carbon footprint 300 pp cb ipl 2010
TRANSCRIPT
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
1/359
IPL Greening Program
DLF IPL 2010 CARBON FOOTPRINT MEASUREMEN
Project RepoREALISE
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
2/359
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
3/359
1 EXECUTIVE SUMMARY 15
2 INTRODUCTION
3 PROJECT GOALS 26
4 PROJECT SCOPE
5 RESEARCH METHODOLOGY
6 ANALYSIS METHODOLOGY
19
28
39
59
64
2.1 The Players 20
2.2 The Arena 22
2.3 The Project 23
2.4 The Report 25
4
35
5.1
.1 Activity Boundaries 30
4.2 Stakeholder Boundaries 34
4.3 Life-cycle Boundaries
Central and Local Footprint Sources 41
5.2 Annual and Tournament-Duration Activity Data 45
5.3 Resource Input, Consumption, and Output Mapping 47
5.3.1 IPL/IMG Activity Data Research 49
5.3.2 State Association Activity Data Research 50
5.3.3 Franchise Activity Data Research 51
5.3.4 Spectator Activity Data Research 52
5.4 Resource Optimization Potential Research 55
5.5 Tournament Operation Air and Road Travel Research 56
6.1 Resource / Activity Tagging 60
6.2 Activity Data Extrapolation
6.2.1 IPL/IMG Data Extrapolation 64
6.2.2 State Association Activity Data Extrapolation 67
6.2.3 Franchise Activity Data Extrapolation 69
6.3 GHG Emission Factors 72
6.4 New Emission Factors Research and Analysis 73
TABLE OF CONTENTS
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
4/359
78
111
7.4.1 Activity-Differentiated Venue Carbon Footprints 114
7.4.2 Stakeholder-Differentiated Venue Carbon Footprints 117
149
151
117
160
166
6.4.1 Stadium Construction Research and Analysis 736.4.2 Ground Maintenance Research and Analysis 75
6.4.3 Fireworks and Pyrotechnics Research and Analysis 76
6.5 Diesel Generator Consumption 77
7.1 IPL Resource/Activity Flow Mapping 79
7.2 Resource Consumption Inventory 85
7.3 Total Carbon Footprint 87
7.3.1 Activity-Differentiated Carbon Footprint 917.3.2 Stakeholder Contributions to Activity-Differentiated Carbon Footprint 92
7.3.3 Stakeholder-Differentiated Carbon Footprint 99
7.3.4 Activity Contributions to Stakeholder-Differentiated Carbon Footprint 102
7.4 Match Venue Carbon Footprints
7.5 Day vs. Night Match Carbon Footprint Implications
7.6 Best Practices
7.6.1 Overall Venue Best Practice Benchmarks 152
7.6.2 Stakeholder Best Practice Benchmarks 152
7.6.3 Franchise Level Best Practices 157
7.6.4 Other Best Practices 158
7.7 Water Footprint
9.1 Assumptions 1679.2 Data Gaps 175
9.3 Uncertainties 176
9.3.1 Activity-Data Uncertainty 176
7 RESULTS
8 CONTEXT OF TOTAL CARBON FOOTPRINT
9 DISCUSSION
TABLE OF CONTENTS
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
5/359
TABLE OF CONTENTS
10 LIMITATIONS 179
180
11 CONCLUSIONS AND RECOMMENDATIONS 181
12 ACKNOWLEDGEMENTS 189
9.3.2 Emission Factor Uncertainty 177
10.1 Water Footprint
11.1 Conclusions 182
11.2 Recommendations 186
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
6/359
TABLE OF FIGURES
Figure 1 Resource/Activity Flow Map IPL/IMG Operations 80
Figure 2 Resource/Activity Flow Map State Association Operations 81
Figure 3 Resource/Activity Flow Map Franchise Operations 82
Figure 4 Resource/Activity Flow Map Spectator Activity 83
Figure 5 Stakeholder Interrelation Map 84
Figure 6 DLF IPL 2010 Activity Contribution to Total Carbon Footprint 90
Figure 7 Total Carbon Footprint Summary Stakeholder Groups Breakdown 95
Figure 8 Stakeholder Groups Carbon Footprint Summary IPL/IMG Operations 96
Figure 9 Stakeholder Groups Carbon Footprint State Association Operations 97
Figure 10 Stakeholder Groups Carbon Footprint Summary Franchise Operations 98
Figure 11 Stakeholder vs. Activity Stadium Construction 101
Figure 12 Stakeholder Groups Carbon Footprint Summary Spectator Activity 107
Figure 13 Spectator Travel Modal Split Cross-Price Range Comparison (All IPL Venue
Cumulation) (%-specatators basis) 108
Figure 14 Spectator Travel Modal Split Cross-Price Range Comparison (All IPL Venue
Cumulation) (kms travelled basis) 109
Figure15 Carbon Emissions Intensity of Transport Modes (India) 110
Figure 16 Cross-Venue Total Carbon Footprint Comparisons per-Match Basis 112
Figure 17 Cross-Venue Total Carbon Footprint Comparisons per-Spectator Basis 113
Figure 18 Venue vs. Activity Average Stadiums 116
Figure 19 Match Venue vs Stakeholder Average Stadium 119
Figure 20 DLF IPL 2010 Match Venue vs. Stakeholder Contributions Cross-Venue
Comparison - per-Match Basis 123
Figure 21 Match Venue Stakeholders Carbon Emissions Intensity Comparison
All-Venue Averages 124
Figure 22 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison
Bvg. Contractor (Soft Drinks) 125
Figure 23 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison
Concessions Catering 126
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
7/359
TABLE OF FIGURES
Figure 24 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison State Association Catering 127
Figure 25 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison VIP Catering 128
Figure 26 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison Ground
Maintenance (per-Match Basis) 129
Figure 27 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison Ground
Maintenance (per-Year Basis) 130
Figure 28 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison Housekeeping 131
Figure 29 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison
Stadium Entertainment 132
Figure 30 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison Stadium Security 133
Figure 31 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison Stadium Utilities 134
Figure 32 Stakeholder Carbon Emissions Intensity Cross-Venue Comparison Stadium Spectators 135
Figure 33 Spectator Travel Modal Split Cross-Venue Comparison (Cumulative Tickets)
(%-specatators basis) 136
Figure 34 Spectator Travel Modal Split Cross-Venue Comparison (Cumulative Tickets)
(kms travelled basis) 137
Figure 35 Spectator Travel Modal Split Cross-Venue Comparison (Ticket Price Level 1) 138
Figure 36 Spectator Travel Modal Split Cross-Venue Comparison (Ticket Price Level 1)
(kms travelled basis) 139
Figure 37 Spectator Travel Modal Split Cross-Venue Comparison (Ticket Price Level 2) 140
Figure 38 Spectator Travel Modal Split Cross-Venue Comparison (Ticket Price Level 2)
(kms travelled basis) 141
Figure 39 Spectator Travel Modal Split Cross-Venue Comparison (Ticket Price Level 3) 142
Figure 40 Spectator Travel Modal Split Cross-Venue Comparison (Ticket Price Level 3)
kms travelled basis) 143
Figure 41 Spectator Travel Modal Split Cross-Venue Comparison (Ticket Price Level 4) 144
Figure 42 Spectator Travel Modal Split Cross-Venue Comparison (Ticket Price Level 4)
(kms travelled basis) 145
Figure 43 Spectator Travel Modal Split Cross-Venue Comparison (Ticket Price Level 5) 146
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
8/359
TABLE OF FIGURES
Figure 44 Spectator Travel Modal Split Cross-Venue Comparison (Ticket Price Level 5)(kms travelled basis) 147
Figure 45 Stakeholder Contribution to Activity Carbon Footprint Cooking Fuel 205
Figure 46 Stakeholder Contribution to Activity Carbon Footprint Generator& Motor Fuel 207
Figure 47 Stakeholder Contribution to Activity Carbon Footprint Generator& Motor Fuel 210
Figure 48 Activity vs. Stakeholder - Water 212
Figure 49 Activity vs. Stakeholder - Domestic Air Travel 214
Figure 50 Activity vs. Stakeholder - International Air Travel 216
Figure 51 Activity vs. Stakeholder - Private Vehicular Travel 219
Figure 52 Activity vs. Stakeholder - Logistics 221
Figure 53 Activity vs. Stakeholder - Luxury Hotel Accommodation 223
Figure 54 Activity vs. Stakeholder - Meat & Seafood 225
Figure 55 Activity vs. Stakeholder - Dairy 227
Figure 56 Activity vs. Stakeholder - Rice 229
Figure 57 Activity vs. Stakeholder - Alcoholic Beverages 231
Figure 58 Activity vs. Stakeholder - Bottled Water / Drinks 233
Figure 59 Activity vs. Stakeholder - Solid Waste 235
Figure 60 Activity vs. Stakeholder - Paper & Cardboard 237
Figure 61 Activity vs. Stakeholder - Plastic 239
Figure 62 Stakeholder vs. Activity IPL/IMG Head Office 242
Figure 63 Stakeholder vs. Activity -IPL/IMG Hospitality & Travel 244
Figure 64 Stakeholder vs. Activity IPL/IMG Sponsors 247
Figure 65 Stakeholder vs. Activity Catering - Concessions 249
Figure 66 Stakeholder vs. Activity Catering - VIP 251
Figure 67 Stakeholder vs. Activity Catering - Broadcasting 253
Figure 68 Stakeholder vs. Activity Stadium Hospitality 255
Figure 69 Stakeholder vs. Activity Stadium Entertainment 257
Figure 70 Stakeholder vs. Activity Television Broadcasting - In-House 259
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
9/359
TABLE OF FIGURES
Figure 71 Stakeholder vs. Activity Television Broadcasting - Vendor 261
Figure 72 Stakeholder vs. Activity Player Security 263
Figure 73 Stakeholder vs. Activity Umpiring 265
Figure 74 Stakeholder vs. Activity Anti-Doping/Anti-Corruption 267
Figure 75 Stakeholder vs. Activity Emergency Training 269
Figure 76 Stakeholder vs. Activity Stadium Office 271
Figure 77 Stakeholder vs. Activity - Stadium Advertising (LED) 273
Figure 78 Stakeholder vs. Activity Stadium Security 276
Figure 79 Stakeholder vs. Activity Stadium Utilities 278
Figure 80 Stakeholder vs. Activity Ground Maintenance 280
Figure 81 Stakeholder vs. Activity Catering - State Assoc. 282
Figure 82 Stakeholder vs. Activity Stadium Housekeeping 284
Figure 83 Stakeholder vs. Activity Franchise - Head Office 286
Figure 84 Stakeholder vs. Activity Franchise - Hospitality & Travel 288
Figure 85 Stakeholder vs. Activity Franchise - Merchandizing 290
Figure 86 Stakeholder vs. Activity Franchise - Sponsors 292
Figure 87 Stakeholder vs. Activity Franchise - Cheerleaders 294
Figure 88 Stakeholder vs. Activity Beverage Contractor - Soft Drinks 296
Figure 89 Stakeholder vs. Activity Beverage Contractor - Alcoholic Bev. 298
Figure 90 Venue vs. Activity Ahmedabad 300
Figure 91 Venue vs. Activity Bangalore 302
Figure 92 Venue vs. Activity Chennai 304
Figure 93 Venue vs. Activity Cuttack 306
Figure 94 Venue vs. Activity Delhi 308
Figure 95 Venue vs. Activity Dharamsala 310
Figure 96 Venue vs. Activity Jaipur 312
Figure 97 Venue vs. Activity Kolkata 314
Figure 98 Venue vs. Activity Mohali 316
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
10/359
TABLE OF FIGURES
Figure 99 Venue vs. Activity Mumbai (Brabourne) 318
Figure 100 Venue vs. Activity Navi Mumbai 320
Figure 101 Venue vs. Activity Nagpur 322
Figure 102 Spectator Travel Modal Split Ahmedabad (%-spectator basis) 323
Figure 103 Spectator Travel Modal Split Ahmedabad (kms basis) 324
Figure 104 Spectator Travel Modal Split Bangalore (%-spectator basis) 325
Figure 105 Spectator Travel Modal Split Bangalore (kms basis) 326
Figure 106 Spectator Travel Modal Split Chennai (%-spectator basis) 227
Figure 107 Spectator Travel Modal Split Chennai (kms basis) 228
Figure 108 Spectator Travel Modal Split Cuttack (%-spectator basis) 229
Figure 109 Spectator Travel Modal Split Cuttack (kms basis) 230
Figure 110 Spectator Travel Modal Split Delhi (%-spectator basis) 231
Figure 111 Spectator Travel Modal Split Delhi (kms basis) 232
Figure 112 Spectator Travel Modal Split Dharamsala (%-spectator basis) 233
Figure 113 Spectator Travel Modal Split Dharamsala (kms basis) 234
Figure 114 Spectator Travel Modal Split Jaipur (%-spectator basis) 235
Figure 115 Spectator Travel Modal Split Jaipur (kms basis) 236
Figure 116 Spectator Travel Modal Split Kolkata (%-spectator basis) 237
Figure 117 Spectator Travel Modal Split Kolkata (kms basis) 238
Figure 118 Spectator Travel Modal Split Mohali (%-spectator basis) 239
Figure 119 Spectator Travel Modal Split Mohali (kms basis) 240
Figure 120 Spectator Travel Modal Split Mumbai (Brabourne) (%-spectator basis) 241
Figure 121 Spectator Travel Modal Split Mumbai (Brabourne) (kms basis) 242
Figure 122 Spectator Travel Modal Split Navi Mumbai (%-spectator basis) 243
Figure 123 Spectator Travel Modal Split Navi Mumbai (kms basis) 244
Figure 124 Spectator Travel Modal Split Nagpur (%-spectator basis) 245
Figure 125 Spectator Travel Modal Split Nagpur (kms basis) 246
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
11/359
LIST OF TABLES
Table 1 Activity Boundary Summary 32
Table 2 Stakeholder Boundary Summary 34
Table 3 Emission Factor LCA Status 38
Table 4 Activity Central/Local Source Classification 42
Table 5 Stakeholder Central/Local Source Classification 43
Table 6 Stakeholder Activity Data Inventory Period 45
Table 7 DLF IPL 2010 Tournament Match Schedule 47
Table 8 Tournament Stadium Spectator Plan 54
Table 9 Tournament Team Travel Plan 57
Table 10 Resource / Activity Tagging 61
Table 11 Activity Data Extrapolation IPL/IMG Data 71
Table 12 Stadium Construction Carbon Footprint Research and Analysis Summary 74
Table 13 DLF IPL 2010 Resource Consumption Inventory 85
Table 14 DLF IPL 2010 Activity-Differentiated Total Carbon Footprint 88
Table 15 DLF IPL 2010 Stakeholder-Differentiated Total Carbon Footprint 93
Table 16 Stakeholder vs. Activity Stadium Construction (Annual Carbon Footprint) 100
Table 17 TV Spectator Carbon Footprint Analysis 104
Table 18 Television viewership IPLvs. Non-IPL period 105
Table 19 Stakeholder vs. Activity Stadium Spectators 106
Table 20 DLF IPL 2010 Venue Carbon Footprint Summary 111
Table 21 Venue vs. Activity Average Stadium 115
Table 22 Venue vs. Activity All Stadium Summary (Tournament Totals) 120
Table 23 Venue vs. Activity All Stadium Summary (per Match) 121
Table 24 Venue vs. Activity All Stadium Summary (per Unit Served) 122
Table 25 Day vs. Night Match Activity Data Analysis 150
Table 26 IPL and other Global Sporting events Comparison with UEFA EURO 2008 165
Table 27 Activity vs. Stakeholder - Fuel - Cooking Fuel 204
Table 28 Activity vs. Stakeholder - Fuel Generator & Motor Fuel 206
Table 29 Activity vs. Stakeholder - Fuel - Fireworks & Other Fuel 208
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
12/359
LIST OF TABLES
Table 30 Activity vs. Stakeholder - Electricity 209
Table 31 Activity vs. Stakeholder - Water 211
Table 32 Activity vs. Stakeholder - Domestic Air Travel 213
Table 33 Activity vs. Stakeholder - International Air Travel 215
Table 34 Activity vs. Stakeholder - Public Road & Rail Travel 217
Table 35 Activity vs. Stakeholder - Private Vehicular Travel 218
Table 36 Activity vs. Stakeholder - Logistics 220
Table 37 Activity vs. Stakeholder - Luxury Hotel Accomodation 222
Table 38 Activity vs. Stakeholder - Meat & Seafood 224
Table 39 Activity vs. Stakeholder - Dairy 226
Table 40 Activity vs. Stakeholder - Rice 228
Table 41 Activity vs. Stakeholder - Alcoholic Beverages 230
Table 42 Activity vs. Stakeholder - Bottled Water / Drinks 232
Table 43 Activity vs. Stakeholder - Solid Waste 234
Table 44 Activity vs. Stakeholder - Paper & Cardboard 236
Table 45 Activity vs. Stakeholder - Plastic 238
Table 46 Activity vs. Stakeholder - Fertilizers & Pesticide 240
Table 47 Stakeholder vs. Activity IPL/IMG Head Office 241
Table 48 Stakeholder vs. Activity -IPL/IMG Hospitality & Travel 243
Table 49 Stakeholder vs. Activity IPL/IMG Merchandizing 245
Table 50 Stakeholder vs. Activity IPL/IMG Sponsors 246
Table 51 Stakeholder vs. Activity Catering - Concessions 248
Table 52 Stakeholder vs. Activity Catering - VIP 250
Table 53 Stakeholder vs. Activity Catering - Broadcasting 252
Table 54 Stakeholder vs. Activity Stadium Hospitality 254
Table 55 Stakeholder vs. Activity Stadium Entertainment 256
Table 56 Stakeholder vs. Activity Television Broadcasting - In-House 258
Table 57 Stakeholder vs. Activity Television Broadcasting - Vendor 260
Table 58 Stakeholder vs. Activity Player Security 262
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
13/359
LIST OF TABLESTable 59 Stakeholder vs. Activity Umpiring 264
Table 60 Stakeholder vs. Activity Anti-Doping/Anti-Corruption 266
Table 61 Stakeholder vs. Activity Emergency Training 268
Table 62 Stakeholder vs. Activity Stadium Office 270
Table 63 Stakeholder vs. Activity - Stadium Advertising (LED) 272
Table 64 Stakeholder vs. Activity Stadium Advertising (Flex Signage) 274
Table 65 Stakeholder vs. Activity Stadium Security 275
Table 66 Stakeholder vs. Activity Stadium Utilities 277
Table 67 Stakeholder vs. Activity Ground Maintenance 279
Table 68 Stakeholder vs. Activity Catering - State Assoc. 281
Table 69 Stakeholder vs. Activity Stadium Housekeeping 283
Table 70 Stakeholder vs. Activity Franchise - Head Office 285
Table 71 Stakeholder vs. Activity Franchise - Hospitality & Travel 287
Table 72 Stakeholder vs. Activity Franchise - Merchandizing 289
Table 73 Stakeholder vs. Activity Franchise - Sponsors 291
Table 74 Stakeholder vs. Activity Franchise - Cheerleaders 293
Table 75 Stakeholder vs. Activity Beverage Contractor - Soft Drinks 295
Table 76 Stakeholder vs. Activity Beverage Contractor - Alcoholic Bev. 297
Table 77 Venue vs. Activity Ahmedabad 299
Table 78 Venue vs. Activity Bangalore 301
Table 79 Venue vs. Activity Chennai 303
Table 80 Venue vs. Activity Cuttack 305
Table 81 Venue vs. Activity Delhi 307
Table 82 Venue vs. Activity Dharamsala 309
Table 83 Venue vs. Activity Jaipur 311Table 84 Venue vs. Activity Kolkata 313
Table 85 Venue vs. Activity Mohali 315
Table 86 Venue vs. Activity Mumbai (Brabourne) 317
Table 87 Venue vs. Activity Navi Mumbai 319
Table 88 Venue vs. Activity Nagpur 321
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
14/359
LIST OF APPENDICES
APPENDIX A 192
APPENDIX B 196
DLF I
APPENDIX C 198
APPENDIX D 203
APPENDIX E 347
FIREWORKS & PYROTECHNICS AIR QUALITY AND HEALTH IMPACTS STUDIES 348
APPENDIX F 351
APPENDIX G 354
APPENDIX H 358
GHG EMISSION FACTORS 193
PL 2010 PRE-EVENT CARBON FOOTPRINT ESTIMATE 197
ROYAL CHALLENGERS BANGALORE FRANCHISE ACTIVITY DATA
PROVIDED BY: NEXTGEN PMS (BANGALORE, INDIA) 199
DLF IPL 2010 CARBON FOOTPRINT ANALYSIS - TABLES AND FIGURES 203
RCB-NEXTGEN PMS 352
CARBON FOOTPRINT MITIGATION
IPL GREENING PROGRAM UNEP RECOMMENDATIONS 355
- PREPARED BY DR. HARTMUT STAHL
IPL GREENING PROGRAM - INDICATIVE ROADMAP 359
PROGRAMME FOR IPL 2010
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
15/359
1.0 EXECUTIVE SUMMARY
Executive Summary
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emiss ions (ECE) Pvt.Ltd. 1
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
16/359
Eliminate Carbon Emissions (ECE) Pvt. Ltd was contracted by the IPL
Management upon the recommendation of the United Nations
Environment Program (UNEP) to calculate their Annual Carbon
Footprint (i.e. an inventory of the total Greenhouse Gas Emissions -
GHGs-that contribute to Climate Change, resulting from direct and
indirect resource consumption through DLF IPL 2010s annual
operations).
The Total Carbon Footprint of DLF IPL 2010 was estimated to be
42,264 tons CO2e. DLF IPL 2010s Carbon Footprint can be thought of
as requiring 169,055 trees to neutralise its impact on Climate Change
over a period of 20 years. This equates to approximately 2,818 trees
per match.
The following activities comprise its Carbon Footprint, in order of
decreasing magnitude: Travel and Logistics (18,073 tons CO2e -
42.8%), Stadium Construction (9,932 tons CO2e - 23.5%), Luxury
Hotel Accommodation (9,927 tons CO2e - 23.5%) , Food, Beverage,
and Waste (1,201 tons CO2e - 2.8%) and Electricity (996 tons CO2e -
2.4%).
Relative Stakeholder contributions to the DLF IPL 2010 Carbon
Footprint are: IPL/IMG Operations (9,861 tons CO2e - 23%), State
Association Operations (12,861 tons CO2e - 30%), Franchise
Operations (5,243 tons CO2e - 12%), Spectator Activities (14,300 tons
CO2e - 35%).
A majority of the Carbon Footprint of DLF IPL 2010 is the consequence
of activities related to its contractors while only 23% of the footprint is adirect consequence of direct IPL/IMG managed operations. It is
imperative that footprint mitigation strategies account for this aspect of
footprint distribution.
Spectators are the most significant Stakeholders in terms of
contribution to Total Carbon Footprint. Private Vehicular Travel is the
single largest contributing factor responsible for 6,517 tons CO2e
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.16
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
17/359
(45%) of Stadium Spectator Carbon Footprint. It is imperative to
address this disproportionately heavy reliance on Private Transport
consumed for Spectator Travel when addressing the overall IPL
Carbon Footprint.
TV viewership related Carbon Footprint for DLF IPL 2010 was
358,039 tons CO2e and far outweighed the contributions of any other
stakeholder or activity considered within the IPL Carbon Footprint
Boundary. This component of Carbon Footprint, and its root cause -
large quantity of consumption of electricity through TV sets, needs to
be addressed with greater emphasis on its analysis and mitigation
through innovative strategies and interventions in future editions of
the IPL
The impact of Stadium Construction, one of the primary activities
contributing significantly to the IPL footprint, needs to be mitigated by
intervening and exploiting opportunities to infuse Low-Carbon and
Green Architecture and Construction practices as the cornerstone of
future stadium construction activities at proposed stadiums that are
intended for use by the IPL.
Best practice examples for a majority of Stakeholder functions within
the IPL have been identified, quantified, and the initial feasibility
assessed. Best practice benchmark replication across the IPL must
be pursued as a potent and actionable strategy for optimizing the
Carbon Footprint of the IPL prior to any resource and capital-intensive
Carbon Footprint Minimisation strategies.
All interventions must be accompanied by effective communication toall internal and external stakeholders. They must also be in
consonance with a well thought-out Greening Strategy, that aims not
just at a Carbon Neutral IPL, but sets itself the loftier target of an IPL
that is a net Carbon Sink (an indicative roadmap is presented in
Appendix H).
Best Practice Incentivisation through formal programs and its
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 1
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
18/359
incorporation into contractual negotiations processes with all vendors,
contractors and other relevant Stakeholders is ascertained to be most
feasible first step on the pathway to drastically reducing the Carbon
Footprint of IPL in the forthcoming seasons. Central IPL support and
nurturing of competitive franchise behavior through formal
recognition of the Lowest Carbon Footprint or Greenest Franchise is
one illustrative example that may be expanded to envelop all aspects
of IPL operations in future editions.
It is abundantly clear that noise levels at match venues needs to becurbed significantly during future editions of IPL to ensure that basic
national environmental laws are not violated. During DLF IPL 2010,
noise levels at matches were measured and found to violate national
noise pollution norms by significant levels.
The Carbon Footprint determined as part of this project phase does
not account for the entire life-cycle of the resources consumed and
their comprehensive impact on Climate Change and ecology.
Accounting for resource acquisition, processing and disposal impacts
could magnify the current extent manifold. A life-cycle analysis (LCA)
of all primary resources consumed is essential to ascertain a morecomprehensive Carbon Footprint that tends towards the true Climate
Change impact of IPL. It is recommended that IPL 2011 be assessed
on a LCA basis and that preparatory work for an LCA study be
commissioned as part of the next phase of the project.
It is recommended that IPL commission ECE to commence a
comprehensive Carbon Footprint Minimization analysis as part of a
Long-Term Greening Program (in fulfillment of its MOU with the
UNEPs Sports and Environment Unit) to identify means and
alternatives for optimising and minimising its resource intensiveness.
Prior to minimising and offsetting the impact of future IPLs, it is
recommended that IPL commit to neutralise the impact of, as
minimum, the four knock-out phase matches of DLF IPL 2010
(estimated to be 3,148 tons). While multiple options for offsetting are
available in the conventional Carbon Offset market, the alternatives
that result in equitable distribution of benefits to the grassroot
Stakeholder communities who are imperative to the projects
implementation are preferred as a more potent agent of social and
environmental transformation. In the context of the prior
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.18
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
19/359
Introduction
IPL Greening Program
DLF IPL 2010 REALISE Project Report
2.0 INTRODUCTION
Eliminate Carbon Emiss ions (ECE) Pvt.Ltd. 1
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
20/359
The Indian Premier League (IPL) is an annual, franchise-based
Twenty20 Cricket tournament under the aegis of the Board of Control
of Cricket in India (BCCI). First held in 2008, IPL features many of the
World's best cricketers playing for eight city-based franchises, owned
by some of the most well-recognised individuals/ brands in India.
Since its inception, IPLs engaging game format, accompanied by its
innovative marketing strategies, has captured the imagination of
spectators and audiences not just in India and the other cricket-playingnations, but across the entire World. IPL today is looked upon and
admired for the standards it has set in the Sporting and Entertainment
arena.
United Nations Environment Program (UNEP) is the designated
authority of the United Nations on environmental issues at the global
and regional level. With a stated mission of aiming to provide
leadership and encouraging partnership in caring for the environment
by inspiring, informing, and enabling nations and people to improve
their quality of life without compromising that of future generations,
UNEPs activities cover a wide range of issues involving the
environment and the diverse ecosystems comprising it. UNEP plays
a key role in developing international environmental conventions,
promoting environmental science, working on the development and
implementation of policy with national governments and regional
institution, and working with environmental Non-Governmental
Organizations (NGOs). UNEP has also been the forefront of guiding
the growing consideration for environment in the world of sports, and
has been advising Sporting events since the 1994 Winter Olympics inLillehammer, Norway
Eliminate Carbon Emissions Pvt. Ltd. (ECE) and the no2co2 Project
were born from the conviction that the primary responsibility for
reversing the effects of Climate Change rests not with the
Government, the Industry and the Policymakers, but with us as
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.20
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
21/359
members of the societies we live in, the businesses we are part of and
as individual consumers. ECEs intervention approach follows the
elegantly simple steps of REALISE, MINIMISE and NEUTRALISE.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 2
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
22/359
The scientific community around the World has accepted the reality of
Climate Change. That it IS happening and it IS the result of
anthropogenic activities is no longer a matter of speculation. As the
warming and the melting, and the positive feedback loop connecting
them gathers momentum, the uncertainty is only about how much time
we have left to slow down, and perhaps reverse, some of the effects of
Climate Change.
As the international community comprising the developed countries,
the newly emerging economies and the under-developed countries
are locked in a stalemate over how much to commit, individual
governments and industries including those in our own country -
have started taking steps aimed at Carbon Footprint control and
mitigation. The Sports arena worldwide is also moving towards
according a high priority to Environmental considerations. The
Olympic Movement, for instance, has incorporated the environment
into its charter, alongside sport and culture. Starting with the Winter
Olympics in 1994, major sporting events around the World all the
subsequent Olympics, the just-concluded FIFA World Cup 2010 and
the Commonwealth Games 2010 - have moved towards including
environmental measures as part of their basic mandates.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.22
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
23/359
In January 2010, IPL announced its vision of green growth in
partnership with UNEP. As part of this program, IPL will green its
cricket league and bring environmental awareness to millions of
cricket fans around the world in a first-of-its-kind initiative undertaken
by any sporting body in India. UNEP will advise IPL in its commitment
to green its sport events, spread environmental messaging to fans
through its star players and green its merchandising. IPL
Management embarked upon this unprecedented approach towardsachieving total environmental accountability motivated by personal
conviction about the reality of Climate Change and its direct
relationship with resource consumption of economic enterprises. IPL
also recognized its esteemed position as a best-practice leader in the
Sports and Live Entertainment Business in India and clearly
recognized the immense leveraging possibilities available to it to
infuse climate change consciousness into its broad customer,
contractor and vendor base. IPL could, therefore, engage with the
global Climate Change solutions movement as a Climate Changesolutions leader, inspiring a vast network of stakeholders to recognize
their potential as individual Climate Change solvers.
The first steps in IPLs Greening roadmap involved using the DLF IPL
2010 as a forum for disseminating messages regarding environmental
consciousness, and the calculation of the Carbon Footprint of DLF
IPL2010.
UNEPs Outreach Unit Division of Communications and Public
Information (DCPI) designed the environmental communication
strategy for IPL2010, and also guided IPL in the selection of the agency
to calculate the Carbon Footprint of DLF IPL 2010. Based on UNEPs
recommendation, ECE was contracted by IPL to carry out the
measurement of DLF IPL 2010 Carbon Footprint.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 2
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
24/359
ECE, through the Realise and Minimise activities of the project,
endeavors to demonstrate the fallacy of the commonly espoused
perception that environmental responsibility and business profitability
are conflicting considerations that require pursuit of disparate decision
making pathways. Thus, drawing up the broad roadmap to continued
delivery of excellent customer experience, identifying cost reduction
avenues emerging from resource conservation practices, while
minimising climate change impact was one of the key objectives of theproject.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.24
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
25/359
This report details the first phase i.e. Realise, of the three-phase
project comprising of Carbon Footprint Calculation (Realise), Carbon
Footprint Minimisation (Minimise) and Carbon Footprint
Neutralisation (Neutralise). Pre-Tournament Carbon Footprint
Estimation (presented in Appendix B) commenced in February 2010
subsequently followed by the final Carbon Footprint Activity data
gathering research process commencing in March 2010. The time-
period of analysis chosen was the entire annual IPL planning,execution and hosting cycle from May 2009 (End of IPL 2) to April 2010
(End of IPL 3).
Given that one of the main objectives of this Report is to document the
analytical and research procedures and methodologies, so that the
document can stand up to scientific scrutiny, it is inevitable that parts of
the Report are technical in nature. However, all efforts have been
made to ensure that the contents of the Report are well within the
scope of understanding of any informed, interested reader, and it can
serve as a basis to stimulate discussion and encourage actions.
Eliminate Carbon Emissions (ECE) Pvt.Ltd.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
2
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
26/359
Project Goals
IPL Greening Program
DLF IPL 2010 REALISE Project Report
3.0 PROJECT GOALS
Eliminate Carbon Emiss ions (ECE) Pvt.Ltd.26
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
27/359
The goals of the Realise phase of the project were to determine, with
the greatest possible degree of accuracy, the following for DLF IPL
2010:
1. Total Annual and Activity-Differentiated resource consumption
inventory.
2. Total Annual Carbon Footprint
3. Activity-Differentiated Annual Carbon Footprint
4. Stakeholder-Differentiated Annual Carbon Footprint.
5. Match Venue-Differentiated Annual Carbon Footprint.6. Carbon Emissions Intensity of Stakeholder Operations.
7. Best Practice Identification amongst Stakeholder Operations.
8. Contextualization of Total Carbon Footprint and Carbon Emissions
Intensity of Stakeholder Operations.
The collective analysis of the above aspects of IPL operation would
represent the GHG Emissions Baseline for IPL, against which future
efforts would be benchmarked for assessing the magnitude and
impact of measurable and verifiable Carbon Footprint mitigation
measures.
Since the above could only be achieved following a comprehensive
dissection of the resource process flow delineating the resource-
based interactions of various stakeholders, a comprehensive
Stakeholder Activity and Interaction Mapping was also identified and
pursued as an added benefit for IPL. It is intended that the resulting
process flow chart be utilized for the optimization of IPLs tournament
planning operations by illustrating key intervention areas for adopting
resource conservation measures.
Finally, the aggregate and dissected Carbon Footprints were to beunderstood and explained in the context of easily understandable
terms (i.e. commonly understood units of Climate Change impacts) to
provide perspective that serves to inspire and define actions towards
participative (i.e. involving all Stakeholders) mitigation of IPLs impact
on Climate Change through footprint minimisation.
Results of the above research and analysis were intended to serve as
a diagnostic tool to lay down a rational, prioritized roadmap for Carbon
Footprint and Resource consumption Minimisation without hindering
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 2
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
28/359
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.28
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
29/359
Boundaries for the Carbon Footprint Calculation process were defined
in consultation with UNEP and IPL/IMG Management. Defining
boundaries involved two key-decision making areas:
1. Activities to be included (i.e. defining a comprehensive yet
manageable set of resources whose consumption was to be
inventoried), and,
2. Stakeholders to be considered (i.e. defining which sets of
peoples/groups/functions are to be included within the footprint
boundary).
Since Carbon Footprint Reporting for businesses in India is not
mandated by the Indian Government, nor by the United Nations
Framework Convention for Climate Change (UNFCCC), and IPLs
initiative to address its Climate Change Impacts are purely voluntary,
no set of pre-established guidelines were required to be followed for
boundary definition. In the absence of explicit guidelines for GHG
Emission Reporting for Indian Businesses, the globally acceptedmethodologies for National GHG Emissions Reporting (adopted by
India as part of the Kyoto Protocol) laid down by the IPCC (Inter-
Governmental Panel on Climate Change) as part of the 2006
Guidelines were used for guidance wherever appropriate. However,
given the unique nature of this project and the niche operational
activity of IPL, the overall methodology reflects a confluence of
standard protocols and business-appropriate approaches which
would provide an accurate estimate of its Climate Change Impact.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 2
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
30/359
In order for Carbon Footprint calculation to be considered
comprehensive it is essential to include all activities that impact it.
However, it would render the entire exercise impossible to complete in
a finite time frame if every activity were to be included within the scope
of the Project. The twin goals of comprehensiveness and
manageability are achieved be defining activities known as Key
Source Categories and analyzing them comprehensively while paying
lesser attention to those outside that framework. Key SourceCategories categories are defined as those whose collective
contribution account for 95% of the total footprint (when added
incrementally in the order of decreasing contribution). It is evident that
technically Key Source Categories can therefore only be determined
following the completion of the Carbon Footprint calculation thereby
defeating its utility as a guiding principle for defining activity boundary.
However, irrespective of the anthropogenic or business activity being
analyzed, certain categories of activities can safely be presumed as
being Key Source Categories. Beyond these, others need to beidentified based on rational considerations related to the specific
nature of the business and following a detailed understanding of its
operations. This process yielded the following activities as comprising
the activity domain for IPLs Carbon Footprint calculation:
Contributing Directly to Carbon Footprint
activities where direct control can be exercised over the magnitude
of activity AND the emission coefficient through technological
choices.
Contributing Indirectly to Carbon Footprint -
activities where direct control can be exercised over the magnitude
of activity BUT NOT the emission coefficient through technological
choices.
Contributing Indirectly to Carbon Footprint -
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.30
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
31/359
activities where direct control can NEITHER be exercised over the
magnitude of activity NOR the emission coefficient through
technological choices.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 3
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
32/359
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.32
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
33/359
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 3
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
34/359
Stakeholders are defined as those groups of persons, service
providers, beneficiaries, customers etc. that directly or indirectly
participate in Carbon Footprint creation activities of a organization. As
in the case of activity boundaries, this list too is technically nearly
infinite since the indirect contributors to an organizations footprint is
an unbounded set of groups engaged in enterprise all across the
globe. Since voluntary Carbon Footprint calculation and emission
inventorying falls outside the domain of any internationally bindingIPCC guidelines, Stakeholder Boundary is determined through
consultation with the Client. While accountability for those entities
directly part of its own operations is the cornerstone of the exercise,
organizations are at liberty to select some operations that are outside
their direct control but are logically connected to, or are natural
extensions of their direct operations. The outcome of these
discussions with UNEP and IPL/IMG Management is the Stakeholder
Boundary presented in the table below
Table 2Stakeholder Boundary Summary
Stakeholder NameID
Stakeholder NameID
Group 1
Sub-Entity 1.01
Sub-Entity 1.02
Sub-Entity 1.03
Sub-Entity 1.04
Sub-Entity 1.05
Sub-Entity 1.06
Sub-Entity 1.07
Sub-Entity 1.08
IPL/IMG
Head Office
Hospitality & Travel
Merchandizing
Sponsors
Catering - Concessions
Catering - VIP
Catering - Broadcasting
Stadium Hospitality
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.34
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
35/359
Sub-Entity 1.09
Sub-Entity 1.10
Sub-Entity 1.11
Sub-Entity 1.12
Sub-Entity 1.13
Sub-Entity 1.14
Sub-Entity 1.15Sub-Entity 1.16
Sub-Entity 1.17
Sub-Entity 1.18
Group 2
Sub-Entity 2.01
Sub-Entity 2.02
Sub-Entity 2.03
Sub-Entity 2.04
Sub-Entity 2.05
Sub-Entity 2.06
Group 3
Sub-Entity 3.01
Sub-Entity 3.02
Stadium Entertainment
Television Broadcasting - In-House
Television Broadcasting - Vendor
Player Security
Umpiring
Anti-Doping/Anti-Corruption
Emergency TrainingStadium Office
Stadium Advertising (LED)
Stadium Advertising (Flex Signage)
State Associations
Stadium Security
Utilities
Ground Maintenance
Catering - State Assoc.
Housekeeping
Stadium Construction
Franchises
Franchise - Head Office
Franchise - Hospitality & Travel
Table 2Stakeholder Boundary Summary
Stakeholder NameID
Sub-Entity 3.03
Sub-Entity 3.04
Sub-Entity 3.05
Sub-Entity 3.06
Sub-Entity 3.07
Group 4
Sub-Entity 4.01
Sub-Entity 4.02
Sub-Entity 4.03
Franchise - Merchandizing
Franchise - Sponsors
Cheerleaders
Beverage Contractor - Soft Drinks
Beverage Contractor - Alcoholic Bev.
Spectators
Stadium Spectators
TV Spectators
Internet
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 3
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
36/359
Carbon Footprint is essentially the product of multiplying activity data
with GHG Emissions Factors (EFs). Emission Factors are indicative of
the quantity of GHGs emitted per unit of activity. As an illustration, an
EF of 1 kgCO2e per kWh of electricity indicates that
generation/consumption of 1 unit of electricity (i.e. 1 kWh) causes the
emissions of 1 kg of Carbon Dioxide Equivalents. It must be
emphasized that these are indicative since the true EF for any activity
is technically unbounded; the reasoning for this is identical to therationale provided in relation to the infinite nature of Activity and
Stakeholder Impacts on Carbon Footprint. As an activitys EFs are
investigated further back into its life-cycle to include, beyond primary
influences, secondary and tertiary impacts, the mathematical
magnitude of the EF increases, albeit to a gradually diminishing
degree. Revisiting the example of electricity emission factors, the
value of 1 kgCO2e/kWh would increase if analysis boundaries were
expanded beyond the impacts of direct combustion of coal, diesel and
other fossil fuels used for power generation to then include the energyexpenditure to mine the fossil fuels. Its magnitude would further
increase if the analysis boundary were radially extended to envelop
the resource and energy consumption to create the capital goods
(machinery, factories etc.) required to harness these natural
resources. This expansion can be understood as penetrating deeper
into the life-cycle of a product or service. Concisely stated, EF
magnitudes are a dynamic function of the extent of life-cycle impacts
selected for analysis in relation to the manufacturing process involved
in creation of goods and services for human consumption.
Any Carbon Footprint analysis, so greatly dependent on the
mathematical magnitude of EFs chosen, is therefore, by induction, a
function of EF life-cycle analysis (LCA); selecting only primary aspects
of LCA (such as direct emissions of fossil fuels) yields lower values of
EFs while a more extensive LCA magnifies the impacts of the same
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.36
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
37/359
activity and leads to a more conservative Carbon Footprint; a footprint
that tends towards the true Carbon Footprint of an activity. The
following table presents the extent of LCA incorporated into the
Emission Factors selected for the IPL Carbon Footprint calculation.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 3
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
38/359
Emission Factor StatusActivity TypeNo.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
Cooking Fuel
Generator Fuel
Petrol
Fireworks
Fuel Oil (Aerosol)
Vehicular Travel - 2 Wheeler
Vehicular Travel - 4 Wheeler
Vehicular Travel - HMV
Electricity
Water
International Air Travel
Domestic Air Travel
Rail Travel Local
Rail Travel - Long Distance
Bus Travel Local
Bus Travel - Long Distance
Taxi Travel
Autorickshaw Travel
Meat
Seafood
Dairy
Alcoholic Beverages
Bottled Water / Drinks
Waste Generation
Paper
Plastic
Fertilizer
Pesticides
Luxury Hotel
Concrete
Steel
Brick
Plywood
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion, Electricity
Direct Combustion, Electricity
Direct Combustion
Direct Combustion
Direct Combustion
Direct Combustion
Partial LCA
Partial LCA
Partial LCA
Partial LCA
Partial LCA
Partial LCA
LCA
LCA
LCA
LCA
Direct Combustion, Electricity
Partial LCA
Partial LCA
Partial LCA
Partial LCA
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.38
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
39/359
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 3
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
40/359
The research methodology followed for the project centered on the
idea of dissecting the organizations operations and disaggregating
consumption of resources to understand the consumption patterns
ground-up. While this approach was more time-consuming, as
opposed to tracking all activities through a centralized approach, it
helped construct a detailed footprint-map that would be invaluable as
an analysis tool to identify stakeholder contributions to overall
footprint. The research methodology can be largely defined throughthe following components:
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.40
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
41/359
The activities listed in Table 1, and by association, the stakeholder
listed in Table 2 which undertook those activities, were divided
amongst two sub-groups; Central and Local Footprint Activities and by
extension Central and Local Footprint Stakeholders. The
distinguishing factor used for this classification was the primary
physical domain where these activities were conducted by respective
stakeholders and extent of impact on actual match day operations.
This classification was identified as crucial to truly differentiate
activities that primarily affect a particular match-day operation (and
hence eligible as a candidate for best-practice identification), versus
those that impact the entire IPL planning and execution process and
cannot be attributed to any single match venue. As illustration: while
air travel by various executives of match-day contractors such as
concessions caterers, stadium entertainment crew were added to the
respective stakeholders total carbon footprint wherein it was allocated
as a Central Footprint Source, it was excluded from the stakeholders
venue-specific footprint (and hence not used as a differentiator for
comparison with other stakeholders).
The following rules prevailed in classification of Central and Local
Footprint Source classification:
1) All air travel related activity across all stakeholders was attributed to
Central Footprint for a stakeholder.
2) All luxury hotel accommodation related activity across all
stakeholders was attributed to Central Footprint for a stakeholder.
3) All stadium construction related activity was attributed to Central
Footprint for the stakeholder.
4) All IPL/IMG Head Office related consumption was attributed to
Central Footprint.
5) All Franchise operations related consumption was attributed to
Central Footprint.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 4
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
42/359
Activity Type Activity GroupNo.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
Activity TypeClassificationCooking Fuel
Generator Fuel
Petrol
Fireworks
Fuel Oil (Aerosol)
Vehicular Travel - 2 Wheeler
Vehicular Travel - 4 Wheeler
Vehicular Travel - HMV
Electricity
Water
International Air Travel
Domestic Air Travel
Rail Travel - Local
Rail Travel - Long Distance
Bus Travel - Local
Bus Travel - Long Distance
Taxi Travel
Autorickshaw Travel
Meat
Seafood
Dairy
Alcoholic Beverages
Bottled Water / Drinks
Waste Generation
Paper
Plastic
Fertilizer
Pesticides
Luxury Hotel
Concrete
Steel
Brick
Plywood
Classification
Fuel
Fuel
Fuel
Flammables
Flammables
Travel
Travel
Logistics
Electricity
Water
Travel
Travel
Travel
Travel
Travel
Travel
Travel
Travel
F&B
F&B
F&B
F&B
F&B
Waste
Consumables
Consumables
Consumables
Consumables
Accommodation
Construction
Construction
Construction
Construction
Local
Local
Local
Local
Local
Local
Local
Local
Local
Local
Central
Central
Local
Local
Local
Local
Local
Local
Local
Local
Local
Local
Local
Local
Local
Local
Local
Local
Central
Central
Central
Central
Central
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.42
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
43/359
Stakeholder NameID
Group 1
Sub-Entity 1.01
Sub-Entity 1.02
Sub-Entity 1.03
Sub-Entity 1.04
Sub-Entity 1.05
Sub-Entity 1.06
Sub-Entity 1.07
Sub-Entity 1.08
Sub-Entity 1.09
Sub-Entity 1.10
Sub-Entity 1.11
Sub-Entity 1.12
Sub-Entity 1.13
Sub-Entity 1.14
Sub-Entity 1.15
Sub-Entity 1.16
Sub-Entity 1.17
Sub-Entity 1.18
Group 2
Sub-Entity 2.01
Sub-Entity 2.02
Sub-Entity 2.03
Sub-Entity 2.04
Sub-Entity 2.05
Sub-Entity 2.06
Group 3
Sub-Entity 3.01
Sub-Entity 3.02
Sub-Entity 3.03
Sub-Entity 3.04
Sub-Entity 3.05
Sub-Entity 3.06
Sub-Entity 3.07
Group 4
Sub-Entity 4.01
Sub-Entity 4.02
Sub-Entity 4.03
IPL/IMG
Head Office
Hospitality & Travel
Merchandizing
Sponsors
Catering - Concessions
Catering - VIP
Catering - Broadcasting
Stadium Hospitality
Stadium Entertainment
Television Broadcasting - In-House
Television Broadcasting - Vendor
Player Security
Umpiring
Anti-Doping/Anti-Corruption
Emergency Training
Stadium Office
Stadium Advertising (LED)
Stadium Advertising (Flex Signage)
State Associations
Stadium Security
Utilities
Ground Maintenance
Catering - State Assoc.
Housekeeping
Stadium Construction
Franchises
Franchise - Head Office
Franchise - Hospitality & Travel
Franchise - Merchandizing
Franchise - Sponsors
Cheerleaders
Beverage Contractor - Soft Drinks
Beverage Contractor - Alcoholic Bev.
Spectators
Stadium Spectators
TV Spectators
Internet
Classification
Central
Central
Central
Central
Local
Local
Local
Central
Local
Local
Local
Central
Central
Central
Central
Local
Local
Local
Central
Central
Central
Central
Central
Local
Local
Local
Local
Local
Local
Local
Central
Local
Central
Central
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 4
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
44/359
Group 4
Sub-Entity 4.01
Sub-Entity 4.02
Sub-Entity 4.03
Spectators
Stadium Spectators
TV Spectators
Internet
Local
Central
Central
Stakeholder NameID Classification
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.44
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
45/359
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
46/359
Group 2
Sub-Entity 2.01
Sub-Entity 2.02
Sub-Entity 2.03
Sub-Entity 2.04
Sub-Entity 2.05
Sub-Entity 2.06
Group 3
Sub-Entity 3.01
Sub-Entity 3.02
Sub-Entity 3.03
Sub-Entity 3.04
Sub-Entity 3.05
Sub-Entity 3.06
Sub-Entity 3.07
Group 4
Sub-Entity 4.01
Sub-Entity 4.02
Sub-Entity 4.03
State Associations
Stadium Security
Utilities
Ground Maintenance
Catering - State Assoc.
Housekeeping
Stadium Construction
Franchises
Franchise - Head Office
Franchise - Hospitality & Travel
Franchise - Merchandizing
Franchise - Sponsors
Cheerleaders
Beverage Contractor - Soft Drinks
Beverage Contractor - Alcoholic Bev.
Spectators
Stadium Spectators
TV Spectators
Internet
Annual
Annual
Annual
Tournament Duration
Tournament Duration
Tournament Duration
Tournament Duration
Tournament Duration
Tournament Duration
Annual
Tournament Duration
Tournament Duration
Lifetime
Tournament Duration
Tournament Duration
Tournament Duration
Table 6Stakeholder Activity Data Inventory Period
Stakeholder NameID Inventory Period
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.46
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
47/359
Activity data for Local Stakeholders under all groups was researched
by surveying one (1) match at each stadium employed during DLF IPL
2010. In the case of Brabourne Stadium (Mumbai), a Day and Night
Match were studied distinctly (except for Spectator Activity) to assess
the relative Carbon Footprint impact of the two match formats. The
table below presents the tournament schedule that was used for
identification of a representative match selected for on-field survey.
Table 7DLF IPL 2010 Tournament Match Schedule
1
2
3
4
56
7
8
9
10
11
12
13
14
15
1617
18
19
20
Fri, 12th March
Sat, 13th March
Sat, 13th March
Sun, 14th March
Sun, 14th MarchMon, 15th March
Tues, 16th March
Tues, 16th March
Wed, 17th March
Thurs, 18th March
Fri, 19th March
Fri, 19th March
Sat, 20th March
Sat, 20th March
Sun, 21st March
Sun, 21st MarchMon, 22nd March
Tues, 23rd March
Wed, 24th March
Thurs, 25th March
Navi Mumbai
Mumbai
Mohali
Kolkata
ChennaiAhmadabad
Bangalore
Kolkata
Delhi
Bengaluru
Delhi
Cuttack
Ahmadabad
Mumbai
Cuttack
ChennaiMumbai
Bengaluru
Mohali
Mumbai
Deccan Chargers
Mumbai Indians
Kings XI Punjab
Kolkata Knight Riders
Chennai Super KingsRajasthan Royals
Royal Challengers Bangalore
Kolkata Knight Riders
Delhi Daredevils
Royal Challengers Bangalore
Delhi Daredevils
Deccan Chargers
Rajasthan Royals
Mumbai Indians
Deccan Chargers
Chennai Super KingsMumbai Indians
Royal Challengers Bangalore
Kings XI Punjab
Mumbai Indians
vs
vs
vs
vs
vsvs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vsvs
vs
vs
vs
N
D
N
D
NN
D
N
N
N
D
N
D
N
D
NN
N
N
N
Kolkata Knight Riders
Rajasthan Royals
Delhi Daredevils
Royal Challengers Bangalore
Deccan ChargersDelhi Daredevils
Kings XI Punjab
Chennai Super Kings
Mumbai Indians
Rajasthan Royals
Chennai Super Kings
Kings XI Punjab
Kolkata Knight Riders
Royal Challengers Bangalore
Delhi Daredevils
Kings XI PunjabKolkata Knight Riders
Chennai Super Kings
Rajasthan Royals
Chennai Super Kings
Game
No.Date Venue Vs
Day/Night
MatchTeam 2Team 1
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 4
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
48/359
Table 7 (Contd.)DLF IPL 2010 Tournament Match Schedule
Game
No. Date Venue VsDay/Night
MatchTeam 2Team 1
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
Fri, 26th March
Sat, 27th March
Sat, 27th March
Sun, 28th March
Sun, 28th March
Mon, 29th March
Tues, 30th March
Wed, 31st March
Wed, 31st March
Thurs, 1st April
Fri, 2nd April
Sat, 3rd April
Sat, 3rd April
Sun, 4th April
Sun, 4th April
Mon, 5th April
Tues, 6th Apri l
Wed, 7th April
Wed, 7th April
Thurs, 8th April
Ahmadabad
Mohali
Bengaluru
Ahmadabad
Navi Mumbai
Delhi
Mumbai
Chennai
Delhi
Kolkata
Mohali
Chennai
Mumbai
Kolkata
Delhi
Nagpur
Chennai
Jaipur
Kolkata
Bengaluru
Rajasthan Royals
Kings XI Punjab
Royal Challengers Bangalore
Rajasthan Royals
Deccan Chargers
Delhi Daredevils
Mumbai Indians
Chennai Super Kings
Delhi Daredevils
Kolkata Knight Riders
Kings XI Punjab
Chennai Super Kings
Mumbai Indians
Kolkata Knight Riders
Delhi Daredevils
Deccan Chargers
Chennai Super Kings
Rajasthan Royals
Kolkata Knight Riders
Royal Challengers Bangalore
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
N
D
N
D
N
N
N
D
N
N
N
D
N
D
N
N
N
D
N
N
Deccan Chargers
Kolkata Knight Riders
Delhi Daredevils
Chennai Super Kings
Mumbai Indians
Kolkata Knight Riders
Kings XI Punjab
Royal Challengers Bangalore
Rajasthan Royals
Deccan Chargers
Royal Challengers Bangalore
Rajasthan Royals
Deccan Chargers
Kings XI Punjab
Royal Challengers Bangalore
Rajasthan Royals
Mumbai Indians
Kings XI Punjab
Delhi Daredevils
Deccan Chargers
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
Fri, 9th April
Sat, 10th April
Sat, 10th April
Sun, 11th April
Sun, 11th April
Mon, 12th April
Tues, 13th Apri l
Tues, 13th Apri l
Wed, 14th April
Thurs, 15th April
Fri, 16th April
Sat, 17th April
Sat, 17th April
Sun, 18th April
Sun, 18th April
Mon, 19th April
Wed, 21st April
Thurs, 22nd April
Sat, 24th April
Sun, 25th April
Mohali
Nagpur
Bengaluru
Delhi
Jaipur
Nagpur
Mumbai
Chennai
Jaipur
Chennai
Dharamsala
Bengaluru
Kolkata
Dharamsala
Delhi
Kolkata
Navi Mumbai
Navi Mumbai
Navi Mumbai
Navi Mumbai
Kings XI Punjab
Deccan Chargers
Royal Challengers Bangalore
Delhi Daredevils
Rajasthan Royals
Deccan Chargers
Mumbai Indians
Chennai Super Kings
Rajasthan Royals
Chennai Super Kings
Kings XI Punjab
Royal Challengers Bangalore
Kolkata Knight Riders
Kings XI Punjab
Delhi Daredevils
Kolkata Knight Riders
SF1
SF2
3rd Place
FINAL
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
vs
N
D
N
D
N
N
D
N
N
N
N
D
N
D
N
N
N
N
N
N
Mumbai Indians
Chennai Super Kings
Kolkata Knight Riders
Kings XI Punjab
Mumbai Indians
Royal Challengers Bangalore
Delhi Daredevils
Kolkata Knight Riders
Royal Challengers Bangalore
Delhi Daredevils
Deccan Chargers
Mumbai Indians
Rajasthan Royals
Chennai Super Kings
Deccan Chargers
Mumbai Indians
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.48
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
49/359
Activity data research for IPL/IMG Central Stakeholders was primarily
related to Air Travel and Luxury Hotel Accommodation. This data was
provided in raw form by Peter Griffiths of IMG Management and was
extracted from pre-event planning documents and records. Data for
other activities related to Annual IPL and IMG Offices was procured
through annual resource consumption records maintained by IPL/IMG
and obtained in electronic form through email correspondence with
IMG Management.
Activity data research for IPL/IMG Local Stakeholders was obtained
by means on on-site observation, measurement (for paper and plastic
consumables) and interviews with appropriate operational personnel
and executives. All data was collected by means of information
recorded in questionnaires developed prior to and refined following
pilot stadium walk-arounds conducted during the March 13, 2010 IPL
Match held at Mohali in conjunction with UNEP Programme Officer Dr.
Hartmut Stahl. Questionnaires used were designed to capture
relevant activity data divided amongst detailed activity types and sub-
types from the appropriate stakeholders involved in match operations.
Data not available through on-site investigation was procured post-
facto and obtained in electronic form through email correspondence
with relevant Management personnel representing Stakeholders.
Special attention was paid to all waste streams, waste management
practices and packaging/ancillary resources consumed in addition to
the apparent primary stakeholder activity. In certain instances related
to catering services, resource consumption off-site in preparation for
match-day operations was also researched and included in the
inventory. All unit items inventoried (counted in terms of pieces) were
converted to appropriate weights and volumes based on samples
collected during match-day operations and weighed off-site. Wherever
appropriate, relevant material densities were investigated through
technical literature research or telephonic vendor interviews.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 4
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
50/359
All data related to State Association Operations was primarily Local
data with the exception of Stadium Construction Activity Data. The
procedure followed for this Local data was identical to the process
used for IPL/IMG Local data sources.
Stadium Construction Activity Data was pursued for the following
stadiums: Eden Gardens (Kolkata), M.A. Chidambaram Stadium
(Chennai), VCA Stadium (Nagpur), PCA Cricket Stadium (Mohali), and
DY Patil Stadium (Navi Mumbai). These stadiums were selected for
construction activity research due to recent construction and/or
renovation dates for these stadiums ass opposed to the relatively old
age of other stadiums, for which construction data was either unlikely
to be available or be irrelevant owing to disparity between modern and
vintage construction techniques and materials. Data was obtained
directly in electronic form from Architects/Contractors engaged in the
construction/renovation projects. Specific Construction activity related
questionnaires for this research were employed for obtaining this
information.
Cricket Operations Research for all IPL stadiums (related to
ascertaining the average number of ODI, Test and Domestic Matches)
was conducted using Statsguru Research Filter Tool available at the
www.cricinfo.com website. Information obtained from this process was
used to determine the appropriate allocation percentage of year-round
ground maintenance related resource consumption to IPL matches
held at the venue as well as the appropriate per-IPL match allocation
for Stadium Construction related footprint (based on a average
stadium lifespan of 30 years).
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.50
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
51/359
Procedures and methods employed for IPL/IMG Central and Local
Stakeholders were also applied in all relevant cases for Franchise
Activity Data research.
Besides Air Travel and Luxury Hotel Accommodation data for
tournament-duration activity of Central Franchise Stakeholders
obtained from IMG Management team based on pre-event planning
documents and records, franchise specific data was sought for year-
round operation of Franchises directly through Franchise
Management teams. The goal was to expand the key-source category
inventory beyond tournament-duration operations to include year-
round activities which were expected to be of comparable or greater
magnitude and hence critical in nature. Additionally, pan-tournament
merchandizing data was researched through Merchandizing
contractors.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 5
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
52/359
A significant part of the emissions generated during the tournament
was anticipated to be caused directly through the travel to the stadia,
the consumption at the stadia, and the accommodation at Luxury
Hotels at match-venues, of the stadium spectators. To ensure an
exhaustive GHG Emissions Inventory of the IPL, it was imperative to
analyze the footprint of the spectators that physically attended the
various matches.
Methodology
A detailed, quantitative audience research was conducted to measure
the emission whose various elements are as under:
A sample size of between 0.75% and 1% of the overall
expected attendance was covered to ensure a statistically valid base
The sampling was a combination of two
methods:
: The total population was divided betweenvarious strata to evaluate the variation between the key segments.
The fundamental basis for stratification was the ticket price bands
as the behaviour of the sub-groups within each band was expected
to remain homogeneous.
A part of the total population was divided into
various clusters and samples were taken from within these defined
clusters to ensure that the overall stratified sampling is consistent
and there were no major variations within the strata selected,
especially since the tournament was held at multiple venues.
Within both the techniques, the respondents were chosen at random
to ensure no bias while conducting the research
The questionnaire was of the
close-ended, multiple choice type and administered by surveyors who
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.52
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
53/359
were specifically trained to record the various elements of information
required for the overall study. Each questionnaire was less than 12
questions and required approximately 3 minutes to record.
Spectator totals for matches and other information related to spectator
activity were also vital research elements for ascertaining the per unit
served Carbon Footprints for various Local Stakeholders. This
information was part of the process of establishing the Carbon
Emissions Intensity of various operations to gage and compare their
resource efficiencies.
The table below presents the Tournament Spectator projections made
prior to commencement of tournament that was used as a planning
tool for the Spectator and Stadium Activity Research effort.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 5
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
54/359
Table8
DLFIPL2010TournamentStadiumSpectatorPlan
No.
StadiumN
ame
City
Theoretical
Capacity
Actual
Capacity
Price
Level1
Price
Level2
Price
Level3
Price
Level4
Price
Lev
el5
Day
Matches
Night
Matches
Total
Matches
Attenda
nce
(DayMa
tch)
Attendance
(NightMatch)
Total
Spectators
1 2 3 4 5 6 7 8 9 10
11
12
SardarPatelGujratStadium
MChinnaswamyStadium
M.A.
ChidambaramStad.
BarabatiStadium
FerozShahKotlaGrounds
HPCACricketStadium
SawaiMansinghStadium
EdenGardensStadium
PCACricketStadium
BrabourneStadium
VCAStadium
DYPatilStadium
Totals
48,0
00
38,0
00
45,0
00
35,0
00
49,0
00
23,2
00
22,0
00
48,0
00
30,8
00
25,0
00
44,9
00
55,0
00
463,900
Ahmedabad
Banga
lore
Chen
nai
Cutta
ck
Delhi
Dharam
sala
Jaipur
Kolkata
Mohali
Mumbai
Nagp
ur
NaviMu
mbai
38,2
69
30,0
00
36,3
70
40,4
64
21,5
60
21,1
27
44,6
95
29,9
29
15,8
63
50,9
53
39,6
13
408,368
39,5
25
0-500
31,5
65
9,0
00
26,5
00
17,1
97
4,2
00
15,0
23
12,2
00
14,5
40
0 0
15,6
69
161,528
15,6
34
500-1000
6,2
04
8,4
00
19,3
93
14,5
00
5,1
24
14,8
01
5,4
39
3,6
27
34,8
43
13,5
16
13,4
86
139,332
1000-2000
1,8
00
7,9
00
4,7
50
0320
0
17,6
94
5,9
50
8,8
42
38,1
59
10,2
77
10,2
54
105,947
500
0+
0 3,9
00
1,6
70
3,8
74
1,0
40
50
0
0 1,4
20
1,4
63
01,6
68
1,6
65
17,200
2000-5000
500
800
3,4
50
01,8
20
480
08,5
30
9,1
27
5,3
92
3,6
22
3,6
13
37,334
(Assum
ed)
80%
80%
80%
80%
80%
80%
80%
80%
80%
80%
80%
80%
(Assumed)
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
163,2
00
300,2
00
274,5
00
59,5
00
298,9
00
39,4
40
57,2
00
292,8
00
135,5
20
152,5
00
116,7
40
198,0
00
2,088,500
2 2 2 1 2 1 1 2 1 2 1 0 17
2 7 5 1 5 1 2 5 4 5 2 4 43
4 9 7 2 7 2 3 7 5 7 3 4 60
Note:ValuesinREDarecalculatedbasedonavg.stadium
characteristics
IP
LGreeningProgram
DLFIPL2010
REALISE
ProjectReport
E l i i t C b E i i ( E C E ) P t L t d
54
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
55/359
A key component of the Local Stakeholder Activity research phase
was the identification of avenues for significant reductions in resource
consumption through efficiency enhancements while avoiding any
visible impact on the overall service delivery to customers/spectators.
All technical and operational personnel helming Stakeholder functions
were engaged in brainstorming discussions to identify non-capital
expenditure intensive options to measurably reduce resource
consumption and enhance the Carbon Emissions efficiency of theirrespective activities. Such expert input was recorded in detail and will
be analyzed further for incorporation into the Carbon Footprint
Minimisation analysis phase of the project.
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 5
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
56/359
Average air-travel and road-travel distances for various stakeholders
were determined based on distance research conducted on the
Franchise Team Travel plan presented in the table below.
Note: the following abbreviations used in the table below
Teams RR (Rajasthan Royals),
KXIP (Kings XI Punjab),
CSK (Chennai Super Kings),
DD (Delhi Daredevils),
MI (Mumbai Indians),
KKR (Kolkata Knight Riders),
RCB (Royal Challengers Bangalore),
DC (Deccan Chargers).
Venues Mu (Mumbai),
Ah (Ahmedabad),
Ba (Bangalore),
Mo (Mohali),
De (Delhi),
Ch (Chennai),
Na (Nagpur),
Ja (Jaipur),
Ko (Kolkata),
Cu (Cuttack),
Dh (Dharamsala),
Nm (Navi Mumbai)
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd.56
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
57/359
Table9
DLFIPL
2010TournamentTeamTravelPlan
No.
RR
KXIP
CSK
DD
M
I
KKR
RCB
DC
Day
Date
1 2 3 4 5 6 7 8 9 10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
12-Mar
13-Mar
14-Mar
15-Mar
16-Mar
17-Mar
18-Mar
19-Mar
20-Mar
21-Mar
22-Mar
23-Mar
24-Mar
25-Mar
26-Mar
27-Mar
28-Mar
29-Mar
30-Mar
31-Mar
1-Ap
r
2-Ap
r
3-Ap
r
4-Ap
r
FRI
SAT
SUN
MON
TUE
WED
THU
FRI
SAT
SUN
MON
TUE
WED
THU
FRI
SAT
SUN
MON
TUE
WED
THU
FRI
SAT
SUN
Venue
Mu
Ah
Ba
Ah
Mo
Ah
Ah
De
Ch
Ven
ue
Mo
Ba Cu Ch Mo
Mo
Mu
Mo
Ko
Venue
Ch
Ko
De
Ch
Ba
Mu
Ah
Ch
Ch
Venue
Mo
Ah
De
De
Cu
Ba
De
De
De
Venue
M
u
D
e
M
u
M
u
M
u
N
m
M
u
M
u
Venue
Nm
Ko
Ko
Ah
Mu
Mo
De
Ko
Ko
Venue
Ko
Ba
Ba
Mu
Ba
Ba
Ch
Mo
De
Venue
Nm
Ch
Cu
Cu
Ah
Nm
Ko
Mu
IP
LGreeningProgram
DLFIPL2010
REALISE
ProjectReport
E l i i t C b E i i ( E C E ) P t L t d
5
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
58/359
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
5-Apr
6-Apr
7-Apr
8-Apr
9-Apr
10-Apr
11-Apr
12-Apr
13-Apr
14-Apr
15-Apr
16-Apr
17-Apr
18-Apr
19-Apr
20-Apr
21-Apr
22-Apr
23-Apr
24-Apr
25-Apr
MON
TUE
WED
THU
FRI
SAT
SUN
MON
TUE
WED
THU
FRI
SAT
SUN
MON
TUE
WED
THU
FRI
SAT
SUN
Na
Ja
Ja
Ja
Ko
Ja Mo De Dh Dh
Ch
Na
Ch
Ch
Dh
Ko
De
Mu
Ch
De
Ch Mo Ja Mu Ba Ko
Ko
Ba
Ch
Ko
Ko
Ba
Ba
Na
Ja
Ba
N
a
B
a
N
a
N
a
D
h
D
e
Table9(Contd.)
DLFIPL
2010TournamentTeamTravelPla
n
No.
RR
KXIP
CSK
DD
MI
KKR
RCB
D
C
Day
Date
IP
LGreeningProgram
DLFIPL2010
REALISE
ProjectReport
E l i i t C b E i i ( E C E ) P t L t d
Eliminate Carbon Emissions (ECE) Pvt.Ltd.58
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
59/359
IPL Greening Program
DLF IPL 2010 REALISE Project Report
Eliminate Carbon Emissions (ECE) Pvt.Ltd. 5
-
8/13/2019 Carbon Footprint 300 Pp CB IPL 2010
60/359
The activities included within the footprint boundary were further
differentiated into multiple activity sub-types. Each resource/activity
inventoried during research was tagged and collated under footprint-
head groups. The table below presents the list of Activity Groups,
Types and Sub-Types used for data classification. The governing
principle for the elaborate data classification was to provide intrinsic
intra-stakeholder and cross-stakeholder analytic capability across any
specific Activity Group and aggregated footprint analysis acrossStakeholders to compare relative Stakeholder impacts.
Data collation done in such a manner allowed for quantities (i.e. liters,
kgs, pieces of items, kilometers of air travel etc.) of the same resources
or activities to be aggregated across Stakeholders. This would prove to
be of utility as an overall planning and organizational tool for
tournament operations redesign and other administrative
interventions, if desired, beyond the purp