case study tagabi 2 - kenya

1
CASE STUDY Tagabi 2 - Kenya Customer: Unilever Tea Kenya Ltd Net Head: 50.8 m Flow: 1.875m 3 /s Turbine type: 500 mm dia G270 Francis turbine Output power: 856 kW KEY STATISTICS CONTACT Email: [email protected] Tel: 01539 720028 Fax: 01539 732110 www.gilkes.com Gilbert Gilkes & Gordon Ltd, Canal Head North, Kendal, Cumbria LA9 7BZ. Registration No.173768 London Scope of Supply: Francis turbine 500G270 Hydraulic pressure unit Main inlet valve c/w pressure equalising bypass Synchronous generator and flywheel 415V/3PH/50HZ, 0.8 PF PLC Control, instrumentation, metering and protec- tion panel Generator switchgear 1000 KVA 415V/11000V step up transformer Delivery CIF Mombasa Installation, commissioning, testing & start up Unilever Tea Kenya Ltd. started as Brooke Bond Kenya. Tom Rutter, then in charge of Brooke Bond in Calcutta, India, during a hunting safari in Kenya in 1914, realised that the country was ideal for tea growing. Brooke Bond Kenya’s first major tea factory in Kenya was completed at Kerenga in 1927. Hydroelectricity has played a major role in providing power for the tea production from the outset. Gilkes provided their first turbine-generator units for the estate the year after it was completed in 1928. Three different hydro project locations have been developed over the years with Gilkes supplying a total of seven turbine- generator units. Gilkes installed the Tagabi 2 turbine-generator equip- ment in an extension to the existing Tagabi project supplied in 1989. Total Hydro Capacity: 2870 kW *The Chemosit Project was supplied by Gilkes to another tea estate which was acquired by Brooke Bond Kenya as their tea production expanded Project Capacity Year of Installation Tagabi 1620 kW 1989 & 2010 Jamji 630 kW 1948 & 1949 Kerenga 99kW 1929 & 1932 Chemosit* 90 kW 1928

Upload: others

Post on 28-Feb-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CASE STUDY Tagabi 2 - Kenya

CASE STUDYTagabi 2 - Kenya

Customer: Unilever Tea Kenya Ltd Net Head: 50.8 mFlow: 1.875m3/s

Turbine type: 500 mm dia G270 Francis turbineOutput power: 856 kW

KEY STATISTICS

CONTACTEmail: [email protected] Tel: 01539 720028 Fax: 01539 732110www.gilkes.comGilbert Gilkes & Gordon Ltd, Canal Head North, Kendal, Cumbria LA9 7BZ. Registration No.173768 London

Scope of Supply:• Francis turbine 500G270 • Hydraulic pressure unit • Main inlet valve c/w pressure equalising bypass • Synchronous generator and flywheel

415V/3PH/50HZ, 0.8 PF• PLC Control, instrumentation, metering and protec-

tion panel• Generator switchgear• 1000 KVA 415V/11000V step up transformer• Delivery CIF Mombasa • Installation, commissioning, testing & start up

Unilever Tea Kenya Ltd. started as Brooke Bond Kenya. Tom Rutter, then in charge of Brooke Bond in Calcutta, India, during a hunting safari in Kenya in 1914, realised that the country was ideal for tea growing. Brooke Bond Kenya’s first major tea factory in Kenya was completed at Kerenga in 1927.

Hydroelectricity has played a major role in providing power for the tea production from the outset. Gilkes

provided their first turbine-generator units for the estate the year after it was completed in 1928. Three different hydro project locations have been developed over the years with Gilkes supplying a total of seven turbine-generator units.

Gilkes installed the Tagabi 2 turbine-generator equip-ment in an extension to the existing Tagabi project supplied in 1989.

Total Hydro Capacity: 2870 kW

*The Chemosit Project was supplied by Gilkes to another tea estate which was acquired by Brooke Bond Kenya as their tea production expanded

Project Capacity Year of Installation

Tagabi 1620 kW 1989 & 2010

Jamji 630 kW 1948 & 1949

Kerenga 99kW 1929 & 1932

Chemosit* 90 kW 1928