.69 26.13 62.95 390.77 87,300 8,363 2,852,972

Coke oven gas 108 m

3 2.82 2.02 3.25 8.09 37,300 16,726 504,719

Blast furnace gas 108 m

3 0.79 42.32 9.32 48.03 100.46 219,000 3763 8,278,878

BOF gas 108 m

3 0.33 4.25 1.8 6.38 145,000 7945 734,992

Gasoline 104 t 0 67,500 43,070 0

Diesel 104 t 4.65 0.41 2.29 0.76 0.08 8.19 72,600 42,652 253,606

Fuel oil 104 t 83.39 0.1 83.49 75,500 41,816 2,635,869

Petroleum coke 104 t 20.4 20.4 82,900 31947 540,275

LPG 104 t 164.94 164.94 61,600 51,434 4,606,554

Refinery gas 104 t 0.56 0.56 48,200 46,055 12,431

Natural gas 108 m

3 34.04 7.62 41.66 54,300 38,931 8,806,729

Other petroleum

products 10

4 t 0.63 0.47 1.1 72,200 41,816 33,210

Other coke

products 10

4 t 95,700 28,435 0

Other energy 10

4 t-

tce 163.95 77.36 26.02 23.47 290.8 0 0 0

Total 412,274,132

Data source: China Energy Statistical Yearbook 2011, EdL Annual Report 2010

Page 36: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 36 of 45

Note: The electricity import from CCPG in 2010 is 23,423,940 MWh, and the simple OM emission factor of CCPG in 2010 is 0.9923tCO2e/MWh, so the total CO2 emission of CSPG &Loung Namtha in 2010 is 412,274,132 + 0.9923 ×23,423,940 = 435,517,738 tCO2e.

Table 4 2010 Coal Firing Power Generation

Province

Electricity

Generation

Electricity

Generation

Plant own

consumption

Power Supplying to

Grid

(108 kWh) (MWh) (%) (MWh)

Guangdong 2,535 253,500,000 5.97 238,366,050

Guangxi 557 55,700,000 6.55 52,051,650

Guizhou 956 95,600,000 6.85 89,051,400

Yunnan 546 54,600,000 6.93 50,816,220

Hainan 139 13,900,000 7.57 12,847,770

Luang Namtha 0 0 0

Total 443,133,090

Data source: China Electric Power Yearbook 2011, EdL Annual Report 2010

Note: When calculating simple OM emission factor of CSPG&Luang Namtha in 2010, the electricity import from CCPG is 23,423,940MWh, so the total thermal power generation in 2010 is 443,133,090 +23,423,940 = 466,557,030 MWh.

Page 37: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 37 of 45

Table 5 2011 OM

Fuel

Unit Guangdo

ng Guangxi Guizhou Yunnan Hainan

Luang

Namtha

Total of

Fuel

(FCi,y)

Emission

Factor

(kgCO2/TJ)

Average NCV

(MJ/t,km3)

CO2 emission(tCO2e)

A B C D E F G=A+…+F H I

J=I×H×E/105

(in mass)

L=I×H×E/104(in

volume)

Raw coal 104 t 11,799.44 2,807.29 4,266.00 3,520.42 607.41 23,000.56 87,300 20,908 419,821,954

Cleaned coal 104 t 0 87,300 26,344 0

Other washed

coal 10

4 t 1,291.29 22.96 1,314.25 87,300 8,363 9,595,207

Briquette 104 t 182.83 182.83 87,300 20,908 3,337,138

Coke 104 t 0 95,700 28,435 0

Gangue 104 t 320.15 71.26 36.78 428.19 87,300 8,363 3,126,172

Coke oven gas 108 m

3 3.05 1.88 2.66 7.59 37,300 16,726 473,525

Blast furnace gas 108 m

3 1.58 44.78 9.16 50.65 106.17 219,000 3763 8,749,438

BOF gas 108 m

3 0.33 2.71 2.38 5.42 145,000 7945 624,398

Gasoline 104 t 67,500 43,070 0

Diesel 104 t 2.80 0.58 3.58 1.05 0.03 8.04 72,600 42,652 248,961

Fuel oil 104 t 24.44 0.07 24.51 75,500 41,816 773,807

Petroleum coke 104 t 16.51 1.38 17.89 82,900 31,947 473,800

LPG 104 t 195.10 195.10 61,600 51,434 5,448,882

Refinery gas 104 t 0.91 0.91 48,200 46,055 20,201

Natural gas 108 m

3 38.19 0.76 6.83 45.78 54,300 38,931 9,677,678

Other petroleum

products 10

4 t 0.53 0.53 72,200 41,816 16,001

Other coke

products 10

4 t 0 95,700 28,435 0

Other energy 10

4 t-

tce 34.53 159.22 25.20 218.95 0 0 0

Total 462,387,161

Data source: China Energy Statistical Yearbook 2012, EdL Annual Report 2011

Page 38: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 38 of 45

Note: The electricity import from CCPG in 2011 is 16,118,680 MWh, and the simple OM emission factor of CCPG in 2010 is 0.98268tCO2e/MWh, so the total CO2 emission in 2010 is 462,387,161 + 0.98268 × 16,118,680 = 478,226,638 tCO2e.

Table 6 2011 Coal Firing Power Generation

Province

Electricity

Generation

Electricity

Generation

Plant own

consumption

Power Supplying to

Grid

(108 kWh) (MWh) (%) (MWh)

Guangdong 3046 304,600,000 5.6 287,542,400

Guangxi 637 63,700,000 6.6 59,495,800

Guizhou 1022 102,200,000 7.3 94,739,400

Yunnan 536 53,600,000 7.7 49,472,800

Hainan 158 15,800,000 7.8 14,567,600

Luang Namtha 0 0 0

Total 505,818,000

Data source: China Electric Power Yearbook 2012, EdL Annual Report 2011

Note: When calculating simple OM emission factor in 2011, the electricity import from CCPG is 16,118,680 MWh, so the total thermal power generation in 2010 is 505,818,000 +16,118,680 = 521,936,680 MWh.

Table A7 Weighted Emission Factor

Year Power Supplying(MWh) (EGy) Total Emission(tCO2e)

A B

1 2009 415,850,690 381,437,884

2 2010 466,557,030 435,517,738

3 2011 521,936,680 478,226,638

Weighted OM (tCO2/MWh)=(B1+B2+B3)/(A1+A2+A3) 0.9223

Page 39: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 39 of 45

Table 8 2011 Calculation of λs for the calculation of the BM

Fuel

Unit Guangdong Guangxi Guizho

u Yunnan Hainan

Loung

Namtha

Total of

Fuel

Caloric

Value

CO2

emission

factor

Oxidation

Rate CO2 emission

(MJ/t,km3)

(kgCO2/TJ

) (%) (tCO2e)

A B C D E F G=A+…+

F H I J

K=G×H×I×J/107(in mass)

K=G×H×I×J /106

(in

volume)

Raw coal 104 t 11,799.44 2,807.29 4,266.00 3,520.42 607.41 23000.56 20,908 87,300 100 419,821,954

Other

washed coal 10

4 t 1,291.29 22.96 1314.25 8,363 87,300 100 9,595,207

Briquette 104 t 182.83 182.83 20,908 87,300 100 3,337,138

Gangue 104 t 320.15 71.26 36.78 428.19 8,363 87,300 100 3,126,172

Coal, total 435,880,470

Diesel 104 t 2.80 0.58 3.58 1.05 0.03 8.04 42,652 72,600 100 248,961

Fuel oil 104 t 24.44 0.07 24.51 41,816 75,500 100 773,807

Petroleum

coke 10

4 t 16.51 1.38 17.89 82,900 31,947 100 473,800

Other

petroleum

products

104 t 0.53 0.53 41,816 72,200 100 16,001

Oil, total 1,512,570

Natural gas 10

7

m3

381.90 7.60 68.30 457.80 54,300 38,931 100 9,677,678

Coke oven

gas

107

m3

30.50 18.80 26.60 75.90 37,300 16,726 100 473,525

Blast furnace

gas

107

m3

15.80 447.80 91.60 506.50 1061.70 219,000 3,763 100 8,749,438

BOF gas 10

7

m3

3.30 271.00 23.80 298.10 145,000 7,945 100 3,434,187

LFG 104 t 195.10 195.10 54,300 51,434 100 5,448,882

Refinery gas 104 t 0.91 0.91 48,200 46,055 100 20,201

Gas, total 27,803,910

Total 465,196,950

Data source: China Energy Statistical Yearbook 2012, EdL Annual Report 2011

Page 40: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 40 of 45

Table A9 Best Practice Commercialized Technology Emission Factors

Variabl

e

Efficiency

of

advanced

thermal

power

plant

additions

Fuel

Emission

Factor

Oxidatio

n Factor

Emission

Factor

CO2

Emission

amount of

2011

comparing

to the total

emission

(%) (kgCO2/TJ

) (%) (tCO2/MWh) (%)

A B C D=B*C*3.6/A

/106

λ

Coal Firing

power

plants

EFCoal,

Adv 39.84% 87,300 100 0.7889 93.70%

Gas Firing

Power

Plants

EFGas,

Adv 52.50% 75,500 100 0.5177 0.33%

Oil Firing

Power

Plants

EFOil, Adv 52.50% 54,300 100 0.3723 5.98%

Thermal

Emission

Factor

(tCO2/MWh)

EF Thermal i

iiD )( 0.76317

Table A10-1 Installed Capacity 2011

Installed

Capacity

Uni

t Guangdong

Guangx

i Yunnan Guizhou Hainan

Luang

Namth

a

Total

Thermal MW 56,350 11,770 11,360 20,300 3,150 102,930

Hydro MW 13,020 15,260 28,420 18,660 810 1.5 76,171.5

Nuclear MW 6,120 6,120

Wind Power

and Others

MW 748 50 690 40 275 1,803

Total MW 76,238 27,080 40,470 39,000 4,235 1.5 187,024.

5

Data source: China Electric Power Yearbook 2012, EdL Annual Report 2011

Table A10-2 Installed Capacity 2010

Installed

Capacity

Uni

t Guangdong

Guangx

i Yunnan

Guizho

u Hainan

Luang

Namth

a

Total

Thermal MW 52,870 10,390 11,330 17,530 2,970 95,090

Hydro MW 12,600 14,940 24,350 16,550 750 69,190

Nuclear MW 5,030 5,030

Wind Power and

MW 620 360 210

1,190

Page 41: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 41 of 45

Others

Total MW 71,120 25,330 36,040 34,080 3,930 170,500

Data source: China Electric Power Yearbook 2011, EdL Annual Report 2010

Table A10-3 Installed Capacity 2009

Installed

Capacity

Uni

t Guangdong

Guangx

i Yunnan

Guizho

u Hainan

Luang

Namth

a

Total

Thermal MW 48,300 10,770 10,710 17,310 3,090 90,180

Hydro MW 11,260 14,750 20,900 13,610 700 61,220

Nuclear MW 3,950 3,950

Wind Power

and Others

MW 560 80 60

700

Total MW 64,070 25,520 31,690 30,920 3,850 156,050

Data source: China Electric Power Yearbook 2010, EdL Annual Report 2009

Table A10-4 Installed Capacity 2008

Installed

Capacity

Uni

t Guangdong

Guangx

i Yunnan

Guizho

u Hainan

Luang

Namth

a

Total

Thermal MW 45,730 10,270 10,030 17,170 2,370 85,570

Hydro MW 10,280 13,970 15,740 9,470 410 49,870

Nuclear MW 3,780 3,780

Wind Power and

Others MW 290 80 10

380

Total MW 60,080 24,240 25,850 26,640 2,790 139,600

Data source: China Electric Power Yearbook 2009, EdL Annual Report 2008

Page 42: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 42 of 45

Table A11 The Calculation of BM Emission Factor

Installed

Capacity

in 2008

Installed

Capacity

in 2009

Installed

Capacity

in 2010

Installed

Capacity

in 2011

2008~2011

Incrementa

l Capacity

Installation10

2009~2011

Incremental

Capacity

Installation7

2010~2011

Incrementa

l Capacity

Installation7

New Installed

Capacity

Percentages in

the total Capacity

Increment

A B C D E F G

Thermal(MW) 85,570 90,180 95,090 102,930 26,984 19,184 8,154 49.38%

Hydro(MW) 49,870 61,220 69,190 76,171.5 23,901.5 12,551.5 6,681.5 43.74%

Nuclear(MW) 3,780 3,950 5,030 6,120 2,340 2,170 1,090 4.28%

Wind Power and Others(MW)

380 700 1,190 1,803 1,423 1,103 613 2.60%

Total(MW) 139,600 156,050 156,050 187,023 54,647 35,007 16,537 100.00%

Installed capacity comparing to 2011 capacity

29.22% 18.72% 8.84%

Thermal

Total

Thermal

y,BM EFCAP

CAPEF = 49.38%×0.76317= 0.3769 (tCO2/MWh)

According to “Tool to calculate the emission factor for an electricity system” (Version 04), the default weight of all the projects other than wind and solar power generation projects is (WOM = 0.5; WBM = 0.5):

Table A12 Weighted Combined Margin Emission Factor

Weighted OM (tCO2/MWh) 0.9223

Weighted BM (tCO2/MWh) 0.3769

Weighted CM (tCO2/MWh) 0.6496

10 The value is calculated in considering the capacity of the incremental and shut down power stations.

Page 43: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 43 of 45

Appendix 5: Further background information on monitoring

plan

Please refer to the Section B.7 of the PDD.

Page 44: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 44 of 45

Appendix 6: Summary of post registration changes

- - - - -

Page 45: CDM-PDD-SCC-FORM Project design document form for ...CDM-PDD-SCC-FORM Version 05.0 Page 1 of 45 Project design document form for small-scale CDM project activities (Version 05.0) PROJECT

CDM-PDD-SCC-FORM

Version 05.0 Page 45 of 45

Document information

Version Date Description

05.0 25 June 2014 Revisions to:

Include the Attachment: Instructions for filling out the project design document form for small-scale CDM project activities (these instructions supersede the "Guidelines for completing the project design document form for small-scale CDM project activities" (Version 01.1));

Include provisions related to standardized baselines;

Add contact information on a responsible person(s)/ entity(ies) for the application of the methodology (ies) to the

project activity in B.7.4 and 错误!未找到引用源。;

Change the reference number from F-CDM-SSC-PDD to CDM-PDD-SSC-FORM;

Editorial improvement.

04.1 11 April 2012 Editorial revision to change history box by adding EB meeting and annex numbers in the Date column.

04.0 13 March 2012 EB 66, Annex 9

Revision required to ensure consistency with the “Guidelines for completing the project design document form for small-scale CDM project activities”

03.0 15 December 2006 EB 28, Annex 34

The Board agreed to revise the CDM project design document for small-scale activities (CDM-SSC-PDD), taking into account CDM-PDD and CDM-NM.

02.0 08 July 2005 EB 20, Annex 14

The Board agreed to revise the CDM SSC PDD to reflect guidance and clarifications provided by the Board since version 01 of this document.

As a consequence, the guidelines for completing CDM SSC PDD have been revised accordingly to version 2. The latest version can be found at <http://cdm.unfccc.int/Reference/Documents>.

01.0 21 January 2003 EB 07, Annex 05

Initial adoption.

Decision Class: Regulatory

Document Type: Form

Business Function: Registration

Keywords: project design document, SSC project activities