careers contact c//-1:j- i · 2020. 1. 21. · ampc aid to cross 9 1/17/2020 letter from bc hydro...
TRANSCRIPT
AMPC Aid to Cross 9 1/17/2020 Letter from BC Hydro President & COO to BCUC on Interior to Lower Mainland Transmission Line arbitration decision
About us Careers Contact us
C//-1:J-I Q How can we help?
Accounts Energy savings News Projects & operations Community Work with us
Media centre StorlH & faature1 Power ■mart Idea■
Home • News• Media centre • 2018 News releue 1rchlw
News May 16, 201 8
Letter from BC Hydro President & COO to BCUC on Interior to Lower Mainland Transmission Line arbitration decision
Mr. David Morton
Chair
Bri tish Columbia Umities Commission
Suite 410. 900 Howe Street
Vancouver, BC. V6Z 2N3
Dear Chairman Morton
RE: British Columbia Hydro and Power Authority (BC Hydro) Interior to Lower Mainland (ILM) Project
Arbitration Decision
I am wri ting to you today lo provide you wilh an update and further information regarding BC Hydro's completed
Interior to Lower Mainland Transmission Line project, and in particular. the arbi lration process that BC Hydro has
been engaged in since 201 4 with our prime contractor on the project, Flatiron Graham Joint Venture (FGJV) . The
arbilration decision was released on March 29, 2018.
As you know, the Interior to Lower Mainland Transmission Line is a 247 kilometre long, 500-kilovolt power line that
stretches from Merritt to Coqu1tlam. The line is the largest expansion to B.C.'s transmission syslem in the past 30
years. BCHydro awarded a design build con lracl for the line in 2011 to FGJV and construction began in the spring
of 2012. FGJV was to complele the line by October 2014 and the forecast in-service date for the project was
January 201 5. However, the in-service date was pushed back to late 2015, a year later than planned.
The new line was built through challenging and diverse terrain in B.C.'s southern interior on Crown and private
land and crosses mountains. grasslands. major rivers and highways.
The portion of the line running through the area of the Fraser Valley near Spuzzum was part1cularty challenging.
An alternate route alignment was explored as part of an arrangement with a local First Nation group Ultimately. we
decided to return to the original route alignment and to construct the Spuzzum portion of the line ourselves, rather
than using FGJV. The arbitrator found that changes In the Spuzzum portion of the hne delayed FGJV's work and
that BC Hydro is responsible under the contract for certain costs associated with this delay
There were also disruptions to FGJVs construction schedule due to issues related to access to private land and
archaeological sites that were identified. The arbitrator determined that BC Hydro is required under the contract to
compensate FGJV for some costs due to lost productivity because of these disruptions.
The contractor's claim against BC Hydro was substantial, ranging in value over time from $285 to $360 million.
While the arbitrator dismissed a number of elements of the FGJV claim. he determined that the contractor was
entitled to additional payments under the contract, largely attributable to the Spuzzum portion of the line and the
disruption costs as discussed above. We have calculated these additional costs payable under the award to be
approximately $84.7 million. In addition . BC Hydro has held-back $17 4 million from amounts we owed to FGJVas
compensation for liquidated damages payable to BC Hydro under the contract. However, based on the arbitrator's
award. BC Hydro must now pay out approximately $13.1 million of the hold-back amount because we are nol
entitled to all the liquidated damages we claimed . We also must pay interest on some of these award amounts.
Based on our calculations, the total award, including interest and the payment of hold-back amounts, is in the
range of $95 to $105 million . BC Hydro and FGJV have asked the arbitrator to clarify certain aspects of the
Decision and his clanfications may affect the final award amounts. We antiapate that the clarification process will
conclude in May or June. at which time we should be able to determine the total value of lhe award with more
certainty. It is also possible that BC Hydro or FGJV may appeal the award .
The final construction cost of the ILM transmission hne was $723 million. which Is slighUy less than the budgeted
amount of $725 million in the BCuc·s deasion approving the Certificate of Public~ nvenience and Necessity
https://www.bchydro.com/news/press _ centre/news _releases/2018/bchydro-ilm-project-decision.html
Sign Up Login I
Outages & safety
1/2
C11-17
AMPC Aid to Cross 9 1/17/2020 Letter from BC Hydro President & COO to BCUC on Interior to Lower Mainland Transmission Line arbitration decision
(BCUC Order No. C-4-08). Based on our calculations, the arbitrator's award to FGJV increases the forecast cost of
the Interior to Lower Mainland transmission project to approximalely $818 million to $828 million , subject to the
outcome of the clarifications and any appeals.
1/Vhile the arbitration decision isn 't the outcome we were hoping for, there are lessons learned we can take forward,
several have already been implemented. These lessons include potentially different contractual arrangements on
linear-impact projects as compared to point-impact projects and management of interfaces between project
activities and third parties. BC Hydro has also made significant investments in systems and staff to improve
contract management and understanding of contractor performance to allow better project management on all BC
Hydro projects. Those lessons and final project costs will be more fully described in our final Project Completion
Report. which we expect to file in summer 2018.
Sincerely,
Chris O'Riley
President & Chief Operating Officer. BC Hydro
Need help with your bill?
CHt an::iwers !o qU<-mtions about
piying your bill, rates. mooing
yot,r account and more.
Get help
Careers
V\/e it>ok for Hxcep!ion~•l! peopl<·J
to bring nf;W ideas and fres-h
tl1inkmg 10 BC Hydro
Learn more
Copyright ~ 2020 BC Hydro All Rights Reser..,ed.
Legal I Pnvacy Statements I Careers
View Mobile Sita
30 https://www.bchydro.com/news/press_centre/news_releases/2018/bchydro-ilm-project-decision.html
Get in touch with us
Cail us it> rnport a powm outauc.? ill your area or to get Information
you couldn't find online.
Contact us
2/2