Town of MoragaCanyon Road Bridge Replacement Project
April 24, 2019 Town Council Meeting
NV5 Contract Amendment and Project Update Presentation
6/14/174/24/2019
➔Edric Kwan, P.E., Public Works Director and Town
Engineer
➔Shawn Knapp, P.E., Senior Civil Engineer
➔Jack Walker, P.E., Director of Transportation, NV5
➔David Wang, PhD, P.E., Senior Principal, PARIKH
Consultants, Inc.
➔Kevin James Ryan, CEG, Principal, Ryan Geological
Consulting, Inc.
PRESENTATION TEAM
2
6/14/174/24/2019
Canyon Road Bridge Reopening Project
➔April 27, 2017 - Update on Canyon Road Bridge Closure
and Consider Declaring a Local Emergency
➔June 14, 2017 - Receive Presentation on the Alternatives
for Reopening Canyon
➔October 12, 2017 - Consider Additional Appropriation
$1,234,388
➔January 24, 2018 – Consider Acceptance Canyon Road
Bridge Reopening Project
PAST PRESENTATIONS
3
6/14/174/24/2019
Canyon Road Bridge Replacement Project
➔October 23, 2013 – Consider Awarding Bridge Engineering
Design to NV5
➔April 23, 2014 – Authorization to Execute Master Cooperative
Agreement with CCTA
➔June 27, 2018 – Consider Authorizing NV5 Amendment No. 3
➔October 4, 2018 - Consider Authorizing the Acquisition of
Permanent Right-of-Way and Temporary Construction
Easement
➔October 10, 2018 – Project Update Presentation
➔April 24, 2019 – Project Update and Consider NV5 Contract
Amendment No. 4
PAST PRESENTATIONS
4
6/14/174/24/2019
➔Risk Management
➔Revised Canyon Road Bridge Replacement Project
➔Project Cost Estimates
➔Project Finances
➔Project Construction Schedule
➔NV5 Contract Amendment
PRESENTATION OVERVIEW
5
6/14/174/24/2019
LOCATION MAP
Adjacent Hill and Residents
Joaquin Moraga Intermediate School
Pear Orchard
Adjacent Residents
Canyon Road Bridge
Lafayette-Moraga Regional Trail/Fire Trail
Moraga Creek and Larch Creek
Canyon Road
6
6/14/174/24/2019
RISK MANAGEMENT
7
6/14/174/24/2019
➔Caltrans Local Assistance Procedures Manual
➔Prescriptive Step-by-Step project procedures that addresses
Risk Analysis process by identifying, avoiding or eliminating,
transferring, mitigating or accepting the risks
RISK MANAGEMENT
8
6/14/174/24/2019
➔Preliminary Engineering Phase
➔Field Review results in 17 Environmental Studies
➔5 Years To Complete Studies And Obtain Permits That Eliminated or Mitigated Risks And Impacts
➔Bridge Type Selection Report
➔ROW and Utility Clearance
RISK MANAGEMENT
9
6/14/174/24/2019 1010
Original Design
110.5’ Long x 48.5’ Wide
BRIDGE DESIGN CHANGES
4/24/2019
➔56% Larger Bridge = Increases Concrete, Steel, and Pilings.
➔44% Longer Retaining Walls:
▪ 240 vs 318 ft. longer wall
▪ 40 vs. 71 more piles
▪ 1,200 vs. 2,000 ft. total length of pilings
Revised Design
165’ Long x 50.2’ Wide
6/14/174/24/2019 11
TEMPORARY VS. PROPOSED BRIDGE LOCATION
4/24/2019
6/14/174/24/2019
SLIDE IMPACTS NEAR BRIDGE
ABOVE TENSION
CRACKS DEVELOPED
AT PEDESTRIAN
BRIDGE LANDING
4/3/19
TENSION CRACK
APPROXIMATE LOCATION
SHOWN RELATIVE TO
STITCH-PIER WALL FOR
TEMPORARY BRIDGE
12
6/14/174/24/2019 13
KEY SAFETY ELEMENTS
13
▪ Bike Lanes And Multi-use Path Across Bridge
▪ Lighting For Motorists And Pedestrians
▪ Widen Bridge To Current Bridge Standards
▪ Improved Sight Distance
▪ Upgraded Guard Rails
▪ Bike Railing On Concrete
Barriers
▪ Floodway Capacity
6/14/174/24/2019 14
BRIDGE AND ROADWAY COORDINATION
Preliminary Moraga Way & Canyon - Camino Pablo Improvements
6/14/174/24/2019 15
RENDERING PROPOSED BRIDGE DESIGN
154/24/2019
6/14/174/24/2019
CALTRANS APPROVED PROJECT BUDGET
▪ March 7, 2019 Caltrans HQ HBP Approved the Project’s
Revised Scope and Budget
▪Includes Design Budget for NV5 Bridge for Amendment No. 4
16
PROJECT PHASES
TOTAL
BUDGET
FEDERAL
PORTION
(88.53%)
TOWN CO-
MATCH
(11.47%)
Preliminary Engineering 1,590,000$ 1,407,627$ 182,373$
Right of Way 175,000$ 154,927$ 20,073$
Construction 6,351,000$ 5,622,540$ 728,460$
Construction Contingency 635,100$ 562,254$ 72,846$
Construction Engineering 952,650$ 843,381$ 109,269$
Totals 9,703,750$ 8,590,729$ 1,113,021$
393,000$
720,021$
CCTA Major Street (Fund 700)
Net Town Contribution
6/14/174/24/2019
PROJECT ALTERNATIVE COST COMPARISON
* Sunbelt Rental has said NO to selling of their leased temporary bridge. Add $600,000 for removal and
erection of different vendor’s steel truss bridge.
NV5 Design 154,044$ NV5 Design 965,000$ NV5 Design 965,000$
ROW 20,073$ ROW 85,000$ ROW 85,000$
Staff Time 19,040$ Staff Time 105,000$ Staff Time 105,000$
Purchase Bridge -$ Purchase Bridge 448,100$ Lease Bridge (20 yrs.) 2,832,000$
CCTA (393,000)$ CCTA 70,000$ CCTA 70,000$
Other Project Costs
(Permitting, Env.
Analysis, etc..) 4,588$
Other Project Costs
(Permitting, Env.
Analysis, etc..) 40,000$
Other Project Costs
(Permitting, Env.
Analysis, etc..) 40,000$
Bridge Modifications,
Maintenance,
Additional Inspection
(100 yrs.) -$
Bridge Modifications,
Maintenance,
Additional Inspection
(20 yrs.) 155,000$
Bridge Modifications,
Maintenance,
Additional Inspection
(20 yrs.) 155,000$
Removal and Installing
New Vendor
Temporary Bridge* -$
Removal and
Installing New Vendor
Temporary Bridge* 300,000$
Removal and
Installing New Vendor
Temporary Bridge* -$
Bridge Construction 910,575$
Creek Bank Armoring
and Vegetation 279,000$
Creek Bank Armoring
and Vegetation 279,000$
Totals 715,319$ Totals 2,447,100$ Totals 4,531,000$
OWN TEMPORARY BRIDGE LEASE TEMPORARY BRIDGE
TOWN PORTION - 100 yrs. TOWN FULL PORTION - 20 yrs.
NEW REPLACEMENT BRIDGE
TOWN FULL PORTION - 20 yrs.
17
6/14/174/24/2019
PROJECT ALTERNATIVE COST COMPARISON
* Sunbelt Rental has said NO to selling of their leased temporary bridge. Add $600,000 for removal and
erection of different vendor’s steel truss bridge.18
NV5 Design 154,044$ NV5 Design 965,000$ NV5 Design 965,000$
ROW 20,073$ ROW 85,000$ ROW 85,000$
Staff Time 19,040$ Staff Time 105,000$ Staff Time 105,000$
Purchase Bridge -$ Purchase Bridge 448,100$ Lease Bridge (20 yrs.) 2,832,000$
CCTA (393,000)$ CCTA 70,000$ CCTA 70,000$
Other Project Costs
(Permitting, Env.
Analysis, etc..) 4,588$
Other Project Costs
(Permitting, Env.
Analysis, etc..) 40,000$
Other Project Costs
(Permitting, Env.
Analysis, etc..) 40,000$
Bridge Modifications,
Maintenance,
Additional Inspection
(100 yrs.) -$
Bridge Modifications,
Maintenance,
Additional Inspection
(20 yrs.) 155,000$
Bridge Modifications,
Maintenance,
Additional Inspection
(20 yrs.) 155,000$
Removal and Installing
New Vendor
Temporary Bridge* -$
Removal and
Installing New Vendor
Temporary Bridge* 600,000$
Removal and
Installing New Vendor
Temporary Bridge* -$
Bridge Construction 910,575$
Creek Bank Armoring
and Vegetation 279,000$
Creek Bank Armoring
and Vegetation 279,000$
Totals 715,319$ Totals 2,747,100$ Totals 4,531,000$
NEW REPLACEMENT BRIDGE OWN TEMPORARY BRIDGE LEASE TEMPORARY BRIDGE
TOWN PORTION - 100 yrs. TOWN FULL PORTION - 20 yrs. TOWN FULL PORTION - 20 yrs.
6/14/174/24/2019
RISKS ASSOCIATED WITH TEMPORARY BRIDGE
➔Increased Project Costs
➔Potential Loss Future Grants
➔Increase CO Gases
➔Lower Long Term Site Stability
➔Shorter Lifespan 20-30 Years Vs.
100 Years For Permanent Bridge
➔Higher Maintenance Costs and Liability
➔Higher Safety Risks for Pedestrians and Cyclists
➔Slower Emergency Response and Evacuation Route
19
6/14/174/24/2019
May 2019 – November 2019 Complete Bridge Design
October 2019 – November 2019
Final ROW Clearing Prior to Migratory Bird Nesting Season
December 2019 – January 2020
Project Advertisement
February 2020 Town Council Consider Construction Award
March 2020 – October 2020 Phase 1 Bridge Construction
March 2021 – October 2021 Phase 2 Bridge Construction
CONSTRUCTION SCHEDULE – 2 SEASONS
20
6/14/174/24/2019
• Construct Bridge’s Northbound Lane And Approaches
Temporary Bridge Continues To Handle Traffic In Both
Directions
2020 CONSTRUCTION –PHASE I
21
6/14/174/24/2019
Construct Bridge’s Southbound Lane And Remove Temporary
Bridge
New Northbound Lane Handles Traffic In Both Directions
2021 CONSTRUCTION - PHASE 2
22
6/14/174/24/2019
NV5 Contract Authorizations Amounts
Original Contract $567,017
Amendment No. 1 (Reimbursed through the Temporary
Bridge project)
$130,000
Amendment No. 2 (Reimbursed through the Temporary
Bridge project)
$34,987
Amendment No. 3 $398,000
Amendment No. 4 $378,000
Total $1,508,004
NV5 AMENDMENT
23
6/14/174/24/2019
➔Adopt Resolution ____ - 2019 authorizing the Town
Manager to amend the Consultant Services agreement
with Nolte Vertical 5 (NV5) (Walnut Creek) for civil
engineering and bridge design services for the Canyon
Road Bridge Replacement project (CIP 14-101) in an
amount of $378,000 for a total amount not to exceed
$1,508,004.
STAFF RECOMMENDATION
24