can training boiler

Upload: egehan-uemer

Post on 07-Jul-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 CAN Training Boiler

    1/207

    February 2003February 2003

    Training

    ÇAN THERMAL POWER PLANT

  • 8/18/2019 CAN Training Boiler

    2/207

  • 8/18/2019 CAN Training Boiler

    3/207

  • 8/18/2019 CAN Training Boiler

    4/207

    Steam Generator 

     with Circulating FBC

    Untertitel (Arial 22 bis 24)

    Training CAN Seite 4

    Customer  TEAS

    Plant location CAN / Turkey

    Firing capacity 358,6 MW

    Steam data SH RH

      485 t/h 437 t/h

      175 bar 38 bar 

      543 °C 542 °C

    Fuel turkish lignite

     Year of Commissioning  2003

  • 8/18/2019 CAN Training Boiler

    5/207

    Steam Generator 

    Cross section furnace centre

    Training CAN Seite 5

  • 8/18/2019 CAN Training Boiler

    6/207

    Steam Generator 

    Circulating Fluidized Bed

    Training CAN Seite 6

    furnace

    nozzle grid

    primary air 

    flue gas

    cyclone

  • 8/18/2019 CAN Training Boiler

    7/207

    General description

    process - fluidization

    Training CAN Seite 7

    Combustion air is mainly divided in

    primary air - air through nozzle grid

    secondary air - air through air nozzles above grid

    bed material consists of approx. 98 % ash or sand

    nozzle grid causes for a homogenous fluidization of 

    bed material

  • 8/18/2019 CAN Training Boiler

    8/207

    General description

    process - fluidization

    Training CAN Seite 8

    primary air transports bed material in direction of 

    ceiling

    coarse bed material falls down along sidewalls

    other material is separated in cyclones

    separated material returns to furnace through loop

    seals with fluidization air 

    flue gas leaves cyclones through exit tubes to 2nd

    pass

    fly ash is separated in electrostatic precipitator 

  • 8/18/2019 CAN Training Boiler

    9/207

    General description

    process flow

    Process flow schematic

    Training CAN Seite 9

  • 8/18/2019 CAN Training Boiler

    10/207

    General description

    process - fuel supply

    Training CAN Seite 10

    crushed raw lignite is stored in four coal bunkers

    coal is discharged through coal feeders to 8 feedingpoints of the four double ash loop seals for a

    uniform disribution of the fuel across nozzle grid

    mixing with hot ash in loop seals predries coal

    already

    Coal feeding system

  • 8/18/2019 CAN Training Boiler

    11/207

    General description

    process - limestone supply

    Training CAN Seite 11

    Limestone powder is stored in two limestone

    bunkers

    limestone is discharged through fluidizing

    conveyors to the 8 coal drag link chain conveyors

    Limestone system

  • 8/18/2019 CAN Training Boiler

    12/207

    General description

    process - bed material supply

    Training CAN Seite 12

    for first start up of boiler or after revision, furnace is

    filled up with sand or available bed material

    bed material is discharged through a rotary feeder 

    and a drag link chain conveyor to furnace

    for a uniform distribution of bed material,there shallbe a minimum primary air flow during feeding

  • 8/18/2019 CAN Training Boiler

    13/207

    General description

    process - bed material discharge

    Training CAN Seite 13

    bed ash is discharged via four openings in bottom

    of furnace

    ash flow from furnace to the two ash coolers are

    controlled with L-valves

    bed ash is fluidized in ash cooler and cooled downthrough feeding water and condensate

    cooled down bed ash can conveyed to bed materialsilo

    L-valve

     Ash cooler 

  • 8/18/2019 CAN Training Boiler

    14/207

    General description

    particle size characteristics

    Training CAN Seite 14

    Particle size distribution mainly depends on :

    particle size of the supplied coal

    particle size of the limestone

    particle size of the externally supplied bed material separation characteristics of the cyclones

    abrasion characteristics of ash

    Grain size distr 

  • 8/18/2019 CAN Training Boiler

    15/207

    General description

    particle size characteristics

    Training CAN Seite 15

    Expected particle size distribution

    m a te r ia l m a x . g ra in s iz e (m m ) m a in p a r t ic le (m m )

    C o a l < 2 0 4 -5

    L im e s to n e < 1 0 ,1 -0 ,1 5B e d a s h < 1 0 ,2 -0 ,5

    approx. values for

    initial adjustment

  • 8/18/2019 CAN Training Boiler

    16/207

    General description

    Steam generator data

    Steam dataSteam data

    Steam capacity SH / RH 457 / 407 t/h

    Pressure SH / RH 190 / 39.8 bar 

    Temperature SH / RH 543 / 542 °C

    Feedwater temperature 250 °C

    Waste gas temperature 138 °C

    Training CAN Seite 16

  • 8/18/2019 CAN Training Boiler

    17/207

    Steam generator data

    H-p diagram

    Training CAN Seite 17

    Fuel Data:Fuel Data:

    Fuel: Brown Coal

    LCV: 10.890 MJ/kg

    Ash: 32.0 %

    Water: 22.0 %

     Eco

    Evaporator 

     SH 1/1SH 1/2SH 1/3INJ-1

    SH 2-PL

    INJ-2SH 3

    ..

    .

    ....

    ..

    ..

    .

    RH 1RH-INJ

    RH 2-PL

    .

    ..

    .

    Pressure

    0 50 100 150 200 250 300 bar 400

       E  n   t   h  a   l  p  y

    4,000

    3,600

    3,200

    2,800

    2,400

    2,000

    1,600

    1,200

    800

    400

    kJ/kg

    100 °C 

    150 °C 

    200 °C 

    250 °C 

    300 °C

    350 °C 

    375 °C 

    40 0  ° C  

    45 0  ° C  

    5 0 0  ° C  

    5 5 0  ° C  

    600 °C 

    650 °C 

    7 00 °C 

    750 °C 

  • 8/18/2019 CAN Training Boiler

    18/207

    General description

    Steam generator data

    Training CAN Seite 18

    Fuel dataFuel data

    Brown coal

    Calorific value (NCV) 10.9 MJ/kg  Ash 32 %

    Moisture 22%

    Sulphur 4.0 % (max. 7.0 %) Fuel capacity 128 t/h

    Desulphurization 95 %

    SO2 Emission 1,000 mg/m3

     s.t.p. (5 % O2) Fuel ash composition SiO2 50 %, Al2O3 30 %,

    FeO3 15 %, other const 5 %

  • 8/18/2019 CAN Training Boiler

    19/207

    Flue Gas Temperature

    Versus Load Nozzle Grid/Furnace

    Training CAN Seite 19

    1000

    900

    800

    700

    600

    500

    400

    300

    200

    100

    0

    0   40   60 80 100

    Steam output (%)

       F   l  u  e  g  a  s   t  e  m

      p  e  r  a   t  u  r  e   (   °   C   )

    20

    Furnace

    Nozzle Grid

    Fuel DataFuel Data::

    Fuel: Brown Coal

    LCV: 10.890 MJ/kg

     Ash: 32.0 %

    Water: 22.0 %

    approx. values for

    initial adjustment

  • 8/18/2019 CAN Training Boiler

    20/207

    Description of systems

    Water / steam system

    components

    Training CAN Seite 20

    feedwater supply

    feedwater preheating

    evaporator 

    superheater  reheater 

    high pressure heatersash coolers

    economiser 

    heating surfaces

    drum

  • 8/18/2019 CAN Training Boiler

    21/207

    Description of systems

    Natural circulation boiler 

    Training CAN Seite 21

    Feedwater control

    Level

    Feedwater 

    Steam flow m•

    EvaEco

    T

  • 8/18/2019 CAN Training Boiler

    22/207

    Description of systems

    Water steam scheme

    Training CAN Seite 22

         

     

  • 8/18/2019 CAN Training Boiler

    23/207

    Description of systems

    Feedwater supply

    2 controlled feed pumps

    for controlling of sufficient differential pressure

    between inlet and outlet of the

    feedwater control station

    2 feedwater control valves

    one start up feed control valve (up to 30 % )

    one full load feed control valve

    for controlling of required feedwater flow

    Training CAN Seite 23

  • 8/18/2019 CAN Training Boiler

    24/207

    Description of systems

    feedwater supply

    P&I feedwater control station

    Training CAN Seite 24

  • 8/18/2019 CAN Training Boiler

    25/207

    Description of systems

    Feedwater preheating

    HP heater 6 and 7

    feeded from bleeding or CRH steam

    cooling of HP ash coolers with feedwater 

    normal boiler operation:

    all feedwater is sent through ash coolers

    if one ash cooler out of operation,

    bypass available

    economiser 

    arranged in second pass flue gas

    last heating surface upstream flue gas air heater 

    Training CAN Seite 25

  • 8/18/2019 CAN Training Boiler

    26/207

    Description of systems

     Ash cooler 

    Training CAN Seite 26

  • 8/18/2019 CAN Training Boiler

    27/207

    Description of systems

    evaporator 

    Wall heating surfaces of the furnace

    Training CAN Seite 27

  • 8/18/2019 CAN Training Boiler

    28/207

    Description of systems

    superheater 

    Two parallel steam lines

    SH 1/1 supporting tubes of the second pass

    SH 1/2 walls of second pass

    SH 1/3 convective heating surface in second pass spray attemperator 1

    SH 2 platen heating surface in furnace

    spray attemperator 2

    SH 3 convective heating surface in second pass

    Training CAN Seite 28 

    D i i f

  • 8/18/2019 CAN Training Boiler

    29/207

    Description of systems

    P&I attemperator 

    Training CAN Seite 29

    D i ti f t

  • 8/18/2019 CAN Training Boiler

    30/207

    Description of systems

    Live steam piping

    One SH safety valve (≈30 % MCR flow)

    one SH standstill cooling valve (≈10% GCC flow)

    one HP bypass control valve (70 % MCR flow)

    with safety function

    two HP turbine valves (2 x 50 % MCR flow)

    Training CAN Seite 30

    D i ti f t

  • 8/18/2019 CAN Training Boiler

    31/207

    Description of systems

    P&I live steam

    Training CAN Seite 31

    D i ti f t

  • 8/18/2019 CAN Training Boiler

    32/207

    Description of systems

    HP safety devices

    Safety device MCRflow

    MCR operatingpressure

    One HP safety valve atdrum

    70 % +17 bar  

    One HP bypass controlvalve at SH 3 outlet

    70 % + 10 bar  

    One HP safety valve atSH 3 outlet

     Approx.30 %

    + 17 bar 

    Training CAN Seite 32

    LP safety devices

    Pressure control

    Description of systems

  • 8/18/2019 CAN Training Boiler

    33/207

    Description of systems

    reheater 

    Two parallel steam lines

    RH 1 convective heating surface in second pass

    spray attemperator 1

    RH 2 platen heating surface in furnace

    Training CAN Seite 33

    Description of systems

  • 8/18/2019 CAN Training Boiler

    34/207

    Description of systems

    Hot reheat steam piping

    One LP start up standby control valve

    ( 30 % GCC)

    one RH safety valve (MCR flow)

    one LP bypass control valve

    ( > 315 t/h at 39.2 bar)

    two LP turbine interceptor valves

    (2 x 50 % MCR flow)

    Training CAN Seite 34

    Description of systems

  • 8/18/2019 CAN Training Boiler

    35/207

    Description of systems

    LP safety device

    Safety device MCR

    flow

    MCR operating

    pressure

    One HP safety

    valve at drum

    70 % +17 bar  

    Training CAN Seite 35 Pressure control

    Description of systems

  • 8/18/2019 CAN Training Boiler

    36/207

    Description of systems

    HP auxiliary systems

    Filling line

    Desalting system

    start up drain system ( drum, flash tank,

    boiler condensate tank )

    drain system of heating surfaces

    venting system

    Training CAN Seite 36

    Description of systems

  • 8/18/2019 CAN Training Boiler

    37/207

    Description of systems

    P&I SH drain station

    Training CAN Seite 37

    Description of systems

  • 8/18/2019 CAN Training Boiler

    38/207

    Description of systems

    air fluegas system

    components

    Training CAN Seite 38

    2 secondary air (SA) fans with vane guide

    function: supply of the CFB system withsecondary air 

    capacity: 2 x 70%

    2 primary air (PA) fans with vane guide

    function: supply of the CFB system with

    primary air 

    capacity: 2 x 70%

    Description of systems

  • 8/18/2019 CAN Training Boiler

    39/207

    Description of systems

    P&I PA / SA fan

    Training CAN Seite 39

    Description of systems

  • 8/18/2019 CAN Training Boiler

    40/207

    Description of systems

    air fluegas system

    components

    Training CAN Seite 40

    4 steam air heaters (SAHs)

    function: heating up the combustion air for start up and to prevent flue gas

    temperature falling below dew point

    2 regenerative air heaters (RAH)

     function: heating up combustion air 

    Description of systems

  • 8/18/2019 CAN Training Boiler

    41/207

    Description of systems

    air fluegas system

    components

    Training CAN Seite 41

    3 fluidizing air fans

    function: fluidization of loop seals,supply of flame scanners, ignitors

    and oil lances with cooling and

    ignition air  capacity: 3 x 50%

    Description of systems

  • 8/18/2019 CAN Training Boiler

    42/207

    Description of systems

    air fluegas system

    components

    Training CAN Seite 42

    2 ash coolers with immersed cooling surfaces

    and 2 ash cooler fansfunction: cooling of the extracted bed ash from

    850°C to 60°-140°C

    capacity: 2 x 100%

    Description of systems

  • 8/18/2019 CAN Training Boiler

    43/207

    p y

    air fluegas system

    components

    Training CAN Seite 43

    2 electrostatic precipitators (ESP)

     function: cleaning flue gas from ash particles capacity: 2 x 70%

    2 induced draught (ID) fans with vane guide

     function: leading flue gas to chimney

    control flue gas pressure at cyclone

    outlet

     capacity: 2 x 70%

    Description of systems

  • 8/18/2019 CAN Training Boiler

    44/207

    p y

    start-up burner 

    Use of start up burner 

    Training CAN Seite 44

    start up burners are used for heating up of the

    bed material in the furnace until the releasetemperature for coal feeding is reached

    HFO shall be used with an combustion air temperature of at least 120 °C

    Description of systems

  • 8/18/2019 CAN Training Boiler

    45/207

    p y

    start-up burner 

    components

    Training CAN Seite 45

      number of burners 8 (3 front wall, 3 rear wall,

    1 left and 1 right side wall)

      number of levels 1

      fuel heavy oil N° 6/ light oil N° 2

      type of burner jet burner 

      atomising system pressure atomisation

      fitting position 30 °

    Description of systems

  • 8/18/2019 CAN Training Boiler

    46/207

    y

    start-up burner 

    Releases

    Training CAN Seite 46

    LFO ignition permit time is running

    (boiler is purged)or 

    >7 bed temperature >570° C

    or 

    start up burner is on

    HFO see LFOand

    temperature HFO > 90°C

    Description of systems

  • 8/18/2019 CAN Training Boiler

    47/207

    start-up burner 

    Technical data light oil

    Training CAN Seite 47

    oil flow max. 1656 kg/h

    oil flow min. 828 kg/h

    oil pressure max. 75 bar  

    oil pressure min. 20 bar  

    control range 1 : 2

    Description of systems

  • 8/18/2019 CAN Training Boiler

    48/207

    start-up burner 

    Technical data heavy oil

    Training CAN Seite 48

    oil flow max. 1728 kg/h

    oil flow min. 865 kg/h

    oil pressure max. 70 bar  

    oil pressure min. 15 bar  

    control range 1 : 2

    Description of systems

  • 8/18/2019 CAN Training Boiler

    49/207

    start-up burner 

    operation

    Training CAN Seite 49

    Either light oil operation or heavy oil operation

    can be preselected.Then oil supply must be started.

    The start up burner can be started or stopped

    manually from local panel in the field or controlroom.

    Description of systems

  • 8/18/2019 CAN Training Boiler

    50/207

    start-up burner 

    operation

    Training CAN Seite 50

    If oil lance is empty and heavy oil operation is

    preselected, oil lance will be prewarmed for 90sec with steam

    Signal "lance prewarmed" is displayed for 600

    sec, if steam cleaning valves have been open for at least 80 sec

    Description of systems

  • 8/18/2019 CAN Training Boiler

    51/207

    start-up burner 

    operation

    Training CAN Seite 51

    If oil lance is empty, safety time is running for 12

    secIf oil lance is not empty ( filled lance ) safety time

    is running for 5 sec

    Description of systems

    t t b

  • 8/18/2019 CAN Training Boiler

    52/207

    start-up burner 

    operation

    Training CAN Seite 52

    Start up burner shuts down automatically with FG

    boiler shutdown or if ignition trial failed Scavenging is done with steam valve opened

    and ignition in operation for 15 sec, then 5 min

    without ignition.

    Description of systems

    t t b

  • 8/18/2019 CAN Training Boiler

    53/207

    start-up burner 

    Training CAN Seite 53

    impeller 

    oil lance

    ignitor 

    flame scanner 

    core air 

    Description of systems

    t t b

  • 8/18/2019 CAN Training Boiler

    54/207

    start up burner 

    P&I start up burner 

    Training CAN Seite 54

    Description of systems

    start up burner

  • 8/18/2019 CAN Training Boiler

    55/207

    start up burner 

    burner station

    Training CAN Seite 55

    Description of systems

    bed lances

  • 8/18/2019 CAN Training Boiler

    56/207

    bed lances

    Use of bed lances

    Training CAN Seite 56

    ignition of bed lances possible with at least

    500° C / 550 °C bed temperature

    bed lances are used for heating up of the bed

    material in the furnace until the releasetemperature for coal feeding is reached

    bed lances are used for maintaining a constant

    bed material temperature at low loads

    Description of systems

    bed lances

  • 8/18/2019 CAN Training Boiler

    57/207

    bed lances

    components

    Training CAN Seite 57

      number of burners 8 (2 front wall, 2 rear wall,

    2 left and 2 right side wall)

      number of levels 1

      fuel heavy oil N° 6/ light oil N° 2

    atomising system pressure atomisation

      max. load 15 % of boiler load

      fitting position 30 °

    Description of systems

    bed lances

  • 8/18/2019 CAN Training Boiler

    58/207

    bed lances

    Technical data light oil

    Training CAN Seite 58

    oil flow max. 612 kg/h

    oil flow min. 300 kg/h

    oil pressure max. 72 bar  

    oil pressure min. 17 bar  

    control range 1 : 2

    Description of systems

    bed lances

  • 8/18/2019 CAN Training Boiler

    59/207

    bed lances

    Technical data heavy oil

    Training CAN Seite 59

    oil flow max. 648 kg/h

    oil flow min. 320 kg/h

    oil pressure max. 75 bar  

    oil pressure min. 20 bar  

    control range 1 : 2

    Description of systems

    bed lances

  • 8/18/2019 CAN Training Boiler

    60/207

    bed lances

    Releases

    Training CAN Seite 60

    LFO start up burner in operationand

    >7 bed temperature >500° Cor >7 bed temperature >570° C

    HFO start up burner in operation

    and>7 bed temperature >550° Cand

      temperature HFO > 90°C

    or >7 bed temperature >570° Cand

      temperature HFO > 90°C

    approx. values for

    initial adjustment

    Description of systems

    start-up burner / bed lances

  • 8/18/2019 CAN Training Boiler

    61/207

    start up burner / bed lances

    Training CAN Seite 61

    Description of systems

    ash cooler

  • 8/18/2019 CAN Training Boiler

    62/207

    ash cooler 

    components

    Training CAN Seite 62

    The bed ash discharge system extracts the bed

    ash from the furnace automatically depending

    on the pressure above primary air nozzle grid

    The bed ash system is equipped with 4

    horizontal L-valves , 2 to each ash cooler.

    general

    Description of systems

    ash cooler

  • 8/18/2019 CAN Training Boiler

    63/207

    ash cooler 

    pressure above nozzle grid versus load

    Training CAN Seite 63

    80

    90

    100

    110

    120

    130

    0 10 20 30 40 50 60 70 80 90 100

    load BMCR (%)

      p  r  e  s  s  u  r  e  a

       b  o  v  e  g  r   i   d   (  m   b  a  r   )

    setpoint 1

    setpoint 2

    setpoint 3

    setpoint 4

    general

    description

    L-valve

    approx. values for

    initial adjustment

    Description of systems

    P&I ash cooler

  • 8/18/2019 CAN Training Boiler

    64/207

    P&I ash cooler 

    Training CAN Seite 64

    furnace

    from

    ash cooler fan

    general

    Description of systems

    ash cooler 

  • 8/18/2019 CAN Training Boiler

    65/207

    overview

    Training CAN Seite 65 general

    Description of systems

    ash cooler 

  • 8/18/2019 CAN Training Boiler

    66/207

    components

    Training CAN Seite 66

    The bottom ash discharge via horizontal L-valve

    is done discontinuously. The horizontal L-valve

    is set into a basic position. The opening

    sequence and amplitude of the horizontal L-

    valve is controlled by the reference value,

    pressure above primary air nozzle grid. During

    normal operation both horizontal L-valves are in

    operation and work alternating for each

    sequence. The horizontal L-valve is kept at itsbasic position when the reference value is

    below a specified minimum set point.

    Setpoint L-valves

    Description of systems

    L-valve

  • 8/18/2019 CAN Training Boiler

    67/207

    ash control valve

    Training CAN Seite 67 Setpoint L-valves

    Plug

    Valve Seat

    Water Cooled

    Valve Shaft

    Hydraulic

     Actuator 

     Assembly

    Refractory Lined

    Valve Bodygeneral

    Description of systems

    auxiliaries

  • 8/18/2019 CAN Training Boiler

    68/207

    arrangement

    Training CAN Seite 68

    Description of systems

    air preheater 

  • 8/18/2019 CAN Training Boiler

    69/207

    regenerative air preheater 

    Training CAN Seite 69

     Air preheaters consist of a large number of heat

    transfer plates arranged like the spokes of a

    wheel, which slowly rotate at speeds lower than

    one revolution per minute and up to approximately

    five r/mm from a hot side exhaust environment

    into a cold side intake. The cold intake air is thus

    "preheated" improving efficiencies and reducing

    wasted process energy.

    Description of systems

    air preheater 

  • 8/18/2019 CAN Training Boiler

    70/207

    regenerative air preheater 

    Training CAN Seite 70

     Air flow downstream of APH Flue gas upstream of APH

     Air flow upstream of APH Flue gas downstream of APH

    Description of systems

    cyclones

  • 8/18/2019 CAN Training Boiler

    71/207

    Purpose of cyclones

    Training CAN Seite 71

     Arrangement downstream of the furnace

    cyclone inlets have a spiral shape

    cyclones have an interior lining which isfireproof, wear resistant and insulates

    particles above an significant size are completely

    separated

    solid mass flow is transported from the from the

    loop seals to the furnace

    loop seals prevent a backflow of fluegas from

    furnace

    flue gas leaves cyclones through exit tubes

    Description of systems

    cyclones

  • 8/18/2019 CAN Training Boiler

    72/207

     Arrangement cyclones

    Training CAN Seite 72

    Çan

    355.6 MW

    Description of systems

    cyclones

  • 8/18/2019 CAN Training Boiler

    73/207

    Cyclone overview

    Training CAN Seite 73

    InclinedDownward

    Inlet Duct

    High PerformanceRefractory for Inlet Area

    Eccentric VortexFinder Arrangement

     Advanced VortexFinder Shape

    Second Pass

    Description of systems

    cyclones

  • 8/18/2019 CAN Training Boiler

    74/207

      cyclone performance

    Training CAN Seite 74

    Description of systems

    cyclones

  • 8/18/2019 CAN Training Boiler

    75/207

    velocity and dust loading

    Training CAN Seite 75

    velocity dust loading

    Description of systems

    loop seal

  • 8/18/2019 CAN Training Boiler

    76/207

    P&I loop seal

    Training CAN Seite 76

    Description of systems

    loop seal

  • 8/18/2019 CAN Training Boiler

    77/207

    loop seal

    Training CAN Seite 77

    Description of systems

    loop seal

  • 8/18/2019 CAN Training Boiler

    78/207

    loop seal

    Training CAN Seite 78

    downcomer 

    lift

    line

    Description of systems

    auxiliaries

  • 8/18/2019 CAN Training Boiler

    79/207

    section lower furnace

    Training CAN Seite 79

    Description of systems

    sootblower 

  • 8/18/2019 CAN Training Boiler

    80/207

    Rotary long retractable sootblower 

    Training CAN Seite 80

    Description of systems

    sootblower 

  • 8/18/2019 CAN Training Boiler

    81/207

    Rotary extended lance sootblower 

    Training CAN Seite 81

    Description of systems

    sootblower 

  • 8/18/2019 CAN Training Boiler

    82/207

    Installation 2nd pass

    Training CAN Seite 82

    No Level(m)

    KKS-No Fluegastemperature

    ( °C)

    Fluegaspressure(mbar)

    Type of construction

    1 33.630 01 HCB20 AT001 860 -1.0 Long retractable blower2 33.630 01 HCB20 AT001 860 -1.0 Long retractable blower

    3 33.630 01 HCB20 AT001 860 -1.0 Long retractable blower

    4 30.560 01 HCB20 AT001 700 -2.0 Long retractable blower

    5 30.560 01 HCB20 AT001 700 -2.0 Long retractable blower

    6 30.560 01 HCB20 AT001 700 -2.0 Long retractable blower7 25.170 01 HCB20 AT001 540 -4.0 Helical blower

    8 25.170 01 HCB20 AT001 540 -4.0 Helical blower

    9 25.170 01 HCB20 AT001 540 -4.0 Helical blower

    10 19.250 01 HCB20 AT001 435 -6.0 Helical blower

    11 19.250 01 HCB20 AT001 435 -6.0 Helical blower12 19.250 01 HCB20 AT001 435 -6.0 Helical blower

    13 12.950 01 HCB20 AT001 375 -8.0 Helical blower

    14 12.950 01 HCB20 AT001 375 -8.0 Helical blower

    15 12.950 01 HCB20 AT001 375 -8.0 Helical blower

    Description of systems

    limestone feeding

  • 8/18/2019 CAN Training Boiler

    83/207

    limestone feeding system

    Training CAN Seite 83

    two limestone silos

    one fluidizing conveyor, divides the conveying

    route in two parts

    adjustable rotary feeders

    adjustable drag link conveyors

    two manual operated gate valves

    <

    Description of systems

    limestone feeding

  • 8/18/2019 CAN Training Boiler

    84/207

    P&I limestone feeding

    Training CAN Seite 84

    limestone silo

    fluidizing conveyor 

    rotary feeders

    drag link conveyors

    <

    Description of systems

    coal and limestone feeding

  • 8/18/2019 CAN Training Boiler

    85/207

    arrangement coal and limestone feeding

    Training CAN Seite 85

    Description of systems

    coal feeding

  • 8/18/2019 CAN Training Boiler

    86/207

    arrangement

    Training CAN Seite 86

    cyclone Coal bunker furnace

    Gravimetric

    coal feeder 

    Drag link

    chain conveyor 

    Loop seal

    Rotary

     feeders

    <

    Description of systems

    coal feeding

    l f di t

  • 8/18/2019 CAN Training Boiler

    87/207

    coal feeding system

    Training CAN Seite 87

    four coal bunkers each with two outflows

    altogether eight adjustable gravimetric coal

    feeders with clean out conveyor 

    eight adjustable drag link chain conveyors with

    connection with limestone feeding

    downstream of drag link conveyors route divides

    in two conveying routes

    each route is lockable with manual operated shutoff gate valves

    <

    Description of systems

    coal feeding

    l f di t

  • 8/18/2019 CAN Training Boiler

    88/207

    coal feeding system

    Training CAN Seite 88

    each route is lockable with manual operated shut

    off gate valves

    each route consists of one rotary feeder  downstream one manual operated shut off gate

    valve

    one auto operated shut off gate valve

    both shut off gate valves, rotary feeder and drag

    link chain conveyors are supplied with adjustable

    sealing air 

    upstream of loop seal both conveying routes are

    linked up<

    Boiler protection

    Boiler protection part I

    I t l k

  • 8/18/2019 CAN Training Boiler

    89/207

    ID fan protection

    SA fan protection

    secondary air way release

    primary air way release

    reheater release

    general interlocking

    Interlocks

    Training CAN Seite 89

    symbols

    Logic diagram

    Boiler protection

    Boiler protection part II

    Interlocks

  • 8/18/2019 CAN Training Boiler

    90/207

    boiler purge

    ignition release

    start up burner release

    bed lance burner LFO release

    bed lance burner HFO release

    oil burner purge release

    coal feeder release

    Interlocks

    Training CAN Seite 90

    Boiler protection

    ID fan protection

    Both ID fans are tripped if

  • 8/18/2019 CAN Training Boiler

    91/207

    Both ID fans are tripped if 

    >=2 furnace pressure < min

     >=2 reg air heater speed < min

    one of four ID fan bearing temperature

    > 90 °C

    cooling air flow < min ( for > than 30 min)ID fan motor winding temperature > 140°C

    ID fan motor cooling air inlet temperature

    > 70°CID fan motor cooling air outlet temperature

    > 110°C

    ID fan vibration > 11 mm/sTraining CAN Seite 91 approx. values forinitial adjustment

    Boiler protection

    SA fan protection

  • 8/18/2019 CAN Training Boiler

    92/207

    Both SA fans are tripped if 

    no ID fans in operation and ”command on”

    SA fan   ≤ 2 furnace pressure > max

    SA fan bearing temperature > 95°C

    SA fan motor winding temperature > 140°C SA fan motor cooling air inlet temperature

    > 70°C

    SA fan motor cooling air outlet temperature> 110°C

    SA fan vibration > 11 mm/s

    Training CAN Seite 92approx. values forinitial adjustment

    Boiler protection

    Secondary air way release

  • 8/18/2019 CAN Training Boiler

    93/207

    Secondary air way release is available if 

    no boiler emergency switch is activated

    furnace pressure is > min and < max

    ID fan and SA fan are in operation

    fluegas dampers are open

    Failure of air and fluegas way release signal leads

    to boiler trip.

    Training CAN Seite 93

    Boiler protection

    Primary air way release

    Primary air way release is available if following

  • 8/18/2019 CAN Training Boiler

    94/207

    Primary air way release is available, if following

    signals are available

    secondary air way release

    a minimum fluidising air pressure ( 300 mbar)

    a minimum secondary air pressure ( 30 mbar) reheater release

    water level in the drum < max ( 200 mm)

    water level in the drum > min

    Training CAN Seite 94approx. values forinitial adjustment

    Boiler protection

    Reheater release

  • 8/18/2019 CAN Training Boiler

    95/207

    Training CAN Seite 95

    Boiler protection

    General interlocking

  • 8/18/2019 CAN Training Boiler

    96/207

    master fuel fault is existing, if 

    failure of the primary air way release signal both PA Fans out of operation

    furnace windbox pressure below a minimum( 40 mbar )

    primary air flow below minimum (38570 Nm³/h) condenser level not > max

    Training CAN Seite 96approx. values forinitial adjustment

    Boiler protection

    Boiler purge

    The purging is done with 50% MCR air flow

  • 8/18/2019 CAN Training Boiler

    97/207

    Training CAN Seite 97

    The purging is done with ~50% MCR air flow(78.5 kg/s). The purge time is set to a value thatmeets the total volume of 3 times boiler fluegas

    way volume (16 min). On completion of the presetvolumes i.e. 3 times volume change for fluegaspath the signal boiler purge time completed is

    activated. Any interruption during this processresets the boiler purge time relay. In this case thepurge cycle has to start all over again. If the boiler was in operation and the bed temperature at the

    nozzle grid level exceeded 570 °C there is noneed to purge the boiler.

    approx. values forinitial adjustment

    Boiler protection

    Ignition release

  • 8/18/2019 CAN Training Boiler

    98/207

    Once the purge is completed the ignition permit

    time is set and a secondary air flow < 30% is

    maintained. For the normal start time a maximumof 3 failstarts is allowed. The start attempts of the

    burners is monitored through a fail start counter. If 

    the burner is not established within the allowedpreset number failstart counts the boiler has to be

    purged again.

    Training CAN Seite 98

    Boiler protection

    Ignition release

  • 8/18/2019 CAN Training Boiler

    99/207

    Ignition oil burner release permit is available

    provided there are the following

    start up burner on

    or 

    bed temperature > 570°C

    boiler protection existing

    or  ignition permit time running

    secondary air flow < 30%

    Training CAN Seite 99approx. values forinitial adjustment

    Boiler protection

    Start up burner release

    Oil burner burner release permit is available

  • 8/18/2019 CAN Training Boiler

    100/207

    Oil burner burner release permit is availableprovided there are the following:

    Primary air way release

    Ignition release

    Minimum primary air flow available or oil valvesstart up burners closed at least 10 min

    Min LFO supply pressure available (if light oiloperation selected)

    Min HFO supply pressure available (if heavy oiloperation selected)

    control air pressure > min available ( 3,5 bar)

    Training CAN Seite 100approx. values forinitial adjustment

    Boiler protection

    LFO bed lance burner release

    b d l b LFO l it i il bl

  • 8/18/2019 CAN Training Boiler

    101/207

    bed lance burner LFO release permit is available

    provided there are the following:

    Ignition release

    boiler protection

    Primary air flow > min (38570 Nm³/h)

    control air pressure > min ( 3,5 bar)

    bed temperature > 500 °C

    Training CAN Seite 101approx. values forinitial adjustment

    Boiler protection

    HFO bed lance burner release

    b d l b HFO l it i il bl

  • 8/18/2019 CAN Training Boiler

    102/207

    bed lance burner HFO release permit is available

    provided there are the following:

    Ignition release

    boiler protection

    Primary air flow > min ( 38570 Nm³/h)

    control air pressure > min ( 3,5 bar)

    bed temperature > 550 °C

    Training CAN Seite 102approx. values forinitial adjustment

    Boiler protection

    Oil burner purge release

    Oil b rner p rge release permit is a ailable

  • 8/18/2019 CAN Training Boiler

    103/207

    Oil burner purge release permit is available

    provided there are the following:

    bed lance burner LFO release

    or 

    bed lance burner HFO release

    or 

    start up burner release

    and minimum purge steam pressure available

    Training CAN Seite 103

    Boiler protection

    Coal feeder release

    Coal feeder release permit is available provided

  • 8/18/2019 CAN Training Boiler

    104/207

    Coal feeder release permit is available provided

    there are the following

    boiler protection existing

    ignition release existing

    >=2 primary air flow > min 52550 Nm³/h)

    >=7 bed temperature > min ( 650° C)

    Training CAN Seite 104approx. values forinitial adjustment

    Boiler protection

    unit load runback

    one of two ID Fan is tripped

  • 8/18/2019 CAN Training Boiler

    105/207

    one of two ID Fan is tripped

    target: 70 % BMCR not delayed

    one of two SA Fan is trippedtarget: 70 % BMCR not delayed

    one of two PA Fan is trippedtarget: 70 % BMCR not delayed

    one of two FB ash cooler fan

    target: 70 % BMCR not delayed

    turbine trip

    target: 60 % BMCR not delayedTraining CAN Seite 105

    approx. values forinitial adjustment

    System operation

    overview

    fi t filli f b il

  • 8/18/2019 CAN Training Boiler

    106/207

    first filling of boiler 

    cold start up boiler 

    warm start up boiler 

    hot start up boiler 

    normal operation

    shut down boiler 

    blackout

    failures

    Training CAN Seite 106

    System operation

    first filling of boiler 

    Filling line is used for filling the evaporator after a

  • 8/18/2019 CAN Training Boiler

    107/207

    Filling line is used for filling the evaporator after a

    repair standstill. Evaporator and downcomer are

    filled from bottom up to avoid thermal stress of drum during filling operation

    all isolating valves upstream of measurementsshall be opened

    Filling of eco, evaporator and of drum via fillingline ( 01 LAE10) until drum level > min

    Training CAN Seite 107

    System operation

    General

    Operation conditions for start / stop and

  • 8/18/2019 CAN Training Boiler

    108/207

    Operation conditions for start / stop and

    monitoring of the boiler is given in the form of 

    functional group logics whole system is divided into functional groups

    and subgroups

    function group control can be started in automode or manually.

    group control is used to START or STOP in

    steps.

    Training CAN Seite 108

    System operation

    General

    every step is activated when its previous step

  • 8/18/2019 CAN Training Boiler

    109/207

    every step is activated, when its previous step

    command is carried out and the necessary

    conditions previous to this step are fulfilled step is overriden or overruled, if the subsequent

    conditions meet the overruling criterias to this

    step selection control blocks are for either one out of 

    two or three equipments

    some operational conditions require manualintervention (e.g. start of oilburners, coalfeeding)

    Training CAN Seite 109

    System operation

    Overview function groups

  • 8/18/2019 CAN Training Boiler

    110/207

    Training CAN Seite 110

    System operation

    Overview function groups

  • 8/18/2019 CAN Training Boiler

    111/207

    Training CAN Seite 111

    System operation

    Overview function groups

  • 8/18/2019 CAN Training Boiler

    112/207

    Training CAN Seite 112

    System operation

    cold start

    criterion for cold start up

  • 8/18/2019 CAN Training Boiler

    113/207

    p

    bed temperature < 100 °C

    bed temperature control

    The brick lining of the cyclone part admits amaximum rate of temperature change of approx.

    100 K /h. Therefore, the bed temperature is used

    as most important control variable during the start-up process, the required target being a bed

    temperature increase of approx. 100 K/h.

    Training CAN Seite 113

    System operation

    cold start

    Steam pressure control

  • 8/18/2019 CAN Training Boiler

    114/207

    p

    The life steam pressure is controlled by the HPbypass control valve during start-up of the steam

    generator. The hot reheat steam pressure is

    controlled by the LP bypass control valve. In caseof failures, a steam flow of 30% at maximum can

    be released to atmosphere via SH start-up standby

    control valve.

    Training CAN Seite 114

     Adj live st

     Adj reheat st

    System operation

    cold start

    Steam temperature control

  • 8/18/2019 CAN Training Boiler

    115/207

    p

    spray attemperators are ready for operation to keepsteam temperatures below given limits

    due to the very slow rate of bed temperature increase,

    the steam temperature rate of change both of lifesteam and of hot reheat steam normally will be in a

    safe range without any spray attemperator operation

    as soon as the required turbine coupling temperature

    in the life steam line or in the hot reheat line is reached,

    the relevant spray attemperator will open and will keep

    this temperature.

    Training CAN Seite 115

    System operation

    cold start

    Start-up of fans and of steam air preheater with Adjustment of firing

  • 8/18/2019 CAN Training Boiler

    116/207

    Start up of fans and of steam air preheater with

    FG air fluegas

    Fill-in of required bed material

    Purge via secondary air with FG purge

    Training CAN Seite 116

    System operation

    cold start

    Ignition of start-up burner (LFO) with a firing rate Adjustment of firing

  • 8/18/2019 CAN Training Boiler

    117/207

    g p ( ) g

    of approx. 10%

    use HFO start up burners not until combustionair temperature has reached 120 °C

    adjustment of primary air minimum flow

    minimum air flow for 

    start-up burner 38570 Nm³/h bed lances 46400 Nm³/h

    Training CAN Seite 117

    approx. values for

    initial adjustment

    System operation

    cold start

    Ignition of bed lance LFO or HFO (minimum bed Adjustment of firing

  • 8/18/2019 CAN Training Boiler

    118/207

    Ignition of bed lance LFO or HFO (minimum bed

    temperature for bed lance release LFO 500° C

    HFO 550° C )

    Firing rate increase to approx 40%. The increase

    takes place in steps adapted to avoid a rate of 

    change of the bed temperature > 100 K/h.

    Start-up at least one ash cooler 

    Training CAN Seite 118

    approx. values for

    initial adjustment

    System operation

    cold start

    Start-up of the first coal feeder after Adjustment of firing

  • 8/18/2019 CAN Training Boiler

    119/207

    Start up of the first coal feeder after 

    bed temperature > 650 °C is reached

    waiting time until coal ignition (coal ignition is

    recognized by fast increasing of bed

    temperature)

    Increase of coal firing rate, synchronous

    reduction of oil firing rate and oil firing turnoff 

    Training CAN Seite 119

    approx. values for

    initial adjustment

  • 8/18/2019 CAN Training Boiler

    120/207

    System operation

    cold start

    SH and RH start-up drains are set to autoDrain system

  • 8/18/2019 CAN Training Boiler

    121/207

    operated mode with starting FG air fluegas

    condensate obtained in the HP and LP steam

    system is automatically discharged

    Training CAN Seite 121

    System operation

    cold start

    controlled with HP bypass control valve Adjustment of live steam pressure

  • 8/18/2019 CAN Training Boiler

    122/207

    yp

    1. control valve opens to minimum position

    pressure will increase in sliding pressure mode

    2.pressure control mode with variable target rate

    up to turbine coupling pressure3.fixed pressure setpoint (until steam turbine has

    taken over all steam)

    4.increase steam pressure to operation pressure

    Training CAN Seite 122 Steam pr ctrl

    System operation

    cold start

    controlled with LP bypass control valve Adjustment of hot reheat steam pressure

  • 8/18/2019 CAN Training Boiler

    123/207

    yp

    1. control valve opens to maximum position -

    pressure will increase in sliding pressure mode

    2.pressure control mode with fixed pressure

    setpoint (until steam turbine has taken over allsteam)

    Training CAN Seite 123 Steam pr ctrl

    System operation

    cold start

  • 8/18/2019 CAN Training Boiler

    124/207

    Training CAN Seite 124

    System operation

    warm start

    criterion for warm start up

  • 8/18/2019 CAN Training Boiler

    125/207

    drum temperature > 100 °Cbed temperature < 650 °C

    Training CAN Seite 125

    System operation

    warm start

    start-up of fans and of steam air preheater with

    FG air fluegas

     Adjustment of firing

  • 8/18/2019 CAN Training Boiler

    126/207

    FG air fluegas

    if bed temperature < 570 °C :purge via secondary air 

    if bed temperature > 570 °C :

    ignition of the oil firing ignition of the oil firing ( start-up burner ) with a

    firing rate of approx. 10%

    adjustment of primary air minimum flow( see cold start )

    Training CAN Seite 126

    approx. values for

    initial adjustment

    System operation

    warm start

    Ignition of bed lance LFO or HFO (minimum bed

     Adjustment of firing

  • 8/18/2019 CAN Training Boiler

    127/207

    temperature for bed lance release LFO 500° C

    HFO 550° C )

    Firing rate increase to approx. 40%. First the

    increase is accelerated to reach quickly thesame bed temperature value, that was measured

    before purge. The following increase takes place

    in steps adapted to avoid a rate of change of the

    bed temperature > 100 K/h.

    Training CAN Seite 127

    approx. values for

    initial adjustment

    System operation

    warm start

    start-up of the first coal feeder after both bed

     Adjustment of firing

  • 8/18/2019 CAN Training Boiler

    128/207

    temperature > 650 °C is reached and the cooling

    of one FB-ash cooler at least is in service.

    increase of coal firing rate, synchronous

    reduction of oil firing rate and oil firing turnoff 

    Training CAN Seite 128

    approx. values for

    initial adjustment

    System operation

    warm start

    usual feedwater flow control during start-up of 

    Feedwater supply

  • 8/18/2019 CAN Training Boiler

    129/207

    the firing

    discharge of obtained excess water from drum

    by the drum blow down system

    normally the feedwater will always be sent

    through FB-ash coolers. However it is allowed to

    send the feedwater via ash cooler bypass aslong as bed temperature < approx. 200 °C.

    Training CAN Seite 129

    System operation

    warm start

    SH and RH start-up drains are set to auto

    Drain system

  • 8/18/2019 CAN Training Boiler

    130/207

    operated mode with starting FG air fluegas

    condensate obtained in the HP and LP steam

    system is automatically discharged

    Training CAN Seite 130

    System operation

    warm start

    controlled with HP bypass control valve

     Adjustment of live steam pressure

  • 8/18/2019 CAN Training Boiler

    131/207

    1. control valve opens to minimum position -

    pressure will increase in sliding pressure mode

    2.pressure control mode with variable target rate

    up to turbine coupling pressure

    3.fixed pressure setpoint (until steam turbine has

    taken over all steam)

    4.increase steam pressure to operation pressure

    Training CAN Seite 131

    System operation

    warm start

    controlled with LP bypass control valve

     Adjustment of hot reheat steam pressure

  • 8/18/2019 CAN Training Boiler

    132/207

    1. control valve opens to minimum position

    2.pressure control with pressure setpoint approx.

    equal to the HRH pressure value at ignition until

    LP bypass reaches maximum position

    ( approx.50% )

    3.pressure control mode with fixed pressure

    setpoint (until steam turbine has taken over allsteam)

    Training CAN Seite 132

    System operation

    warm start

  • 8/18/2019 CAN Training Boiler

    133/207

    Training CAN Seite 133

    System operation

    hot start

    criterion for hot start up

  • 8/18/2019 CAN Training Boiler

    134/207

    bed temperature > 650 °C

    Training CAN Seite 134

    System operation

    hot start

    restart of fans, adjustment of primary air 

    minimum flow ( > 52550 Nm³/h)

     Adjustment of firing

  • 8/18/2019 CAN Training Boiler

    135/207

    minimum flow ( 52550 Nm /h)

    restart of first coal feeder  rapid increase of firing rate to approx 40% in

    order to keep the bed temperature above 650 °C.

    Training CAN Seite 135

    approx. values for

    initial adjustment

    System operation

    hot start

    Feedwater supply

  • 8/18/2019 CAN Training Boiler

    136/207

    feedwater supply and drum blow down are

    working in the warm start-up manner.

    due to the high bed temperature the feedwater 

    shall always sent through FB ash cooler.

    Training CAN Seite 136

    System operation

    hot start

    Drain system

     Adjustment of live steam pressure

     Adjustment of hot reheat steam pressure

  • 8/18/2019 CAN Training Boiler

    137/207

    Training CAN Seite 137

    beginning at a higher pressure level

    actions to be taken in warm start-up manner 

    System operation

    hot start

  • 8/18/2019 CAN Training Boiler

    138/207

    Training CAN Seite 138

    System operation

    Normal operation

    feedwater supply and drum blow down

    desalting of boiler water

    overview

  • 8/18/2019 CAN Training Boiler

    139/207

    desalting of boiler water 

    steam pressure

    steam temperature

    control O2

    air distribution

    primary air control

    steam air preheater 

    Training CAN Seite 139

    System operation

    Normal operation

    pressure and temperature condition in the

    furnace

    overview

  • 8/18/2019 CAN Training Boiler

    140/207

    grain size distribution of the bed

    sootblowing

    limestone feeding desulphurization

    formation of NOx

    Training CAN Seite 140

    System operation

    Normal operation

    boiler feedwater pumps have the control task to

    ensure an appropriate differential pressure

    Feedwater supply and drum blow down

  • 8/18/2019 CAN Training Boiler

    141/207

    between inlet and outlet of the feedwater control

    station respectively between inlet of feedwater 

    control station and drum.

    the feedwater control valve in service has to

    adjust the feedwater mass flow. All feedwater is

    normally sent through the FB-ash cooler.

    overfed water is automatically discharged fromdrum by drum emergency blow down system.

    Training CAN Seite 141

    System operation

    Normal operation

    blow down valve is used for keeping conductivity

    of boiler water below 50 µS/cm

    Desalting of boiler water 

  • 8/18/2019 CAN Training Boiler

    142/207

    of boiler water below 50 µS/cm

    blow down valve can be operated intermittent or 

    continuously.

    blow down valve shall be closed when boiler is

    not in operation

    Training CAN Seite 142

    System operation

    Normal operation

    During normal operation the total live steam flow

    and the total hot reheat steam flow are sent to

    Steam pressure

  • 8/18/2019 CAN Training Boiler

    143/207

    turbine. If the turbine is not able to take the total

    steam flow, HP bypass and LP bypass take the

    remaining steam flow up to 70% MCR. In this

    case the load capability is restricted to approx.

    70% MCR.

    Fixed-pressure operation in the HP system

    combined with sliding-pressure operation in the

    LP system is the usual operation mode within the

    whole range of load. Bypass operation at 70%

    MCR load requires 100% hot reheat pressure.Training CAN Seite 143 Safety devices

    System operation

    Normal operation

     At ignition the HP bypass control valve opens to a

    given start-up minimum position

    Superheated steam pressure control

  • 8/18/2019 CAN Training Boiler

    144/207

    The first part of the pressure rise takes place insliding pressure mode with this HP bypass position

    Then HP bypass is switched to pressure control

    mode. The pressure setpoint is increased infunction of steam flow and pressure until required

    steam turbine coupling pressure is reached

    further pressure increase up to normal operationpressure after steam turbine has taken over all the

    steam

    Training CAN Seite 144

    System operation

    Normal operation

     After ignition the LP bypass opens to a given start-

    up maximum position

    reheated steam pressure control

  • 8/18/2019 CAN Training Boiler

    145/207

    the HRH pressure is rising in sliding pressuremode up to the required turbine coupling pressure

     After that the start-up maximum position limit is

    eliminated. The LP bypass is switched to pressurecontrol mode, setpoint being the required turbine

    coupling pressure value

    set-point is set somewhat above the operatingpressure. Thus, the LP bypass is kept close during

    the further turbine load operation.

    Training CAN Seite 145

    System operation

    Normal operation

    life steam temperature is controlled by SH spray

    attemperators 2.1 / 2.2. A constant temperature

    i id d i th l d f 50 100 % GCC

    Steam temperature

  • 8/18/2019 CAN Training Boiler

    146/207

    is provided in the load range of 50-100 % GCC.

    The task of the spray attemperators 1.1/ 1.2 is to

    keep the control valve position of the spray

    attemperators 2.1 / 2.2 within a well suited range.

    hot reheat steam temperature is controlled by

    RH spray attemperators. A constant temperature

    is provided in the load range of 50-100 % GCC.

    Below this load range, usually the hot reheat

    steam temperature is lower and not yet

    controlled, the spray control valves are closed.Training CAN Seite 146

    System operation

    Normal operation

      The main steam temperature downstream of SH 3is controlled and adjusted to setpoint by means of 

    4 desuperheaters ( two downstream of SH 3 and

    Superheated steam temperature control

  • 8/18/2019 CAN Training Boiler

    147/207

    4 desuperheaters ( two downstream of SH 3 and

    two downstream of SH 2)

    maximum setpoint is 543 °C

    or is set manually

    or is set by unit master controller ( lower setpoint

    during startup of boiler)

    The spray mass flow for the four injections is

    extracted by the feedwater control valvesTraining CAN Seite 147

    System operation

    Normal operation

      The reheater steam temperature downstream of 

    RH2 is controlled and adjusted to setpoint by

    means of 2 attemperators (downstream of RH 1)

    reheated steam temperature control

  • 8/18/2019 CAN Training Boiler

    148/207

    means of 2 attemperators (downstream of RH 1)

    maximum setpoint is 542 °C

    or is set manuallyor is set by unit master controller ( lower setpoint

    during startup of boiler)

    The spray mass flow for the two injections is

    extracted by the feedwater control valves

    Training CAN Seite 148

    System operation

    Normal operation

    The air flow must be regulated in accordance

    with the fuel flow

    If th f l fl i t ll d ll h i

    Control O2

  • 8/18/2019 CAN Training Boiler

    149/207

    If the fuel flow is controlled manually, changes in

    the fuel flow carried out too quickly are to be

    avoided.

    Training CAN Seite 149

    System operation

    Normal operation

    Control O2

    O2-content in flue gas downstream

    2nd passapprox values for

  • 8/18/2019 CAN Training Boiler

    150/207

    Training CAN Seite 150

    11,31

    3,44

    0

    2

    4

    6

    8

    10

    12

    0 20 40 60 80 100

    GCC Load [%]

       O

       2  -  c  o  n   t  e  n   t   d  r  y   [   V  o   l .  -   %   ]

    approx. values for

    initial adjustment

    System operation

    Normal operation

     Air distribution

    70,00

    80,00

    The diagram gives approx.

    values

    for the initial adjustment.

  • 8/18/2019 CAN Training Boiler

    151/207

    Training CAN Seite 151

    0,00

    10,00

    20,00

    30,00

    40,00

    50,00

    60,00

    40 50 60 70 80 90 100GCC [%]

      a   i  r  m  a

      s  s   f   l  o  w

       [   k  g   /  s   ]

    primary air

    upper secondary air

    burner air

    lower secondary air

    coal feeding air

    ash cooler fluidization

    sealing air, cooling air ingnitor, flamescanner, limestone feeding air

    ash loop seal fluidization

    System operation

    Normal operation

    Primary air control

    Primary air flow setpoint is formed of 

    an function of unit load demand of unit master 

  • 8/18/2019 CAN Training Boiler

    152/207

    Training CAN Seite 152

    controller and primary air flow (valid for bedtemperatures > 650°C)

    and an function of bed temperature and primary

    air flow (valid for bed temperatures< 650°C)

    there is a possibility to adjust primary air flowmanually

    approx. values for

    initial adjustment

    System operation

    Normal operation

    Steam air preheaters

    The task of steam air heater is

    to keep constant the air outlet temperature

  • 8/18/2019 CAN Training Boiler

    153/207

    Training CAN Seite 153

    to avoid the operation of the regenerative air preheater below the flue gas dew point

    System operation

    Normal operation

    During normal operation both ash coolers are in

    operation. The bottom ash discharge from the

    furnace is controlled automatically depending on

    Pressure and temperature in the furnace

  • 8/18/2019 CAN Training Boiler

    154/207

    furnace is controlled automatically depending on

    the pressure above nozzle grid. The bedpressure in the lower level is supposed to be

    between 80 and 90 mbar with 100 % BMCR.

    The horizontal L-valves are opened alternating.

    The bed temperature shall be

    approx. 840 - 860 °C.

    Training CAN Seite 154

    approx. values for

    initial adjustment

    System operation

    Normal operation

    Pressure in the furnace

    120

    130

    r   )approx. values for

    initial adjustment

  • 8/18/2019 CAN Training Boiler

    155/207

    Training CAN Seite 155

    80

    90

    100

    110

    0 10 20 30 40 50 60 70 80 90 100

    load BMCR (%)

      p  r  e  s  s  u  r

      e  a   b  o  v  e  g  r   i   d   (  m   b

      a  r

    setpoint 1

    setpoint 2

    setpoint 3

    setpoint 4

    Descr ash cooler 

    initial adjustment

    System operation

    Normal operation

    Grain size distribution of bed

    30

    Case 1 Case 2

    m

  • 8/18/2019 CAN Training Boiler

    156/207

    Training CAN Seite 156

    + 30

    + 20

    + 10

    0 20 40 60 80 100 mbar

    System operation

    Normal operation

    Tendency to a fine bed

    to be recognized by:

    Grain size distribution of bed

  • 8/18/2019 CAN Training Boiler

    157/207

    decreasing bed temperature increased bed pressures on the upper levels

    Measures

    reduce ash cooler cooling air flow (min. flow)

    feed coarse bed material

    Training CAN Seite 157

    System operationNormal operation

    Tendency to a coarse bed

    to be recognized by

    Grain size distribution of bed

  • 8/18/2019 CAN Training Boiler

    158/207

    increasing bed temperature low pressures on the upper levels

    Measures

    increase ash cooler air flow

    increase primary air portion

    Training CAN Seite 158

    System operationNormal operation

    Particle size distribution of solid inventory0.11.0(%)

    10.020.030.040 0

    solids

  • 8/18/2019 CAN Training Boiler

    159/207

    Training CAN Seite 159

    10 µm100 1000Grain size d

    40.0

    50.060.070.0

    80.0

    90.0

    99.0

    99.9

       R  e  s   i   d  u  e   R

    approx. values for

    initial adjustment

    System operationNormal operation

    Particle size distribution of lignite

    Acceptable particle size

    distribution:

     99,9 % < 6.0-9.0 mm

    0,1

    1

    10

    20%

    99,9

    99

    90

    80%

    0,1 0,2 0,5 1 2 5 20 50 100106

  • 8/18/2019 CAN Training Boiler

    160/207

    Training CAN Seite 160

    ,

     55 % < 1.0 mm

  • 8/18/2019 CAN Training Boiler

    161/207

    - the boiler load

    - the fouling of the heating surfaces

    (CO increase)- the increase of fluegas temperature

    The complete cycle is to be operated at leastonce per shift.

    Training CAN Seite 161

    System operationNormal operation

    Even if the control is off, the limestone feeding

    has to be carried out such that the admissible

    SO2 limit values are kept in every operating

    Limestone feeding

  • 8/18/2019 CAN Training Boiler

    162/207

    phase if possible.

    Training CAN Seite 162

    System operationNormal operation

    The task of the limestone control is to reduce the

    SO2 content in the flue gas to a predefined value

    control SO2 content

  • 8/18/2019 CAN Training Boiler

    163/207

    by dosing limestone

    To improve the dynamic response of the

    controlled system due to its inertia - from

    limestone dosing into boiler to SO2-

    measurement in the stack - the lignite flow is

    used as a feedforward signal

    Training CAN Seite 163

    CFB DesulfurizationChemical Reaction Basics

    1. Calcination of LimestoneCaCO3 => CaO + CO2for temperatures above ca. 750 °CEndothermic reaction DH = +178 kJ/mol

  • 8/18/2019 CAN Training Boiler

    164/207

    Training CAN Seite 164

    Endothermic reaction DH 178 kJ/mol

    2. Sulfur Dioxide Reaction

    S + O2 => SO2

    for temperatures above ca. 650 °CExothermic reaction, DH = - 297 kJ/mol

    3. Desulfurization Reaction

    CaO + 1/2 O2 + SO2 => CaSO4for temperatures between 750 °C and 900 °CExothermic Reaction DH = - 500 kJ/mol

    CFB Desulfurizationreaction inside particles

     macro pores

    sulfated lime

    unreacted

  • 8/18/2019 CAN Training Boiler

    165/207

    Training CAN Seite 165

    Calcination and Desulphurization Reaction inside Limestone Particles

    micro pores  lime

    - CO2

    CaCO3 CaO CaSO4

    + SO2 +1/2 O2

    CFB Boiler - SO2 Capture

      Achieved by limestone injection

    CaCO3  --> CaO + CO2Optimum temperature:

    CaO + SO2 + ½ O2 --> Ca SO4 850 °C

  • 8/18/2019 CAN Training Boiler

    166/207

    Training CAN Seite 166

    • Main parameter :

    Furnace temperature control

      - Limestone consumption  varies enormously with

      furnace temperature

    No low cost remedial measure to

    a poor furnace temperaturecontrol

    790 810 830 850 890870 910

    Temperature

    Ca/S

    Desulphurization Rate vsCFB Furnace Temperature

    6

    5

    a   t  e

  • 8/18/2019 CAN Training Boiler

    167/207

    Training CAN Seite 167

    4

    3

    2

    1

    0

    650 700 750 800 850 900 950 1000

    Temperature (°C)

       R  e   l  a   t   i  v  e

       S  o  r   b  e  n   t   F   l  o  w  r  a

    Main Factors of influence

    System operation

    CFB NOX Emissions

    Fuel Characteristics- Increase of NOx with fuel nitrogen content

    - Increase of NOx with fuel volatile matter content

  • 8/18/2019 CAN Training Boiler

    168/207

    Training CAN Seite 168

    Furnace Temperature- Decrease of NOx with low temperature in furnace

    ( approx. 850 °C )

    Excess Air - Decrease of NOx with low excess air level ( 20 % )

    Air Staging- Decrease of NOx with low primary air feeding

    Fuel / Air Mixing- Decrease of NOx with intense and homogeneous

    fuel / air mixing

    System operationshut down

    Two different cases

  • 8/18/2019 CAN Training Boiler

    169/207

    Shut-down with fast cooling down

    (repair standstill)

    Shut-down with pressure maintaining

    (hot standby standstill)

    Training CAN Seite 169

    System operationshut down

    load reduction to minimum load approx. 30%

    the change from turbine mode to HP/LP bypass

    First part

  • 8/18/2019 CAN Training Boiler

    170/207

    mode takes place before the steam temperature

    drops. During and after this change HP bypass

    and LP bypass keep the operating pressure

    values of life steam and of HRH steam.

    turn off of the coal feeders

    Training CAN Seite 170

    System operationCooling down with pressure maintaining

    To manage pressure maintaining without the risk

    of excessive SH wall temperatures rise, a

    i i b t

    general

  • 8/18/2019 CAN Training Boiler

    171/207

    compromise is necessary between

    some cooling down of the cyclone refractory

    lining on the one hand

    and

    maintaining hot the bed material on the other 

    hand

    Training CAN Seite 171

    System operationCooling down with pressure maintaining

     After the turn off of the coal feeders the followingactions have to be done:

    Primary air fan OFF. Lower secondary air 

    d l d

     Air fluegas system

  • 8/18/2019 CAN Training Boiler

    172/207

    dampers closed

    The secondary air fan and the induced draught

    fan remain in operation for a period of several

    minutes. Some secondary air flow is adopted inorder to obtain sufficient cooling of the refractoy

    lining. At the same time the bed temperature in

    both FB ash coolers has to be reducedto < approx. 400 °C

    Then all fans OFFTraining CAN Seite 172

    System operationCooling down with pressure maintaining

    The feedwater supply remains in operation,adjusting the drum level to a constant value. The

    feedwater is still sent through the FB-ash cooler.

    feedwater 

  • 8/18/2019 CAN Training Boiler

    173/207

    Shut-down of the feedwater supply not before the

    response of the enabling criteria

    maximum outside tube wall temperature of SH 1/1

      < approx. 400°C for > 15 minutes

    Some adjusting of the drum level before shut-downof the feedwater supply may be advantageous for 

    the following standstill and the restartTraining CAN Seite 173

    System operationCooling down with pressure maintaining

    HP bypass and LP bypass are switched to

    pressure limiting control mode. Their task is

    li iti f th lif t d HRH

    HP and LP bypass

  • 8/18/2019 CAN Training Boiler

    174/207

    limiting of the life steam pressure and HRH

    pressure to values close below the response

    pressure values of the safety devices

    Training CAN Seite 174

    System operationCooling down with pressure maintaining

     After shut-down of the induced draught fan, theSH standstill cooling valve has to do a

    temperature limiting control task. That means: In

    case of maximum outside tube wall temperature

    SH standstill cooling valve

  • 8/18/2019 CAN Training Boiler

    175/207

    case of maximum outside tube wall temperatureof SH 1/1 > approx. 430°C,

    it is opened to cooling position

    Thus, a small steam flow of approx. 2,5 % BMCR

    is produced and released via SH standstill

    cooling valve to the ambient air, which ensures asufficient longterm cooling of the critical SH 1

    heating surfaceTraining CAN Seite 175

    System operationCooling down with pressure maintaining

    The SH relief valve is closed again by the criterion

    SH standstill cooling valve

  • 8/18/2019 CAN Training Boiler

    176/207

    maximum outside tube wall temperature

    of SH 1/1 < approx. 400°C

    Training CAN Seite 176

    System operationfast cooling down

    The task is to cool the steam generator down as

    f t ibl i h kf

    general

  • 8/18/2019 CAN Training Boiler

    177/207

    fast as possible in a shockfree manner.

     After the turn off of the coal feeders the following

    actions have to be done

    Training CAN Seite 177

    System operationfast cooling down

     Air fluegas system

     All fans remain in operation.

    The cooling is practised with small air flow rates

    of approximately 30 50 % of the GGC secondary

  • 8/18/2019 CAN Training Boiler

    178/207

    Training CAN Seite 178

    of approximately 30-50 % of the GGC secondaryair flow.

    This cooling operation mode is continued untilthe bed temperature has dropped to the required

    value.

    System operationfast cooling down

    feedwater 

    The feedwater supply remains in operation,adjusting the drum level to a constant value.

    The feedwater ist still sent through the

    ash cooler

  • 8/18/2019 CAN Training Boiler

    179/207

    Training CAN Seite 179

    ash cooler.

    Shut-down of the feedwater supply not before

    the response of the enabling criteria :

    maximum outside tube wall temperature

    of SH 1/1 < approx. 400°C for > 15 minutes

    The cooling down process may possibly besupported by continuing the feedwater supply for 

    some time

    System operationfast cooling down

    HP and LP bypass

    Cooling down of the water-steam system by well-

    directed pressure reduction down to depressurized

    state

  • 8/18/2019 CAN Training Boiler

    180/207

    Training CAN Seite 180

    state The operator has to open slowly HP bypass and

    LP bypass to position values, that ensure to get a

    rate of pressure change within the safe range.

    In case of condenser being out of service the

    pressure can be reduced manual via RH start-up

    standby control valve.

    System operationblack out

    general

    In case of a failure of the main power supply, asafe state of the plant must be achieved.

    Besides an emergency shutdown of the firing it ist th fl id t d i th

  • 8/18/2019 CAN Training Boiler

    181/207

    Training CAN Seite 181

    Besides an emergency shutdown of the firing it isnecessary to use the fluid stored in the

    HP system for well-directed long-term cooling of 

    endangered heating surfaces (support tubes at

    the transition cyclone 2nd pass).

     Any other loss of stored HP fluid is to be

    prevented.

    System operationblack out

    Safe state water steam system

    Final control element Safe state

    Drum emergency blow down control

    valve

    Closed

  • 8/18/2019 CAN Training Boiler

    182/207

    Training CAN Seite 182

    valveDrum emergency blow down gate valve Closed

    Demine drum gate valve Closed

    SH standstill cooling valve controlledcooling position

    Gate valve upstream SH standstill

    cooling valve

    Open

    HP bypass control valve Closed

    System operationblack out

    First measures

    If the failure of the main power supply cannot be

    eliminated within approx 15 minutesth f ll i l t ti ti h t

  • 8/18/2019 CAN Training Boiler

    183/207

    Training CAN Seite 183

    eliminated within approx. 15 minutes,the following manual protection actions have to

    be carried out

    System operationblack out

    measures

    Final control element action target

    swirl dampers of induceddraught fans,

    swirl dampers of secondary air fans

    open upto 100%

    cooling by natural draught

  • 8/18/2019 CAN Training Boiler

    184/207

    Training CAN Seite 184

    y

    upper secondary air dampers,

    oil burner air dampers

    open upto 100%

    cooling by natural draught

    manual shut-off valve01HAC10AA403Hin the economiser-

    evaporator short circuitline

    open The water contained in theeconomiser (approx. 29 t) isdrained into the evaporator.

    Thus this water can be usedfor emergency coolingpurpose of the endangeredheating surfaces.

    System operationblack out

    Second measures

    If the failure of the main power supply cannot be

    eliminated within approx 45 minutes

  • 8/18/2019 CAN Training Boiler

    185/207

    Training CAN Seite 185

    eliminated within approx. 45 minutes,

    the following manual protection actions can be

    done for better cooling :

    System operationblack out

    measures

    Final control element action target

    cover of manhole,

    arranged betweenf d l

    open

    withti

    improved cooling

    by natural draught

  • 8/18/2019 CAN Training Boiler

    186/207

    Training CAN Seite 186

    arranged betweenfurnace and cyclone

    withcaution

    by natural draught

    upper secondary air 

    dampers

    reduce

    opening

    keeping sub-

    atmosphericpressure in thefurnace

    Failuresleakages

    Leakage boiler pressure parts

    tube leaks or tube ruptures will ultimately lead toa boiler shut down

     it is up to the operator or shift charge engineer 

    to decide when

  • 8/18/2019 CAN Training Boiler

    187/207

    Training CAN Seite 187

    to decide when

    Generally boiler operation may continue for 

    some time if a tube leak is negligible small, easyto locate and easy to watch

    Failuresleakages

    Leakage evaporator 

    take the firing system out of service

    separate the boiler from the common main steam

    line

    stop limestone dosing

  • 8/18/2019 CAN Training Boiler

    188/207

    Training CAN Seite 188

    stop limestone dosing

    discharge bed material

    reduction of the main steam pressure observingthe admissible gradient

    maintain water level in the drum

    by make-up feeding

    Failuresleakages

    Leakage evaporator 

    cooling of the boiler by means of the fans -observing the admissible temperature gradient in

    the cyclone area

    open overfire and oilburner air dampers to 50%

  • 8/18/2019 CAN Training Boiler

    189/207

    Training CAN Seite 189

    p pand set the minimum primary air flow

    at a bed temperature of approx. 400°C

    the make-up feeding can be stopped

    Failuresleakages

    Leakage evaporator 

    unpressurize boiler with attention toadmissible gradient

    further cooling of the boiler by means of the

    primary air fan until inspection temperature has

  • 8/18/2019 CAN Training Boiler

    190/207

    Training CAN Seite 190

    p y p pbeen reached

    draining of evaporator or superheater 

    Failuresleakages

    Leakage economizer 

    Small leaks are not very easy to detect (sounddetectors may help) and deviation of feedwater to

    steam ratio or decreasing flue gas temperatures

    after eco can only be noticed if leakage hasid bl i d

  • 8/18/2019 CAN Training Boiler

    191/207

    Training CAN Seite 191

    y gconsiderably increased.

    The unit should be shut down in the normal way

    and feeding should be stopped immediately after "fire out".

    Failuresleakages

    Leakage superheater, reheater 

    These leakages may easily be detected bysound detectors.

    Decision should be a normal shut down as the

    leakage can be neither located or judged

  • 8/18/2019 CAN Training Boiler

    192/207

    Training CAN Seite 192

    g j g

    Feeding can continue after fire out to equally

    decrease temperature in the boiler's water parts.

    FailuresHP bypass

    HP bypass

    If the HP bypass doesn't open adequatelyalthough opening is required,

    sufficient cooling of the RH heating surfaces is

    impossible.

  • 8/18/2019 CAN Training Boiler

    193/207

    Training CAN Seite 193

    In addition, sufficient cooling of the SH heating

    surfaces would also be impossible

    as long as the pressure is below

    the response pressure of the HP safety devices

    FailuresHP bypass

    HP bypass

    In case of high bed temperatures (above approx.600 °C), an emergency firing shutdown must be

    initiated within approx. 30 s to avoid damage of 

    the platen heating surfaces (SH2, RH2) in thefurnace

  • 8/18/2019 CAN Training Boiler

    194/207

    Training CAN Seite 194

    furnace.

    In case of bed temperatures below approx.

    600 °C, the operator shall reduce firing rate

    to minimum.

    If he does not succeed in opening the HP bypass,

    he normally has to initiate a firing shut-down after 

    a maximum of 10 minutes.

    FailuresLP bypass

    after turbine trip

    In case of turbine trip the load capability of thesteam generator is restricted to

    approx. 55 % BMCR

    The HP bypass ensures the cooling of theSH h ti f b l i t i t

  • 8/18/2019 CAN Training Boiler

    195/207

    Training CAN Seite 195

    SH heating surfaces by releasing steam into

    the CRH system

    If the LP bypass does not open (e. g. because of 

    condenser malfunction), the LP start-up standby

    control valve is automatically opened, doing

    some cooling releasing about 30% steam to

    atmosphere

    FailuresLP bypass

    after turbine trip

    The other steam is stored in the RH system, untilthe pressure is high enough to initiate opening of 

    HRH safety valves.

    Then the HRH safety valves ensure a sufficient

  • 8/18/2019 CAN Training Boiler

    196/207

    Training CAN Seite 196

    longterm cooling of the the RH heating surfaces.

    FailuresLP bypass

    during start up

    In case of malfunction of both LP bypass and theLP start-up standby control valve,

    the RH pressure increase up to the HRH safety

    valve response pressure value would take toomuch time because of small start-up steam

  • 8/18/2019 CAN Training Boiler

    197/207

    Training CAN Seite 197

    much time because of small start-up steam

    production.

    In case of high bed temperatures (above approx.600 °C), an emergency firing shutdown must be

    initiated within approx. 60 s to avoid damage of 

    the platen reheat heating surfaces (RH2) in thefurnace during this period of HRH pressure

    increase.

    FailuresLP bypass

    during start up

    In case of bed temperatures below approx.600 °C, the operator shall reduce firing rate to

    minimum.

    If he does not succeed in opening the LP bypassfinally he shall initiate a firing shut down after a

  • 8/18/2019 CAN Training Boiler

    198/207

    Training CAN Seite 198

    finally, he shall initiate a firing shut-down after a

    maximum of 10 minutes.

    FailuresLP bypass

    during start up

     After a malfunction of the LP bypass only (e. g.because of condenser trip) the LP start-up

    standby control valve is automatically opened to

    100 % to ensure the cooling of the RH2 As soon as the LP bypass is ready for operation

  • 8/18/2019 CAN Training Boiler

    199/207

    Training CAN Seite 199

     As soon as the LP bypass is ready for operation

    again, the LP start-up standby control valve has

    to be closed manually If the operator does not succeed in opening the

    LP bypass finally, he normally has to initiate a

    firing shut-down after a short while

    Failuresfiring permit signal

    emergency fire shut down

  • 8/18/2019 CAN Training Boiler

    200/207

    Training CAN Seite 200

    Failuresfiring permit signal

    emergency fire shut down

    There are 4 possibilities to fulfill reheater release: Bed temperature < 570 °C (7 of 10)

    During start-up firing the primary air flow

    between 10 and 30 %

  • 8/18/2019 CAN Training Boiler

    201/207

    Training CAN Seite 201

    The turbine is in operation and the outlet

    temperature of the reheater is < 562 °C

    The HP-bypass is opened > 15 % and LP-

    bypass is opened > 15 % or reheater start-up

    valve is opened > 30 % and temperature of the

    reheater is < 562 °C

    approx. values for

    initial adjustment

    Failuresash cooler 

    temperatures

    ash temperature 1st chamber > 500 °C

    shut off L-valve and lock hoppering sequence

    until temperature < 400 °C

  • 8/18/2019 CAN Training Boiler

    202/207

    Training CAN Seite 202

    ash cooler overflow > 200°C

    shut off L-valve and rotary seal

    until temperature < 150 °C

    approx. values for

    initial adjustment

    Failuresash cooler 

    operation with one ash cooler 

      close L-valves

      fluidization of the ash cooler has to be

  • 8/18/2019 CAN Training Boiler

    203/207

    Training CAN Seite 203

      maintained as sealing against the flue gas

    atmosphere from the furnace

      In case of worst coal a boiler load reduction

    can be necessary

    Failuresash cooler 

    cooling circuit of ash cooler 

    Detection of leaks

    pressure increase in the ash cooler chamber  temperature decrease in the ash cooler chamber

  • 8/18/2019 CAN Training Boiler

    204/207

    Training CAN Seite 204

    temperature decrease in the ash cooler chamber 

    increased moisture content of ash which may

    lead to an increased plugging tendency

    Failuresash cooler 

    cooling circuit of ash cooler 

    measures

    shut off and emptying of the L-valves

    shut off of the cooling water flow through

    th h l

  • 8/18/2019 CAN Training Boiler

    205/207

    Training CAN Seite 205

    the ash cooler 

    maximum fluidization of the ash cooler has to bemaintained

    emptying the ash cooler via lock hopper system

    as fast as possible

    Overview symbols

    AND gate

    OR gate

    BISTABLE

    PULSE t t

    If any of all the inputs to an AND gate are logic 1,

    then the output is logic 1 otherwise the output is

    logic 0.If any one or more inputs to an OR gate is logic 1

    then the output is logic 1, otherwise the output is

    logic 0.

    If S=1, while R=O then Q=1, Q’ =O, and flip flop is

    in SETstate.

    If R=1. while S=O then Q=O.Q’ =1, and flip flop isin RESET state.

    Output goes to logic 1 immediately when input

    goes to logic 1 Output remains at logic 1 for the

    &

    >=1

    R S

  • 8/18/2019 CAN Training Boiler

    206/207

    Training CAN Seite 207

    PULSE output

    DELAYED ON time

    DELAYED OFF time

    NOT gate

    goes to logic 1. Output remains at logic 1 for the

    specified time and then returns to logic 0

    regardless of state of input in.

    If input goes to logic 1, then after a timedelay of specified duration, output changes

    to logic 1.Output goes to logic 0 as soon as

    input returns to logic 0.

    Output goes to logic 1 immediately when

    input goes to logic 1.

    When input returns to logic 0, outputremains at logic 1.

    Lo