ccr groundwater monitoring system ... - xcel energy

25
4300 MarketPointe Drive, Suite 200 Minneapolis, MN 55435 952.832.2600 www.barr.com CCR Groundwater Monitoring System Certification Report Black Dog Generating Plant Burnsville, Minnesota Prepared for Northern States Power Company April 2019

Upload: others

Post on 12-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CCR Groundwater Monitoring System ... - Xcel Energy

4300 MarketPointe Drive, Suite 200

Minneapolis, MN 55435

952.832.2600

www.barr.com

CCR Groundwater Monitoring System Certification

Report

Black Dog Generating Plant

Burnsville, Minnesota

Prepared for

Northern States Power Company

April 2019

Page 2: CCR Groundwater Monitoring System ... - Xcel Energy

ii

CCR Groundwater Monitoring System Certification Report

Black Dog Generating Plant

Burnsville, Minnesota

April 2019

Contents

1.0 Introduction ........................................................................................................................................................................... 1

2.0 Site Setting ............................................................................................................................................................................. 4

2.1 CCR Management........................................................................................................................................................... 4

2.1.1 Former Ash Basins (1950s – 1970s) .................................................................................................................... 4

2.1.2 CCR Units (1970s – 2017) ....................................................................................................................................... 4

2.2 Geology .............................................................................................................................................................................. 5

2.2.1 Non-Native Deposits ............................................................................................................................................... 5

2.2.2 Native Deposits .......................................................................................................................................................... 5

2.3 Hydrogeology .................................................................................................................................................................. 6

2.3.1 Groundwater Occurrence ....................................................................................................................................... 6

2.3.2 Groundwater Flow Directions and Rates .......................................................................................................... 6

3.0 CCR Unit Groundwater Monitoring System .............................................................................................................. 8

3.1 Network Installation and Development ................................................................................................................. 8

3.2 Background Wells ........................................................................................................................................................... 9

3.3 Downgradient Wells ....................................................................................................................................................10

4.0 References ............................................................................................................................................................................11

Page 3: CCR Groundwater Monitoring System ... - Xcel Energy

iii

List of Tables

Table 1 Rule Requirements and Compliance

Table 2 Hydraulic Conductivity Summary

Table 3 Well Construction Details

Table 4 Monitoring System Summary

List of Figures

Figure 1 Site Location

Figure 2 Site Map

Figure 3 Cross Section Locations

Figure 4 Geologic Cross Section A-A’

Figure 5 Geologic Cross Section B-B’

Figure 6 Geologic Cross Section C-C’

Figure 7 Geologic Cross Section D-D’

Figure 8 Water Table Map, December 11, 2017

Figure 9 Water Table Map, October 22, 2018

Page 4: CCR Groundwater Monitoring System ... - Xcel Energy

iv

Certifications

I hereby certify that I have examined the facility and, being familiar with the provisions of 40 CFR 257

Subpart D, attest that the groundwater monitoring system has been selected and that this Groundwater

Monitoring System Report has been prepared in accordance with good engineering practice, including

consideration of applicable industry standards and the requirements of 40 CFR §257.91. I hereby certify

that the monitoring system is adequate for this facility. I further certify that I am a duly Licensed

Professional Engineer under the laws of the state of Minnesota.

Jeremy Gacnik Date

PE #: 49292

Revision Date Summary of Revisions

04/15/2019

Page 5: CCR Groundwater Monitoring System ... - Xcel Energy

1

1.0 Introduction

Northern States Power Company, a Minnesota corporation doing business as Xcel Energy (NSPM),

formerly operated three coal combustion residuals (CCR) units, referred to as Ash Ponds 1, 2 and 3

(collectively the Ash Ponds) at its Black Dog Generating Plant (Plant or Site), located in Burnsville, MN

(Figure 1). Coal operations ceased at the Plant in April 16, 2015 and CCR discharges to the Ash Ponds

ceased prior to October 19, 2015. Decommissioning of the Plant’s coal-fired boilers and associated

equipment eliminated placement of CCR related materials in the Ash Ponds. The remaining wastewater

discharged from the Plant was redirected to an alternate discharge system in 2016, thereby allowing for

closure of the Ash Ponds and their associated components. Subsequently, the Ash Ponds were excavated

and backfilled between October 2016 and November 2017.

The United States Environmental Protection Agency (EPA) published a final rule to regulate the disposal of

CCR as solid waste under Subtitle D of the Resource Conservation and Recovery Act (RCRA), 40 CFR Parts

257 and 261 (CCR Rule) in 2015. This report has been prepared to describe the groundwater monitoring

system for the former CCR units and how the groundwater monitoring system has been designed to meet

the requirements of the Rule. This report fulfills the requirement of §257.91(f):

The owner or operator must obtain a certification from a qualified professional engineer

stating that the groundwater monitoring system has been designed and constructed to

meet the requirements of this section.

Specific requirements and demonstration of compliance of the groundwater monitoring system to Part

§257.91 of the Rule are summarized in Table 1 below, and further described in Sections 2.0 through 4.0 of

this report.

Page 6: CCR Groundwater Monitoring System ... - Xcel Energy

2

Table 1 Rule Requirements and Compliance

CCR Rule Requirements (§257.91) Compliance with CCR Rule

Performance Standard (a): The owner or operator of a CCR unit must install a

groundwater monitoring system that consists of a sufficient number of wells,

installed at appropriate locations and depths, to yield groundwater samples from

the uppermost aquifer” that:

(1) Accurately represent the quality of background groundwater that has not been

affected by leakage from a CCR unit. A determination of background quality

may include sampling of wells that are not hydraulically upgradient of the CCR

management area where:

a. Hydrogeologic conditions do not allow the owner or operator of the

CCR Unit to determine what wells are hydraulically upgradient; or

b. Sampling at other wells will provide an indication of background

groundwater quality that is representative or more representative than

that provided by the upgradient wells; and

(2) Accurately represent the quality of groundwater passing the waste boundary of

the CCR unit. The downgradient monitoring system must be installed at the

waste boundary that ensures detection of groundwater contamination in the

uppermost aquifer. All potential contamination must be monitored.

See Section 2.0 (Site

Setting) and Section 3.0

(CCR Unit Groundwater

Monitoring System) of this

report.

Well Spacing and Site Specific Information (b): The number, spacing, and depths

of monitoring systems shall be determined based upon site-specific technical

information that must include thorough characterization of:

(1) Aquifer thickness, groundwater flow rate, seasonal and temporal fluctuations in

groundwater flow; and

(2) Saturated and unsaturated geologic units and fill materials overlying the

uppermost aquifer, materials comprising the uppermost aquifer, and materials

comprising the confining unit defining the lower boundary of the uppermost

aquifer, including, but not limited to, thickness, stratigraphy, lithology, hydraulic

conductivities, porosities, and effective porosities.

See Section 2.0 (Site

Setting) and Section 3.0

(CCR Unit Groundwater

Monitoring System) of this

report.

Number of Monitoring Wells (c): The groundwater monitoring system must

include the minimum number of monitoring wells necessary to meet the

performance standards specified in paragraph (a) of this section, based on the site-

specific information specified in paragraph (b) of this section. The groundwater

monitoring system must contain:

(1) A minimum of one upgradient and three downgradient monitoring wells; and

(2) Additional monitoring wells are necessary to accurately represent the quality of

background groundwater that has not been affected by leakage from the CCR

unit and the quality of groundwater passing the waste boundary of the CCR

unit.

Seven background wells

and five downgradient

wells exceed the minimum

requirements. See Section

3.0 (CCR Unit Groundwater

Monitoring System) of this

report.

Page 7: CCR Groundwater Monitoring System ... - Xcel Energy

3

CCR Rule Requirements (§257.91) Compliance with CCR Rule

Multiunit Groundwater Systems (d): The owner or operator of multiple CCR units

may install a multiunit groundwater monitoring system instead of separate

groundwater monitoring systems for each CCR unit.

This facility is being

monitored as a multiunit

system using the well

network summarized in

Section 4.0.

Monitoring Well Construction (e): Monitoring wells must be cased in a manner

that maintains the integrity of the monitoring well borehole. This casing must be

screened or perforated and packed with gravel or sand, where necessary, to enable

collection of groundwater samples. The annular space (i.e. the space between the

borehole and well casing) above the sampling depth must be sealed to prevent

contaminating of samples and the groundwater.

(1) The owner or operator of the CCR unit must document and include in the

operating record the design, installation, development, and decommissioning

of any monitoring wells, piezometers, and other measurements, sampling, and

analytical devices. The qualified professional engineer must be given access to

this documentation when completing the groundwater monitoring system

certification required under paragraph (f) of this section.

(2) The monitoring wells, piezometers, and other measurements, sampling, and

analytical devices must be operated and maintained so that they perform to the

design specifications throughout the life of the monitoring program.

See Section 3.0 (CCR Unit

Groundwater Monitoring

System) and the Well

Documentation Memo.

Certification (f): The owner or operator must obtain a certification from a qualified

professional engineer stating that the groundwater monitoring system has been

designed and constructed to meet the requirements of this section. If the

groundwater monitoring system includes the minimum number of monitoring wells

specified in paragraph (c)(1) of this section, the certification must document the

basis supporting this determination.

See the Certifications page

of this report.

Page 8: CCR Groundwater Monitoring System ... - Xcel Energy

4

2.0 Site Setting

The Site is located in the Minnesota River Valley on the south bank of the Minnesota River in Burnsville,

Minnesota (Figure 1). The Plant and associated operational areas, including an electrical substation,

former coal yard, and former Ash Ponds, occupy approximately 115 acres. NSPM’s property also includes

Black Dog Lake, a 500-acre water body developed for cooling Plant discharge water, consisting of Lyndale

Basin, which is located southwest of the Plant, and Cedar Basin, which is located southeast of the Plant

(Figure 1). The undeveloped portion of the property largely consists of lowlands located along the river

and around Black Dog Lake. All of the property except for the 115-acre operating area is under lease to

the United States Fish and Wildlife Service for wildlife refuge management and limited outdoor

recreational use.

2.1 CCR Management

CCR has been managed in basins or ponds at the Site since the facility was constructed in the early 1950s

through closure in 2017, as described in the following subsections.

2.1.1 Former Ash Basins (1950s – 1970s)

Starting in the early 1950s, prior to the construction of the CCR Units, CCR was managed in on-site ash

basins (Figure 2), as approved by the Minnesota Water Pollution Control Commission. The ash basins were

closed in phases during this period (1950s through 1970s), with the waste surface stabilized and the

facility closed as a solid waste facility. These basins were incised, closed in place, have a soil cover system

and do not impound water. The ash basins are not regulated by the CCR Rule because they were closed

prior to publication of the CCR Rule.

2.1.2 CCR Units (1970s – 2017)

In the 1970s, following closure of the former ash basins, new CCR units (Ash Ponds 1, 2, and 3) were

constructed as incised impoundments within the footprint of the former basins. Legacy materials, which

included legacy materials from historic landfilling and beneficial use activities, were left in place beneath

(i.e., below elevation 695 feet mean sea level (MSL)) and around the footprints of the CCR Units. These

legacy materials are not subject to regulation under the CCR rule and are being managed separately

under a State-approved Response Action Plan. Closure of the ponds consisted of the removal of CCRs

from an elevation of 694.5 feet MSL and above.

The Ash Ponds served as the primary component of the process water treatment system at the Plant

between the 1970s and October 2016. During this time, two pipelines—the ash sluice pipeline and the

bilge water/yard drainage pipeline—discharged into the west end of Ash Pond 3 and a return water

pipeline with an intake at the west end of Ash Pond 2 provided for water reuse in the Plant. Each of the

Ash Ponds was approximately two acres in size, separated from each other by berms. Corrugated metal

culverts in the berms allowed the Ash Ponds to be operated in series (3, 2, 1). Process water that was not

reclaimed for reuse in the Plant was discharged to a settling pond, designated Pond 4. A NPDES approved

discharge control structure in Pond 4 allowed periodic batch releases of water to Cedar Basin. The batch

Page 9: CCR Groundwater Monitoring System ... - Xcel Energy

5

discharges occurred periodically after isolating Pond 4 and determining that the water met permit

discharge criteria.

2.2 Geology

The primary geologic units at the Site include non-native sediments, native sediments, and bedrock. These

units are described in the following subsections.

2.2.1 Non-Native Deposits

The predominant surficial deposit at the Site is fill, comprised of imported soil brought in for the

construction of flood protection berms, raising grade inside the flood control berms, or backfilling the Ash

Ponds. The imported fill consists of structural fill (primarily road base aggregate) or granular fill with sandy

to gravelly silt or silty to lean clay textures. Lesser amounts of native soils consisting primarily of silty or

fine sand-textured river deposits and organic topsoil are present along the northern and southern

margins of the Site. These native soils have been disturbed in many areas with regrading or excavations

conducted as part of Site development and/or operations. The thickness of the non-native fill soils varies

from less than five feet along the Site margins to approximately 20 feet at areas inside the flood

protection berm. The estimated hydraulic conductivity of the saturated non-native deposits is provided in

Table 2.

Legacy materials include ashes generated and deposited into the former ash basins under various

operational permits prior to the construction of the Ash Ponds, and coal from the former Coal Yard, which

was located northeast of the Plant (Figure 2). Legacy materials are present below the footprint of the Ash

Ponds, and extend to an approximate depth of 690-ft MSL in some areas (Barr, 2012). These legacy

materials are not subject to regulation under the CCR rule and are being managed separately under a

State-approved Response Action Plan.

The distribution and thickness of the non-native and underlying deposits in the vicinity of the Ash Ponds

are shown on Figures 4 through 7 (see Figure 3 cross section alignments).

2.2.2 Native Deposits

Alluvium—consisting primarily of fine-grained native sediments described as lean clay, fat clay, and

organic clay/silt with lesser amounts of peat, silt, and silty sand—underlies the non-native deposits across

the Site. The clay and peat deposits are interpreted to be backwater deposition from the Minnesota River

and the silt and silty sand are likely the result of slightly higher energy fluvial regimes of the Minnesota

River channel as it meandered through the river valley or flooded. The alluvial sediments are

distinguishable from underlying fine-grained glacial deposits due to their higher organic content (Balaban

and Hobbes 1990) and/or snail shell fragments. The overall thickness of the alluvium varies from 40 to 60

feet at the Site.

Glacial deposits consisting of till and outwash and bedrock consisting of sandy dolostone of the Prairie du

Chien Group are present below the alluvium. The till is described as a gray to grayish brown, lean clay to

gravelly lean clay, and the outwash consists of silty sand to sand with gravel. Collectively, the glacial

Page 10: CCR Groundwater Monitoring System ... - Xcel Energy

6

deposits vary in thickness from 12 to 40 feet, with a top elevation varying from approximately 630 to 670

feet MSL. The depth to bedrock encountered in investigation borings varied from 70 to 92 feet below

ground surface (bgs) and the elevation of the top of bedrock varies from 620 to 630 feet MSL (Barr, 2012).

2.3 Hydrogeology

The hydrogeologic conditions at the Site have been the subject of detailed site characterization

investigations dating back to the early 1980s. These investigations have included advancing more than

100 soil borings, installing 60+ groundwater monitoring points, conducting field and laboratory hydraulic

testing, monitoring hydraulic head, developing a groundwater flow model, and sampling and analyzing

water chemistry. The following subsections describe the key results of the hydrogeologic investigations

that were considered in the design and construction of the groundwater monitoring system.

2.3.1 Groundwater Occurrence

The water table is located in the non-native deposits across the Site throughout the year. The underlying

alluvium, glacial deposits, and bedrock are fully saturated. The position of the water table in the vicinity of

the Ash Ponds is illustrated on Figures 4 through 7.

2.3.2 Groundwater Flow Directions and Rates

Groundwater elevations and inferred flow directions along the water table for two synoptic water level

measuring events, December 11, 2017 and October 22, 2018, are shown on Figures 8 and 9, respectively.

In both instances, groundwater elevation maxima occur in close proximity to unlined temporary

stormwater sedimentation basin A (Pond A) with groundwater flowing away from Pond A radially. A

groundwater divide that is roughly aligned with the axis of the Site and parallel to unlined temporary

stormwater sedimentation basin 3 (Pond 3) is present east of Pond A in the vicinity of the Ash Ponds

during both measurement events. The presence of this groundwater divide is consistent with prior Site

investigation results and is a function of the consistent upward hydraulic gradient that results from the

Site location in a regional groundwater discharge zone. Groundwater flow directions in the vicinity of the

Ash Ponds are to the north towards the Minnesota River, to the south towards Cedar Basin, and to the

east towards Pond 4. Pond 4, which is located outside of the flood control berm, was under natural

conditions during the December 2017 monitoring event and shows flow to the north and south consistent

with the groundwater divide. Pond 4 was being dewatered during a dredging project in October 2018

and, as a result of the dewatering, shows inward groundwater flow from the north and south and an

increased gradient from the Ash Ponds.

Since the Ash Ponds were dredged and backfilled, horizontal hydraulic gradients at the Site have varied

from approximately 0.001 ft/ft to 0.04 ft/ft. Based on the hydraulic conductivity of the non-native

sediments (Table 2; Barr, 2012), an effective porosity of 0.27, and the hydraulic gradients observed on the

water table maps, horizontal average linear groundwater velocity estimates range from 0.005 to 0.2 feet

per day.

Page 11: CCR Groundwater Monitoring System ... - Xcel Energy

7

Table 2 Hydraulic Conductivity Summary

Unit

Hydraulic Conductivity1

Horizontal Vertical

(meters/day) (meters/day)

Surficial / Non-Native 4.37E-01 1.95E-01

(n = 7) (n = 5)

Alluvium 5.78E-02 9.96E-05

(n = 20) (n = 31)

1 Geometric mean value of n number of tests.

Prior investigations have demonstrated the consistent vertically upward gradient between the

bedrock/glacial outwash deposits and the water table at the Site (Barr, 2012). The upward vertical gradient

is one to two orders in magnitude greater than the shallow horizontal hydraulic gradient. The upward

vertical gradient prevents downward migration of shallow groundwater to the underlying regional

bedrock aquifer.

Page 12: CCR Groundwater Monitoring System ... - Xcel Energy

8

3.0 CCR Unit Groundwater Monitoring System

The hydrogeologic data from past investigations served as the initial design basis for the CCR

groundwater monitoring system. The CCR groundwater monitoring system components are shown on

Figure 2 and are described below. Cross sectional views of the groundwater monitoring system wells are

provided on Figures 4 through 7. Because the Ash Ponds are close to each other and it is not feasible to

construct a monitoring system that would distinguish the potential impacts of each pond, the background

and downgradient groundwater monitoring network was designed as a multiunit system.

3.1 Network Installation and Development

Each well included in the monitoring system was installed by a well driller licensed by the State of

Minnesota. Well materials and construction methods were consistent with Minnesota Well Code and local

well ordinance. Each well was cased to maintain integrity of the borehole, the well screen was installed

and surrounded by filter pack sand to enable collection of water samples from the targeted interval, and

the well annular space above the screened interval was sealed to prevent surface water infiltration into the

screened interval. The well construction details are provided in Table 3.

Table 3 Well Construction Details

Well

Unique

Well ID

No.

Type Top of

Riser

Elev.

Bottom

of

Screen

Depth

Well Construction Details

Back

-

gro

un

d

Do

wn

-

gra

die

nt

Wate

r

Level

On

ly

Casing Screen

Dia

.

Screen

Length

Slot

Size

(ft msl) (ft bgs) Material Material (in) (ft) (in)

W502A 772793 X 708.02 15.5 Steel Stainless 2 10 0.01

W502B 782669 X 707.04 30 Steel Stainless 2 10 0.01

W504A 772794 X 706.93 15.5 Steel Stainless 2 10 0.01

W504B 772795 X 706.19 29 Steel Stainless 2 10 0.01

W506A 772790 X 711.27 16.5 Steel Stainless 2 10 0.01

W600A 824832 X 712.25 18 Steel Stainless 2 10 0.01

W601A 824833 X 709.57 15 Steel Stainless 2 10 0.01

W7A 491943 X 706.03 17.7 Steel Stainless 2 10 0.01

W602A 824834 X 707.25 21 Steel Stainless 2 14 0.01

W603A 824835 X 716.58 25 Steel Stainless 2 14 0.01

W604A 824836 X 716.52 25 Steel Stainless 2 10 0.01

W605A 824837 X 716.74 28 Steel Stainless 2 14 0.01

W14A 496033 X 702.58 16.4 Steel Stainless 2 10 0.01

W505A 772792 X 716.26 22 Steel Stainless 2 10 0.01

W506B 772791 X 711.27 29 Steel Stainless 2 10 0.01

W507A 782677 X 704.60 16.5 Steel Stainless 2 10 0.01

W510A 782674 X 705.79 19 Steel Stainless 2 10 0.01

W511A 784715 X 708.49 15 Steel Stainless 2 10 0.01

W514A 784711 X 712.02 15 Steel Stainless 2 10 0.01

W514B 784712 X 712.15 30 Steel Stainless 2 5 0.01

Page 13: CCR Groundwater Monitoring System ... - Xcel Energy

9

Table 3 Notes:

MSL - mean sea level

bgs - below ground surface

Each well in the monitoring network was developed to remove fines from the water column and to

improve hydraulic connection with well screen filter pack and the surrounding aquifer. The wells were

developed by repeated cycles of disrupting the water column with a surge block, purging, and allowing

the water levels to recover. Monitoring well development was conducted until water purged at sampling

rates yielded turbidity values of 20 NTU (Nephelometric Turbidity Units) or less.

Well nomenclature is generally defined by well screen elevations. A-series wells are screened across the

water table (at depths less than 22 feet), with basal elevations ranging from 684.8 to 695.6 feet MSL.

These wells are generally constructed in the non-native sediments. B-series wells are screened below the

A wells (at depths ranging from 29 to 39 feet), with basal elevations ranging from 665.9 to 685.6 fee MSL.

These wells are generally constructed in the upper to middle portions of alluvium. Due to variable

groundwater elevations across the Site, minor overlap of A and B-series screened intervals exist.

3.2 Background Wells

The location of the Site in a regional groundwater discharge area and the presence of legacy materials

beneath the footprint of the Ash Ponds did not allow the determination of the background groundwater

quality with a standard configuration of upgradient well(s). Therefore, the background monitoring

network was established with multiple wells installed in locations and completed at depths that were

unaffected by the former Ash Ponds but representative of background groundwater quality at the Site

(including legacy materials in the former ash basins). Major cation and anion groundwater chemistry was

used to assess the water quality conditions in each background monitoring system well and to

demonstrate that the wells were not affected by leakage from the Ash Ponds.

The resultant monitoring system includes the seven background wells listed in Table 4, which exceeds the

minimum number (one) required by the rule. The background wells include three wells located in the

footprint of former ash basins (W600A, W601A, and W506A), two wells located in native materials along

the north margin of the Site (W502A and W504A), and two wells completed in the top of the alluvium

beneath (but hydraulically upgradient of) the uppermost aquifer (W502B and W504B).

Page 14: CCR Groundwater Monitoring System ... - Xcel Energy

10

Table 4 Monitoring System Summary

Category Monitoring Well Screen

placement Rationale (CCR Rule)

Background

Wells

W502A A-series

To accurately represent the quality of background

groundwater that has not been affected by leakage from a

CCR unit. A determination of background quality may include

sampling of wells that are not hydraulically upgradient of the

CCR management area where: Hydrogeologic conditions do

not allow the owner or operator of the CCR Unit to determine

what wells are hydraulically upgradient, or Sampling at other

wells will provide an indication of background groundwater

quality that is representative or more representative than that

provided by the upgradient wells... (§257.91(a) (1) and (2).

W502B B-series

W504A A-series

W504B B-series

W506A A-series

W600A A-series

W601A A-series

Downgradient

Wells

W7A A-series

To detect a release from the Site and to account for geologic

and hydrogeologic variability, and to establish a sufficient

number of downgradient monitoring wells at appropriate

locations and depths to yield groundwater samples of the

uppermost aquifer accurately representing the quality of

groundwater passing through the waste boundary (§257.91(a)

(1) and (2)).

W602A A-series

W603A A-series

W604A A-series

W605A A-series

3.3 Downgradient Wells

Five monitoring wells installed at (or as close as practical to) the CCR units boundaries were utilized for

the downgradient monitoring system (Table 4), which exceeds the minimum required (three) by the rule.

Each of these wells is completed in the uppermost aquifer and designed to yield samples that are

representative of the quality of groundwater passing through the three downgradient sides of the former

Ash Ponds waste boundaries.

Page 15: CCR Groundwater Monitoring System ... - Xcel Energy

11

4.0 References

Balaban and Hobbes 1990. Balaban N.H. and Hobbs H.C., eds., 1990. Geological Atlas of Dakota County,

Minnesota: Minnesota Geological Survey County Atlas C-6, plate 4, scale 1:100,000.

http://conservancy.umn.edu/handle/58494.

Barr, 2012. Phase II Investigation / Risk Evaluation Report, Coal and Ash Pond Decommissioning Project,

VIC Site VP26870. July 2012.

Page 16: CCR Groundwater Monitoring System ... - Xcel Energy

Figures

Page 17: CCR Groundwater Monitoring System ... - Xcel Energy

SITE LOCATION

13

77

77

P o w e r p l a n t

§̈¦35W

§̈¦35W

13

NSPM Property Boundary

0 0.25 0.5Miles

Z

Source: USGS 1:24,000 Scale Topographic Map

FIGURE 1SITE LOCATION

Black Dog Generating PlantNSPM

Burnsville, Minnesota

Barr F

ooter

: ArcG

IS 10

.6.1,

2019

-03-18

10:02

File:

I:\Cli

ent\X

cel_E

nergy

\Blac

k_Do

g_Pla

nt\Wo

rk_Or

ders\

Envir

onme

ntal_M

onito

ring\M

aps\R

eport

s\201

9 Grou

ndwa

ter N

etwork

Cert

ificati

on\Fi

gure

1 Site

Loca

tion.m

xd U

ser: b

al

Revision Date: 03/18/20191 Inch = 1/2 Mile

Page 18: CCR Groundwater Monitoring System ... - Xcel Energy

%9%9

%9 !>

!>

!>

!>

!>

!>

!>!>

!>

!>!>

!>

!>

!>!>

!>

!>

!>!>

!>

!>

%2

%2

Cedar Basin

FormerCoalYard

Plant/Substation

Minnesota

River

Ash Pond 1

Ash Pond 2

Ash Pond 3

Former Pond 4

Lyndale Basin

­

­

Pond A Pond

B

ProcessWater Pond

W7A

W507A

W14A

W514A

W511A

W510A

W506A

W505A

W504AW504B

W502AW502B

W514B

W506B

W605A

W604A

W603AW602A

W601A

W600A

Barr F

ooter

: ArcG

IS 10

.6.1,

2019

-04-12

13:32

File:

I:\Cli

ent\X

cel_E

nergy

\Blac

k_Do

g_Pla

nt\Wo

rk_Or

ders\

Envir

onme

ntal_M

onito

ring\M

aps\R

eport

s\201

9 Grou

ndwa

ter N

etwork

Cert

ificati

on\Fi

gure

2 Site

Map

.mxd

Use

r: bal

0 400 800

Feet1 inch = 400 feet

ZData Sources:Site Features: AeroMetric 2010Process and Stormwater Ponds, Sampling, Well and Piezometer Locations, VIC Site Boundary,and Groundwater Contours: Barr Engineering Company

FIGURE 2SITE MAP

Black Dog Generating PlantNSPM

Burnsville, Minnesota

Source Drawing: 1101101pln1ft.dwg

Revision Date: 03/26/2019

!> Downgradient Well!> Background Well!> Water Level Only Well%2

Surface Water ElevationMeasurement LocationFormer CCR Unit (Former Ponds 1-3)Legacy Ash Basin BoundaryLined Stormwater PondUnlined Stormwater Pond­ River Flow Direction

Page 19: CCR Groundwater Monitoring System ... - Xcel Energy

á

á

á

á

á

áá

á

!(

!(

!(!(

!>

!>

!>

!>

!>

!>

!.

!.

!.

!.

Cedar BasinFormerCoalYard

Minnesota

River

Ash Pond 1

Ash Pond 2

Ash Pond 3

Former Pond 4

Pond APond B

A

A'

C

B

C'

B'

D

D'

W7A

W605A

W604A

W603A

W602A

W601A

L3

P-6

L14W7B

W108

W509B W509A

P-3

Barr F

ooter

: ArcG

IS 10

.6.1,

2019

-04-12

13:31

File:

I:\Cli

ent\X

cel_E

nergy

\Blac

k_Do

g_Pla

nt\Wo

rk_Or

ders\

Envir

onme

ntal_M

onito

ring\M

aps\R

eport

s\201

9 Grou

ndwa

ter N

etwork

Cert

ificati

on\Fi

gure

3 Cros

s Sec

tion L

ocati

ons.m

xd U

ser: b

al

0 50 100 150 200

Feet1 inch = 100 feet

ZData Sources:Site Features: AeroMetric 2010Process and Stormwater Ponds, Sampling, Well and Piezometer Locations, VIC Site Boundary,and Groundwater Contours: Barr Engineering Company

FIGURE 3CROSS SECTION LOCATIONS

Black Dog Generating PlantNSPM

Burnsville, Minnesota

Source Drawing: 1101101pln1ft.dwg

Revision Date: 03/26/2019

!> Downgradient Well!> Background Well!( Well Location!. Boring_Locations

á

á Cross_Sections_Former_CCR_UnitLegacy Ash Basin BoundaryLined Stormwater PondUnlined Stormwater Pond

Page 20: CCR Groundwater Monitoring System ... - Xcel Energy

3/8”

1/4”

1/4”

1/4”

SAND AND GRAVEL

BEDROCKBEDROCK

PEAT

FILL

SAND AND GRAVEL

PEAT

FILL

ASOUTH

A'NORTH

MW

-1

PZ-

5

PZ-

3SB

-6

Elev

atio

n, F

eet (

MSL

)

6pt Arial

8pt Arial Italic

Soil classifications - ALL CAPS 8pt ArialAll other text - Caps and Lower Case 8pt Arial

11pt Arial Bold

9pt Arial

11pt Arial

8pt Arial

8pt Arial

8pt Arial

2.0 Th

.6 Th

.75 to 1.0 Th

Update horziontal scale every time

Upd

ate

verti

cal s

cale

eve

ry ti

me

filep

ath

does

NO

T au

to u

pdat

e

690

700

710

720

680

670

690

700

710

720

680

670

LEGEND

Geologic Contact

Inferred Geologic Contact

Approximate Water Table (December 2017)

Monitoring Well Screen

Soil Boring/Piezometer

\\bar

r.com

\pro

ject

s\M

pls\

23 M

N\1

9\23

1910

85 B

lack

Dog

Site

Env

ironm

ent\2

3191

085.

17 B

lack

Dog

Rem

edia

tion\

Wor

kFile

s\10

-CC

R-G

W M

onito

ring\

Con

fiden

tial R

epor

ting\

Gro

undw

ater

Net

wor

k C

ertif

icat

ion\

Figu

res\

supp

ort\C

ross

Sec

tion

AA.a

i

0 100

Approximate Horizontal Scale in Feet10X Vertical Exaggeration

Figure 4

GEOLOGIC CROSS SECTION A-A'Black Dog Generating Plant

NSPMBurnsville, Minnesota

""" "

660

680

700

720

W7BW7A

W602A P-6W60

2A

P-6

W7A

SILTY CLAY(ALLUVIUM)

SILTY CLAY(FILL)

SAND

ASOUTHWEST

A’NORTHEAST

PG sand with silt

clayey sand

sandy lean clay

silty clay - fill

fat clay

silty clay

Fill

Lean clay

Fat clay

Page 21: CCR Groundwater Monitoring System ... - Xcel Energy

3/8”

1/4”

1/4”

1/4”

SAND AND GRAVEL

BEDROCKBEDROCK

PEAT

FILL

SAND AND GRAVEL

PEAT

FILL

ASOUTH

A'NORTH

MW

-1

PZ-

5

PZ-

3SB

-6

Elev

atio

n, F

eet (

MSL

)

6pt Arial

8pt Arial Italic

Soil classifications - ALL CAPS 8pt ArialAll other text - Caps and Lower Case 8pt Arial

11pt Arial Bold

9pt Arial

11pt Arial

8pt Arial

8pt Arial

8pt Arial

2.0 Th

.6 Th

.75 to 1.0 Th

Update horziontal scale every time

Upd

ate

verti

cal s

cale

eve

ry ti

me

filep

ath

does

NO

T au

to u

pdat

e

690

700

710

720

680

670

690

700

710

720

680

670

LEGEND

Geologic Contact

Inferred Geologic Contact

Approximate Water Table (December 2017)

Monitoring Well Screen

Soil Boring/Piezometer

\\bar

r.com

\pro

ject

s\M

pls\

23 M

N\1

9\23

1910

85 B

lack

Dog

Site

Env

ironm

ent\2

3191

085.

17 B

lack

Dog

Rem

edia

tion\

Wor

kFile

s\10

-CC

R-G

W M

onito

ring\

Con

fiden

tial R

epor

ting\

Gro

undw

ater

Net

wor

k C

ertif

icat

ion\

Figu

res\

supp

ort\C

ross

Sec

tionB

B.ai

0 100

Approximate Horizontal Scale in Feet10X Vertical Exaggeration

Figure 5

GEOLOGIC CROSS SECTION B-B'Black Dog Generating Plant

NSPMBurnsville, Minnesota

"

""

"""

660

680

700

720

W7BW7A

W603A W509BW509AL14

0 50 10

Feet

silty clay - fill

fat clay

silty clay

silty sand with gravel - fill

legacy materials

silt

lean and fat clay

PG sand

silty sand

sandy silt

lean clay

silty sand (sometimes with gravel) - fill

legacy materials

silty or clayey sand

FAT CLAY

W7A

L14 W60

3A

W50

9A /

W50

9B

Ash Pond 1

CLAY(ALLUVIUM)

SILTY CLAY AND SILTY SAND(FILL)

LEGACY MATERIALS

LEGACY MATERIALS

BNORTHWEST

B’SOUTHEAST

SILTY SAND(ALLUVIUM)

Ash Pond 3

Page 22: CCR Groundwater Monitoring System ... - Xcel Energy

3/8”

1/4”

1/4”

1/4”

SAND AND GRAVEL

BEDROCKBEDROCK

PEAT

FILL

SAND AND GRAVEL

PEAT

FILL

ASOUTH

A'NORTH

MW

-1

PZ-

5

PZ-

3SB

-6

Elev

atio

n, F

eet (

MSL

)

6pt Arial

8pt Arial Italic

Soil classifications - ALL CAPS 8pt ArialAll other text - Caps and Lower Case 8pt Arial

11pt Arial Bold

9pt Arial

11pt Arial

8pt Arial

8pt Arial

8pt Arial

2.0 Th

.6 Th

.75 to 1.0 Th

Update horziontal scale every time

Upd

ate

verti

cal s

cale

eve

ry ti

me

filep

ath

does

NO

T au

to u

pdat

e

690

700

710

720

680

670

690

700

710

720

680

670

LEGEND

Geologic Contact

Inferred Geologic Contact

Approximate Water Table (December 2017)

Monitoring Well Screen

Soil Boring/Piezometer

\\bar

r.com

\pro

ject

s\M

pls\

23 M

N\1

9\23

1910

85 B

lack

Dog

Site

Env

ironm

ent\2

3191

085.

17 B

lack

Dog

Rem

edia

tion\

Wor

kFile

s\10

-CC

R-G

W M

onito

ring\

Con

fiden

tial R

epor

ting\

Gro

undw

ater

Net

wor

k C

ertif

icat

ion\

Figu

res\

supp

ort\C

ross

Sec

tion

CC

.ai

0 100

Approximate Horizontal Scale in Feet10X Vertical Exaggeration

Figure 6

GEOLOGIC CROSS SECTION C-C'Black Dog Generating Plant

NSPMBurnsville, Minnesota

""

"

""

660

680

700

720

W108

W605A

W602AW601A

L3

0 50 100

Feet

W60

2A

L3

W60

1A

W10

8

W60

5A

CLAY (ALLUVIUM)

LEGACY MATERIALS

SILTY SAND(ALLUVIUM)

SAND WITH SILT(FILL)

Ash Pond 1

Ash Pond 2

CNORTH

C’SOUTH

Ash Pond 3

POND 2

POND 1

PG sand with silt

clayey sand

sandy lean clay

PG sand

Legacy material

silt with sand

PG sand

Legacy material

sandy lean clay

silty sand with gravel (fill)

Legacy material

lean clay

rock, sand and gravel

legacy material

lean clay

silty sand

fat clay

Page 23: CCR Groundwater Monitoring System ... - Xcel Energy

3/8”

1/4”

1/4”

1/4”

SAND AND GRAVEL

BEDROCKBEDROCK

PEAT

FILL

SAND AND GRAVEL

PEAT

FILL

ASOUTH

A'NORTH

MW

-1

PZ-

5

PZ-

3SB

-6

Elev

atio

n, F

eet (

MSL

)

6pt Arial

8pt Arial Italic

Soil classifications - ALL CAPS 8pt ArialAll other text - Caps and Lower Case 8pt Arial

11pt Arial Bold

9pt Arial

11pt Arial

8pt Arial

8pt Arial

8pt Arial

2.0 Th

.6 Th

.75 to 1.0 Th

Update horziontal scale every time

Upd

ate

verti

cal s

cale

eve

ry ti

me

filep

ath

does

NO

T au

to u

pdat

e

690

700

710

720

680

670

690

700

710

720

680

670

LEGEND

Geologic Contact

Inferred Geologic Contact

Approximate Water Table (December 2017)

Monitoring Well Screen

Soil Boring/Piezometer

\\bar

r.com

\pro

ject

s\M

pls\

23 M

N\1

9\23

1910

85 B

lack

Dog

Site

Env

ironm

ent\2

3191

085.

17 B

lack

Dog

Rem

edia

tion\

Wor

kFile

s\10

-CC

R-G

W M

onito

ring\

Con

fiden

tial R

epor

ting\

Gro

undw

ater

Net

wor

k C

ertif

icat

ion\

Figu

res\

supp

ort\C

ross

Sec

tion

DD

.ai

0 100

Approximate Horizontal Scale in Feet10X Vertical Exaggeration

Figure 7

GEOLOGIC CROSS SECTION D-D'Black Dog Generating Plant

NSPMBurnsville, Minnesota

"""""

660

680

700

720

W605A W604A W509B W509AP-3

0

W60

5A

P-3 W60

4A

W50

9A /

W50

9B

LEGACY MATERIALS

LEAN AND FAT CLAY(ALLUVIUM)

SAND(FILL)

DSOUTHWEST

D’NORTHEAST

SAND(ALLUVIUM)

PG sand

Legacy material

sandy lean clay

silty sand (sometimes with gravel) - fill

legacy materials

silty or clayey sand

PG sand

legacy materials

PG sand

lean clay with sand

legacy materials

lean clayFAT CLAY

Page 24: CCR Groundwater Monitoring System ... - Xcel Energy

%9

!>

!>

!>

!>

!>

!>

!>

!>

!>

!>

!>

!>

!>!>

!>

!>

­

­

­

­­­

­

­

­

­

Cedar Basin

Plant/Substation

Minnesota

River

Pond 4

Lyndale Basin

­

­Process

Water PondPo

nd B

696

Ash Pond 1

Ash Pond 2

Ash Pond 3

W7A698.78

W605A696.9

W14A697.65

W604A699.02

W603A699.64

W602A698.58

W601A700.62

W600A703.22

W514A700.89

W511A699.49

W510A699.55

W507A694.66

W506A700.35

W504A696.23

W502A698.44

ScreenHouse689.2

Pond A702.8

Pond 3698.9

Pond 4699.9698

698

700

700

698

702

702

SW512694.9

698

W505A

Barr F

ooter

: ArcG

IS 10

.6.1,

2019

-04-12

13:29

File:

I:\Cli

ent\X

cel_E

nergy

\Blac

k_Do

g_Pla

nt\Wo

rk_Or

ders\

Envir

onme

ntal_M

onito

ring\M

aps\R

eport

s\201

9 Grou

ndwa

ter N

etwork

Cert

ificati

on\Fi

gure

8 Wate

r Tab

le Ma

p Dec

embe

r 11,

2017

.mxd

Use

r: bal

0 400 800

Feet1 inch = 400 feet

ZData Sources:Site Features: AeroMetric 2010Process and Stormwater Ponds, Well and Piezometer Locations, VIC Site Boundary,and Groundwater Contours: Barr Engineering Company

FIGURE 8WATER TABLE MAPDecember 11, 2017

Black Dog Generating PlantXcel Energy

Burnsville, Minnesota

Source Drawing: 1101101pln1ft.dwg

Revision Date: 03/26/2019

!> Monitoring Well

%9Surface Water ElevationMeasurement LocationWater Table Contour (2 ft)­ Apparent Groundwater Flow DirectionFormer CCR Unit (Former Ponds 1-3)Lined Stormwater PondUnlined Stormwater Pond­ River Flow Direction

700.04 Elevation in Feet MSL

Page 25: CCR Groundwater Monitoring System ... - Xcel Energy

­

­

­

­

­

­

­

­

­

%9

!>

!>

!>

!>

!>

!>

!>

!>

!>

!>

!>

!>

!>!>

!>

!>

ScreenHouse699.3

SW512699.1

Pond A704.9

Cedar Basin

Plant/Substation

Minnesota

River

Lyndale Basin

­

­

Pond A

Pond 4

ProcessWater Pond

Pond

B

Note: Pond 4 was drained on June 21, 2018and dewatering, dredging and filling occurredthrough 2018.

694696698

698

694

Ash Pond 1

Ash Pond 2

Ash Pond 3

702

704

70470

2

Pond 3702.1

700

700

700

W511A693.25W14A

696.78

W7A698.9

W602A700.12

W510A694.69W603A

701.6

W604A702.12

W605A702.07

W601A702.33

W506A702.62

W600A704.15W502A

701.29

W504A700.17

W514A703.12

W507A698.78

W505A

Barr F

ooter

: ArcG

IS 10

.6.1,

2019

-04-12

13:23

File:

I:\Cli

ent\X

cel_E

nergy

\Blac

k_Do

g_Pla

nt\Wo

rk_Or

ders\

Envir

onme

ntal_M

onito

ring\M

aps\R

eport

s\201

9 Grou

ndwa

ter N

etwork

Cert

ificati

on\Fi

gure

9 Wate

r Tab

le Ma

p Octo

ber 2

2 201

8.mxd

Use

r: bal

0 400 800

Feet1 inch = 400 feet

ZData Sources:Site Features: AeroMetric 2010Process and Stormwater Ponds, Well and Piezometer Locations, VIC Site Boundary,and Groundwater Contours: Barr Engineering Company

FIGURE 9WATER TABLE MAP

October 22, 2018Black Dog Generating Plant

Xcel EnergyBurnsville, Minnesota

Source Drawing: 1101101pln1ft.dwg

Revision Date: 03/26/2019

!> Monitoring Well

%9Surface Water ElevationMeasurement LocationWater Table Contour (2 ft)­ Apparent Groundwater Flow DirectionFormer CCR Unit (Former Ponds 1-3)Lined Stormwater PondUnlined Stormwater Pond­ River Flow Direction

700.04 Elevation in Feet MSL