CURRENT CONSTRUCTION AND LOGISTICS SCHEDULE
CONSTRUCTION ACTIVITY Start Complete
Close 1801 Congress Ave. (Lot 7) July 16, 2018 Building complete in 2022
Construction barriers placed around 1801 Congress Ave. July 16, 2018 Open at end of project, 2022
Close 18th St. between Brazos and Congress Ave. July 23, 2018 Open at end of project, 2022
Begin Excavation at 1801 Congress Ave. July 24, 2018 Summer 2019
Close Congress from 15th St. to MLK Blvd. (DPS Parking, REJ drop off, and Southbound Museum and Bus drop off still open.)
December 1, 2018 Becomes Texas Mall in May 2022
Construct Utility Support across Congress Ave. September 2018 February 2019
Construct Utilities throughout and around Capitol Complex January 2019 June 2019
Close 1601 Congress Ave. (Lot 2) January 2019 Building Completion 2022
Begin 1601 Congress Ave. excavation February 2019 July 2019
Install Traffic signal at MLK & Colorado February 2019 April 2019
Begin Construction of Central Utility Plant March 2019 December 2020
Begin Congress Ave excavation April 2019 July 2020
Begin Construction of 1801 Congress Ave. Building May 2019 May 2022
Begin Construction of 1601 Congress Ave. Building August 2019 March 2021
Begin Construction of Texas Mall Garage July 2020 February 2022
Permanent Two-Way street reconfigurations 2021 2021
Construct Texas Mall Hardscape and Install Landscaping March 2021 May 2022
SITE LOGISTICS DESCRIPTION Start Complete
Construction Office Trailers and Parking (SW Corner) November 2017 May 2022
Construction Office Trailers and Parking (NE Corner) December 2018 May 2022
Contractor Staging Area (half of lot) February 2019 May 2022
Bullock Museum Bus Drop Off September 10, 2018 April 2019
Bullock Museum Bus Staging Area July 2018 May 2022