capital budgeting - gagan

26
CAPITAL BUDGETING Gagan Deep Sharma (Dr) USMS, GGSIPU, New Delhi

Upload: anchal-chhabra

Post on 23-Apr-2017

271 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Capital Budgeting - Gagan

CAPITAL BUDGETING

Gagan Deep Sharma (Dr)

USMS, GGSIPU, New Delhi

Page 2: Capital Budgeting - Gagan

CONTENTS

Overview and “vocabulary”

Methods

Payback, discounted payback

NPV

IRR, MIRR

Profitability Index

Unequal lives

Economic life

3/8/2014 GDS 2

Page 3: Capital Budgeting - Gagan

WHAT IS CAPITAL BUDGETING?

Analysis of potential projects

Long-term decisions; involve large expenditures

Very important to firm’s future

3/8/2014 GDS 3

Page 4: Capital Budgeting - Gagan

STEPS IN CAPITAL BUDGETING

Estimate cash flows (inflows & outflows).

Assess risk of cash flows.

Determine r = WACC for project.

Evaluate cash flows.

3/8/2014 GDS 4

Page 5: Capital Budgeting - Gagan

INDEPENDENT V/S MUTUALLY EXCLUSIVE PROJECTS?

Projects are:

independent, if the cash flows of one are unaffected by the acceptance of the other.

mutually exclusive, if the cash flows of one can be

adversely impacted by the acceptance of the other.

3/8/2014 GDS 5

Page 6: Capital Budgeting - Gagan

PAYBACK PERIOD?

The number of years required to recover a project’s cost,

or how long does it take to get the business’s money back?

3/8/2014 GDS 6

Page 7: Capital Budgeting - Gagan

PAYBACK FOR FRANCHISE L

10 8060

0 1 2 3

-100

=

CFt

Cumulative -100 -90 -30 50

PaybackL 2 + 30/80 = 2.375 years

0

100

2.4

3/8/2014 GDS 7

Page 8: Capital Budgeting - Gagan

PAYBACK FOR FRANCHISE S

70 2050

0 1 2 3

-100CFt

Cumulative -100 -30 20 40

PaybackS 1 + 30/50 = 1.6 years

100

0

1.6

=

3/8/2014 GDS 8

Page 9: Capital Budgeting - Gagan

Strengths of Payback:

1. Provides an indication of a

project’s risk and liquidity.

2. Easy to calculate and understand.

Weaknesses of Payback:

1. Ignores the TVM.

2. Ignores CFs occurring after the

payback period.

3/8/2014 GDS 9

Page 10: Capital Budgeting - Gagan

10 8060

0 1 2 3

CFt

Cumulative -100 -90.91 -41.32 18.79

Discountedpayback 2 + 41.32/60.11 = 2.7 yrs

Discounted Payback: Uses discounted

rather than raw CFs.

PVCFt -100

-100

10%

9.09 49.59 60.11

=

Recover invest. + cap. costs in 2.7 yrs.

3/8/2014 GDS 10

Page 11: Capital Budgeting - Gagan

.

10t

tn

t r

CFNPV

NPV: Sum of the PVs of inflows and

outflows.

Cost often is CF0 and is negative.

.

10

1

CFr

CFNPV

t

tn

t

3/8/2014 GDS 11

Page 12: Capital Budgeting - Gagan

WHAT’S FRANCHISE L’S NPV?

10 8060

0 1 2 310%

Project L:

-100.00

9.09

49.59

60.11

18.79 = NPVL NPVS = $19.98.

3/8/2014 GDS 12

Page 13: Capital Budgeting - Gagan

EXERCISE

3/8/2014 GDS 13

Page 14: Capital Budgeting - Gagan

EXERCISE

3/8/2014 GDS 14

Page 15: Capital Budgeting - Gagan

RATIONALE FOR THE NPV METHOD

NPV = PV inflows - Cost

= Net gain in wealth.

Accept project if NPV > 0.

Choose between mutually

exclusive projects on basis of

higher NPV. Adds most value.

3/8/2014 GDS 15

Page 16: Capital Budgeting - Gagan

USING NPV METHOD, WHICH FRANCHISE(S) SHOULD BE ACCEPTED?

If Franchise S and L are mutually exclusive, accept S because NPVs > NPVL .

If S & L are independent, accept both; NPV > 0.

3/8/2014 GDS 16

Page 17: Capital Budgeting - Gagan

INTERNAL RATE OF RETURN: IRR

0 1 2 3

CF0 CF1 CF2 CF3

Cost Inflows

IRR is the discount rate that forces

PV inflows = cost. This is the same

as forcing NPV = 0.

3/8/2014 GDS 17

Page 18: Capital Budgeting - Gagan

.

10

NPVr

CFt

tn

t

t

nt

t

CF

IRR

0 1

0.

NPV: Enter r, solve for NPV.

IRR: Enter NPV = 0, solve for IRR.

3/8/2014 GDS 18

Page 19: Capital Budgeting - Gagan

WHAT’S FRANCHISE L’S IRR?

10 8060

0 1 2 3IRR = ?

-100.00

PV3

PV2

PV1

0 = NPV

IRRL = 18.13%. IRRS = 23.56%.

3/8/2014 GDS 19

Page 20: Capital Budgeting - Gagan

RATIONALE FOR THE IRR METHOD

If IRR > WACC, then the project’s

rate of return is greater than its

cost-- some return is left over to

boost stockholders’ returns.

Example: WACC = 10%, IRR = 15%.

Profitable.

3/8/2014 GDS 20

Page 21: Capital Budgeting - Gagan

DECISIONS ON PROJECTS S AND L PER IRR

If S and L are independent, accept both. IRRs > r = 10%.

If S and L are mutually exclusive, accept S because IRRS > IRRL .

3/8/2014 GDS 21

Page 22: Capital Budgeting - Gagan

MIRR

MIRR is the discount rate whichcauses the PV of a project’s terminalvalue (TV) to equal the PV of costs.TV is found by compounding inflowsat WACC.

Thus, MIRR assumes cash inflows are reinvested at WACC.

3/8/2014 GDS 22

Page 23: Capital Budgeting - Gagan

MIRR = 16.5%

10.0 80.060.0

0 1 2 310%

66.0

12.1

158.1

MIRR for Franchise L (r = 10%)

-100.010%

10%

TV inflows-100.0

PV outflowsMIRRL = 16.5%

$100 = $158.1

(1+MIRRL)3

3/8/2014 GDS 23

Page 24: Capital Budgeting - Gagan

EXERCISE

3/8/2014 GDS 24

Page 25: Capital Budgeting - Gagan

WHY USE MIRR VERSUS IRR?

MIRR correctly assumes reinvestment at opportunity cost = WACC. MIRR also avoids the problem of multiple IRRs.

3/8/2014 GDS 25

Page 26: Capital Budgeting - Gagan

[email protected]

THANKS FOR YOUR TIME

3/8/2014 GDS 26