case study and knowledge sharing on waste management2)_sudan... · 1. collect basic information of...
TRANSCRIPT
![Page 1: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/1.jpg)
African Clean Cities Platform
June 2018
Gosai Ahmed, MENRPD (Sudan)
Diseremo Sebit John, JCC (South Sudan)
Case Study and Knowledge Sharing
on Waste ManagementNorth/South Cooperation Across the Border
in Sudan
1
![Page 2: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/2.jpg)
Table of Contents
1. Background
1.1 History of Sudan SWM Project
1.2 Current Situation of South Sudan SWM Project
1.3 Cooperation among Sudan/South Sudan/JICA
2. Study Tour in Sudan
2.1 Outline of Study Tour
2.2 Experiences gained during the Study Tour
3. Lessons Learnt & Challenges
4. Way forwards
2
![Page 3: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/3.jpg)
1. Background
1.1 History of Sudan SWM Project
Framework of the Project
Overall project :Improved sustainable
solid waste management (SWM) system
in Khartoum state .
Project Purpose: the SWM becomes more
efficient and effective .
Budget : 15,000,000 USD
Period : 2014 - 2017 ( 3 years )
3
![Page 4: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/4.jpg)
Project Activities 2014 - 2017
Sign agreement for technical cooperation
Implement pilot projects in residential area
Training (workers, communities, supervisors)
Awareness (Bus Tours, lectures, work shops,
community meetings)
Collection trucks and landfill equipment procured
by Grant Aid in 2015
Training regarding Grant Aid equipment's for
Drivers, Mechanics and Collection crews
Constructed central work shop (two floors)
4
![Page 5: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/5.jpg)
منزل نظام الجمع من كثرة النقاط يودى ال صعوبة جمع من كل النقاط لمنزل - ①
السيارة متحرك يودي تساقط نفايات اثناء الجمع ②عامل النفايات يبذل مجهود اكثر ③
ال ترجع السلة الى النقطة الجمع
نفايات منسية
❶
➋ ➌
نفايات مبعثرة
نفايات ساقطة من السيارة
Fix Time Fix Place Method
BEFORE
5
![Page 6: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/6.jpg)
نظام الجمع في المكان المحدد و الزمان المحدد
AFTER
6
![Page 7: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/7.jpg)
Central Workshop in Soba7
![Page 8: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/8.jpg)
8 Japanese Embassy with Project Team
![Page 9: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/9.jpg)
1. Background
1.2 Current Situation of South Sudan SWM Project9
![Page 10: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/10.jpg)
Waste Management By-law of Juba City Council
Department of Environment is responsible for waste collection from markets and main roads.
Operation Permits for garbage collection, Licenses for private sewage tankers.
Donations from well wishers
General campaign involving all stakeholders
Defaulters and offenders
The By – Law determinates the above points to happen
10
![Page 11: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/11.jpg)
Practical Collection of waste from main
Roads on daily basis11
![Page 12: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/12.jpg)
1. Background1.3 Cooperation among Sudan/South Sudan/JICA
Project Purposes (FEB2017 – JUlY2018)
1. Collect basic information of solid waste
management system (waste generation, collection
and transportation, intermediate treatment,
recycling and landfill), which will be a foundation of
the new master plan of SWM in Juba.
2. Review lessons learnt from SWM system at the city
level in Sudan, and identify priority issues and
effective supports for the future to improve SWM in
Juba.
12
![Page 13: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/13.jpg)
Summary of Study tour and meeting
Activity preparation
1 Kick-off meeting To collect the data & analysis
2 1st study tour To analyze field data collection
3 2nd study tour To make the annual report
To plan pilot project outline
4 Final workshop To make action plan of pilot project
To summarize data collection activity
5 (Extension) Pilot project
preparation
To make realistic pilot project plan
6 (Extension) Pilot project
implementation
To analyze data from pilot project
13
![Page 14: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/14.jpg)
2. Study Tour in Sudan2.1 Outline of Study Tour
1. Courtesy CallA) Ministry of Environment, Natural Resources and
Physical Development (MENRPD )
B) Minister / Higher Council, Khartoum State
C) Khartoum Cleaning Corporation (KCC)
2. Site VisitA) AU Office (Karary & Khartoum): Fixed-Time Fixed-
Point Collection
B) Transfer Station (Omdurman/ Khartoum/ Umbadah)
C) Landfill Site (Omdurman/ Bhahari)
D) Central Workshop (Soba)
14
![Page 15: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/15.jpg)
FIX-TIME FIX-PLACE COLLECTION15
![Page 16: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/16.jpg)
AU Office16
![Page 17: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/17.jpg)
Transfer Station
![Page 18: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/18.jpg)
CLOSING CEREMONY
MENRPD of SudanRepresentative of
Govt. of South Sudan
![Page 19: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/19.jpg)
2.2 Experiences gained during the Study
Tour
How to formulate action plan and Master Plan (M/P) through data collection.
The collection system in Khartoum State (the waste from the residential areas, markets, streets etc. to the transfer station and finally to the landfill site) and the importance of weighing machine (weigh bridge) and the use of incinerators for medical waste.
Establishment of Workshop including training of maintenance of collection vehicles.
Establishment of recycling facility is important for Juba but also the feasibility and sustainability should be taken into consideration
19
![Page 20: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/20.jpg)
3. Lessons Learnt & Challenges
JICA pilot project has succeeded in Khartoum State through
cooperation, commitment and hard work.
Before the pilot project the department of Environment and
Sanitation did not know the amount of waste which had been
collected but now we came to know that the collection ratio is
only 4% and the rest are dumped illegally.
Involvement and participation of the leadership in decision
making regarding the pilot Project.
Hard work, hospitality, commitment and team work by the
localities and KCC.
The Japanese history of Solid Waste management and the
current situation.
20
![Page 21: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/21.jpg)
4. Way Forward
Exchange experience and knowledge is important,
such as survey instruction, mechanic training,
collection system improvement. E.g. Mr. Gosai was
dispatched to support to conduct waste amount
generation survey in Juba on September 2017.
Governmental cooperation between Juba and
Khartoum continue.
Expansion of SWM project from Khartoum to other state,
and pilot project in Juba.
Temporary dumping site and Official landfill should be
renovated and new dumping site is required to be
open for expanded area.
21
![Page 22: Case Study and Knowledge Sharing on Waste Management2)_Sudan... · 1. Collect basic information of solid waste management system (waste generation, collection and transportation,](https://reader033.vdocuments.us/reader033/viewer/2022050523/5fa730ede4d749502918a7e6/html5/thumbnails/22.jpg)
Thank you for your
attention22