cbi ni energy conference: harry mcgrath

17
Wind Turbine Project 2011-2012 Harry McGrath Production Director Feb 2012

Upload: confederation-of-british-industry

Post on 21-Jan-2015

557 views

Category:

Business


0 download

DESCRIPTION

Presentation by Harry McGrath, production director, Brett Martin Ltdn at the CBI NI energy conference. February 2012

TRANSCRIPT

Page 1: CBI NI energy conference: Harry McGrath

Wind Turbine Project2011-2012

Harry McGrathProduction DirectorFeb 2012

Page 2: CBI NI energy conference: Harry McGrath

Global Performer

years50

million£110

employees800

Page 3: CBI NI energy conference: Harry McGrath

Global Performer

Continents5 Countries74Export sales50%

Page 4: CBI NI energy conference: Harry McGrath
Page 5: CBI NI energy conference: Harry McGrath
Page 6: CBI NI energy conference: Harry McGrath
Page 7: CBI NI energy conference: Harry McGrath
Page 8: CBI NI energy conference: Harry McGrath
Page 9: CBI NI energy conference: Harry McGrath

Multi Site Operations

Coventry Staveley Luton & ScotlandBurscoughMallusk

Page 10: CBI NI energy conference: Harry McGrath

www.youtube.com/w

Feasibility study………..2005 Planning Application…..Jul 2006EIS Submitted ………...July 2007Planning Decision… …Sept 2008Resubmission ……. ….May 2009Planning Approval …….Feb 2010Order Placed………….Aug 2010Installation…Sept 2010/May 2011

Page 11: CBI NI energy conference: Harry McGrath

ENERCON E-70 Technical Data• Max Output 2.3 MW• Height 99.5m• Rotor Diameter 71m• Hub height 64m• Cut-in wind speed 2.5m/s• Cut-out wind speed 28-34m/s• Rated wind speed 14m/s• Weights..blade 6T, gen 50T tower 139T• Foundation 30m diameter

Page 12: CBI NI energy conference: Harry McGrath

Costs• Planning/Project management £50k+• Anemometer hire £20k• Foundations £50K• Turbine £2mill • Cabling/Ducting £40k

Page 13: CBI NI energy conference: Harry McGrath

Issues to Consider

• Planning/Local Knowledge/PPS 18

• Grid Connectivity/NIE Grid Connection Code• Height, wildlife, bats, shadow flicker, noise

Page 14: CBI NI energy conference: Harry McGrath

Performance Expectations• Site demand >25 Gwhr

• 15% contribution from wind

• 20% contribution to cost

• All generated units used/no spillage

• Carbon Reduction

Page 15: CBI NI energy conference: Harry McGrath

Operation of E-70

• SCADA Remote performance monitoring

• 15 year maintenance contract

Page 16: CBI NI energy conference: Harry McGrath

Performance to date• Operational since late June

2011• July/Aug low wind speeds!• Sept to date above average• Generated 2.5mill units to

Jan 2012• Forecast >3 mill

units/annum

Page 17: CBI NI energy conference: Harry McGrath