CATHODIC PROTECTION WORKS COMPLETION REPORTSOCAR TURKEY ALIAGA REFINERY PROJECT ARP
IZMIR/TURKEY
INDEX
1. COVER
2. INDEX
3. PURPOSE & SCOPE
4. WHO IS MERTEK
5. WHAT IS MERTEK DOING
6. INTRODUCTION TO STAR ARP PROJECT
7. OUR CONTRATS IN STAR PROJECT
8. PROJECT TAG FOR STAR ARP CATHODIC REPAIR WORKS
9. INTRODUCTION TO CATHODIC PROTECTION PROJECT IN STAR ARP PROJECT
10. WHAT WE ACCOMPLISHED IN CATHODIC WORKS OF STAR ARP PROJECT
11. KICK-OFF MEETING AND FIRST SURVEY
12. APPROACH
13.TEST AND MEASURE METHOD STATEMENT
14.CONSTRUCTION METHOD STATEMENTCIVIL WORKS
15.CONSTRUCTION METHOD STATEMENTMECH WORKS
16.CONSTRUCTION METHOD STATEMENTELECTRICAL WORKS
17.COMMISSIONING METHOD STATEMENT
18.FINAL QUALITY DOSSIER
19.REASONS IDENTIFIED DURING RECONSTRUCTION(MAY BE USED AS CORRECTIVE/PREVENTIVE ACTIONS)LESSONS LEARNED
20.CONCLUSION AND LESSONS LEARNED
21.REFERENCES
22.MERTEK INFO
w w w . m e r t e k . l t d 2
PURPOSE & SCOPE
• Purpose of this Document is to give a brief information
about the repair and re-construction works of a
cathodic protection system of a huge new-installment
refinery Project as also a detailed reference
information of our company’s work.
• Scope of this Document is the Cathodic Protection
Re-construction and Repair Works installed in a huge
new-installment Refinery Project called as Star ARP.
Star ARP Project’s construction phase began in 2014
and MAC is accomplished in 2019. Warranty period is
still in progress. One of the biggest issues during the
punch phase and MAC phase was to be able to repair
(and if necessary reconstruct in some units) the
Cathodic Protection System which was not working as
a whole at that moment.
w w w . m e r t e k . l t d 3
WHO IS MERTEK ?
Oil & Gas
Petrochemical
Heavy Industry
Power Plants
Renewable Energy
MERTEK ELECTRICAL ENGINEERING LIMITED COMPANY is serving in Electrical and Instrumentation EPC (Engineering, Procurement, Construction) works for ex-proof heavy industry facilities since 2014.
Our company is operating with Project Management Profession (PMP), Planning and Document Control Center (DCC) norms according to ISO 14001, OHSAS 18001 HSE standarts and ISO 9001 Quality standards.
w w w . m e r t e k . l t d 4
WHAT IS MERTEK DOING ?
High Voltage
Low Voltage Distribution
Inner Electrical Installation & Lighting
Earthing, Lightning Protection AndCathodic Protection
Fire & Gas Detection
CCTV, Access Control, PAGA
Structural Cabling and IT Systems
Instrumentation and Automation
w w w . m e r t e k . l t d 5
INTRODUCTION TO STAR ARP PROJECT
• Star Aegean Refinery Project is the construction of a newOil&Gas Refinery in Aliağa / İZMİR region next to Petkim andTüpraş.
• Total Invesment Of Project is 6.3 billion USD.
• Aim of the Project is to reduce current account deficit around 3 billion USD per year.
• Major items produced in the facility is Euro-Diesel and Jet Fuel.
• Refinery is a stand-alone one with its own Jetties, storage tanks, utilities, cokers, flares etc… only with an exception of a powerplant which is planned to be constructed in a few years.
w w w . m e r t e k . l t d 6
OUR CONTRACTS IN STAR ARP PROJECT
TCF POWER RING 10 MVA•Supply & Installation of Step-up and Distribution Transformers of Temporary Power Ring•Maintenance of Temporary Power Ring of 10 MVA since 2015
GUARD TOWER FEEDERS•Installation of Power Cables, Fiber Optic Cables and Fire&Gas Detection System Cables to the
Guard Towers
PERIMETER FENCE LIGHTING CCTV IDS•Installation and Commissioning of the Lighting, CCTV and Intrusion Detection of the Perimeter
Fence which has a length of over 10 km
CATHODIC PROTECTION REPAIR WORKS•Installation & Commissioning of new Anodes, reference electrodes, Test JBs and Power JBs•Repair of damaged CP cables, anodes, negative points and Jbs•Revising the plot plans, cable schedules, termination schedules, wiring diagrams according to
the site, Mark-ups and As-builts and finally preparing the FQD
w w w . m e r t e k . l t d 7
MERTEK PROJECT TAG FORSTAR ARP CATHODIC REPAIR WORKS
Duration•Begin : 02/2019•End : 08/2019
Total Value:•Planned : 200.034,20 USD•Committed : 406.252,03 USD
Total Manhour•Direct :20000mh•Indirect :2000mh
w w w . m e r t e k . l t d 8
INTRODUCTION TO CATHODIC PROTECTION PROJECT IN STAR ARP PROJECT
• We started the scope of Cathodic Protection Works on 02/2019 at Star Aliağa Refinery. Ourscope for cathodic protection consists of checkingdamaged or fault points such as positive anodelocations or negative welding points, etc.We have installed new 104 pieces of anode points, 24 pieces of negative points and 20 pieces of test stations. We also did maintenance and repairs of 255 anodes. We achieved test & commissioning activities of CP Works of 17 different Ex-d Units with 22000 Man-hours. Works have been completed on 08/2019.
w w w . m e r t e k . l t d 9
WHAT WE ACCOMPLISHED IN CATHODIC WORKS OF STAR ARP PROJECT
11 nos of PJB
6 nos of Rectifiers
15 nos of Reference Electrodes
255 nos of Anodes Maintenance
107 nos of new Anodes Installation
20 points Test Stations resolved
22000 direct mh / 2000 İndirect mh
w w w . m e r t e k . l t d 10
KICK-OFF MEETING AND FIRST SURVEY
69 nos of 0 mA
82 nos of broken conductor
107 nos of anodes misplaced
135 nos of test JB failure
15 nos of reference failure
First kick-off meeting was held on Jan-2019. The first survey numbers arelisted at right side. There were around136 points of failure, almost %70 of thehuge refinery. There were 6 monthsahead for the accomplishment.
w w w . m e r t e k . l t d 11
APPROACH
Fault• Plot Plans may be wrong• Vendor reports cable tags may be
different than site• Cables mostly damaged during
infrastructure• Anodes may come close to some
basement metal infrastructure• Some power or test JBs may fail
Correction• Plot plans revised according to site
installation• JB clamp tags revised according to
Vendor Reports• Cables are measured and repaired• If anode is still not working properly, a
new anode has been installed to close-by and connected to the repairedcable
• All power and test JBs are reorganized
w w w . m e r t e k . l t d 12
TEST AND MEASURE METHOD STATEMENT
1-Check of plot plan, vendor report and theinstallation at site to
correct labeling
2- Revise the plot plans, vendor reports and cables
schedules according tocorrected labeling
3- Test and measure againto detect actual faults and
create the report of theUnit (for instance Unit-
100)
4- Site visit with theContractor to decide theactions: go for repair or
construct a new one
5- Excavate the anodepoint and cut the
conductor to determinewhich one is not workingproperly: cable (cut) or
anode (misplaced)
6- Repair the cable orinstall the new anode. Do
the tests again.
7-Repeat all for each JB within the unit and finallyenergise the rectifier andtest and commission the
system.
Hand over to theContractor and close all
openings at site andrecover its soil, concrete, gravel etc… to make ready
for MAC
w w w . m e r t e k . l t d 13
CONSTRUCTION METHOD STATEMENTCIVIL WORKS
Concretecutting and
drilling
Removal of gravel,
geotextileand soil
Drillingdown to 5
meters
Reformingthe soil,
geotextileand gravel
Concretepouring with
menholesand coupons
w w w . m e r t e k . l t d 14
CONSTRUCTION METHOD STATEMENTMECH WORKS
New Cable Trays New Conduits New Installationsabove Pipe Racks
w w w . m e r t e k . l t d 15
CONSTRUCTION METHOD STATEMENTELECTRICAL WORKS
Cable Splice Cable Pulling Installation of new anodes
JB Reconnectionsand ReTagging
w w w . m e r t e k . l t d 16
COMMISSIONING METHOD STATEMENT
1-Ptw / Loto2-Continuity
test forcables
3-Positive andNegative JB
Tests
4-Transformer Rectifier Tests
5-System Tests6-Mark-up7-Reports8-Handover
w w w . m e r t e k . l t d 17
FINAL QUALITY DOSSIER
Revision of projects by Site Survey Mark-ups (Red-Marks) As-built Plot Plans
Test ReportsFinal Cable Schedules Final Wiring Diagrams
w w w . m e r t e k . l t d 18
REASONS IDENTIFIED DURING RECONSTRUCTION(MAY BE USED AS CORRECTIVE/PREVENTIVE ACTIONS)
Conductors have been cut during the construction of cabletrenches, cable duct banks, pipe rack basements and suchinfrastructure works
After the installation of anodes, some additionalpipelines or basement iron meshes has been installedclose to the anode and resulting misfunction
Subcontractors mislabeled some of cables resulting thefailure of the identification the faulty point at site
These are the possible reasons that wemay identify during thereconstructionand repair works:
w w w . m e r t e k . l t d 19
CONCLUSION AND LESSONS LEARNED
These are the lessons learned by ourcontractor that has been conductedduring the meetings during our repairand re-construction works.
Cathodic Protection works may be differentiated into 2 parts: infrastructure and abovestructure
Before the infrastructure works of site, conduits for cables, frames for anodes and manholes and stub-ups for JBs may be installed.
Anodes may be installed at this stage and portable rectifiermay be used for the verification of the location of the anode.
After the infrastructure, cables can be pulled and JBs can be installed.
w w w . m e r t e k . l t d 20
w w w . m e r t e k . l t d 21
Mertek Electrical Engineering LLC
Mansuroğlu Mahallesi 1593/1 Sk. B Apt. No:24/12 Bayraklı – İzmir /Turkey
Phone Number of HQ : +90 (232) 459 30 42
E-Mail for Information : [email protected]
Request for Quotations : [email protected]
_____________________________________________________
w w w . m e r t e k . l t d 22