Failure Mode & Effects Methodology

© 2010 Omnex Inc 2

Block Diagram

Block Diagram

Customer Requirements

Customer Requirements

SystemFMEA

Design InputsDesign Inputs

Process FlowProcess Flow

ProcessFMEA

ProcessFMEA

Control PlansControl Plans

Shop Floor Checklists

Page 3: Case Study Large Automotive OEM – FMEA Managed Service

Review, Investigate, Evaluate

48%

Monitor2%

Supplier6%

Design Change7%

Analytical9%

Physical Test10%

Process Issue13%

Other5%

Benchmark20%

Design Improvements

40%Escalation

1%

Process Review

3%

SSR11%

Verification / Testing

13%

Analytical / Math12%

Before AQP After AQP

Design Failure Mode and Effects Analysis-- Distribution of Recommended Actions

Automotive OEM – FMEA Managed Service

© 2010 Omnex Inc 3

Page 4: Case Study Large Automotive OEM – FMEA Managed Service

Initial Quality of U.S. and Import Brands 1999-2010

Note: Import Brands Include Europe and Asia

Page 5: Case Study Large Automotive OEM – FMEA Managed Service

Case StudyCase Study

Large Aerospace Engine Manufacturer

Page 6: Case Study Large Automotive OEM – FMEA Managed Service

New Product Introduction & PPV

6

CAB Activity

Planning

Program Start

Experimental Production

Product Design and Dev.

Process Design and Development

Product and Process Validation

Production

Corrective Action Board activity

Plan & Define

Program

Product Design &

Development Verification

Process Design &

Development Verification

Product & Process

Validation

Ongoing Part & Process Control

Product & Process Planning

PPV Activities Consolidation

Industrialization

© 2010 Omnex Inc

Page 7: Case Study Large Automotive OEM – FMEA Managed Service

Large Aerospace Engine Manufacturer

• Conducting PPV (Product and Process Validation including FAI) training and facilitation for internal resources and 200 suppliers

• Rollout PPV to ensure product and process conformance for all new products

• Currently in initial stages – 10% to 30% improvement expected in RCNs

Page 8: Case Study Large Automotive OEM – FMEA Managed Service

Case StudyCase Study

Truck – System Supplier

Page 9: Case Study Large Automotive OEM – FMEA Managed Service

Purchasing

FUNCTIONALEXCELLENCE

FOUNDATIONALEXCELLENCE

QOSQOS TS16949/APQP/PPAPTS16949/APQP/PPAP

Team SkillsTeam Skills Global 8DGlobal 8D

6S/VISUAL WORKPLACE6S/VISUAL WORKPLACE

Quality

Materials

MANUFACTURING

Operations Excellence

© 2010 Omnex Inc 9

Page 10: Case Study Large Automotive OEM – FMEA Managed Service

Truck Industry Large Sub System Provider

Improvement Before After Comments

Quality Rejects measured in percentages

3 Years – 187 PPM Implementation of APQP and PPAP internally and with Supply Base

187 DPM

Page 11: Case Study Large Automotive OEM – FMEA Managed Service

Semiconductor Semiconductor Industry TransitionIndustry Transition

Semiconductor Assembly Council – Representing 95% of Chip Industry

Outside Japan

Page 12: Case Study Large Automotive OEM – FMEA Managed Service

Semiconductor Industry Methodology

© 2010 Omnex Inc 12

8-D 8-D

MSA, SPC, and Process Control

ISO TS 16949 plus APQP and PPAPISO TS 16949 plus APQP and PPAP

Customer Involvement Similar

to Aerospace Industry

Customer Involvement Similar

to Aerospace Industry

Page 13: Case Study Large Automotive OEM – FMEA Managed Service

Customer Driven Changes: 1998 to 2004

• Productivity improvements: 10% – 30%– Equipment– People

• Yield improvement– Subcontractor yields improved to 99.6%

• Performance to schedule improvement– Consistently sustaining 100%

• Number of customer complaints decreased– Up to 15x reduction

• PPM improved by over 100 times to under 30 PPM

© 2010 Omnex Inc 13