capacity demand curve for the office of the massachusetts attorney general
DESCRIPTION
Capacity Demand Curve for the Office of the Massachusetts Attorney General. Feb. 27 th , 2014. Prepared By: Randell Johnson Andrew Bachert Energy Exemplar. Guiding Principles. - PowerPoint PPT PresentationTRANSCRIPT
MA AGO 1
Capacity Demand Curve for the Office of the Massachusetts Attorney General
Prepared By: Randell Johnson Andrew Bachert
Energy Exemplar
Feb. 27th , 2014
27 February, 2014
MA AGO 2
Guiding Principles
• Determine a peak price of capacity curve that will minimize the build costs, production cost (E&AS), and shortage costs (VOLL*Unserved Energy) to achieve on a target 1 day in 10 year LOLE reliability metric
• Consider load risk impact during LOLE simulations• Assess price volatility of the capacity demand curve• Reconcile results with other regional markets• Review magnitude of incentives at peak price and rate of return on equity for
investments
27 February, 2014
MA AGO 3
Description of Optimization
• PLEXOS optimization determines the minimum net present value (NPV) of the system in terms of investments, production cost, ancillary services cost, and shortage costs– Subject to constraints of:
• Meeting demand• Feasible builds• Feasible production• 1 in 10 LOLE reliability standard• and others
• Investments are additional production, demand response, or other equipment of the system to meet constraints and at lowest cost
• Production cost is the short run marginal cost of the system to supply load subject to constraints• Ancillary services cost is the additional costs for meeting reserve provisions • Shortage Costs are costs when there is loss of load and these costs are a value of lost load (VOLL)
multiplied by the unserved energy• Capacity payments help to minimize shortage costs
Capacity Demand Curve has impact to least cost optimization27 February, 2014
MA AGO
Least Cost Optimization
Cost $
Investment x
Production Cost P(x)
Investment cost/ Capital cost C(x)
Total Cost = C(x) + P(x)
Minimum cost plan x
4
• Chart shows the minimization of total cost of investments and of production cost
• As more investments made production cost trends down however investment cost trends up
27 February, 2014
Objective: Minimize net present value of the sum of investment and production costs over time
MA AGO 5
Cost Minimization with Capacity Curve Peak Price Cont.
• Objective:– Minimize net present value of capital costs, production costs, ancillary costs, ancillary shortages,
demand shortages
• Minimize: – [Build Cost]+[Production Cost]+[Demand Shortage Cost]+[Ancillary Services Shortage Cost]
• Subject to:– [Electric Production] + [Electric Shortage] = [Electric Demand] + [Electric Losses]– [Ancillary Service Provision] >= [Ancillary Services Requirements]– [Electric Production] and [Ancillary Services Provision] feasible– [Build]<=[Max Build]– [Production]<=[Production Max] – [Intergrality] i.e. whole blocks of capacity – others
27 February, 2014
MA AGO 6
Illustrative Least Cost Optimization
VOLL Unserved Energy
Individual Unit Production Cost
Individual Unit Production
Individual Unit Build Cost
Amount Built
Investment Cost Production Cost
27 February, 2014
This simplified illustration shows the essential elements of the PLEXOS mixed integer programming formulation for determination of a demand capacity curve that would achieve a target reliability level of LOLE at 1-in-10.
PLEXOS also has many other variables and costs as part of the optimization such as capacity payments as well as other possible constraints
Due to time constraints method partially tested with
one year optimization
= for all= year = interval = unitY = Horizon
MA AGO 7
Least Cost Optimization with Capacity Demand Curve Explanation of Terms
• = Capital Cost • = Capacity Built by Type • • = Individual Unit Production• = VOLL• = Unserved Energy
27 February, 2014
• = MW Demand• = Max Capacity of individual Units• = Max Build Capacity by Type• = Target LOLE• Symbol means: for all• ∑ Symbol Means: sum up the individual items
MA AGO 8
Features of Capacity Demand Curve
27 February, 2014
Capacity Demand Curve Feature Observations for Feature
Peak Price- Determine a peak price of capacity curve that will minimize the build costs, production cost (E&AS), and
shortage costs (VOLL*Unserved Energy) to achieve on average a 1-in-10 reliability metric- Review the ROE of new plant at the peak price - Compared to NY-ISO peak price
Start of downward slope at less than 100% NICR
- Considered slope feature of other regional markets when quantity is less than NICR- Noted that the Initial Candidate Curve can peg capacity price at 2x CONE for an estimated 2.8% shortage
of 948 MW from 2017/18 NICR of 33,855- Considered a slope feature to reduce volatility
Curve crossing point over 100% NICR- Simulated 1 in 10 LOLE of 0.1 for crossing NICR above Net CONE- Consider load risk impact during LOLE simulations- Considered NICR crossing levels of other regional markets
Kink point- Set kink point to reduce volatility via more gradual slope compared to initial candidate curve- Capacity Prices of 70% and 80% Net CONE exceed many existing unit FO&M- Considered downward slopes of other regional markets in relation to foot of capacity demand curve
Foot- Adopted foot of initial candidate curve since the initial candidate curve has a foot at approximately 22%
ICAP and exceeds the LOLE 1 in 10 day criteria- Considered foot location for other regional markets
MA AGO 9
90.0
%
91.0
%
92.0
%
93.0
%
94.0
%
95.0
%
96.0
%
97.0
%
98.0
%
99.0
%
100.
0%
101.
0%
102.
0%
103.
0%
104.
0%
105.
0%
106.
0%
107.
0%
108.
0%
109.
0%
110.
0%
111.
0%
112.
0%
113.
0%
114.
0%
115.
0%
116.
0%
117.
0%
118.
0%
119.
0%
120.
0%
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
% of NICR
Price
(% o
f Net
CO
NE)
MA AGO Capacity Demand Curve
27 February, 2014
NICRLOLE: 1-in-10
Peak Price
NICR CrossingPoint
Start of Downward
Slope
FootKink
MA AGO 10
90.0%91.5%
93.0%94.5%
96.0%97.5%
99.0%100.5%
102.0%103.5%
105.0%106.5%
108.0%109.5%
111.0%112.5%
114.0%115.5%
117.0%118.5%
120.0%0.00
0.50
1.00
1.50
2.00
2.50
Initial Candidate Curve (xNet CONE)NY Curve (xNet CONE)PJM Curve (xNet CONE)MA AGO Curve (xNet CONE)
% of NICR
Price
(% o
f Net
CO
NE)
Comparison of Capacity Demand Curves
Initial Candidate Curve, NY Curve, PJM Curve coordinates estimated from MC materials: “Draft Recommendations for a Capacity Demand Curve in ISO-NE”, Slide 15, Jan 14, 2014
NICRLOLE: 1-in-10
27 February, 2014
MA AGO 11
Calculated 1-in-10 LOLE
27 February, 2014
28325
28590
28940
29340
29790
30265
30750
31445
32210
32900
32000 33000 34000 35000 36000 37000 38000
Installed Capacity (MW)
Sum
mer
201
7 Pe
ak Lo
ad F
orec
ast D
istrib
ution
(MW
)
ForecastProbability
2017Peak LoadForecast
10/90 28,32520/90 28,59030/70 28,94040/60 29,34050/50 29,79060/40 30,26570/30 30,75080/20 31,44590/10 32,21095/5 32,900
160 PLEXOSSimulations of High LevelISO-NE Control AreaModel
Results: NICR = 33,855 MW LOLE = 0.1 - Simulated load risk in calculating LOLE
- Simulated multiple capacity levels
MA AGO 12
Net CONE: many multiples of plant FOM
27 February, 2014
New Entrants Net CONE 11.71 % of Net CONEReference Technology
Capacity (MW)
Fixed O&M ($/kW-m) NET CONE/FOM 80% NET CONE ($/kW-m) 70% NET CONE ($/kW-m)
4x0 LM6000 173 3.26 3.6 9.4 8.22x0 LMS100 188 2.85 4.1 9.4 8.22x0 Frame CT 417 1.52 7.7 9.4 8.22x1 CC 715 2.4 4.9 9.4 8.2
Existing UnitsVarious sources of FOM data for existing units can range from 1 to 9 ($/kW-m) depending on type, size, and ageMany existing units would earn far in excess of FOM for capacity price of $11.71/kW-m
Source: New Entrants Data from MC Feb 27 Net CONE presentation
MA AGO 13
MA AGO Curve Reduces Price Volatility Compared to Initial Candidate Curve
27 February, 2014
Consumer Cost Items $ Billion SourceWholesale Electricity Markets $9.2 http://www.iso-ne.com/nwsiss/grid_mkts/key_facts/index.htmlTraded Energy Markets $8.0 http://www.iso-ne.com/nwsiss/grid_mkts/key_facts/index.htmlTraded Capacity and AS $1.2 http://www.iso-ne.com/nwsiss/grid_mkts/key_facts/index.html
NICR Capacity Procurement at capacity price of $11.71/kW-m $4.8 Calculation
Swing in Consumer Cost for Initial Candidate Curve from 102% to 100% NICR $3.4 EstimatedSwing in Consumer Cost for PLEXOS Curve from 102% to 100% NICR $1.6 Calculation
MA AGO 14
Net CONE Benchmarks
27 February, 2014
Net CONE Assumes a 13.8% Equity Rate of Return for the following technologies:
• 4 x LM 6000: $20.60/kW-m• 2 x LMS 100: $17.85/kW-m• 2 x Frame CT: $ 8.95/kW-m• 2 x 1 Combined Cycle: $11.71/kw-m
This was done by solving the Net CONE value in $ / kW-month for each technology given a specific rate of return for equity of 13.8%. The financial models for these calculations are complex and include a number of different assumptions and properties.
The following analysis reviews the equity rate of returns for these same projects assuming different Net CONE assumptions.
Source: MC Feb 27th Net CONE Presentation
MA AGO 15
Net CONE Benchmarks (continued)
27 February, 2014
First, we benchmarked each technology based on their Net CONE values and the 13.8% equity rate of return.
Economic Life: 20 yearsDebt Leverage: 50% of Overnight Project CostDebt Amortization: standard amortization over 10 yearsDebt Interest rate: 7.0%Tax Depreciation: MACRS 15 Year Depreciation for the LMS and CT and 20 Year for CCCorporate Tax Rate: 35%Inflation Rate: 2.25%Size and cost of plant as per the Feb 27, 2014 Presentation
Source: MC Feb 27th Net CONE Presentation
MA AGO 16
ROE for Peak Price
27 February, 2014
Return on EquityNet CONE$/kW-m
Penalty Price Net CONE Multiplier 4 x LM 6000 2 x LMS 100 2x0 Frame CT 2x1 CC
11.71
1.60 11.96% 14.8% 35.0% 25.3%
2.00 16.50% 19.9% 45.3% 33.1%
MA AGO 17
Capacity Clearing Price of 1.6 x $11.71/kW-m
27 February, 2014
Assuming a capacity price of $18.73/kW-m for the new Capacity Resources, the Equity Rate of Return for these same hypothetical projects would be a follows:
• 4 x LM 6000: 12.0%• 2 x LMS 100: 14.8%• 2 x Frame CT: 35.0%• 2 x 1 Combined Cycle: 25.3%
Again, the LM 6000 project would face a slight degradation of equity returns from 13.8% to 12.0%, but the other projects have a significantly improved results relative to their original position. These results also suggest that the returns are far in excess of market expectation at that capacity price for several technologies.
MA AGO 18
Capacity Clearing Price of 2 x $11.71/kW-m
27 February, 2014
Finally, assuming a value 2 x $11.71 /kW-m, the Equity Rate of Return for these same hypothetical projects would increase as follows:
• 2 x LM 6000: 16.5%• 2 x LMS 100: 19.9%• 2 x Frame CT: 45.3%• 2 x 1 Combined Cycle: 33.1%
In this case, all projects have a significantly improved results relative to their original net cone economics. These results also suggest that the returns are far in excess of market expectation at that capacity price for several technologies.
MA AGO 19
ROE Comparison for Net CONE Multipliers of 1.6 and 2
27 February, 2014
With Net CONE of 11.71and 2x Net CONE MultiplierExcess Equity Returns Possible
MA AGO 20
Recommendations of Future Capacity Demand Curve
– Consider a 20 year outlook for development of Capacity Demand Curve shape– Consider least cost constrained optimization of short run and long run marginal costs
including minimization of the value of lost load– Run multiple scenarios of technologies, demands, fuel prices, and possibly others and
allow the optimization to deactivate units if necessary for least cost system development– Use a stakeholder driven process for the above
27 February, 2014