case study of g+2 structure located at railway quarters, warangal

18
PRESENTATION BY R.RAGHAVENDRA I/II M.Tech, CTM

Upload: nit-warangal

Post on 21-Nov-2014

671 views

Category:

Education


3 download

DESCRIPTION

In this presentation possible rehabilation methods for the G+2 structure are discussed

TRANSCRIPT

Page 1: Case study of G+2 Structure located at railway quarters, warangal

PRESENTATION BY

R.RAGHAVENDRAI/II M.Tech, CTM

Page 2: Case study of G+2 Structure located at railway quarters, warangal

CONTENTS :1. SALIENT FEATURES2. GLANCE ON BUILDING PICTURES3. OBSERVATIONS4. Reasons5. tests to be recommended 6. Suggested methods7. conclusion

Page 3: Case study of G+2 Structure located at railway quarters, warangal

Quarters located at KAZIPET Railway station

G + 2 Building with 4 Flats at each level

Constructed Building more than 30 years ago

All flats are occupied

Date of inspection: 30-03-2013

Salient Features:

Page 4: Case study of G+2 Structure located at railway quarters, warangal

ELEVATION REENTRANT CRACKS

Page 5: Case study of G+2 Structure located at railway quarters, warangal

VERTICAL & DIAGONAL CRACKS

Page 6: Case study of G+2 Structure located at railway quarters, warangal

CORROSION OF RIENFORCEMENT

Page 7: Case study of G+2 Structure located at railway quarters, warangal

LINTEL FAILURE

Page 8: Case study of G+2 Structure located at railway quarters, warangal

CRACK IN THE FLOORCRACK IN THE WALL

Page 9: Case study of G+2 Structure located at railway quarters, warangal

WATER LEAKAGE FROM DRAINAGE PIPES

Page 10: Case study of G+2 Structure located at railway quarters, warangal

PLANTGROWTH

Page 11: Case study of G+2 Structure located at railway quarters, warangal

NEW WATER TANK

DEMOLISHED OLD WATER TANK (expected)

Page 12: Case study of G+2 Structure located at railway quarters, warangal

DAMPNESS

SPALLING FROM SLAB

Page 13: Case study of G+2 Structure located at railway quarters, warangal

VISUAL OBSERVATIONS:

Structural cracks are observed in walls

Spalling & Peeling of cover

Corrosion of Reinforcement

Settlement of the floor

Plant & Algae growth

Severe Dampness in the walls

Discolouration of the building

Page 14: Case study of G+2 Structure located at railway quarters, warangal

REASONS: Major cracks in compound wall due to differential

settlement of the foundation

Reentrant cracks due to Stress concentration

Spalling & Peeling of cover

Corrosion of bars due to seepage of water

Settlement of the floor due to poor soil conditions

Plant & Algae growth due to leakage of water from pipes

Dampness in the walls due penetration of water from tank

Poor Maintenance & No repair at initial stages of damage

Page 15: Case study of G+2 Structure located at railway quarters, warangal

Tests to be Recommended:

Ultrasonic Pulse Velocity test

Half-cell Potential test

Rebound Hammer Test

Carbonation test

Resistivity test

Page 16: Case study of G+2 Structure located at railway quarters, warangal

Suggested Repair

Techniques:

o Cracks: Stiching Method

o Spalling & Peeling: Bond coats & Grouts

o Corrosion: Proper cover & coating

o Dampness: Thin Polymer & Epoxy overlays

o Settlement of floor: Proper Soil Compaction

o Plant & Algae Growth: New Drainage pipes

Page 17: Case study of G+2 Structure located at railway quarters, warangal

Conclusion:

As Many parts of the building are damaged immediately

repair has to be done.

The Repair Techniques improve the remaining life of

the structure up to a considerable extent.

Hence This Moderately damaged building has to be

tested in detail and appropriate methods are to be

applied.

Periodic inspection & Maintenance

Page 18: Case study of G+2 Structure located at railway quarters, warangal

R.RAGHAVENDRA

THANK YOU