2
Consultant BAM Client BAM M&E Sector Education Products Dinak Flue System Equipment Clyde Modulex 290 & 900 Application High Efficiency Condensing 0844 809 2509 | airtherm.co.uk | [email protected] Project Profile UCL Academy, Adelaid Road, Camden Front Entrance Aerial View of site Camden gets all fired up…. Airtherm Engineering Limited have designed, supplied and installed a 500mm diameter stainless steel, twin wall, fully welded, 4 hour fire rated, gas and water tight Dinak DWhp flue system serving three high efficiency Clyde condensing boilers, with a total 2.2MW output load. Airtherm Engineering Limited liaised with both the consultant and the contractor at all times, attending site meetings, providing comprehensive technical submission, including calculations and drawings for approval prior to manufacture of the equipment. The system installed comprised of a 12m horizontal run and a 26m vertical, complete with draft stabilisers and the necessary drains incorporated to allow any unwanted condense to evacuate to the system. The flue system was installed back in April 2012, however the design and liaising with the contractor begin some months earlier. Working closely with BAM Construction the installation was certainly a success. Clyde Modulex Boiler

Upload: airtherm-engineering-limited

Post on 13-Jul-2015

70 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Case Study for Flue Sstem at Camden Academy

Consultant

■ BAM

Client

■ BAM M&E

Sector

■ Education

Products

■ Dinak Flue System

Equipment

■ Clyde Modulex 290 & 900

Application

■ High Efficiency Condensing

0844 809 2509 | airtherm.co.uk | [email protected]

Project Profile

UCL Academy, Adelaid Road, Camden

Front Entrance

Aerial View of site

Camden gets all fired up…. Airtherm Engineering Limited have designed, supplied and installed a 500mm diameter stainless steel, twin wall, fully welded, 4 hour fire rated, gas and water tight Dinak DWhp flue system serving three high efficiency Clyde condensing boilers, with a total 2.2MW output load. Airtherm Engineering Limited liaised with both the consultant and the contractor at all times, attending site meetings, providing comprehensive technical submission, including calculations and drawings for approval prior to manufacture of the equipment. The system installed comprised of a 12m horizontal run and a 26m vertical, complete with draft stabilisers and the necessary drains incorporated to allow any unwanted condense to evacuate to the system. The flue system was installed back in April 2012, however the design and liaising with the contractor begin some months earlier. Working closely with BAM Construction the installation was certainly a success. Clyde Modulex Boiler

Page 2: Case Study for Flue Sstem at Camden Academy

• Boilers: Clyde

• Model: Modulex 1 x 290kw & 2 x 900kw

• Application: Chimney / Flue system

• Operating mode: Dry / Wet

• Pressure: Negative / positive pressure

• Working pressure: 200 Pa (product will operate 1000pa max)

• Inner wall: 316L1.4404/1.457 thickness ≤ Ø250 0,4 mm, ≥ Ø300 0,5 mm

• Outer wall: AISI 304/ 1.4301 thickness 0,5 / 0,6 mm

• Insulation: 25mm thick Rockwool insulation

• Sealant : tri-lip 'o' type silicone ring

• Fuel type: Gas/Oil/Coal/Wood

• Other Application Dinak Flues can be used:

• Condensing boilers

• Atmospheric gas-fired boilers

• Gas blown boilers

• Industrial ovens, large-scale establishments

• Wood-fired stoves

0844 809 2509 | airtherm.co.uk | [email protected]

Product Solution

Airtherm Masterflue

Contact Details:

Airtherm Engineering Ltd

Ventilation House

Pedmore

Stoubridge

West Midlands

DY9 0DS

Tel: 0844 8092509

Fax: 01562 887312

MasterFlue