capital projects & portfolio management augurst 20-22, 2014 vail, co 2014 transmission &...
TRANSCRIPT
Capital Projects & Portfolio Management
Augurst 20-22, 2014
Vail, CO
2014 Transmission & Distribution BenchmarkingInsights Conference
Agenda
DILBERT
2
◼Portfolio Management◼Project Management◼Outcomes◼Practices
Matrix organization
3
EARNED VALUE
4
The Capital project process
The capital project and portfolio management process is at the heart of a how a utility conducts business.
• Phase 1: work plan development creates a feasible schedule for the year
• Phase 2: executes the work plan through project and portfolio management
5
Role of asset management is described in the individual practice sections
Portfolio Management
PORTFOLIO MANAGEMENT QUESTIONS
Page 7
Portfolio Management•Workplan Development: Software •Workplan Development: Regulatory mandates•Processes in place to re- evaluate portfolios •Adding new projects during the year•Estimating Accuracy -- % of projects completed within +/ - •% Capital Projects: Average "Actual as a % of Estimate"•Percent of the projects that are typically completed on time•Projects that are typically completed on or under budget•Percent of the completed projects that are walked- in during the year
Workload Volume•Capital budget projections for the next 3 years: T, D, S
Transmission Line Spending
We saw increased spending in 2013 . . .We saw increased spending in 2013 . . .
8
Total Transmission Capital Additions: US Utilities
Total market size for the US for the last 7 years has grown consistently, following a drop off during the recession. Only a portion of this will be for labor costs since some portion will be for materials.
This is total US utility population – FERC Capital Additions. Capital additions represents capital spending that closed to the books and became part of the asset base in the given year. 9
2014 T&D: Capital Projects
CAPITAL PROJECT SPENDING PER ASSET NEXT 3 YEARS - DISTRIBUTION
Mean Quartile
Mean
16 %
Comments
Calculation used
( CP125.1C ) / ( DF70.1 ) * 100 , ( CP125.2C ) / ( DF70.1 ) *
100 , ( CP125.3C ) / ( DF70.1 ) * 100
Page10
2014 T&D: Capital Projects
CAPITAL PROJECT SPENDING PER ASSET NEXT 3 YEARS - SUBSTATION
Mean Quartile
Mean
20 %
Comments
Calculation used
( CP125.1B ) / ( DF70.2 + TF65.2 ) * 100 , ( CP125.2B ) /
( DF70.2 + TF65.2 ) * 100 , ( CP125.3B ) / ( DF70.2 + TF65.2 ) *
100
Page 11
Key Success Factors:Portfolio Management
12
2014 T&D: Capital Projects
PERCENT OF THE COMPLETED PROJECTS THAT ARE WALKED-IN DURING THE YEAR
Comments
Calculation used
CP46.4
Page 13
Mean Quartile
Mean 17.3 %
Quartile 1 12.0 %
Quartile 2: 16.5 %
Quartile 3: 23.3 %
“Walked in” is terminology from one of our clients that refers to projects that are not in the original annual budget (usually approved prior to January 1 or sooner), but are added during the year. Usually these rushprojects do not always get the same degree of planning and vetting.
2014 T&D: Capital Projects
CAPITAL PROJECTS: AVERAGE "ACTUAL AS A % OF ESTIMATE"
Comments
Calculation used
CP46.1
Page 14
Mean Quartile
Mean 96 %
Quartile 1 92 %
Quartile 2: 95 %
Quartile 3: 102 %
2014 T&D: Capital Projects
% OF PROJECTS THAT ARE COMPLETED ON TIME
Calculation used
CP46.2
Page 15
PROJECTS THAT ARE TYPICALLY COMPLETED ON OR UNDER BUDGET
Timeliness
Calculation used
CP46.3
Improve Accuracy at each project phase
Phase Accuracy [# of companies]
Conceptual +75%/-50% [1]+-40% [1]+-30% [2]+-20% [3]+-10% [1]
Preliminary +-20% [1]+-10%[6]
Release to Construction
+10% [5]+-5% [2]
EXAMPLE: Substation EstimatingEstimating gets increasingly defined as a job progresses through design to construction. Based upon our 2011 survey, the typical accuracy goal is +/- 20-30% at the conceptual stage, decreasing to +/- 10-20% going to final design, and then +-10% when released to construction.
16
% accuracy 22 27 31 33 359 38 40 Avg%+/- 5% 94 % 9 % * 62 % 16 % 33 % 20 % 36%+/- 10% 3 % * 90 % 20 % 14 % 20 % 24 % 22%+/- 20% * 27 % 13 % 29 % 7 % 16 % 15%> 20% * 59 % * 41 % 40 % 40 % 32%
2014 Results – Estimating Accuracy at Release to construction
2011
Res
ults
Use Software tools for Work plan Development
17Capital Projects Pg 3
Source: CP15
Category Comments
In-house software 2
35 We utilize a specially- designed software to assess project attributes and to develop portfolios that satisfy key company objectives.
37 We utilize in- house database and spreadsheet tools to capture project attributes and perform comparisons based on established prioritization criteria.
Davies AIS and other tools 230 Davies - Asset Investment Strategy (AIS) tool31 MS Excel, AIS (Dist only)
Hyperion and other tools 2
16 Hyperion, an Oracle enterprise management system; Power Plant, Passport
18 Hyperion, an ORACLE Enterprise Performance Management System; Powerplant, PassPort
SAP and other tools 222 Distribution: LDPRO, SAP, DDS38 SAP, WMIS, Obvient, Crystal Business Objects
Other tools 226 Model web based overlay32 IES
None 1 34 None
A few companies use software tools to evaluate projects against multiple criteria.A few companies use software tools to evaluate projects against multiple criteria.
2013 Results
2014 T&D: Capital Projects
WORKPLAN DEVELOPMENT: SOFTWARE TOOLS USED TO EVALUATE PROJECTS AGAINST MULTIPLE CRITERIA
Calculation used
CP15.1
Page 18
ID Response22 Davies - Asset Investment Strategy (AIS) tool31 Substation: Davies. Distribution: SAP, DDS
LDPRO33 With large projects will model the project using in
house Excel process. Normal budgeting process tools are engineering based LD- Pro, PLSCad
23 We utilize a specially- designed software to assess project attributes and to develop portifolios that satisfy key company objectives.
37 Primavera with web based overlay for prioritization questions
38 SAP, WMIS, Obvient, Crystal Business Objects40 None24 IES30 In - house analysis protocol (Excel platform)359 Primavera, Asset Suite, Excel32 Informal spreadsheet using risk matrixes
In-house software
#
Davies AIS and other tools
2
Hyperion and other tools 2
2
SAP and other tools 2
2
Other tools 2 2
None 1 1
2013 Results
PM ROLE
20
• Size/types of projects have project managers• Full - time PMs per $100M Capital Additions: T, D & S• Support per project managers: T, D, & S• Project Dollars per PM: T, D, &S • Projects per PM: T, D &S• Software tools used for project management Authority the PM has over project execution• Relationship between construction and project management• Organizational relationship between PM, and Planning, Engineering • Construction report project progress• Software tools the project manager has to monitor projects Measuring "earned value”• PM’s role in project close- out Conducting a post- implementation evaluation• Using project management techniques to manage programs
Project Management Questions
2014 T&D: Capital Projects
ADDING NEW PROJECTS DURING THE YEAR
Page 21
IDS Response
22 Specific projects may be identified during the year due to New Business (customer) requests and emergent
requests to address system issues. Project funding is 'drawn down' from established budgeted funds that have
been based on historic trends and projections.31 Substation: Based on need. No portfolio or ranking is done with all in progress projects. Distribution: unplanned
new loads are evaluated on a per project basis.33 New capital projects added during the year must be approved through Executive Capital Committee. Projects
are submitted with full explanation and costs. Entered into SAP Appropriation requests23 Individual requests for funding are submitted for evaluation and prioritization, and inserted in the asset plan under
a 'Hold' status. If the project or program is to receive funding, the status is changed to 'Funded.'37 Projects are added and deleted as business needs change and are re - evaluated at monthly program status
meetings and quarterly re-projections.
38 Projects are added as needed by the PRC after evaluating the project to ensure that it doesn't impact reliability, the budget or human resources in a negative manner.
40 Driven by customer demands and/or reliability issues
24 Through approval at Utility Review Board and Corporate Capital Review Committee meetings.
30 Request and approval through leadership based on project size
27 Capital projects are only added during the annual budget development. Capital budget evaluations are
developed from a 5 - year budget plan. Change orders are evaluated for projects that need to be advanced on a
case by case basis.359 Asset management performs technical challenge, project officially proposed at monthly organizational review
and funding granted for project planning phase, project planning phase completed and strategic in - service date
identified, finally project budget and cashflows submitted to governance
32 These go through project review (PRC) and are approved at appropriate level dependent on forecasted cost.Calculation used
CP40.1
PM ROLE
Key Success Factors:Project Management
23
Key Success Factors: Project Managers
24
Most utilities have PM’S for all unique projects
All projects (5)37 Distribution Projects - 100%
22 Distribution: Major overhead, URD and Street Light have individual
Division managers. Substation: All projects have a project coordinator
35 All capital funded projects have PMs. Serve New > 500KVA, Serve
Existing such as large road widening & system improvement type projects.
26 All projects are assigned a PM.17 PMs are assigned to all capital construction projects regardless of size.
Less complex capital projects may be assigned to engineers, designers
or planners to fill the role of PM
Complex projects (3)38 Complex, cross -functional and/or highly political projects and programs that usually spend >$5M.
32 230 kV and 500kV and UG Transmission Projects; these are outside consultant PMs.
31 345kV transmission line builds
Projects >$1M 34 Projects > $1,000,000 have PMP PM's, Projects <$100,000 do not require PM 's
Projects > $500k39 Projects that have a budget greater than $500,000 and have an engineering component have Engineering PMs. Line construction projects driven by private new business, public agencies,
system integrity and system reinforcement have RMT PMs.
Projects >$100k27 Over $100,000
Survey Results
2010 2011
2012 2013
All Projects 8 9 3 5
Significant Projects
3 1 6 3
>$1MM 3 3 2 1
>$500k 3 0 2 1
>$100k 4 4 2 1
25Source: Question, Page 12
2013 Results
SIZE/TYPES OF PROJECTS HAVE PROJECT MANAGERS
Comments
Calculation used
CP55.1
Page 26
Responses
Total Participants 19
Number of Respondants 8
ID Response22 Distribution, Transmission, Substation Projects31 Substation: All. Distribution: Major overhead, URD joint trench and Street Lighting have individual
managers23 All capital funded projects have Project Managers. Serve New 500KVA, Serve Existing such as large
road widening & system improvement type projects; Transmission - Projects with accelerated
timelines or unique challenges may have a project manager (typically $3M). All other projects are
managed directly by the engineers and construction managers, and the portfolios are managed
holistically by the program managers.38 Complex, cross - functional and/or highly political projects and programs that usually spend more
than $5M.40 All projects have PM's. Projects $1M have PMP PM's.33 This is based upon our project assessment. All projects are ran through this assessment, if these
project exceeded a certain monetary value they were assigned a manager and were sujected to our
established major project management policy. This has changed effective 2015 projects to a more
risk based approach.27 Line construction projects driven by private new business, public agencies, system integrity and
system reinforcement have RMT Project Managers.35 All transmission projects/programs with the exception of relay test compliance work
2014 Survey
FULL-TIME PROJECT MANAGERS: T, D, & S PER $100M CAPITAL ADDITIONS
#32 reported a very high number of project managers
Comments
Calculation used
( CP60.1 ) / ( (Total T&D Capital FERC) / 100000000 ) , ( CP60.2 ) /
( (Total T&D Capital FERC) / 100000000 ) , ( CP60.3 ) / ( (Total
T&D Capital FERC) / 100000000 ) , ( CP60.4 ) / ( (Total T&D
Capital FERC) / 100000000 )
Page 27
Mean Quartile
Mean 11.7
Quartile 1 11
Quartile 2: 5
Quartile 3: 5
2014 Results
CP p13
Project Managers per $100M Capital Spent
One measure of workload is the capital budget managed by PMs.
A simple ratio of capital additions to PMs is only a proxy, since not all of the projects have PMs. Another complication is that capital additions is a backward looking measure that only occurs once the project is in service.
Source: Question CP60, page 13
Median2013DRC = 3.5 FTEs/$100M2012 = 5 FTEs/$100M2011 = 3 FTEs/$100M
Note: the inverse is Budget Managed per PM
28
2013 Results
Thank you for your Input and Participation!
29
Corporate Offices
California
400 Continental Blvd. Suite 600El Segundo, CA 90245(310) 426-2790
Maryland
3 Bethesda Metro Center Suite 700Bethesda, MD 20814(301) 961-1505
New York | Texas | Washington | Wisconsin
First Quartile Consulting is a utility-focused consultancy providing a full range of consulting services including continuous process improvement, change management, benchmarking and more. You can count on a proven process that assesses and optimizes your resources, processes, leadership management and technology to align your business needs with your customer’s needs.
Visit us at www.1stquartileconsulting.com | Follow our updates on LinkedIn
About 1QC
Satellite Offices
Debi McLain [email protected]
Tim. [email protected]
Dave [email protected]
Dave [email protected]
Your Presenters
Ken Buckstaff [email protected]
scqa
1QC Industry Perspective:Project Management
31
1QC Industry Perspective:Project Management
32
1QC Industry Perspective:Project and Portfolio Management
33