capital markets presentation, november 2015 - ophir energy · pdf filecapital markets...
TRANSCRIPT
Capital Markets Presentation, November 2015
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
DISCLAIMER
Capital Markets Presentation - Fortuna FLNG Slide 2
THIS DOCUMENT IS CONFIDENTIAL This document has been prepared and issued by and is the sole responsibility of Ophir Energy plc (the “Company”) and its subsidiaries for selected recipients. It comprises the written materials for a presentation to investors and/or industry professionals concerning the Company’s business activities. By attending this presentation and/or accepting a copy of this document, you agree to be bound by the following conditions and will be taken to have represented, warranted and undertaken that you have agreed to the following conditions. This presentation is strictly confidential and may not be copied, published, distributed or transmitted. If you do not accept these conditions, you should immediately destroy, delete or return this document. The document is being supplied to you solely for your information and for use at the Company’s presentation to investors and/or industry professionals concerning the Company’s business activities. It is not an offer or invitation to subscribe for or purchase any securities and nothing contained herein shall form the basis of any contract or commitment whatsoever. This presentation does not constitute or form part of any offer or invitation to sell or issue, or any solicitation of any offer to purchase or subscribe for, any shares in the Company in any jurisdiction nor shall it or any part of it nor the fact of its distribution form the basis of, or be relied on in connection with, any contract commitment or investment decision in relation thereto nor does it constitute a recommendation regarding the securities of the Company. This presentation is for informational purposes only and may not be used for any other purposes. The distribution of this presentation in jurisdictions other than the United Kingdom may be restricted by law and therefore persons into whose possession this presentation comes should inform themselves about and observe such restrictions. Any failure to comply with these restrictions may constitute a violation of securities laws of any such jurisdictions. This presentation and any materials distributed in connection with this presentation may include certain forward-looking statements, beliefs or opinions, including, without limitation, statements with respect to the Company’s business, financial condition, results of operations, plans, objectives and estimates, including, among others, resource estimates. These statements, which contain the words “anticipate”, “believe”, “intend”, “estimate”, “expect” and words of similar meaning, reflect the Directors’ beliefs and expectations and involve a number of risks and uncertainties because they relate to events and depend on circumstances that will occur in the future. No representation is made that any of these statements or forecasts will come to pass or that any forecast results will be achieved. There are a number of known and unknown risks, uncertainties and other factors that could cause actual results, performance and developments of the Company or industry results to differ materially from those expressed or implied by such forward looking statements, therefore, undue reliance should not be placed on forward looking statements. Past performance of the Company cannot be relied on as a guide to future performance. Forward-looking statements speak only as at the date of this presentation and the Company expressly disclaims any obligations or undertaking to release any update of, or revisions to, any forward-looking statements in this presentation, whether as a result of new information or future events. No statement in this presentation is intended to be a profit forecast or should be interpreted to mean that future earnings per share of the Company will necessarily match or exceed its historical published earnings per share. As a result, you are cautioned not to place any undue reliance on such forward-looking statements. Certain data in this presentation was obtained from various external data sources, and the Company has not verified such data with independent sources. Accordingly, no representation or warranty, express or implied, is made and no reliance should be placed, on the fairness, accuracy, correctness, completeness or reliability of that data, and such data involves risks and uncertainties and is subject to change based on various factors. No reliance may be placed for any purposes whatsoever on the information contained in this presentation or on its completeness. The Company and its members, directors, officers and employees are under no obligation to update or keep current information contained in this presentation, to correct any inaccuracies which may become apparent, or to publicly announce the result of any revision to the statements made herein except where they would be required to do so under applicable law, and any opinions expressed in them are subject to change without notice, whether as a result of new information or future events. No representation or warranty, express or implied, is given by the Company or any of its subsidiaries undertakings or affiliates or directors, officers or any other person as to the fairness, accuracy, correctness, completeness or reliability of the information or opinions contained in this presentation, nor have they independently verified such information, and any reliance you place thereon will be at your sole risk. Without prejudice to the foregoing, no liability whatsoever (in negligence or otherwise) for any loss howsoever arising, directly or indirectly, from any use of this presentation or its contents or otherwise arising in connection therewith is accepted by any such person in relation to such information.
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
AGENDA
Capital Markets Presentation - Fortuna FLNG Slide 3
TOPIC PRESENTER
I. Introduction and Welcome Nick Cooper
II. Overview of Fortuna Project Bill Higgs
III. Subsurface Simon Smith
IV. Development Philip Dobson
V. Midstream Solution – Golar LNG Gary Smith
VI. Commercial and Marketing Andy Arnold
VII. Project Financials Tony Rouse
VIII. Closing comments Bill Higgs
IX. Q&A Panel
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Fortuna LNG team - Depth and breadth of knowledge and experience
SPEAKERS BIOGRAPHIES
Capital Markets Presentation - Fortuna FLNG Slide 4
Bill Higgs, Chief Operating Officer • Bill has over 25 years of global exploration, development and operations experience, the majority with Chevron Corporation
• His roles at Chevron included Senior Vice President of Operations for Saudi Arabia Chevron, Reservoir Manager for Tengizchevroil in Kazakhstan, Asset Manager for the BBLT development in Block 14 Angola and General Manager for Strategy for Chevron Corporation
• CEO of Mediterranean Oil & Gas plc prior to being acquired
Simon Smith, Equatorial Guinea Asset Manager • An oil and gas professional with 14 years of worldwide experience from working with companies including Engie, Total and BP in the UKCS
in addition to roles covering Equatorial Guinea, Libya, Indonesia, Mauritania and Malaysia
• A proven track record of delivery in areas such as: Operated and non-operated Asset Management, Commercial negotiation, Reserves and Production Reporting, Strategy, Economic Evaluation, Internal and External Stakeholder management, Asset redevelopment
• African experience includes Mauritania (Blocks 1 & 7) and onshore Libya; and LNG experience through the Eni Operated Jangkrik project
Philip Dobson, Project Manager • 35 years oil & gas experience covering all aspects of Oil & Gas developments through appraisal, concept select define and execute
• Managed Projects, including Offshore Fixed platform, FPSO, Onshore compression, Onshore LNG
• Worked internationally for Oil Majors including Marathon Talisman Hess BP & Shell
• Countries worked include Sudan, Gabon and Equatorial Guinea (Marathon EGLNG train 1)
Andy Arnold, Director - Commercial • Andy has 30 years’ upstream technical, commercial, business development and asset management experience gained with Exxon,
PowerGen, BHP Billiton and most recently with BG Group
• His roles at BG included UKCS Asset Management (both operated and non-operated), Group Commercial Assurance Manager for all BG’s material commercial arrangements (commodity term deals, LNG projects, M&A and New Country entry) and Senior Business Development Manager for the E&P business, managing entries into the Caribbean and Myanmar
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Depth and breadth of knowledge and experience
SPEAKERS BIOGRAPHIES
Capital Markets Presentation - Fortuna FLNG Slide 5
Tony Rouse, Chief Financial Officer • Tony Rouse joined Ophir in October 2014. Tony has over 30 years’ experience in the Upstream Oil and Gas industry including 13 years of
assignments in Europe, Africa, Asia and South America
• Tony started his career with BP, before moving to LASMO plc, Premier Oil and most recently Salamander Energy where he was Group Financial Controller for 9 years
Nick Cooper, Chief Executive Officer • Dr Nick Cooper was appointed as an executive director and Chief Executive in June 2011
• Prior to joining Ophir, Nick Cooper was Chief Financial Officer and co-founder of Salamander Energy plc
• He began his career as a geophysicist with BG and Amoco before working as a consultant to the Dolphin gas export project (Qatar/UAE). From 1999-2005 he was a member of the oil and gas team at Goldman Sachs
Gary Smith, Chief Executive Officer Golar LNG • Gary ’s career in oil and gas spans 35 years including 20 years with Shell in various roles including General Manager of LNG shipping and
most recently 5 years with Caltex Australia (a Chevron affiliate) as General Manager Refining, Supply and Distribution
• Between 2002 and 2005 Gary served as President and Director of SIGTTO (Society of International Gas Tanker and Terminal Operators)
• Gary was CEO of Golar in the period 2006 to 2009 and during this time oversaw the Company’s entry into the then non-existent FSRU business and made the first preparations for the company’s subsequent pursuit of floating liquefaction
• Gary re-joined Golar as CEO in February 2015
INTRODUCTION
Nick Cooper CEO
Slide 6
Positioned to thrive in uncertain times
STRATEGY
Slide 7 Capital Markets Presentation - Fortuna FLNG
VALUE CREATION THROUGH EXPLORATION
FOCUS ON ROCE THROUGH CAPITAL ALLOCATION AND COST MANAGEMENT
ACTIVE PORTFOLIO AND RISK MANAGEMENT
Focus: Commercialising our gas resources
LARGE RESERVES AND RESOURCE BASE
Slide 8
Significant 2P reserves base from Thai and Indonesian assets
• 60 MMboe 2P – over 10 years of production at current levels
• Underpins strong production and cash flow in the medium term
• Over 55% is high margin gas, which is sold on long-term contracts
Large 2C resources base from Thai, Indonesian and African LNG assets
• Strong economics from Thai and Indonesian 2C by leveraging on existing infrastructure at Bualuang, Sinphuhorm and Kerendan
• High value African LNG to drive longer term production and growth
LARGE 2P + 2C BASE SKEWED TOWARD HIGH MARGIN GAS IN THE LONG TERM
Reserves (MMboe) 1P 2P 3P
Bualuang 17.6 24.9 31.1
Sinphuhorm 5.1 17.9 17.9
Kerendan 16.5 16.8 16.8
Total Reserves (MMboe) 39.2 59.6 65.8
Resources (MMboe) 1C 2C 3C
Bualuang 6.7 15.5 31.3
Sinphuhorm & Dong Mun 5.0 18.0 126.8
Kerendan 3.6 62.3 144.3
Equatorial Guinea 337.8 400.7 481.7
Tanzania 366.7 501.0 483.3
Total Resources (MMboe) 719.8 997.5 1267.4
Total Reserves and Resources (MMboe) 759.0 1057.1 1333.2
2P + 2C BY GEOGRAPHY 2P + 2C BY PRODUCT
Thailand 7%
Indonesia 8%
Equatorial Guinea 38%
Tanzania 47%
Oil 4%
Gas 96%
Capital Markets Presentation - Fortuna FLNG
Many other developments are not reaching FID
Many options available – back fill, terrestrial LNG, floating LNG…
World class asset delivering attractive economics
- World class resource – high quality clean gas, simple to liquefy
- Simple upstream development; low cost midstream solution, proven technology
- Robust, attractive IRR’s
- Stable, supportive political environment
- Substantial upside
Ophir has the expertise to deliver a successful project
- In-house expertise
- World-Class partners
- Playing to everyone's strengths
Development can be financed
- Several funding options are well advanced
- Midstream FEED and costs well understood
- Upstream FEED well advanced and costs coming down
WHY PROGRESS WITH FORTUNA FLNG?
Slide 9 Capital Markets Presentation - Fortuna FLNG
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
INVESTMENT HIGHLIGHTS
Capital Markets Presentation - Fortuna FLNG Slide 10
World-Class Resource
Biogenic Dry Gas, 99.7% Methane
Simple Upstream Development
Low Cost Midstream Solution, Proven Technology
Robust Economics
Stable, Supportive Political Environment
Substantial Upside
1
2
3
4
5
6
7
OVERVIEW OF FORTUNA FLNG
Bill Higgs COO
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
FORTUNA FLNG PROJECT – HIGHLIGHTS
Capital Markets Presentation - Fortuna FLNG Slide 12
Globally Competitive Project
Source: Wood Mackenzie, Ophir Energy
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
NP
V 1
0%
Bre
ak E
ven
DES
Jap
an
FOB Cost (Breakeven) ($/mmBtu) Shipping Cost ($/mmBtu)
World class resource
• 3.7 Tcf, shallow, high quality reservoirs
Clean, dry gas
• Minimal processing required
Simple upstream development in FLNG project
Midstream solution utilising proven technology
Economically robust
Stable, supportive political environment
Substantial upside
Low risk Low cost Quick to first gas
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
KEY PROJECT DATAPOINTS
Capital Markets Presentation - Fortuna FLNG Slide 13
Recoverable Resources
Base Case 3.7 Tcf
Wellhead Gas Production
720 mmcf/d plateau (120 mboe/d plateau)
882 mmcf/d peak (147 mboe/d peak)
LNG Production 4.4 mmtpa plateau
Timing
FEED Completed
Q1 2016
Project FID Mid-2016
First Gas Mid-2019
Second Vessel FID
Mid-2022
Second Vessel Onstream
Mid-2025
Low risk Low cost Quick to first gas
Punta Europa LNG Terminal
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
WHY FLOATING LNG?
Capital Markets Presentation - Fortuna FLNG Slide 14
Biogenic Gas Resource
• 99.7% methane – simple gas-to-LNG processing requirements
• Negligible water to handle
Benign Metocean Conditions
• Side-by-side offloading
• High uptime
Water depth
• Block R is located in water depths of 1,000m to 1,900m
Distance from land
• 100km off the southwest coast of Bioko Island and 150km from Punta Europa
PROVIDES THE HIGHEST RETURN
Low risk Low cost Quick to first gas
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
No two FLNG projects are the same
COST COMPARATORS
Capital Markets Presentation - Fortuna FLNG Slide 15
Shallow reservoir
Hydrocarbon composition
Benign sea state
Low cost vessel solution
Proximity to 2+ markets
Fortuna FLNG
Nearshore solutions
Low risk Low cost Quick to first gas
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Low cost, quick delivery, value enhancing
ADVANTAGES OF A CONVERSION
Capital Markets Presentation - Fortuna FLNG Slide 16
Low Capex to First Gas for Upstream Participants
• $0.8bn of Upstream capex to first gas
• c.$1.5bn of Midstream capex payable by Golar
Speed of delivery
• 3 years after FID, first gas expected
Proven Technology and World-Class Partners
• Golar LNG: Midstream FLNG supplier
• Keppel Shipyard: Vessel construction
• Black & Veatch: Liquefaction process supplier
• Worley Parsons: Owner’s engineer
Low risk Low cost Quick to first gas
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
SIMPLE CONTRACTING STRATEGY
EPCIC
WBS Assets / Activity
Owner’s Engineer in support of
PMT
FEED Detailed Design
Procure Fabrication / Construction
Installation Hook-up
& pre-commission
Start Up Operations
Inspection, Maintenance
& Repair (IMR)
Drilling
Up
stre
am
Wellhead & Xmas Trees
Control System
Umbilicals
Manifolds incl. Foundations
Mooring Piles (Optional)
Risers & Flowlines incl. FTAs & Jumpers
FLNG Vessel
or
Wells to be executed by Ophir drilling team in London
Slide 17 Capital Markets Presentation - Fortuna FLNG
PM/Engineering contractor with subsea and FLNG experience
SURF / SPS partnership – FEED followed by LS EPCIC
BOO contractor to provide facility on leaseback, plus operating fee Subsea facility operation on instruction from Ophir
Low risk Low cost Quick to first gas
Proven expertise as upstream operator
OPHIR DRILLING
Slide 18 Capital Markets Presentation - Fortuna FLNG
• Operated 22 deepwater wells
• Best in basin on both sides of the continent
• Leading African deepwater explorer
Gabon 2008, 2014 5 wells 630m – 1,430m WD
Ghana 2013 1 well 1,520m WD
Senegal 2011 1 well 2,650m WD
Tanzania 2010, 2013, 2014 6 wells 700 – 2,640m WD
Equatorial Guinea 2008 , 2012, 2014 9 wells 1,450m – 1,815m WD
Mkuki Well Best in Basin 1,650m WD 3,230m TD
Lykos Best in Basin 1,530m WD 2,300m TD Fortuna development:
• Minimal wells and easy to drill
• Drill, complete and tie-back to FLNG vessel
• Manage reservoir performance over time
Low risk Low cost Quick to first gas
Project delivering to schedule
MILESTONES
Slide 19
2014 2015 2016 2017 2019 2020
Commercial milestones achieved
May 2015 Charter Term Sheet agreed with Golar for provision of leased FLNG vessel
Jun 2015 Launched offtake process
Jul 2015 Awarded Competitive FEED contracts to McDermott / GE and Aker / Subsea 7
Nov 2014 Renegotiation of PSC for gas development
Capital Markets Presentation - Fortuna FLNG Low risk Low cost Quick to first gas
Nov 2015 Heads of Agreement signed for gas offtake
Q1 2016 FEED completed
Mid-2016 Project FID
Mid-2019 First gas
Milestones to first gas
Oct 2014 Flow tested gas Surpassed threshold volumes
Exploration and appraisal milestones achieved
SUBSURFACE
Simon Smith Equatorial Guinea Asset Manager
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Block R in Equatorial Guinea is located in the south-eastern part of the Niger Delta complex
• Close to numerous significant oil and gas discoveries in the Nigerian sector, including Akpo, Usan/Ukot and Zafiro
• 100km off the southwest coast of Bioko Island, Equatorial Guinea and 150km from Punta Europa
• Water depths up to 1,900m
Block R qualities contribute to low cost development
• Excellent reservoir petrophysical characteristics
• Ideal gas quality
• Ideal reservoir depth
Ophir 80% operated interest, GEPetrol 20% interest
BLOCK R
Capital Markets Presentation - Fortuna FLNG Slide 21 Resources Upstream Midstream Financials Marketing
• Entered into Block R PSC in 2006
• Currently covers 2,051km2
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
REGIONAL GEOLOGICAL SETTING
• Block R lies at the frontal toe-thrust zone and frontal deformation zone between the main Niger Delta and NW-SW trending Cameroon volcanic line
Slide 22 Capital Markets Presentation - Fortuna FLNG Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
BLOCK R; SCHEMATIC CROSS SECTION
Capital Markets Presentation - Fortuna FLNG Slide 23 Resources Upstream Midstream Financials Marketing
1km below mudline
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
DRILLING HISTORY AND DISCOVERIES
Capital Markets Presentation - Fortuna FLNG Slide 24
Well Name Operator Year TMD (mRT) WD (m) Result
Oreja Marina-1 ExxonMobil 2001 3,535 1,417 Gas
Estrella de Mar-1 ExxonMobil 2002 3,202 1,433 Gas
Fortuna-1 (R1) Ophir 2008 3,400 1,692 Gas
Bythos-1 (R2) Ophir 2008 4,222 1,716 Dry
Lykos-1 (R3) Ophir 2008 2,297 1,536 Gas
Tonel-1 (R4) Ophir 2012 3,097 1,599 Gas
Fortuna East-1 (R5) Ophir 2012 3,465 1,828 Gas
Fortuna West-1ST1 (R6) Ophir 2012 3,178 1,758 Gas
Tonel North-1 (R7) Ophir 2014 2,844 1,648 Gas
Silenus East-1 (R8) Ophir 2014 3,562 1,453 Gas
Fortuna-2 (R9) Ophir 2014 2,581 1,815 Gas
Reservoirs included in development scenarios
Development includes 6 commercial discoveries
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Discovered in 2008, appraised in 2012 & 2014
FORTUNA
Capital Markets Presentation - Fortuna FLNG Slide 25
• 4 well penetrations
• 58m of core
• 1 DST (Fortuna-2, 2014)
- 60 mmcf/d achieved on fixed 2” choke with a steady WHFP of c.2,100 psi (tubing and surface facility constrained)
• Preferred depositional model: laterally coalescing multiple channel levee systems
• Water Depth: 1680-1850m
• Reservoir Depth: 800m
• Area: 40.2km2
• Column Height: >115m
• Porosity and Permeability: 35-40%, 1000-1300mD
• Hydrocarbon quality: 99.7% Methane
• Contingent Resources: P50 1.5 TCF
• 3 wells planned in Phase 1 development
GWC: 2561.7mTVD
Fortuna Top Reservoir Depth Map
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Discovered in 2008/2012
VISCATA
Capital Markets Presentation - Fortuna FLNG Slide 26
• 3 well penetrations
• Preferred depositional model: channel levee system
• Water Depth: 1710-1840m
• Reservoir Depth: 1000m
• Area: 70km2 (P50)
• Column Height: 90m
• Contingent Resources: P50 0.4TCF
• One early development well in phase 1 development
• Three wells planned in Phase 3
GWC: 2748mTVD
Viscata Top Reservoir Depth Map
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Discovered in 2012
TONEL
Capital Markets Presentation - Fortuna FLNG Slide 27
• One well penetration
• 18m of core
• Preferred depositional model: Confined, erosional,
Low Sinuosity Channel-fill and spill
• Water Depth: 1520-1630m
• Reservoir Depth: 1000m
• Area: 4.7km2
• Column Height: >190m
• Contingent Resources: P50 0.5 TCF
• One well planned in Phase 2 development
Tonel Top Reservoir Depth Map
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Thrust Belt Accumulations
SILENUS HUB
Capital Markets Presentation - Fortuna FLNG Slide 28
• Three drilled discoveries:
- Estrella de Mar-1 (2002)
- Lykos-1 (2008)
- Silenus East-1 (2014)
• Preferred depositional model: semi-confined
laterally coalescing multiple channel levee systems
• Water Depth: 1400-1600m
• Contingent Resources: P50 0.49 TCF
• 5 Undrilled low risk prospects:
- Mejillon, Rhodes, Euthenia, Helios
• The CoS for all undrilled accumulations in the
Silenus Hub is 80%
Silenus Hub Amplitude Map
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
ERCE certified numbers
SUBSURFACE SUMMARY – ERCE CERTIFIED
Capital Markets Presentation - Fortuna FLNG Slide 29
Tcf (100% Basis) BASE CASE
Fortuna 1.52
Viscata 0.42
Tonel 0.50
Silenus Hub(1) 0.49
Total Contingent Resources(2) 3.01
Silenus Hub Low Risk Prospects(1) 0.65
Total Recoverable Resources(1+2) 3.66
Low cost and simple:
• High permeability and porosity
- Fewer wells and standard drilling techniques
• High quality gas – clean and dry
- Minimal processing required
• Location has benign ocean conditions
- Suitable for FLNG vessel
• Shallow reservoir
- Low cost wells
(1) Deterministic summation (2) Probabilistic summation
Shallow reservoir
Hydrocarbon composition
Benign sea state
Low cost vessel solution
Proximity to 2+ markets
Fortuna FLNG
Resources Upstream Midstream Financials Marketing
20 years at 2.2mmtpa = 2.6 Tcf Additional volumes for 2nd vessel = 1.4 Tcf
4.0 Tcf (including compression)
DEVELOPMENT
Philip Dobson Project Manager
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Playing to Ophirs strength
SIMPLE CONTRACTING STRATEGY
Capital Markets Presentation - Fortuna FLNG Slide 31
EPCIC
WBS Assets / Activity
Owner’s Engineer in support of
PMT
FEED Detailed Design
Procure Fabrication / Construction
Installation Hook-up
& pre-commission
Start Up Operations
Inspection, Maintenance
& Repair (IMR)
Drilling
Up
stre
am
Wellhead & Xmas Trees
Control System
Umbilicals
Manifolds incl. Foundations
Mooring Piles (Optional)
Risers & Flowlines incl. FTAs & Jumpers
FLNG Vessel
or
Wells to be executed by Ophir drilling team in London
PM/Engineering contractor with subsea and FLNG experience
SURF / SPS partnership – FEED followed by LS EPCIC
BOO contractor to provide facility on leaseback, plus operating fee Subsea facility operation on instruction from Ophir
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
UPSTREAM
• Worley Parsons contracted April 2015
• Upstream FEED commenced July 2015
MIDSTREAM
• Golar HoT signed May 2015
• Midstream FEED commenced August 2015
Leveraging expertise of industry leading partners and contractors
OVERALL DEFINE PHASE STRUCTURE
Capital Markets Presentation - Fortuna FLNG Slide 32
Liquefaction & Pre-treatment Naval Architecture & Utilities Inlet Facilities Turret & Mooring
FLNG EPC
Owners’ Engineer
FEED Contractor 2
Marine Simulations
FLNG FEED
Upstream Operator Drilling & Completions
FEED Contractor 1
Safety, Class
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
DEVELOPMENT OVERVIEW
Midstream Development
• Leased FLNG vessel
- Day rate-based charter agreement
• 2.2mmtpa LNG capacity per vessel
- One vessel at start-up 2019
- Second vessel on site by 2025
• Black & Veatch liquefaction process
- Proven, simple process
Capital Markets Presentation - Fortuna FLNG Slide 33
Upstream Development
• JUST 4 development wells for first gas
- Includes contingency of 1 Well
• Standard subsea infrastructure
- Manifold, Flowlines, Risers
• Four phase development with a total of 17 wells
Resources Upstream Midstream Financials Marketing
Later phase tie in example
Phase 1 4 Wells
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
4 phases of development
KEY PARAMETERS
Capital Markets Presentation - Fortuna FLNG Slide 34
• Subsea gathering system to dual risers
• 440 mmscfd design flowrate to match FLNG nameplate of c2.6-2.8 mmtpa
• 360 mmscfd annualised daily average gives 2.2 mmtpa LNG
• 200 mmscfd design flowrate per well
• 25yrs design life
• Water depth = ~1800m
• Reservoir depth =~800-1000m
• 2 FLNG vessels
Daily Production, mmcf/d (100% Basis)
Legend
Flexible Flowline
Flexible Riser
Gas Production Flowline
FLNG Vessel Location
Resources Upstream Midstream Financials Marketing
-
100
200
300
400
500
600
700
20
18
20
19
20
20
20
21
20
22
20
23
20
24
20
25
20
26
20
27
20
28
20
29
20
30
20
31
20
32
20
33
20
34
20
35
20
36
20
37
20
38
20
39
20
40
20
41
20
42
Vessel 1
Vessel 2
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
WELLS PHILOSOPHY
Slide 35
Governance • Wells planned and executed according to Ophir's Drilling Management System (DMS) & Engineering Process
• Wells designed in accordance with Ophir's Well Integrity Standard
• Use of an experienced and proven Well Construction Team
Reliability
• Simple well design
• Application of proven practices for high rate gas and deepwater – Gravel Pack Completions
- Robust sand and erosion management strategy to minimise future well intervention
• Emphasis on utilising field proven technology and equipment
- 5” Horizontal XT has a good track record, deployed successfully in high rate gas and deepwater
• Redundancy in well count
• Engineering phase 1 to run on a minimum of two wells to meet plateau production
Cost • Well designs which enable standardisation of equipment
• Short duration wells (<35 days per well to Drill, Complete & Clean-up)
• Minimal technical and operational risk
Capital Markets Presentation - Fortuna FLNG Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
WELL DESIGN
Capital Markets Presentation - Fortuna FLNG Slide 36
5" HXT
WD: 1,815 m
All depths are mTVD BML
20" x 13-5/8" Swage
36" Conductor @ 100 mBML
Control Lines:
Black TRSV 1
TRSV 2
DHPG
9-5/8" Production Tubing
Tubing Retrievable Safety Valve @ 400 mBML
Downhole Pressure & Temperature Gauge
13-5/8" Upper Completion Packer
13-5/8" Gravel Pack System
13-5/8" Casing @ 645 mBML
Fluid Loss Control Valve
Primary Target @ 680 mBML
7" Production Sand Screens
12-1/4” OH
Well TD @ 710 mBML
DHPG
Equatorial Guinea Block R Development
Fortuna Conceptual Well Schematic
TRSV
2 String Fortuna Well Design
Drilling Strategy
• 2 and 3 string well designs proposed
• 2 String: 36” Conductor x 13-5/8” Surface Casing
• 3 String: 36” Conductor x 13-5/8” Surface Casing x 10-3/4” Production Casing
• 12-1/4” reservoir hole size to optimised for sand face completion
Completion Strategy
• Excellent connectivity and highly productive reservoir allowing well count to be minimised – leveraged through open hole completion
• Gravel pack selected to provide robust sand control in high rate gas environment
• SIMPLE upper completion components (Packer, Gauge, Safety Valve)
• Risk of well failure minimised through simple completion design and effective sand management through gravel pack
Resources Upstream Midstream Financials Marketing
Simple technology, proven technology
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
SUBSEA INFRASTRUCTURE
Capital Markets Presentation - Fortuna FLNG Slide 37
Subsea specifications subject to FEED outcomes
Xmas Trees
• 5-inch Horizontal Xmas Tree (“HXT”)
• Pressure rating 5,000 – 15,000psi
SPS
• Simple concept
• Manifold to individual Wells via jumpers
• Meg injection via cores within the umbilical
SURF
• Steel tube umbilicals,
• Dual 12” Flowlines and Risers
• Riser specification (full flex or Steel)subject to FEED.
Flow Assurance
• System capable of 440mmscfd with 70 bar arrival pressure (30 bar in later field life)
• Production fluids downstream of the choke are expected to be within the hydrate formation region
• Continuous MEG injection via the main umbilical selected to manage hydrate formation
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
External turret production to maximise offloading availability
FROM TREE TO TURRET
Capital Markets Presentation - Fortuna FLNG Slide 38 Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
UPSTREAM/MIDSTREAM INTERFACE
Capital Markets Presentation - Fortuna FLNG Slide 39
Minimum project specific inlet facilities
ETP, External Turret
Production
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Base Case
PROJECT PHASING
Capital Markets Presentation - Fortuna FLNG Slide 40
3
1
3
1
1
3
1
4
17
0
2
4
6
8
10
12
14
16
18
20
Fortuna Viscata Silenus East EDM Tonel Viscata Lykos Silenus HubProspectiveResources
Total
Nu
mb
er o
f W
ells
Phase 1 2018 (pre-first gas)
Phase 2 2024
Phase 3 2027
Phase 4 2030
FLNG 2
FLNG 1
• Four wells to be drilled pre-first gas for Phase 1
- Only two expected to be required to achieve
2.2mmtpa plateau
• Five wells to be drilled in 2024 to elevate plateau to 4.4mmtpa utilising a second FLNG vessel
• Eight further wells in 2027 and 2030 drilling phases
Early development well – full
development in Phase 3
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Simple development
Using proven technology
Minimum interfaces
Front end loading in accordance with AACE and industry standards
Delivered by world class contracting companies
Bench-marked – cost and schedule
UPSTREAM DEVELOPMENT SUMMARY
Capital Markets Presentation - Fortuna FLNG Slide 41
Shallow reservoir
Hydrocarbon composition
Benign sea state
Low cost vessel solution
Proximity to 2+ markets
Fortuna FLNG
Resources Upstream Midstream Financials Marketing
MIDSTREAM - GOLAR
Gary Smith CEO, Golar LNG
43
Ophir Capital Markets Day Midstream Solution
GoFLNG Gandria
Our strategy and investment proposition from 2015 and beyond
Transitioning to Integrated LNG Mid-Stream Player
Golar’s strategic intent: integrated LNG mid-stream services provider: floating liquefaction, LNG shipping and FSRU services.
Intent emanates from success in shipping & regas.
Golar owns one of the largest & most modern fleets.
Dominant market share of FSRU market.
Ambition: LNG liquefaction game changer.
Developed GoFLNG floating liquefaction concept.
GoFLNG:
- substantially lower unit cost liquefaction.
- shorter lead-times.
- significantly lower execution risk profile.
Advantages most pronounced in remote locations & developing economies with stranded gas reserves.
Overview of the LNG Value Chain
Exploration & Drilling
Production & Liquefaction
Shipping Regasification Power
generation
FLNG LNG Carriers FSRU
LNG Midstream
Slide 44
Golar’s Portfolio
Slide 45
Four Successful FSRU Conversions
Golar Spirit Golar Winter
Golar Freeze
Operational Operational Operational
Nusantara Regas Satu
Operational
• 1981 Built / 129,000 m3
• Moss Containment
• 2.5 bcm / year
• Near Shore (Existing Pier)
• Over jetty LNG transfer
• HP arms on pier
• Closed Loop
• 2004 Built / 138,000 m3
• Membrane Containment
• 5.1 bcm / year
• Near Shore (New Pier)
• Over jetty LNG transfer
• HP arms on pier
• Open / Closed Loop
• 1976 Built / 125,000 m3
• Moss Containment
• 4.9 bcm / year
• Near Shore (New Pier)
• Side by side LNG transfer
• HP arms on pier
• Open Loop
• 1977 Built / 125,000 m3
• Moss Containment
• 5.0 bcm / year
• Offshore
• Side by Side LNG transfer
• Gas manifold
• Open Loop
Slide 46
Perenco’s FLNG project in Cameroon
Sanaga gas fields:
500 bcf of natural gas reserved for export.
Benign, shallow water, offshore Kribi.
Lean associated feedgas.
Potential for extension of feedgas volumes and
project life.
Project:
8 year project life at production of 1.2mtpa.
SNH, Perenco and Golar have executed an effective
and binding gas convention.
Binding tolling agreement between Perenco, Golar
and SNH also executed.
EBITDA based on 2 trains will be between $170-
$300m.
If 3 trains are utilised EBITDA will be between $240-
$430m.
Financing in place, Q2 2017 start-up.
FLNG Hilli:
Construction on-going with target delivery in early
2017.
Sanaga field
Slide 47
GoFLNG Concept & Key Philosophies
Conversion of Moss type LNG carrier.
Sponson structures added to the sides as integral structural
sections providing space and deck area for process and utility
systems.
Extensive refurbishing and life-extension scope for hull, marine
and cargo systems.
Proven technologies and equipment.
Low cost solution.
Basis of Design covers a wide envelope of operating and
environmental conditions.
Leveraging Golar’s successful operations experiences to develop
FLNG specific Operations & Maintenance plans.
4 train liquefaction concept selected for high availability and
maximum proven equipment with generic pre-treatment including
CO2 removal, dehydration, Hg and HHC removal.
Side-by-side offloading using industry standard marinised
equipment and operating procedures.
Generic floating liquefaction concept with field-specific inlet or
wellstream production facilities as an option.
Adaptable to various mooring concepts including jetty, spread-
mooring or SPM type systems.
Offshore Classed production facility w/o need for dry-docking
during project life.
Slide 48
Process Overview
Slide 49
• Prico Technology is based on a Single Mixed
Refrigerant liquefaction technology.
• Proven at 25 plants world wide and a further 18 in
engineering/construction stage.
• Simple and robust with good efficiency.
• Refrigerant compressor mechanically driven by single
gas turbine (LM2500+G4 DLE).
• GE BCL centrifugal compressor.
• Train turn-down capability to 50% of max capacity.
• Nameplate liquefaction capacity from 0.5-0.7 mtpa
(depending mainly on inlet pressure, feedgas
composition and ambient air temperature).
• GE LM2500+G4 is well proven offshore and for
mechanical drive configurations (>110).
• Chart Industries selected for BAHX cold box (6 cores).
• Heat Recovery Steam Generation HRSG for process
heat and steam turbine power generation.
Liquefaction Technology
Slide 50
Four Train FLNG Vessel – Starboard View
Amine absorption for acid gas removal
Refrigerant make-up,
boil-off compression,
endflash Dehydration and
mercury removal
Marine Loading Arms
Slide 51
Four Train FLNG Vessel – Port View
4 Prico SMR trains with waste heat steam
generator
Alternative mooring concepts,
e.g. submerged yoke
Accommodation for max
118 POB
Transverse pipebridges
Slide 52
Sponson Structures
Design and functionality:
Fully welded and integral part of the hull. Structural
alignment with existing hull applied where possible
(i.e. flush and continuations).
Providing footprint area for process systems, but
contribute as well to strength, displacement, stability,
utility space/area.
Two deck levels provide the necessary deck area for
the process systems (red markings).
Lower sponson spaces used for utilities and tanks.
Strong focus on the design of the lower sponson
deck for:
Material handling.
Maintenance.
Access.
Safety.
Escape.
Constructability.
Slide 53
FLNG Hilli Sponson Integration Ongoing
Sponson Block P4 in Dry Dock
Sponson block P4 & S4 integration
Sponson Block S4 arriving to DryDock
Sponson block P4 integration to hull
Slide 54
Project / Field specific modifications
Main topics for modification of project specific verification:
Mooring.
Riser system.
Metocean conditions.
Feedgas compositions.
Inlet systems and conditions (pressure, temperature, dynamics).
Wellstream production (flow assurance, well control, inlet facilities (separation, PW
treatment)) by lengthening of the bow.
Emissions and effluents (local/shelf state requirements).
Pre-treatment criteria (higher CO2, H2S, mercaptans, etc..).
HHC separation, stabilisation, storage and offloading (condensate, LPG).
Option for bow modification to
provide additional deck space
for wellstream production.
Slide 55
LNG Offloading
LNG Offloading
• Max rate: 10,000 m3/h
• Vapour return handled by FLNG vessel
• 4 Marine Loading Arms (2 x liquid, 1 x vapour, 1 x dual/spare)
• Side-by-side mooring
• Yokohama fenders and QRHs on FLNG vessel
• Berthing assisted by 2-3 tugs
• Offloading feasible with Carriers up to 180,000 m3
Mooring Simulations
• Statistical evaluation of site-specific metocean data
- High availability for side-by-side offloading
• 15 years of continuous metocean time series data procured comprising:
- Wind seas with direction;
- Two separate swell seas with directions;
- Wind speed and direction;
- Current and direction; and
- Three hour timestep
• Non-linear hydrodynamic simulations and availability assessment performed as part of midstream FEED
Ship-to-ship LNG transfer at Golar FRSU projects
Slide 56
Hilli Peer Review October 2015
Terms of Reference: • evaluate the design, layout, interconnections with existing ship systems, documentation, and governance of the project
with particular reference to the operability, maintainability and reliability of the facility, with the following objectives: • safe, practical and timely start up • safe and reliable operation • efficient maintenance of the plant
Review led by Geoffrey Ellison: • 27 years with Shell (LNG, GTL, Refining) • GM Malaysia LNG (2000-2004) - production capacity 24 mtpa.
Overall Assessment: • in terms of process design, operability and maintainability the plant is of a superior standard to many LNG projects • the vast majority of peer best practice and lessons learnt is incorporated into the design
Slide 57
BREAK
Slide 58
COMMERCIAL & MARKETING
Andy Arnold Director - Commercial
Scope for new capacity to be absorbed
GLOBAL LNG SUPPLY – DEMAND
Capital Markets Presentation - Fortuna FLNG Slide 60
Source: Wood Mackenzie, Ophir Energy
• Unsanctioned projects suggest a potential oversupply – this is always the case
• Global LNG market runs at around 85% capacity
• A number of these projects won’t get sanctioned or will be delayed
• Demand from new markets offers higher value pricing but requires greater flexibility
• Cost-advantaged projects that are mature are able to find buyers and FID at present
• Demand always underestimated because doesn’t include latent demand from substitution
0
100
200
300
400
500
600
700
00 03 06 09 12 15 18 21 24
Supply - operational projects
Supply - projects under construction
Supply - possible projects not sanctioned
LNG Demand
Total possible supply
Estimated LNG Supply v Demand 2000-2024
mm
tpa
Resources Upstream Midstream Financials Marketing
Scale, sponsorship and commercial simplicity
Larger projects planning to take FID in 2015 are delayed, struggling to find buyers or reengineering to smaller scale
GLOBAL LNG SUPPLY RESPONSE IN 2015
Slide 61
FID in 2015
FID timing uncertain
FID Delayed / Cancelled
Tangguh Train 3 delayed ($12bn cost, no Buyers)
Moz LNG – 21 mmtpa – no clear indication of
FID in 2015
Pacific North West –
12mmtpa – Land access delaying full
FID
Cameroon FLNG –
1.2mmtpa – FID Sept
2015
• Excelerate FLNG – 8mmtpa cancelled
• Lake Charles 10mmtpa – postponed • Sabine T6 (4.5) and Corpus T3 (4.5)
requires more customers to FID
Expansion Trains at
Freeport (4.4) & Sabine Pass
(4.5)
Coral FLNG – 2.5 mmtpa announces BP as Buyer
Browse FLNG (4.0mmtpa)
uncertain
Douglas Channel 0.6 mmtpa FID in 2015
Capital Markets Presentation - Fortuna FLNG Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Commodity price slump creates challenging conditions for LNG projects
• Sharp decline in global oil prices and LNG prices
• Reduction in Asian growth coupled with corresponding price uncertainty
• Market sentiment of oversupply drawn from Australian and US start ups and unsanctioned possible projects
Fortuna FLNG has sought to take advantage of LNG market hiatus
• Reengineered project
- Lower cost upstream development
- Moved to FLNG conversion solution
- Innovative marketing approach to attract wider market interest
FORTUNA FLNG - OPHIR RESPONSE TO THE MARKET
Capital Markets Presentation - Fortuna FLNG Slide 62 Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
DES
ROBUST COMMERCIAL STRUCTURE
Slide 63
FOB NETBACK
$ CASHFLOW
GAS / LNG FLOW
LEASE AND OPERATE EUROPE/ASIA
TOLLING MODEL
UPSTREAM PSC MIDSTREAM LNG BUYERS
Capital Markets Presentation - Fortuna FLNG Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
STRAIGHTFORWARD AGREEMENTS FRAMEWORK
Long Term Buyer 1
Long Term Buyer 2
Golar SPC
“Umbrella Agreement”
PSC State
JOA
Ophir
GEPetrol
Golar OPCO
Existing agreements:
• PSC – gas terms agreed
• JOA
New agreements:
• Umbrella Agreement
- Fiscal treatment and legal structure for
the FLNG Vessel
• Chartering Agreement
- Terms under which Golar will provide
the FLNG vessel to Ophir
• O&M Agreement
- Terms under which Golar will operate
and maintain the FLNG vessel
• LNG SPAs
- Entered into with LNG purchasers for
the sale of LNG volumes
Slide 64
LNG Sale & Purchase Agreements
Upstream EPCIC Contractor
Capital Markets Presentation - Fortuna FLNG
Chartering Agreement
O & M Agreement
EPCIC Agreement
Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Conventional oil indexation
FOCUSED MARKETING STRATEGY
End Users Aggregators Traders
Hold European capacity
Secure investment floor
Access to New Markets
Incentivised to divert
Trading experience Indexation value
Value driven - oil indexation
Core LNG markets
European Market (NBP/TTF) with diversion profit sharing
Slide 65 Capital Markets Presentation - Fortuna FLNG Resources Upstream Midstream Financials Marketing
Use these buttons to set whether the text is a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
“EUROPEAN SINK” CONTRACTING STRATEGY (INDICATIVE PRICES)
LNG BUYERS SHIPPING MIDSTREAM
EUROPE
HIGHER VALUE
MARKET (FOB)
PRICE: $11.4/mmBtu
Incremental COST:
$1/mmBtu
NETBACK: $3.1/mmBtu
UPSTREAM PSC
PRICE: $7/mmBtu COST:
$1.9/mmBtu NETBACK
$2.3/mmBtu
REGAS & SHIPPING
LIQUEFACTION NETBACK
COST: $2.8/mmBtu
BA
SE C
ASE
D
IVER
SIO
N
(5
0%
of
Vo
lum
es)
BASE CASE PRICE
COST: $7.0/mmBtu
NET INCREMENTAL FOB VALUE
$0.85/mmBtu
COST: $2.9/mmBtu
Slide 66 Capital Markets Presentation - Fortuna FLNG Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
COST COMPARISON: US V EG
Capital Markets Presentation - Fortuna FLNG Slide 67
Fortuna will be a low cost supplier into European market
• Liquefaction costs are comparable
• Fortuna is cheaper at the well-head v Henry Hub
• European buyers do not need to take Henry Hub price risk
0
1
2
3
4
5
6
7
8
US LNG Fortuna
$ p
er m
mb
tu
FOB Breakeven into Europe (NPV10)
Liquefaction
Upstream
Resources Upstream Midstream Financials Marketing
$4.40
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
LNG SPAs (Mar 2016)
TARGETED MARKETING PROCESS
Market Scoping
From June 2015
Selected Negotiation
Sept 2015 Finalising
Heads of Agreement
Traders 10
End Users 6
Aggregators 3
Traders - 3
End Users - 3
Aggregators - 1
Final SPA Negotiations
Full draft discussion
Jan 2016
3 Buyers
Engagement with over 30
Buyers
1 - 2 Buyers
Slide 68 Resources Upstream Midstream Financials Marketing Capital Markets Presentation - Fortuna FLNG
Ophir choice to shortlist competing offers
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Fortuna FLNG attractive to LNG buyers
MARKETING SUMMARY
FORTUNA FLNG
Speed of execution Right project partners means marketing can break the mould
Cost competitiveness Low upfront costs combined with phased development
Commercial flexibility to respond to market
Flexibility for foundation customers on volume, term, structure
Line of sight to FID Not reliant on other buyers or project financiers to underpin FID
Tailored commodity exposure Offer alternative commodity indexation to meet Buyer needs
Slide 69 Capital Markets Presentation - Fortuna FLNG
Shallow reservoir
Hydrocarbon composition
Benign sea state
Low cost vessel solution
Proximity to 2+ markets
Fortuna FLNG
Resources Upstream Midstream Financials Marketing
PROJECT FINANCIALS
Tony Rouse CFO
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Gross upstream capex to 1st gas $800 million
Life of field opex (upstream) $476 million / $0.14 per mcf / $0.80 per boe
Plateau production rate (2 vessels) 720 mmscfd; 120,000 boepd
Peak (gross) cash flow $1bn per annum
FOB Breakeven Price (NPV 10) $5.30 per mmbtu (Pacific basin) $4.40 per mmbtu (European sink)
Project payback period 3 years from first gas 6 years from FID
Minimum economic field size for tie-ins 40 Bcf
KEY FIGURES
Capital Markets Presentation - Fortuna FLNG Slide 71 Resources Upstream Midstream Financials Marketing
Robust at current commodity prices; highly levered to upside in commodity prices
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
CAPEX
Capital Markets Presentation - Fortuna FLNG Slide 72
• 2016–18 Subsea capex relates to the EPCIC contract to be awarded to the successful FEED partnership
• Drilling CAPEX assumptions reflect conservative estimates based on forecasted 2017-18 rig rates
• Ophir expects final drilling costs to be lower than illustrated as well plans are optimised
• Full upstream capex of $3 bn over four development phases; unit capex of $0.80 per mmbtu
Second vessel
Resources Upstream Midstream Financials Marketing
First vessel
1
0
250
500
750
Gro
ss C
apit
al E
xpen
dit
ure
($
mill
ion
, 20
15
Rea
l)
UPSTREAM OPEX
Slide 73
$ million (100% Basis, 2015 real, phases 1 – 4) BASE CASE
Well replacement(s) 132.2
Well workover(s) 162.3
Planned inspections 83.9
Planned maintenance and contingent repairs 98.0
Total Life of Field Opex 476.4
Total Opex per Annum 22.7
Total Opex per mmBtu 0.14
Opex of $0.14/mmBtu ($0.80/boe)
• Inspection, maintenance and repair scope based on reliability performance data for Conceptual SURF layout and critical well sub-systems
• Probability of well failure requiring re-drill estimated at 1 in 9 based on completion complexity, geological setting and production conditions
Capital Markets Presentation - Fortuna FLNG Resources Upstream Midstream Financials Marketing
Highly cash generative, fast payback
• Payback within 3 years of first gas
• Gross project cash flow (unlevered) approaching $12 billion
CASH FLOW PROFILE
Slide 74 Capital Markets Presentation - Fortuna FLNG
(8,000)
(4,000)
-
4,000
8,000
12,000
(800)
(400)
-
400
800
1,200
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041
Cu
mu
lati
ve F
ree
Cas
h F
low
($
mm
)
Free
Cas
h F
low
($
mm
)
Free Cash Flow
Cumulative Free Cash Flow
Annual Free Cash Flow (Base Case, Gross)
Economics shown at 55p/therm NBP, $85/bbl Brent
Resources Upstream Midstream Financials Marketing
Low level of commitment spend, robust production base
Strong cash position
• Guidance of $650 million of cash on balance sheet at YE 15
Reducing capex to maintain balance sheet strength
• 2016 capex guidance of $175 million - $225 million
Underlying operating cash flow
• Guidance of $100 million of operating cash flow from production
High degree of financial flexibility
• Total E&A commitment spending of $75 MM through end 2017
FINANCIAL FLEXIBILITY
Capital Markets Presentation - Fortuna FLNG Slide 75 Resources Upstream Midstream Financials Marketing
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Multiple options, not reliant on any one source
FUNDING FORTUNA FLNG
Capital Markets Presentation - Fortuna FLNG Slide 76
LENDING BALANCE SHEET
$640 MM net cost to first gas
Variety of potential sources to cover up to 60% of capex to first gas:
• Pre FID – lending banks, value chain partners
• Post FID – project financing, lending banks, debt markets
Cash
• $700MM cash (mid ‘15)
• $400MM net cash (mid ’15)
• Asset Divestment
Up to 40% W.I. farm-out:
• reduces capex by $320 million
• contribution against past costs of $600 million
Resources Upstream Midstream Financials Marketing
PROJECT EQUITY
(expect to reduce in FEED)
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Balance sheet strength
• Drive to reduce capex and cost across the business
• Financial flexibility in a low oil price environment
• Incremental debt finance
Fortuna offers robust project economics
• Low capex to first gas
• Low unit operating costs
• Flexible tolling arrangement
Options to reduce Ophirs capex to first gas
• Farm out
• Competitive upstream FEED
FUNDING SUMMARY
Capital Markets Presentation - Fortuna FLNG Slide 77 Resources Upstream Midstream Financials Marketing
ROBUST PROJECT IN LOW PRICE ENVIRONMENT WITH MATERIAL CASH FLOW FROM 2019
SUMMARY
Bill Higgs
COO
SELF FUND
• Not all barrels are equal
• We explore for high quality barrels that generate cash in a low price environment
• Project equity is a source of capital
No fresh capital deployed to development
SELF FUNDING DEVELOPMENT ASSETS
Slide 79
PRODUCTION
TOTA
L V
OLU
ME
2C
:
99
8 M
Mb
oe
TANZANIA W.I. 20%
KERENDAN W.I. 70%
BUALUANG W.I. 100%
EQUATORIAL GUINEA W.I. 80%
CASH FOR E&A
First gas 2019
First gas 2022
First gas 2016 2nd phase of dev.
On production 3rd phase of dev.
2P RESERVES
SELF FUND
Capital Markets Presentation - Fortuna FLNG Low risk Low cost Quick to first gas
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
Making the Fortuna FLNG project attractive to buyers
FLNG – DELIVERING SUCCESS
Capital Markets Presentation - Fortuna FLNG Slide 80
• Finalise chartering agreement • Ophir & GEPetrol • Agreed • 3.7 TCF
• 2.2 Mtpa project
Resources Fiscal Terms JV Partner Alignment Midstream
• Well delineated resource
• Fortuna well test flowed at 60 mmscf/d (equipment constrained), implied unconstrained rate of 180mmscf/d
• PSC Fiscal terms have been agreed in accordance with an LNG project
• Provides robust returns
• Government support
• GEPetrol is the state entity created to participate in all licences in EG
• Supportive of Ophir exploration and development activity to date
• Will fund equity percentage in development
• Golar LNG appointed as a midstream partner to provide an FLNG vessel on a tolling basis
• Key commercial terms agreed for Golar to build, operate and maintain an FLNG vessel
• Full charter agreement to be negotiated by Q2 2016
1 2 3 4
Low risk Low cost Quick to first gas
Project delivering to schedule
MILESTONES
Slide 81
2014 2015 2016 2017 2019 2020
Commercial milestones achieved
May 2015 Charter Term Sheet agreed with Golar for provision of leased FLNG vessel
Jun 2015 Launched offtake process
Jul 2015 Awarded Competitive FEED contracts to McDermott / GE and Aker / Subsea 7
Nov 2014 Renegotiation of PSC for gas development
Capital Markets Presentation - Fortuna FLNG Low risk Low cost Quick to first gas
Nov 2015 Heads of Agreement signed for gas offtake
Q1 2016 FEED completed
Mid-2016 Project FID
Mid-2019 First gas
Milestones to first gas
Oct 2014 Flow tested gas Surpassed threshold volumes
Exploration and appraisal milestones achieved
Use the buttons on the graphic below to set the text as a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
INVESTMENT HIGHLIGHTS
Capital Markets Presentation - Fortuna FLNG Slide 82
World-Class Resource
Biogenic Dry Gas, 99.7% Methane
Simple Upstream Development
Low Cost Midstream Solution, Proven Technology
Robust Economics
Stable, Supportive Political Environment
Substantial Upside
1
2
3
4
5
6
7
Low risk Low cost Quick to first gas
Q&A
Use these buttons to set whether the text is a bullet header or normal bullet
Default slide has bullet header first to change this to a normal bullet click the increase list level button
Decrease or Increase lift level style
For further information contact:
Head of IR and Corporate Communications [email protected]
Geoff Callow
Level 4 123 Victoria Street London SW1E 6DE UNITED KINGDOM
Tel: +44 (0)29 7811 2400 Fax: +44 (0)20 7811 2421
Capital Markets Presentation - Fortuna FLNG Slide 84