maasbusinesscase.commaasbusinesscase.com/business case/new western sydney museu… · web...

37
JOHNSTA

Upload: vanlien

Post on 13-Aug-2019

213 views

Category:

Documents


0 download

TRANSCRIPT

JOHNSTA

Attachment H:Infrastructure

Warren Smith 8 Partners

PROJECT # 5486000

ISSUE For Approval

DATE 29 September 2016

REVISION 1

AUTHOR N. Meo

REVIEWED BY M. Cahalane

STATUS Current

161Museum of i l i kS Applied Arts& Sciences

PREPARED BY:

WARREN SMITH & PARTNERS PTY LTD

Consulting Engineers

ACN 002 197 088 ABN 36 300 430 126

1st Floor, 123 Clarence Street

Sydney 2000 NSW Australia

T 02 9299 1312 F 02 9290 1295

Warren

Smi th 8

Par tners

PREPARED FOR:

MUSEUM OF APPLIED ARTS & SCIENCES

Contemporary Museum

ABN 59 354 516 818

500 Harris St

Ultimo 2007 NSW Australia

T 02 9217 0111

· Hydraulic Services • Fire Protection X Civil Engineering IN Sydney Water Accredited Water Servicing Co-ordinator • Design Project Management - Building Plan Approvals

Warren Smith 8 Partners

CIVIL ENGINEERING SERVICES1. INTRODUCTION

Warren Smith & Partners (WS+P) has been engaged by the New Museum to prepare a services

investigation report of the infrastructure located in close proximity to the MAAS development. The

purpose of the investigation is to ascertain what services will be affected by the proposed development

and to provide a recommendation on what works are required, if any, in terms of diversions and

connections to ensure that there is sufficient access to water with appropriate pressures. WS+P will also

make recommendations on the required infrastructure extensions/amplifications that will need to be

installed in order for the development to be served by sewer, water, and gas

The following tasks were undertaken in relation to gathering information for the purposes of this

investigation:-

· Receipt and checking of the proposed development plan with the existing services drawings;

· A 'Dial Before You Dig' services search, and;

· Report providing recommendation on the works required.

The following upgrades have been recommended to facilitate the proposed development:-

· Amplification of the existing DN150 watermain in Phillip Street to DN200 between the front of the

property and Church Street;

· Deviation of the existing DN225 sewer mains within the development site, and;

· Deviation of the existing DN150 sewer mains within the development site.

1.1 PROPOSED DEVELOPMENT

The proposed development will see the relocation of MAAS, including all museum pieces, from its

location in Ultimo to Parramatta. The proposed site is bound by Wilde Avenue to the east, Phillip St

to the south and the Parramatta River to the north. It is located approximately 500m north of the

Parramatta CBD. Currently, the site is used as a multi-storey carpark with small commercial

properties facing Phillip St.

Please refer to Figure 1 for an aerial view of the development site area.

n Hydraulic Services ■ Fire Protection 0 Civil Engineering 0 Sydney Water Accredited Water Servicing Co-ordinator • Design Project Management - Building Plan Approvals

a2

Warren Smith 8 Partners

2. DATA COLLECTION

2.1 SYDNEY WATER HYDRA DATABASE DRAWINGS

WS+P has obtained Sydney Water's Hydra database to assess the available water and sewer

infrastructure in close proximity to the development site.

Please find attached in Schedule 2, the following drawing:-

· Sydney Water Hydra plan at Scale 1 in 1500 which shows the development site on the

northwest corner of Phillip St and Wilder Ave.

The database has shown that the development site has frontage to two (2) Sydney Water water

assets on the southern side of the development site along Phillip St:-

· A DN900mm trunk water main, and;

· A DN150mm water main.

The following Sydney Water water asset is also located on the western side of the development

site along Church St:-

· A DN375 water main

The following Sydney Water sewer assets have also been identified within the development site:-

· A DN525 main which reticulates across the development site parallel to the Parramatta River;

· Two (2) DN225 mains which reticulate in a north south direction across the development site;

· Two (2) DN150 mains which reticulate east across the development site, and;

· A DN500 main which runs under the bridge crossing in Parramatta River.

Please refer to Figure 2 for details.

n Hydraulic Services ■ Fire Protection ■ Civil Engineering • Sydney Water Accredited Water Servicing Co-ordinator Design Protect Management - Building Flan Approvals

>4

105M x 110MM ST

Warren Smith 8 Partners

2.2 JEMENA GAS DIAGRAM

The Jemena diagram received illustrates that there are no network mains traversing the site. The

following is a list of gas networks which run along Phillip St as illustrated in Figure 3.

Please find attached in Schedule 3, the following drawing:-

· Jemena Gas Diagram plan at Scale 1 in 2000.

The database has shown that the development site has frontage to two (2) Jemena assets along

Phillip St:-

· A DN150mm high pressure 1050 kPa secondary main that runs along Phillip St and crosses

to the opposite side of Parramatta River, and;

· A DN110mm low pressure 7 kPa nylon network main.

Please refer to Figure 3 for details.

Figure 3: Jemena Assets (Source: Jemena)

n Hydraulic Services ■ Fire Protection ■ Civil Engineering M Sydney Water Accredited Water Servicing Co-ordinator -Design Project Management - euwe g Plan Approvals

>6

OPTION 1 -

SEWERMAINS TO

OPTION 2 -

114 / · I I /

SEWERMAIN DEVIATION

Figure 5: Proposed Sewer Main Connection and Deviations (Source: Sydney Water)

CONNECT INTO

INTERCEPT AND

DN525 SEWER

Warren Smith Partners

3.1.2 SYDNEY WATER SEWER MAINS

Multiple sewer mains have been noted within the development site. As per Sydney

Water's previous correspondence with AECOM, connections to the DN525 main can be

made through extensions to existing manholes. However, the DN525 main may require

amplification depending on when developments related to the wider Parramatta CBD

area will be occurring. These developments include the relocation of the DN500 main

crossing Parramatta River which will impact future DN525 capacity.

In order to facilitate the proposed museum footprint, the DN225 and DN150 sewer mains

will need to be deviated. Option 1 to deviate the DN225 sewer main involves intercepting

the main and deviating it north to connect into the DN525. Option 2 to deviate the DN225

sewer main involves intercepting the main, deviating it south and reticulating it along

Phillip St before connecting into the DN450 main located in Wilde Ave. The DN150 sewer

main is to be intercepted and deviated south to connect into the DN225 sewer deviation

along Phillip St. The DN150 which runs through Oyster Lane is to be removed and a new

connection to the lots established from the proposed deviation is to be made through

Phillip St and Wilde Ave.

Please refer to Figure 5 below for details.

· Hydraulic Services • Fire Protection 1111 Civil Engineering MI Sydney Water Accredited Water Servicing Co-ordinator -Design Protect Management - Building Pan Approvals

>$

Warren Smith 8 Partners

4. COST ESTIMATES

4.1 WATERMAIN

The existing DN150 watermain along Phillip Street, from the front of the proposed new building to

Church Street, shall be amplified to a DN200 watermain. Please refer to Table 1 below for a cost

estimate of the proposed watermain.

Table 1: Watermain Amplification Cost Estimate

Item Quantity Unit Rate Total

Amplification of existing DN150 to DN200 170 m j $1,500 r$255,000

4.2 SEWERMAIN

It is proposed that the existing DN225 and DN150 sewers within the development site be deviated

in order to facilitate the new building footprint. Please refer to Figure 5 in Section 3.1.2 for the

proposed sewer main deviations.

4.2.1 EXISTING DN225 DEVIATION

Option 1 involves intercepting and deviating the existing DN225 sewer main north for

approximately 64m and connecting into the existing DN525 sewer main running along the

north of the property.

Option 2 involves intercepting and deviating the existing DN225 sewer main south to

Philip Street, reticulating it east and connecting into the existing DN450 sewer main in

Wilde Avenue. This sewer main deviation option is approximately 272m in total.

n Hydraulic Services ■ Fire Protection SI Civil Engineering

Sydn

ey

Wate

r

Accre

dited

Wate

r

Servi

cing

Co-

ordin

ator -

Desig

n

Project

Manag

ement

-

Buildin

g Plan

Appro

vals >

10

Warren Smith Er Partners

SCHEDULE 1

PROPOSED LOT SURVEY

n Hydraulic Services ■ Fire Protection ■ Civil Engineering Si Sydney Water Accredited Water Servicing Co-ordinator Design Project Management - Building Plan Approvals

> 12

Warren Smith 8 Partners

SCHEDULE 2

WATER HYDRA

n Hydraulic Services ■ Fire Protection i Civil Engineering S Sydney Water Accredited Water Servicing Co-ordinator -Design Project Management - Building Plan Approvals

> 1 3

Warren Smith a Partners

SCHEDULE 3

GAS DIAGRAM

· Hydraulic Services W Fire Protection If Civil Engineering U Sydney Water Accredited Water Servicing Co-ordinator -Design Ana Management • Bu!ding Plan Approvals

> 14

Warren Smith Er Partners

SCHEDULE 4

WATER PRESSURE FLOW

n Hydraulic Services IIII Fire Protection it Civil Engineering 51 Sydney Water Accredited Water Servicing Co-ordinator -Design Project Management &Aiding Plan Approvals

> 1 5

Sydney

Statement of Available Pressure and Flow WATERNick Watts PROPOSED DN250 AMPLIFICATION OF123 Clarence Street WATERMAIN TO MARSDEN STREETSydney, 2000

Attention: Nick Watts Date: 18/08/2016

Pressure & Flow Application Number: 97802

Your Pressure Inquiry Dated: 2016-07-12Property Address: 36 Phillip St, Parramatta 2150

The expected maximum and minimum pressures available in the water main given below relate to modelled existing demand conditions, either with or without extra flows for emergency fire fighting, and are not to be construed as availability for normal domestic supply for any proposed development.

ASSUMED CONNECTION DETAILSStreet Name: Phillip Street • Side of Street: NorthDistance & Direction from Nearest Cross Street 120 metres West from Wilde AvenueApproximate Ground Level (AHD): 8 metresNominal Size of Water Main (DN): Proposed 250 mm as per sketch provided

EXPECTED WATER MAIN PRESSURES AT CONNECTION POINTNormal Supply ConditionsMaximum Pressure 54 metre headMinimum Pressure 40 metre head

WITH PROPERTY FIRE PREVENTION SYSTEM DEMANDSFlow Pressure head m

Fire Hose Reel Installations(Two hose reels simultaneously) 0.66 40

Fire Hydrant / Sprinkler Installations 5 41(Pressure expected to be maintained for 95% of the time) 10 41

15 4120 4126 4130 4140 4050 40

Fire Installations based on peak demand 5 39(Pressure expected to be maintained with flows 10 39combined with peak demand in the water main) 15 39

20 3926 3930 3940 3850 38

Maximum Permissible Flow 120 33(Please refer to reverse side for Notes)

For any further inquiries regarding this application please email :

connectionssydneywater.com.au

Sydney Water Corporation AHN 49 776 225 0381 Smith St Parramatta 2150 PO Box 399 Parramatta 2124 I DX 14 Sydney T 13 20 92 I www.sydneywater.com.au

Delivering essential and sustainable water services for the benefit of the community

Johnstaff Projects November 2016The New Museum, Parramatta — Flood Study 161372

Appendix A

Topographical Survey and site Images

Taylor Thomson Whitting (NSW) Pty Ltd Appendix A© Taylor Thomson Whitting

RIV

PARRAMAT

urs

O p 7 1 t

4:1 DP 393866

MERITON

MULTI-

PRELIMINARY

0 S

$ ;

0 3 1 4 5 9

S

L PARRMARL CRS

ArvD LEVELS OVER LA. AI INEOF DETAILCORNER OF MLLE

Palvvv• 'MuAHD 11 .69,”

1

. DP

"

PRELIMINARY

Perneel,r11° 11 /03 ;4 7 . 1:5 RAN Oi 01 P5 CORNER OF PKV 57.13.7,

Johnstaff Projects November 2016The New Museum, Parramatta — Flood Study 161372

Appendix B

evein n, Pr

Taylor Thomson Whitting (NSW) Pty Ltd Appendix B© Taylor Thomson Whiffing

11 A BASEMENT LEVEL page . 3LANDSCAPED

'1'714 Rio

is Public Space4,949 m2

Security + Ticketing

Touring Hall Prep.

Space250 m2

40 Circulation + Processing 1,949 m2

41 Carparking (20 CARS) 875 m2

§ Public Lift13 m2

i l n r n i Z f t

i § Art11ft

s A r t / S t a f f L i f t

PEDESTRIAN CP061LTION

PEDESTRIAN CIRCULATIO

f",7,57-717/177/7-

RL

CONTENTS BASEMENT PLAN 1:500 @ A3 0

OPTION 1 I BASEMENT LEVEL I 2/11/2016

RETA

4 1 N I /

ACCESS FROM

2.3 GROUND LEVEL 13/1R,9,1444 r_r4

— page. 36LANDSCAPED OUTDOOR

PLJBUC SPACE

CONTENTSPHILLIP STREET

GROUND FLOOR PLAN 1:500 @ A3 0

OPTION 2 I GROUND LEVEL I 2/11/2016

2

3 6

t3 rn2 Arrivals Foyer 3111.2o riffi

Bag g.nCheck50 :13

-‘13

c,Izting

Security50 m2

41:1,-:cnt.1 Space

g Cafe

568 m2

g leeC af7r,2Kitchen/0 Kitchen Store

2 0 rerri,2ts Kitchen1 5 0 ,

§ Visible,2,,

Collections int

Tostic4inmg2 Gallery

§ Touring Retail

is Ilfset'it

ig max17 Bus Bay

mitilefpn.lig Labs

· Resource Centre 398 m2

n 4:,.1;13i1,/: 21 s

Foyer

iIlgesi7 ,c.alent

Offices

250 m2

®WC132 m2WC

al Public Lift

EIN4ozArt/Staff Lift is Art

Lift50 m2

1111 5Aort,vLift

34 Ri r,r147 ,2

39 Riser

PEDESTRI

2

15 000 \AV

L 1RETAISI 9cuss TO EXISTING

LEVE

P

LEVEL 3

Collection Storage

Offices

LEVEL 2

Collection Storage Main

Galleries

LEVE

Main

LEVEL 0

Commercial/Omni

Touring

LEVEL -1 BASEMENT

Carparking

2.9 3D MASSING

Option 2 captures the base requirements of the FDB, with the omission of the Touring Gallery B. This concept envisages utilisation of the entire site and

snot retain the heritage items of VVi..JW Grove or St George's Terrace. The total briefed floor area for this concept is comparable to the current space of the Powerhouse Museum.

LEVEL 4 page. 47PlantLEVEL 3

WorkshopsBioBox

Circulation

LEVEL 2Collection Storage

Auditoriums

Circulation

LEVEL 1Main Galleries - Large ScaleCollection Storage

Children's Gallery

Circulation

LEVEL 0 GROUNDArrivals Hall, Security + Ticketing

Loading Dock + Bus BayEducation Labs

CirculationLEVEL -1 BASEMENT

Circulation + ProcessingSecurity + Tcketing

Public Space

MI

:=1"XS JOHNSTAFF FENDER KATSALIDIS MIRAMS ARCHITECTS OPTION 2 I 3D MASSING I 2/11/2016

3.4 BASEMENT

PEDEST

11 42 ACCESS FROM

CONTENT BASEMENT LEVEL PLAN 1:500 @ A3 Q

39DSCAPED

page.

PEDESTRI

WIPE 7' 'f'flrf--1,7,:,,v/f-'/7',7/V/-7'1, e/pw

RETA

Security + Ticketing eo m2

Public 9 Space

· 250 Touring Hall Prep. Space

41 Circulation + Processing 1,929 m2

42 Carparking (20 CARS)

· raulnl c Liftgo Art IJft

50 m2Ng Art Lift••• -12

Art/Staff Lift

11,1 .4 ,on;Art/Staff Lift 48

OPTION 2A I BASEMENT LEVEL I 2/11/2016

4.3 GROUND LEVEL page. LANDSCAPED

CIRCULATI

pPEDESTRIAN- 1-7;1 /3/1.//i,

7914 e rn2ntral Gallery

is Tech. Space2 0

I I 'MAX

Tourin953 g Gallery B

1111 Touring, B Retail

c 1 Touring Gallery A

§ Touringn.2 A Retail

§ Arrivals1=

Foyer 968 4

Office

1

4 R

§ Learning Labs

1,152 Resource

Centre

Production414 r¢n2 Studio

2

3▪ 120e0siLlent

OfficesW C

n7 4BagrarCheck2 1 Arrivalsz Foyer

129 Loading Dock2 6 5 Security + First Aid

" asfe

s m2 11111A12512

34 .v5erzs KitchenL _BELAU &CUSS

TO

Art Lift·

52 n12

· 5Aortrl_ift

§ Non-Art/Staff,2

Lift

7 nft • Non-Non-Art/Staff

Lift ▪ Art/Staff Lift

· Visible

37 Bus Drop-off

309 512

mi 2Public

Lift4° R45iser

2

41 RiIg

nsE,3;

CONTENTS PHILLIP GROUND LEVEL PLAN 1:500 @ A3 0

OPTION 3 I GROUND LEVEL I

MI

___—.-------,,,> „ , , , ,

< - - - - - - - - : : - : 1 i

"->-, --,, . _____________ I 1

......,`"'N'''''—'-.r.1 I

I II i '--..Iit

LEVEL 4 page.

Circula

LEVEL 3

OffiAuditoriu

LEVE

Collection

O

Main

LEVEL 1 Workshops

Children's

Main

LEVEL a

Loading Dock + Bus

Education

LEVEL -1

Public

LEVE

P

LEVE

Collection

CirculationLEVEL 2

Main Galleries

Circulation

LEVEL 1

Service

LEVEL 0

Willow Grove: Cafe +

Touring

LEVEL -1 BASEMENT Touring Gallery Prep. Space

4.1 0 3D MASSINGOption Three captures the entire requirements of the FDB, including both the Omnimax and Touring Gallery B. This concept envisages

· ''-ation of the Willow Grove and .3eorge's Terrace.

The total briefed floor area for this concept is greater than the

current space of the Powerhouse Museum.

Circulation in this option has been increased, as the main entrance and arrivals hall has been pushed to the east of Willow Grove, separating it further from the museum spaces on the west of the site. The entire built form has moved forward towards the river to accommodate the retention of Willow Grove and St. George's Terrace, decreasing the river bank area available for public space and access.

FENDER KATSALIDIS MIRAMS ARCHITECTS OPTION 3 I 3D MASSING I 3/11/2016

e m . . . 1 0 1 1 , 1 1 1 1 t a t i f t ,- - • - N reel

'1-T*ft"'*--ZgkORgr

r • inoti

\ %IN M7(,.virampssiuftim. _________________ · B‘onkAlk rriO

CARPARK

Public

PEDESTR

i

Circulation +

rr M

e b

N TS SKETCHES I CARPARK OPTION I

1174.7zwiv

mV

firaliteriviffLe9endie=_A l l _ Ground Gontowe (made AHO) -

Upper Parramat la R iver Cross Sect ion

· Stormwater- Stornmater Pipe NetworkME 20 Year Flood (Upper Parronatia River) 1111111 20 Year Flood (Lower Plummets River) III 100 Year Flood (Upper Parremetle River) MN 100 Year Flood (Lower Parrametta River) OM na PMF (Lower Remed& firi

libillgjg/Jew_

..111 TIP

r

..4414,4„- \Avg..,-.7?.4.fariti

-

s

1e

need

is=umaimiumnal r

M I E 1 1 1 1 1 1 8 1 v M 1 1 3 1 1 1 = 1 1 1 1 E i ll M E M =

EMMEIIIMENNI=1;·

=11111ECNINECIIICEI NE131111113MMEEEMEEIr

ESEMENIM13111331WESIIIIIEEINW13111Eall 4111i.

IEZIONIESMIEDINCEM INEMENEEMIIECIE1121111

lE=MMEIMINEENIEEMI INEZINE:1311111EM 11,1111111FilkNOTE: The Upper and Lower Parmmatta River Flood Stud les are current bein u dated. Flood levels in this area ma chan e