carlin law group, apc grounds for additional time and/or compensation a.express changes...

20
CARLIN LAW GROUP, APC Grounds for Additional Grounds for Additional Time and/or Compensation Time and/or Compensation A. Express Changes B. Constructive Changes C. Differing Site Conditions D. Express Suspension of Work E. Constructive Suspension of Work F. Delay G. Acceleration H. Termination for Convenience

Upload: mohamed-bath

Post on 28-Mar-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Grounds for Additional Time Grounds for Additional Time and/or Compensationand/or Compensation

A. Express Changes

B. Constructive Changes

C. Differing Site Conditions

D. Express Suspension of Work

E. Constructive Suspension of Work

F. Delay

G. Acceleration

H. Termination for Convenience

Page 2: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Express ChangesExpress Changes• Should arise by way of a written change directive

– If directive is verbal, the Contractor has the obligation to request it be confirmed in writing.

• Most construction contracts only allow for written change directives.

• Upon receipt of a change directive, the Contractor should provide a proposed change order (PCO) describing in detail the additional time and costs the Contractor will require.– Caution must be exercised in signing change orders so as

not to waive the Contractor’s right to all costs and time associated therewith.

Page 3: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Constructive ChangesConstructive Changes

• Changes are unintended and require the Contractor to perform work beyond what’s required or contemplated by the terms of the Contract Documents.

Page 4: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Causes of Constructive ChangesCauses of Constructive Changes

A. Defective Contract Documents• ie. Errors, omissions, ambiguities, impossible or

impractical requirements

B. Unreasonable inspection or installation requirements

C. Failure to disclose relevant informationD. Constructive Acceleration

Page 5: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Prerequisites to Recovery for Prerequisites to Recovery for Constructive ChangesConstructive Changes

A. The Work performed was not included in the original scope of work

B. Contractor satisfied all contractual/statutory notice requirements

C. Contractor did not volunteer to work under the changed conditions

D. Contractor discreetly tracked and quantified its additional costs incurred due to the change

Page 6: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Differing Site ConditionsDiffering Site Conditions

• Contracts and/or statutes contain provisions which affect a Contractors ability to recover for unanticipated or hidden physical conditions on a project which differ from those represented in the bidding documents or would be normally anticipated in similar work.

Page 7: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Type I Differing Site ConditionsType I Differing Site Conditions

• Physical conditions different from those shown or indicated in the Contract Documents at bid time.– Compensation for these conditions is quantified as the

difference between what the bid documents indicate and what is actually encountered on the Project.

– Examples include:• Rock/unforeseen soils conditions

• Water where none is anticipated

• Buried surface obstructions where none are anticipated

Page 8: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Type II Differing Site ConditionsType II Differing Site Conditions• Conditions which are so unusual or so unpredictable

that the Contractor cannot be reasonably expected to have anticipated them at bid time.– Compensation for these conditions is quantified as the

difference between what the Contractor reasonably anticipated, based on similar work, and what is actually encountered on the Project.

– Examples include:• Hazardous or toxic materials• Unusual soil conditions• Buried obstacles in an area where not expected

Page 9: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Express Suspension of WorkExpress Suspension of Work

• Occasionally, an Owner will direct a Contractor to cease work for a period of time.– Usually the Contractor is obligated to comply with the

direction, but is entitled to recover the time and costs associated with the stop work order.

– A Contractor is not entitled to recover time or costs if the stop work order is issued due to the Contractor’s own fault or negligence.

Page 10: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Constructive Suspension of WorkConstructive Suspension of Work• May be caused by acts or omissions of one party on

a construction project which have the effect of unreasonably delaying the Contractor’s work.– These situations usually arise from unintended tax and

often result in an unanticipated delay. – Examples include:

• Delayed approval of shop drawings• Delayed responses to requests for information• Delayed issuance of change orders• Delayed or obstructed access to work areas• Delayed delivery of items/information by the other contracting

party

Page 11: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Prerequisites to Recovery for Prerequisites to Recovery for Constructive Suspension of WorkConstructive Suspension of Work

• Before a Contractor can recover for constructive suspensions of work it must demonstrate the following:

1. Occurrence of a delay

2. Caused by an action or inaction of the other contracting party

3. Delay was not foreseeable by the Contractor

4. All notices required by contract/statute were given by Contractor

5. Contractor incurred additional cost or time due to delay

6. Contractor discreetly tracked and quantified its additional costs incurred due to the delay

Page 12: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

DelayDelay

• Delays on a construction project are classified as follows:– Excusable, non-compensable delay– Excusable, compensable delay– Inexcusable delay– Concurrent delay

Page 13: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Excusable, Non-Compensable DelayExcusable, Non-Compensable Delay

• Usually caused by a third party or occurrences beyond the control of either the Contractor or Owner.– Examples include:

• Acts of God, unusual weather, strikes, fires, floods, etc.

• Contractor is entitled to additional time and relief from liquidated damages, but is not entitled to recover additional costs incurred as a result of the delay.

Page 14: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Excusable, Compensable DelayExcusable, Compensable Delay

• Caused by the other contracting party or its agents.– Changes to the Work which require additional

time are an example of delays which are excusable but for which the Contractor is entitled to additional time and compensation associated with the delay.

Page 15: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Inexcusable DelayInexcusable Delay• Caused solely by the Contractor or its related parties

• ie. Subcontractors, suppliers, etc.

• Examples include:– Failure to timely prosecute the Work – Late delivery of information, equipment and/or materials

• In these instances the Contractor is usually not entitled to additional time or compensation for the delay. – Instead the Contractor is obligated to take such actions

and incur such costs as are necessary to recover the lost time or pay the Owner damages for late completion.

Page 16: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Concurrent DelaysConcurrent Delays

• Situation where two or more delays occur simultaneously and impact the Project’s critical path of completion.

• If the concurrent delays are caused by both contracting parties, neither party is entitled to damages to the extent the delays overlap.– The Contractor is entitled to a time extension but cannot

recover any costs associated with the concurrent delay.– The Owner is not permitted to assess damages associated

with the Contractor’s late completion to the extent the Owner has also caused the delay.

Page 17: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

AccelerationAcceleration

• Situation where a party incurs more costs to complete a construction activity in a shorter time period than originally anticipated.– Classified as express or constructive.

Page 18: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Express AccelerationExpress Acceleration• An instance where one contracting party directs the

other contracting party to complete its work in a shorter time than that allowed by their contract.– The party who accelerates is entitled to recover its costs

associated therewith so long as the acceleration directive is not issued to recover previous delays for which the party is responsible.

• A related claim is one for deceleration where one contracting party directs the other to slow down its work and for which compensation associated with the inefficiency is recoverable to the extent it is identifiable and quantified.

Page 19: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Constructive AccelerationConstructive Acceleration• Unintended shorting of the time allotted to complete a

construction activity.• To recover on a claim of constructive acceleration, the

Contractor must demonstrate the following:1. A delay occurred on the Project for which a time extension should have

been granted2. All contractual/statutory notices of the delay in corresponding request

for a time extension were properly filed3. The appropriate time extension was not granted4. Contractor was required/directed to complete “on time” or threatened

with the imposition of late completion damages5. Contractor filed a separate notice that it was being constructively

accelerated6. Contractor actually accelerated its operation and incurred additional

costs due to the acceleration7. Contractor discreetly tracked and quantified its additional costs

incurred due to the acceleration

Page 20: CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension

CARLIN LAW GROUP, APC

Termination for ConvenienceTermination for Convenience

• Many construction contracts contain a clause permitting a party to terminate the contract for its convenience.

• Absent expressed contractual provisions outlining the costs and profits recoverable due to a termination for convenience, the terminated party is entitled to recover its reasonable costs and profit.