capacity allocation & congestion management€¦ · allocated across the eu • the first...
TRANSCRIPT
![Page 1: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/1.jpg)
Capacity Allocation & Congestion Management
Methodologies, EU Acquis, Status Quo in Bosnia and Herzegovina and
Gap Analysis
21st of February 2019
Martin Paletar, Dr. Daniel Grote, Waisum Steinborn-Cheng, Nebojša Filipović (DNV GL)
![Page 2: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/2.jpg)
Agenda
Introduction and Objectives01
2
Role of Capacity Management within Open-
Access Model 02
Coffee break (15:30)
Relevant EU Acquis on Capacity Allocation
and Congestion Management05
Status Quo in Bosnia and Herzegovina06
Overview on Principle Mechanisms and
Procedures03
Gap Analysis07
Next Steps08
![Page 3: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/3.jpg)
Role of Capacity Management within Open-Access Model
![Page 4: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/4.jpg)
Introduction: Objective & Scope
To best prepare and assist stakeholders in introduction of implementation
of Capacity and Congestion management in BiH
4
Objective:
Back-
ground
Implementation of according measures necessary due to
• adoption of according EU gas sector legislation by and for the Energy
Community
Directive 2009/73/EC concerning common rules for the internal market in
natural gas
Regulation (EC) 715/2009 on conditions for access to the natural gas
transmission networks;
Regulation (EU) 2017/459 establishing a network code on capacity allocation
mechanisms in gas transmission systems;
Regulation (EU) 2015/703 establishing a network code on interoperability and
data exchange rules
• implementation of an entry-exit system
• economic considerations
![Page 5: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/5.jpg)
Introduction: Background
• It has been established that greater effort is needed to create a secure, competitive and low carbon European energy sector and a pan-European Internal Energy Market.
• Network codes are intended as a tool to reach this objective by complementing existing national rules to tackle cross-border issues in a systematic manner.
• Network codes complement Regulations (EC) No 715/2009 and further detail and clarify the Regulations’ provisions in light of operational procedures and implementation.
5
Why Do We Need Network Codes?
![Page 6: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/6.jpg)
How European liberalization changed traditional models in the gas system
6
Transmission
System Operator
Distribution
System Operators
Producers /
Importers
Direct Customers
UGS
Traders &
Shippers
The Shippers and Traders are
crucial institutions that link the
whole gas system
Services of these market players
composed not only of the
provision of gas volumes but also
booking of capacities from
network system operators
![Page 7: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/7.jpg)
Elements of an Open Access Framework for Gas Transmission
7
Balancing
Arrangements
Network
Access Model
Capacity and
Congestion
Management
Areas of
open
access
• Entry-Exit
System
• Revenue
regulation
• Tariff structure
• TPA
requirements
• Allocation
principles
• Capacity
products
• Supplementary
incentives
• Procurement of
balancing
energy
• Settlement of
imbalances
• Flexibility
market
Options /
Major
determinants
Open access
![Page 8: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/8.jpg)
Entry-Exit System
8
Production
Storage
LNG
N X
X
Cross border
N
Directly
connected
customers
Storage
Cross border
Trading
VP
Local Local
TS
O l
eve
lD
SO
le
ve
l
X
N Physical entry
pointX Physical exit point Contractual flow of
gas
System
boundary
![Page 9: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/9.jpg)
Capacity & Congestion Management: Background & Definitions
9
• Following descriptions based on Entry-Exit model, i.e. network users book
capacity at entry and exit points, capacity is independent of transportation
distance (as compared to the point-to-point-model)
• ‘Interconnection point’ means a physical or virtual point connecting
adjacent entry-exit systems.
• Capacity management is based on explicit capacity arrangements
• Capacity arrangements applicable for national and cross-border markets
• No separate treatment of transit capacities
![Page 10: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/10.jpg)
Background & Definitions
10
• Capacity management
− Used as a major and integral term and sets of rules how to allocate capacity
− Capacity allocation without problems, as long as no physical or commercial
(contractual) congestion exists
− Explicit rules for capacity allocation necessary if congestions occur
− Capacity allocation methods may have a large impact on the appearance of
congestions
• Capacity allocation
− From the Latin "locare" = place, apportion
− Allocation/granting of (scarce) capacity to network users (shippers)
− Several methods for capacity allocation (next slides)
• Congestion management
− Mainly focused on physical congestion
![Page 11: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/11.jpg)
11
Non-discriminatory access for
establishment of competitive environment
AllocationCapacity
assessment
Capacity definition
(Products)
Balancing General network access model
(Entry-Exit model)
PricingImplementation
and steering
Capacity
management
Major
Objective
Network
access
areas
Tasks of
capacity
allocation
and
congestion
management
Congestion Optimisation
Congestion Management: what does is comprise of?
![Page 12: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/12.jpg)
Capacity Management - Overview
Shippers’ activities:
12
Re-nomination Nomination BookingRequest
Capacity request
of shippers to the
TSO
Capacity
reservation at a
specific network
coupling point
for a specific
period of time
Order of a shipper
to the TSO to
transport gas in
the following day
(based on the
booked capacity)
Short-term
modification of
nominations
(e.g. in
Germany: 2 h;
the UK: 4 h
before the actual
gas transport)
![Page 13: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/13.jpg)
Overview on Principle Mechanisms and Procedures
![Page 14: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/14.jpg)
Capacity Management - Overview
Activities of Network Operator:
14
1. Capacity
definition 2. Capacity
assessment
3.
Allocation
4.
Congestion
management
5.
Pricing
6.
Capacity
optimisation
Determination of the
available capacity using the
relevant product definitions
Allocation of the
determined capacity
(granting contractual
rights)
Specific rules in the case of
network constraints
Definition of the
relevant capacity
products
Measures to
maximise the
available capacity
(technical
/commercial)
Closely related to
congestion
managementPricing principles, it
may be interrelated to
the allocation process
![Page 15: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/15.jpg)
Capacity products can be varied in terms of firmness, flexibility and duration.
• Risk of interruption
− Firm capacity: capacity that cannot
be reduced
− Interruptible capacity: capacity that
can be reduced to zero
• Coordinated capacity
bundled or unbundled products
are products consisting of the
corresponding entry and exit
capacities on both sides of the IP
15
• Booking time period
− Day / Week / Month / Quarter/
Year / > 1 Year
− May be differentiated by season
(e.g. winter and summer month)
• Other possible variations
− Specific transport portfolios (e.g.
backhaul-, shorthaul,)
− Temperature dependent (as proxy
for demand) capacity products
By combining the above mentioned determinants a portfolio of
capacity products can be created!
![Page 16: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/16.jpg)
FCFS and Pro Rata
• First-come, first-served (FCFS)
− Dominant capacity allocation model
in EU prior 2015
Advantage: simplicity
Disadvantage: not market-based >
no scarcity signals, no optimisation
of capacity
• Pro rata
− Shippers receive a share of
available capacity which reflects the
level of their requested capacity
Disadvantage: Incentives to
request excessive volumes of
capacity, potentially unfair for small
shippers16
• Open Season
combines demand evaluation with capacity allocation
shippers are faced with uncertainty regarding allocated capacity and costs
Advantage: Market-based, every capacity request can be satisfied, less risk for investor
Disadvantage: Uncertainty for shippers during contracting phase
![Page 17: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/17.jpg)
Auctions
• Used strongly in the EU
• Several design models possible, e.g. auctioning of quarter capacities with start price (published for the respective network point) und ex ante defined price steps
• Various auction techniques possible:
−English auction (open ascending auction with free bids and start price)
−Vickrey auction (sealed-bid second-price auction)
−Reverse auction (tenders)
− …
Advantage: Market-based, provides signals for scarce capacity and ensures market-driven and non-discriminatory allocation
Disadvantage: More burdensome and complex than FCFS-model 17
![Page 18: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/18.jpg)
Congestion Management
What is congestion?
• Physical congestion
− The utilisation of a network point or network area is
technically at or beyond its capacity limit
− The actual load corresponds to the amount of booked
capacity
− In long term it can be relieved only by network extension
• Commercial congestion
− The utilisation of a network point or network area is
technically below its capacity limit
− The actual load is lower than the amount of booked capacity
− It can be relieved by using suitable methods for capacity (re-
allocation) > Capacity Optimisation
18
Sum of all bookings
Max
technical
capacity
Actual flow
Max
technical
capacity
Actual flow
![Page 19: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/19.jpg)
Congestion Management
Why to mitigate congestion?
Effective congestion management is required to ensure “fairness“.
Required congestion management depends on type of congestion:
• Commercial congestion: Freeing up unused capacity for the market
• Physical congestion: Ensure efficient use of scarce capacities
19
![Page 20: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/20.jpg)
Congestion Management
1. Congestion management during capacity allocation process• If demand exceeds supply, capacity allocation needs to aim at
economically efficient results• Pro rata capacity allocation can ensure that no new entrant is excluded
• Auctions provide transparent congestion signals and funds for capacity expansion
• Use-It-Or-Lose-It frees up additional capacities on short notice• Restricting intra-day renominations may firm up
2. Congestion management during everyday network operations• Interruptions of interruptible capacities
• Refining assumptions/simulation algorithms for capacity calculation
• Deployment of commercial solutions, e.g. capacity buy-back, load flow commitments, etc.
• Effective use of linepack and storage capacities (as far as controlled by TSOs)
20
![Page 21: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/21.jpg)
Physical congestion mitigation
21
Administrated(mandated restrictions
and changes)
Voluntary(based on voluntary arrangements)
Counterpart Shippers ShippersInfrastructure
operators
Capacity
0) Normal Operating
Conditions
1) Interruptible /
Conditional capacity
2) Locational
restrictions
3) Capacity buy-
back
Commodity/
Nominations
4) Locational trades
5) Load-flow
commitments
6) TSO-contracted
storage
7) Locational swaps
8) TSO-to-TSO swaps
9) Re-routing
![Page 22: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/22.jpg)
Instruments to Prevent Congestion
• Oversubscription and buy back scheme− TSO sells more capacity then available
− In case of congestion the TSO would attempt to buy capacity back from the network users on a short term basis
− Usually be on a daily basis, but given the circumstance, capacity could also be bought back for longer periods such as on a weekly (even monthly)
• Interruptible capacities Additional interruptible capacities are sold
With contractual congestion only, risk of interruption will be low
• Market coupling / Implicit auctions− The combination of commodity trade with (the utilisation of limited) transmission capacity
allocation that aims to manage limited transmission capacity more efficiently as well as to increase price convergence between two or more commodity markets in different areas
− Serves to utilise technical capacity up until full price convergence
− BUT! Still congestion issues with more liquid markets22
![Page 23: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/23.jpg)
Capacity Allocation and Congestion Management
—EU Acquis
![Page 24: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/24.jpg)
What does it aim at?
• To harmonise how is capacity allocated across the EU
• The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force on April 2017and repealed it.
24
EU Acquis in the Natural Gas Sector
• Directive 73/2009 (EC)
• i.e. Regulation (EC)
715/2009
• Regulation (EU)
2017/459 establishing a
network code on capacity
allocation mechanisms in
gas transmission
systems;
• Regulation (EU)
2015/703
What does it mean for BiH?
NC CAM has now also been adopted for the Energy Community
• transposition deadline: 28 August 2019
• implementation deadline: 28 February 2020
![Page 25: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/25.jpg)
Gas Network Codes Development Process
25
Network Code Delivery
Commissi
on
ACER
ENTSO-G
Council /
Parliamen
t
Stakeholder
s
Priority
setting
Framework
Guidelines
Define
Code
Project
Plan
Code
Proposal
Developmen
t
Comitology
Pre-
Comitology
Evaluation
–
Approval
Code
Finalizatio
n
Stakeholder joint working sessions, technical
workshops and consultations.
Energy
Communit
y
Ministerial Council
adoption
Network Code Adoption and Implementation
![Page 26: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/26.jpg)
EU NC CAMWhat are the key elements?
Introduction Background & Definitions
1. Capacity Allocation Rules
1I.Booking horizons, capacity calculations, and
timings
III. Incremental capacity process procedure
IV. Congestion Mitigation Processes
![Page 27: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/27.jpg)
EU NC CAM: BackgroundRequirements and Outcomes
• Provide appropriate economic signals for efficient and maximum use of capacity.
• Be compatible with market mechanism while being flexible and capable of
adapting to evolving market circumstances.
• Be compatible with connected network access system.
• Outcome of NC CAM appears to be “socialisation” of infrastructure costs.
• Increasing role of regulators in overseeing and implementing infrastructure
projects.
• Higher burden for gas consumers who, in return, get a common system as a basis
for large liberalised, and thus more competitive gas market.
Results of NC CAM
![Page 28: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/28.jpg)
EU NC CAM: BackgroundTimeline
• The first CAM NC, which sought to establish regulatory procedures in respect of allocation of existing – as opposed to incremental capacity, was adopted on 14 October 2013 (CAM NC 2013).
• It was repealed on 6 April 2017 when the 2017 CAM NC was adopted and entered into force.
• The 2017 CAM NC has a wider scope than its 2013 predecessor as it includes detailed regulatory provisions in respect of both existing and incremental capacity.
28
![Page 29: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/29.jpg)
EU NC CAM: BackgroundScope and Definitions
• All interconnection points (IP), with an IP being defined as ‘a physical or virtual point connecting adjacent entry–exit systems;
• As far as these points are subject to booking procedures;
• It applies to interconnections between adjacent entry–exit zones irrespective of whether or not these zones are located in the same country or not.
29
NC CAM applies to:
NC CAM does not
apply to:
• entry points from liquefied natural gas (LNG) terminals and production (in other words connections between upstream and transmission networks facilities;
• exit points to end consumers and distribution networks;
• entry points from, or exit points to, storage facilities
• IP with third countries BUT.
![Page 30: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/30.jpg)
EU NC CAM: BackgroundNew Definitions
Incremental Capacity (Art. 3.1)
• ‘a possible future increase via market-based procedures in technical
capacity or possible new capacity created where none currently
exists that may be offered based on investment in physical
infrastructure or long-term capacity optimization and subsequently
allocated subject to positive outcome of an economic test, in the
following cases:
at existing interconnection points;
by establishing a new interconnection point or points;
as physical reserve flow cap
30
![Page 31: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/31.jpg)
EU NC CAM: Capacity Allocation RulesProducts
• Technical capacity, defined as: ‘the maximum firm capacity that the transmission system operator can offer to the network users, taking account of system integrity and the operational requirements of the transmission network’; 20 per cent minimum levels of reservation quotas
• Interruptible capacity, defined as: ‘gas transmission capacity that may be interrupted by the transmission system operator in accordance with the conditions stipulated in the transport contract’ (Art. 2, Gas Regulation 715);
• Additional capacity (in the meaning of point 2.2.1 of Annex I of Gas Regulation 715), defined as: ‘the firm capacity offered in addition to the technical capacity of an interconnection point calculated on the basis of Art. 16.133 of this Regulation’ whereas ‘any additional capacity made available through the application of one of the congestion management procedures as provided for in points 2.2.2, 2.2.3, 2.2.4 and 2.2.5 shall be offered by the respective TSO(s) in the regular allocation process’ (CMP (Annex I to Gas Regulation 715));
• Incremental capacity (further slides)
31
NC CAM
applies to:
![Page 32: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/32.jpg)
EU NC CAM: Capacity Allocation RulesProcess
• The CAM NC stated that ‘auctions shall be used for the allocation of capacity at an interconnection point, unless provided otherwise’ (Art. 8)
• The CAM NC defines the following standard capacity products for auctions:
yearly,
quarterly,
monthly,
daily,
and within-day
32
# of products per
auction per IP
Auction Process
Auction Process
Auction Process
Auction Process
Auction Process
15
4
11
1
![Page 33: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/33.jpg)
EU NC CAM: Capacity Allocation Rules
• Overview of CAM and their Alignment with 3rd Package Requirements
33
• Auction is most preferable method, however it can only be applied if the market is competitive enough
Non-disciminatory /
transparant
Provide economic
signal
Compatibility with market
mechanism
Auction Strong Strong Strong
FCFS Weak Weak In combination with product
Pro rata Weak Weak N/A as trading tool at hubs
CGWC Weak Weak N/A as trading tool at hubs
![Page 34: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/34.jpg)
EU NC CAM: booking horizons, capacity calculations, and timings
• The CAM NC stipulated that yearly capacity auctions are to be held once a year, with the auction process to ‘offer capacity at least for the upcoming 5 gas years and for no longer than the upcoming 15 gas years for existing capacity’ (Art. 11.3)
• Yearly capacity auctions shall start on the first Monday of July each year (Art. 11.4)
(Art. 11.8) TSO‘s obligation to notify users, a month before the auction, about the amount of firm capacity for each year.
34
![Page 35: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/35.jpg)
• The capacity to be offered during the yearly auction shall be equal to:
A: is the TSO’s technical capacity;
B: is the amount of technical capacity (A) set aside in accordance with reservation quotas
C: is the previously sold technical capacity, adjusted by the capacity which is re-offered in accordance with applicable CMP
D: is additional capacity for such a year, if any;
E: is the incremental capacity for such a year included in a respective offer level, if any;
F: is the amount of incremental capacity (E), if any, set aside in accordance with Art. 8.8 and Art. 8.9 (reservation quota).
A – B – C + D + E – E
EU NC CAM: booking horizons, capacity calculations, and timings
35
![Page 36: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/36.jpg)
The CAM Network Code: Incremental Capacity Process Procedure
• Other than ‘auction’ is possible upon RA’s approval, where reasonable market demand assessment proved auction unsuitable.
1. Demand assessment: Network users can submit non-binding indications of demand for gas transport capacity at entry-exit system borders to the TSOs. The TSOs must assess these demand indications as part of a demand assessment that normally takes place every two years.(Article 26 NC CAM)
2. Design and economic test: If the market demand assessment positive >, the TSOs begin the design phase (Article 27 NC CAM). This includes: the modelling and design of any network expansion that may be necessary, in technical studies; and public consultation of TSOs.
3. Auction and market testing: Once approval has been granted, the new capacity is offered to the market for binding booking together with any existing capacity.
If the outcome of the economic test is positive – in other words sufficient binding capacity is booked to cover the specified proportion of investment costs – the gas transport capacity must be created by the TSOs concerned. The project will then be included as appropriate in the network development plan, at the size confirmed by the market.
36
![Page 37: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/37.jpg)
Congestion Management Procedures
They require companies to make use of their reserved capacity or risk losing it. Unused capacity is placed back on the market.
• Commission Decision (EU) 2015/715/EU amending Annex I to Regulation (EC) 715/2009 on conditions for access to the natural gas transmission networks
• Commission Decision on conditions for access to the natural gas transmission networks [2012/490/EU]
• Guidance on best practices for congestion management procedures in natural gas transmission networks [SWD(2014) 250]
37
![Page 38: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/38.jpg)
Contractual congestion mitigation
38
EU legislation specifies that congestion management instruments must be market-based!
• UIOLI/UIOSI
Capacity is withdrawn from shipper or shipper is forced to sell it, if capacity is not used
Can result in short-term UIOLI, i.e. unused capacity is sold short-term while restricting re-nomination rights; no permanent withdrawal
• Secondary market
− Whether TSO offers interruptible capacity at least on a day-head, shippers with additional un-needed capacity should be entitled to resell it on the secondary market, Directive 2009/73/EC, Art. 8 envisages that TSO must take reasonable steps in this step
Secondary
Market
Oversubscript
ion and Buy
Back
Interruptible
Capacities
Market
Coupling
UIOLI/
UIOSI
![Page 39: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/39.jpg)
Capacity Allocation and Congestion Management
—Status Quo in BiH Transport
System
![Page 40: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/40.jpg)
Bosnia and Herzegovina – Status Quo
40
Legal Framework
State BiH
Does not have jurisdiction in this domain
Republika Srpska
Law on Gas (March 2018)
Transport Network Code of Republika Srpska (January 2010)
Relevant provisions of Third Package are transposed
Federation BiH
Decree on Organization and Regulation of Gas Sector
Negotiated third party access based on Ministry decisions
Relevant provisions of Third Package are not transposed
![Page 41: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/41.jpg)
Bosnia and Herzegovina – Status Quo
41
Republika Srpska - Law on Gas provisions
Article 49 – Defines Capacity Allocation and Congestion Management as part of Transport Network Code:
Article 50 – Provides more requirements about Capacity Allocation and Congestion Management Capacity allocation mechanisms need to:
Be Transparent and non-discriminatory
Provide economic effects for efficient and maximum use of technical capacity
Be compatible with market mechanisms
Be compatible with rules for access to transport system
Congestion management procedures are based on principles:
Transparency and non discrimination
In case of contractual congestion, TSO offers unused capacity on primary market at least on day ahead and interruptible basis
System users are entitled to resell unused capacity on the secondary market
![Page 42: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/42.jpg)
Bosnia and Herzegovina – Status Quo
42
Republika Srpska – Transport Network Code provisions
Article 5 – Definitions
Congestion management is defined as management of transport system capacities with objective of optimal and maximal usage of technical capacity and opportune envisage of congestion place
Contractual congestion is situation in which demand for non-interruptible capacities exceeds technical capacity
![Page 43: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/43.jpg)
Bosnia and Herzegovina – Status Quo
Activity Responsible Art.
No.
Timelines
Publishes data on technical and
available capacity in transport system
TSO 7. Latest till Sep 1st for the next
year
Submits request for access to system Network user 8. From Sep 1st till Oct 1st
Allocates capacity TSO 10.
Adopts decisions on requests for
access to transport system
TSO 11. Latest till Nov 1st
Submits contracts which prove that
requested quantities and capacities
are secured and financial guarantees
are met
Network user 11. Latest till Dec 1st
Submits complaint to RERS on
decision (in case access is denied)
Network user,
RERS
12.
Sign contract on use of transport
system
TSO, Network
user
13. Latest one month after the
submission of proofs for
requested quantities and
capacities43
Republika Srpska – Transport Network Code provisions
![Page 44: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/44.jpg)
Bosnia and Herzegovina – Status Quo
44
Republika Srpska – Transport Network Code provisions
Content of Request for access to transport system
General data about Requestor
Data about requested capacity per entry/exit points Minimum and maximum hourly capacity (Sm3/day)
Maximum daily capacity (Sm3/h)
Maximum annual capacity (Sm3/h)
Data about requested pressure per entry/exit points Min and max pressure (bar)
Planned annual gas volume on monthly level
Duration period
![Page 45: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/45.jpg)
Bosnia and Herzegovina – Status Quo
45
Republika Srpska – Transport Network Code provisions
Allocation of Capacity
Done separately for each entry and exit point
Accounting element “Capacity” is equal to the maximum daily capacity (from request)
All capacities are accepted if sum of all requested capacities is not greater than 5% from maximum available daily capacity
Advantage is given to Network users by the order of Request submission
![Page 46: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/46.jpg)
Bosnia and Herzegovina – Status Quo
46
Republika Srpska – Transport Network Code provisions
Criteria for approval/rejection of Request
Possibility to provide requested capacity in planned period in entire system
Ratio between gas pressure on entry point and requested pressure on exit point
Quality of gas (chemical composition, lower calorific value, allowed deviations, etc...)
Technical possibilities of metering and regulation equipment
Possibility for network user to secure additional quantities of gas for coverage of compressor operation
![Page 47: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/47.jpg)
Bosnia and Herzegovina – Status Quo
47
Republika Srpska – Implementation
Capacity allocation:
Long term
Short term
Non-interruptible
Interruptible
Congestion management
No re-offer of unused capacity to primary market on:
Day ahead basis
Interruptible basis
No capacity trade on secondary market
Third party access in practice:
Is granted only to incumbent suppliers
![Page 48: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/48.jpg)
Gap Analysis
![Page 49: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/49.jpg)
Gap Analysis
49
Area Bosnia and
Herzegovina (national level)
Federation BiH Republika Srpska
Legislation in place N/A N/A Transport Network Code
Implementation of entry-exit system Not implemented Not implemented
Implementation in progress
Tariffs set for network sections
Definition of Capacity Allocation and Congestion Management
Not defined Not defined Art. 49 of Network Code
Requirements ofCapacity Allocaiton Not defined Not defined Art. 50 of Network
Code
Requirements of Congestion Managment Not defined Not defined
Art. 50 and 5 (definitions) of Network Code
![Page 50: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/50.jpg)
Next Steps
50
Analyze international experience
(incl. Serbia and Croatia)
Interim report shared with stakeholders,
opportunity to comment in writing
Development of recommendations
(+ integrating stakeholder feedback)
Presentation and discussion of recommendations
at 2nd meeting (May 2019)
Submission of final report
(integrating stakeholder feedback)
Draft interim report(covering concepts, international experience, current situation in BiH
and gap analysis)
![Page 51: Capacity Allocation & Congestion Management€¦ · allocated across the EU • The first version of the CAM NC of 2013 had been in place until the amended CAM NC came into force](https://reader033.vdocuments.us/reader033/viewer/2022050513/5f9d915798c337486110910a/html5/thumbnails/51.jpg)
Hvala!
Martin Paletar, Energy Markets & Technology
DNV GL Energy
DNV GL Energy Advisory GmbH
Zanderstr. 7
53177 Bonn
Phone: +49 228 44690 64
E-Mail: [email protected]