case study : bilateral · pdf fileelectricity generating authority of thailand power for thai...
TRANSCRIPT
Electricity Generating Authority of ThailandPower for Thai Happiness
Case Study : Bilateral Interconnection
Dr. Suthep ChimklaiAssistant Governor Transmission System Maintenance
27 November 2013
Content
Thailand’s Power Outlook
Power Development Plan
Power Purchase Process
Power Purchase from Neighboring Countries
ASEAN Power Grid
2
Enhanced Single Buyer (ESB) Model
IndependentPower
Producer
Power Purchase
fromNeighboring
Countries
SmallPower
Producer
EndUsers
IndustrialEstate
Generation
Transmission
End User
Distribution
EGATGen.
EGAT Trans.System
Operator
Go
ve
rnm
en
tal b
od
y a
nd
ER
C
Policy
Regulate
Vary SmallPower
Producer
MEAPEA
EGATDirect Customers
Current Thailand ESI Structure
ring fenced
Account Unbundling
Ele
ctric
+ S
team
ERC stands for Energy Regulatory Commission4
17,000
19,000
21,000
23,000
25,000
27,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
MW
2011
2012
4.5%
2010
6.1%
2.5% 3.0% 5.3%
9.4%
2013
5.1%
4.4%
7.5%
% = Growth Rate (on a month-on-month basis)
0.8%
Monthly Statistics of EGAT’s System(Net Peak Generation from 2010 to 2013)
26,598.1 MW16 May 2013, 2.00 p.m.
Peak rose by 5.5 % from a year earlier
4.6%
6.1%
12.0 %
5.5%
3.9%
17.7%
14.1%
5
2.7%
-0.9%
1.5%
-1.6%
0
50,000
100,000
150,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2011
GWh
20102013
Cumulative Growth
1 Jan – 31 Oct 2013 = 1.5 %(compared to 2012)
2012
4.7%
2.3%
1.9%
2.7%
2.3%
Monthly Statistics of EGAT’s System(Net Energy Generation from 2010 to 2013)
6
2.4%
2.0%
1.9%
1.8%
1.5%
Total Peak Demand
(16 May 2013)
26,598.1 MW
Total Contract Capacity
(31 October 2013)
33,591.0 MW
Biomass 313.6 MW
5%
Others 4.5 MW 0.1%
Renewables5,858.9 MW
Generating Capacity by Plant Types
7
Combine Cycle18,718 MW
56%
Thermal 8,589.7 MW
25.6%
Renewables5,858.9 MW
17%
Gas Turbine & Diesel
124.4 MW 0.4%
TNB (HVDC) 300.0 MW
1%
Domestic 3,754.3 MW (11%)Laos 2,104.6 MW ( 6%)
Laos Hydro 2,104.6 MW
35.9%
Thai Hydro 3,436.2 MW
59%
8Corporate Planning Division
Electricity Generating Authority of Thailand
EGAT’s Transmission System
EGAT’s Transmission System
Substation 212
Transformer Capacity 86,924 MVA
Transmission Line Length
32,047 Circuit-km
69 kV
115 kV
132kV
230 kV
300 kV DC
500 kV 12.8%
44%
43%
Circuit-km
as of August 2013
SUMMARY of PDP2010: Revision 3 (2012 - 2030)
Coal-fired Power Plant (Clean coal Technology)
Gas-fired Power Plant
Nuclear Power Plant
Gas Turbine Power Plant
Cogeneration (SPP / VSPP)
Renewable Energy (SPP, VSPP, EGAT)
Power Purchase from Neighboring Countries
7,740 (10 Units)
18,400 (23 Units)
4,000 ( 4 Units)
-
8,264 / 55
4,433
10,982
4,400 ( 6 Units)
25,451 (29 Units)
2,000 ( 2 Units)
750 ( 3 Units
6,374 / 102
9,481
6,572
PDP2010
Rev2
Unit: MW
PDP2010 Rev3
Total Capacity as of December 2011
Total Added Capacity
Total Retired Capacity
Grand Total Capacity at the End of 2030
32,744
53,874
- 17,061
69,557
32,395
55,130
-16,839
70,686
Numbers of Added Power Plants During 2012 - 2030
Capacity During 2012 - 2030
10
0
30,000
80,000
2019 2030
MW
EGAT Power Plant Projects
34,086
2012
SPP, VSPP,
HSA1-2
, PG
S1-2
SPP, VSPP,
SEC1-2
SPP,
VSPP,N
NG
3,
NPS3-4
SPP, VSPP,
KN
2, H
SA3, N
PS 1
-2
SPP,
VSPP,
NN
P,
XPN
SPP, VSPP,
XYB
SPP,
VSPP
Peak Demand + RM 15%
Existing Generating Capacity
26,348
EG
AT R
E
EG
AT R
E,W
N4, CH
A2
EG
AT R
E
EG
AT R
E
EG
AT R
E,L
TK3-4
EG
AT R
E
EG
AT R
E, EG
AT C
F1
EG
AT R
E
SPP,
VSPP
SPP, VSPP,
IPP1,P
P
EGAT
VSPP+SPP+IPP+PP
VSPP, PP
VSPP, PP
VSPP, PP
SPP, VSPP,
PP
SPP, VSPP,
IPP6,P
P
SPP, VSPP,
IPP5,P
P
SPP, VSPP,
IPP4,P
P
SPP, VSPP,
IPP3,P
P
SPP, VSPP,
IPP2,P
P
EG
AT R
E,
BP
K1
EG
AT R
E,
BP
K2
, EG
AT C
F2
70,686
52,256
EG
AT R
E,
SB
12
EG
AT R
E,
BP
K3
, S
B3
EG
AT R
E,
BP
K4
, EG
AT C
F3
EG
AT R
E,
BP
K5
, EG
AT N
UK1
EG
AT R
E, EG
AT G
T3, EG
AT C
C2
EG
AT R
E,
BP
K6
, W
N1
, EG
AT N
UK2
EG
AT R
E,
WN
23
, EG
AT G
T1,E
GAT C
F4
EG
AT R
E,
SB
4, EG
AT G
T2,E
GAT C
C1
Peak Demand
underline Replacement
11
GWh
0
40,000
80,000
120,000
160,000
200,000
240,000
280,000
320,000
360,000
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Diesel
Renewables
Fuel Oil
EGAT-TNB
Natural Gas
Import Coal
Lignite
Nuclear
65% 66% 68% 67% 64% 63% 62% 61%
59%
60%
59%59%
60%
60%59%
57%55% 56%
58%
9% 9% 9%8%
9% 10% 10% 11% 11% 11% 12% 12% 12%12%
12%12% 13% 13% 12%
9% 9% 9% 11% 13% 13% 12% 12% 12% 11% 11% 10% 10%10%
9%9% 9%
18%18%
18%18%
18%
18%18%
18%
18%18%
18%
15%16%
2% 4% 5% 5% 5%
14%
14%14%
14%
8% 7%
15%15%
Nuclear
Lignite
Import Coal
NaturalGas
Renewables
Energy Generation by Fuel Types
1) PDP2010 : Revision 3
Note : Renewables include domestic and imported hydro power
12
Procedures
[ Neighboring Country Name] nominates project to Thailand’s S-ECTN
Investor contacts S-ECTN
Investor discusses with S-ECTN’s Working Group
Investor submits tariff proposal to S-ECTN
Negotiation with Working Group
Draft Tariff MOU Approval by S-ECTN, NEPC, Cabinet
Draft PPA Preparation and Approval (Same Process as Tariff MOU)
S-ECTN = The Sub–Committee on Electric Power Cooperation between Thailand and Neighboring CountriesNEPC = National Energy Policy Council
Thai
Investor contacts [Country Name] government
MOU for Feasibility Study
Feasibility Study
Project Development Agreement
Activities in [Country Name]
Concession Agreement
Investor
14
Agreements on Project Development & Power Purchase
Host Country
PrivateInvestor
Purchaser(EGAT)
1. Right to Develop 3. Electrical Energy
2.1 ConcessionAgreement
2.2 Power Purchase Agreement
5. Royalty Fee, Tax, etc.
4. Payment
15
Tariff Setting
1. Costs of New Transmission System in Thailand
2. Competitive Price
Electricity Purchase Priceat Border
+
Costs of New Transmission System in Thailand
Other Alternatives
Factors to be considered :
≤
X Baht/kWh Y Baht/kWh Z Baht/kWh+ ≤
Note : Typically, payments are set and made in 50% Baht, 50% $US16
Optimized use of energy
resources in the region
Competitive price
Promotion of regional
cooperation
Fuel diversification
Limitation in domestic site
selection issue
System Security
Power Losses
Impact on domestic
investment in power
generation
Knowledge and skill lost
Benefits and Drawbacks
18
Pros Cons
Lao PDR
PPA signed 3,316 MW
COD achieved 2,104.6 MW
Project MW COD
Theun-Hinboun 434 1998, 2012
Houay Ho 126 1999
Nam Theun 2 948 2010
Nam Ngum 2 596.6 2011
Potential Project 2,457 MW
Project MW Earliest
Xe Kong 4-5 570 2021
Nam Kong 1 75 2022
Senakam 660 N.A.
Don Sahong 240 2023
Pak Beng 912 N.A.
Hongsa
Xayaburi
Nam Ngum 2 Nam Ngeip 1
Theun-Hinboun
Nam Theun 2
Houay Ho
Xe-Pian
MOU 7,000 MW
19
Myanmar
Project MW Earliest
Hutgi 1,190 2023
Mai Khot 390 N.A.
Mong Ton 6,300 2026
Dawei 1,800 2018
MOU 1,500 MW
Hutgi
Potential Project MW
Dawei
Mai KhotMong Ton
20
Malaysia
Project MW COD
Sadao-Chuping(HVAC)
85 1980
Khlong Ngae-Gurun(HVDC)
300 2002EGAT-TNB
Project MW Earliest
Su-ngai Kolok -Rantau-Panjang
100 2015
Coal fired 800 2021
Potential project 900 MW
COD achieved 385 MW
21
HAPUA Members
Electricity of VietnamSocialist Republic of Viet Nam
Department of Electrical ServicesBrunei Darussalam
Electricité du CambodgeKingdom of Cambodia
PT. PLN (Persero)Republic of Indonesia
Electricité du LaosLao PDR
Tenaga Nasional BerhadMalaysia
Department of Electric Power of MyanmarUnion of Myanmar
National Power CorporationRepublic of the Philippines
Singapore Power LTDRepublic of Singapore
Electricity Generating Authority of ThailandKingdom of Thailand
25Note : HAPUA = Heads of ASEAN Power Utilities and Authorities
AIMS-II Results
CAMBODIA
INDONESIA
SARAWAK
BRUNEI
P. MALAYSIA
PEOPLE'S REPUBLIC OF CHINA
YUNNAN
BATAM
SINGAPORE
8
11
14
10
6
12
43
1
7
2
5
9
13
15
LAO PDR
16
SABAH
Earliest COD1) P.Malaysia - Singapore (New) 2018
2) Thailand - P.Malaysia • Sadao - Bukit Keteri Existing
• Khlong Ngae - Gurun Existing
• Su Ngai Kolok - Rantau Panjang 2015
• Khlong Ngae – Gurun (2nd Phase, 300MW) 2016
3) Sarawak - P. Malaysia 2015-2021
4) P.Malaysia - Sumatra 2015
5) Batam - Singapore 2015-2017
6) Sarawak - West Kalimantan 2012
7) Philippines - Sabah 2020
8) Sarawak - Sabah – Brunei• Sarawak –Sabah 2020
• Sabah – Brunei Not Selected
• Sarawak – Brunei 2012-2016
9) Thailand - Lao PDR• Roi Et 2 - Nam Theun 2 Existing
• Sakon Nakhon 2 – Thakhek – Then Hinboun (Exp.) Existing
• Mae Moh 3 - Nan - Hong Sa 2015
• Udon Thani 3- Nabong (converted to 500KV) 2017
• Ubon Ratchathani 3 – Pakse – Xe Pian Xe Namnoy 2018
• Khon Kaen 4 – Loei 2 – Xayaburi 2019
• Thailand – Lao PDR (New) 2015-2023
10) Lao PDR - Vietnam 2011-2016
11) Thailand - Myanmar 2016-2025
12) Vietnam - Cambodia (New) 2014-2017
13) Lao PDR - Cambodia 2011
14) Thailand - Cambodia (New) 2015-2017
15) East Sabah - East Kalimantan Newly Proposed
16) Singapore – Sumatra 2020
26
16 interconnection projects are proposed.
Project No.
Interconnected Systems Capacity (MW)
1 P.Malaysia – Singapore 450
2 Thailand – P.Malaysia 380
- Sadao – Bukit Keteri 80
- Khlong Ngae – Gurun 300
9 Thailand – Lao PDR 2,105
- Nakhon Phanom - Thakhek - Theun Hinboun 214
- Ubon Ratchathani 2 – Houay Ho 126
- Roi Et 2 – Nam Theun 2 948
- Udon Thani 3 – Nabong – Nam Ngum 2 597
- Nakhon Phanom 2 - Thakhek - Theun Hinboun (Exp) 220
10 Lao PDR - Vietnam 248
12 Vietnam – Cambodia 170
14 Thailand – Cambodia 100
Existing APG Projects (May 2013)
27
APG Priority Projects(May 2013)
Project No.
Interconnected Systems Capacity (MW)
4 P.Malaysia – Sumatra (2017) 600
- Melaka – Pekan Baru
6 West Kalimantan – Sarawak (2015) 230
28