can training boiler
TRANSCRIPT
-
8/18/2019 CAN Training Boiler
1/207
February 2003February 2003
Training
ÇAN THERMAL POWER PLANT
-
8/18/2019 CAN Training Boiler
2/207
-
8/18/2019 CAN Training Boiler
3/207
-
8/18/2019 CAN Training Boiler
4/207
Steam Generator
with Circulating FBC
Untertitel (Arial 22 bis 24)
Training CAN Seite 4
Customer TEAS
Plant location CAN / Turkey
Firing capacity 358,6 MW
Steam data SH RH
485 t/h 437 t/h
175 bar 38 bar
543 °C 542 °C
Fuel turkish lignite
Year of Commissioning 2003
-
8/18/2019 CAN Training Boiler
5/207
Steam Generator
Cross section furnace centre
Training CAN Seite 5
-
8/18/2019 CAN Training Boiler
6/207
Steam Generator
Circulating Fluidized Bed
Training CAN Seite 6
furnace
nozzle grid
primary air
flue gas
cyclone
-
8/18/2019 CAN Training Boiler
7/207
General description
process - fluidization
Training CAN Seite 7
Combustion air is mainly divided in
primary air - air through nozzle grid
secondary air - air through air nozzles above grid
bed material consists of approx. 98 % ash or sand
nozzle grid causes for a homogenous fluidization of
bed material
-
8/18/2019 CAN Training Boiler
8/207
General description
process - fluidization
Training CAN Seite 8
primary air transports bed material in direction of
ceiling
coarse bed material falls down along sidewalls
other material is separated in cyclones
separated material returns to furnace through loop
seals with fluidization air
flue gas leaves cyclones through exit tubes to 2nd
pass
fly ash is separated in electrostatic precipitator
-
8/18/2019 CAN Training Boiler
9/207
General description
process flow
Process flow schematic
Training CAN Seite 9
-
8/18/2019 CAN Training Boiler
10/207
General description
process - fuel supply
Training CAN Seite 10
crushed raw lignite is stored in four coal bunkers
coal is discharged through coal feeders to 8 feedingpoints of the four double ash loop seals for a
uniform disribution of the fuel across nozzle grid
mixing with hot ash in loop seals predries coal
already
Coal feeding system
-
8/18/2019 CAN Training Boiler
11/207
General description
process - limestone supply
Training CAN Seite 11
Limestone powder is stored in two limestone
bunkers
limestone is discharged through fluidizing
conveyors to the 8 coal drag link chain conveyors
Limestone system
-
8/18/2019 CAN Training Boiler
12/207
General description
process - bed material supply
Training CAN Seite 12
for first start up of boiler or after revision, furnace is
filled up with sand or available bed material
bed material is discharged through a rotary feeder
and a drag link chain conveyor to furnace
for a uniform distribution of bed material,there shallbe a minimum primary air flow during feeding
-
8/18/2019 CAN Training Boiler
13/207
General description
process - bed material discharge
Training CAN Seite 13
bed ash is discharged via four openings in bottom
of furnace
ash flow from furnace to the two ash coolers are
controlled with L-valves
bed ash is fluidized in ash cooler and cooled downthrough feeding water and condensate
cooled down bed ash can conveyed to bed materialsilo
L-valve
Ash cooler
-
8/18/2019 CAN Training Boiler
14/207
General description
particle size characteristics
Training CAN Seite 14
Particle size distribution mainly depends on :
particle size of the supplied coal
particle size of the limestone
particle size of the externally supplied bed material separation characteristics of the cyclones
abrasion characteristics of ash
Grain size distr
-
8/18/2019 CAN Training Boiler
15/207
General description
particle size characteristics
Training CAN Seite 15
Expected particle size distribution
m a te r ia l m a x . g ra in s iz e (m m ) m a in p a r t ic le (m m )
C o a l < 2 0 4 -5
L im e s to n e < 1 0 ,1 -0 ,1 5B e d a s h < 1 0 ,2 -0 ,5
approx. values for
initial adjustment
-
8/18/2019 CAN Training Boiler
16/207
General description
Steam generator data
Steam dataSteam data
Steam capacity SH / RH 457 / 407 t/h
Pressure SH / RH 190 / 39.8 bar
Temperature SH / RH 543 / 542 °C
Feedwater temperature 250 °C
Waste gas temperature 138 °C
Training CAN Seite 16
-
8/18/2019 CAN Training Boiler
17/207
Steam generator data
H-p diagram
Training CAN Seite 17
Fuel Data:Fuel Data:
Fuel: Brown Coal
LCV: 10.890 MJ/kg
Ash: 32.0 %
Water: 22.0 %
Eco
Evaporator
SH 1/1SH 1/2SH 1/3INJ-1
SH 2-PL
INJ-2SH 3
..
.
....
..
..
.
RH 1RH-INJ
RH 2-PL
.
..
.
Pressure
0 50 100 150 200 250 300 bar 400
E n t h a l p y
4,000
3,600
3,200
2,800
2,400
2,000
1,600
1,200
800
400
kJ/kg
100 °C
150 °C
200 °C
250 °C
300 °C
350 °C
375 °C
40 0 ° C
45 0 ° C
5 0 0 ° C
5 5 0 ° C
600 °C
650 °C
7 00 °C
750 °C
-
8/18/2019 CAN Training Boiler
18/207
General description
Steam generator data
Training CAN Seite 18
Fuel dataFuel data
Brown coal
Calorific value (NCV) 10.9 MJ/kg Ash 32 %
Moisture 22%
Sulphur 4.0 % (max. 7.0 %) Fuel capacity 128 t/h
Desulphurization 95 %
SO2 Emission 1,000 mg/m3
s.t.p. (5 % O2) Fuel ash composition SiO2 50 %, Al2O3 30 %,
FeO3 15 %, other const 5 %
-
8/18/2019 CAN Training Boiler
19/207
Flue Gas Temperature
Versus Load Nozzle Grid/Furnace
Training CAN Seite 19
1000
900
800
700
600
500
400
300
200
100
0
0 40 60 80 100
Steam output (%)
F l u e g a s t e m
p e r a t u r e ( ° C )
20
Furnace
Nozzle Grid
Fuel DataFuel Data::
Fuel: Brown Coal
LCV: 10.890 MJ/kg
Ash: 32.0 %
Water: 22.0 %
approx. values for
initial adjustment
-
8/18/2019 CAN Training Boiler
20/207
Description of systems
Water / steam system
components
Training CAN Seite 20
feedwater supply
feedwater preheating
evaporator
superheater reheater
high pressure heatersash coolers
economiser
heating surfaces
drum
-
8/18/2019 CAN Training Boiler
21/207
Description of systems
Natural circulation boiler
Training CAN Seite 21
Feedwater control
Level
Feedwater
Steam flow m•
EvaEco
T
-
8/18/2019 CAN Training Boiler
22/207
Description of systems
Water steam scheme
Training CAN Seite 22
-
8/18/2019 CAN Training Boiler
23/207
Description of systems
Feedwater supply
2 controlled feed pumps
for controlling of sufficient differential pressure
between inlet and outlet of the
feedwater control station
2 feedwater control valves
one start up feed control valve (up to 30 % )
one full load feed control valve
for controlling of required feedwater flow
Training CAN Seite 23
-
8/18/2019 CAN Training Boiler
24/207
Description of systems
feedwater supply
P&I feedwater control station
Training CAN Seite 24
-
8/18/2019 CAN Training Boiler
25/207
Description of systems
Feedwater preheating
HP heater 6 and 7
feeded from bleeding or CRH steam
cooling of HP ash coolers with feedwater
normal boiler operation:
all feedwater is sent through ash coolers
if one ash cooler out of operation,
bypass available
economiser
arranged in second pass flue gas
last heating surface upstream flue gas air heater
Training CAN Seite 25
-
8/18/2019 CAN Training Boiler
26/207
Description of systems
Ash cooler
Training CAN Seite 26
-
8/18/2019 CAN Training Boiler
27/207
Description of systems
evaporator
Wall heating surfaces of the furnace
Training CAN Seite 27
-
8/18/2019 CAN Training Boiler
28/207
Description of systems
superheater
Two parallel steam lines
SH 1/1 supporting tubes of the second pass
SH 1/2 walls of second pass
SH 1/3 convective heating surface in second pass spray attemperator 1
SH 2 platen heating surface in furnace
spray attemperator 2
SH 3 convective heating surface in second pass
Training CAN Seite 28
D i i f
-
8/18/2019 CAN Training Boiler
29/207
Description of systems
P&I attemperator
Training CAN Seite 29
D i ti f t
-
8/18/2019 CAN Training Boiler
30/207
Description of systems
Live steam piping
One SH safety valve (≈30 % MCR flow)
one SH standstill cooling valve (≈10% GCC flow)
one HP bypass control valve (70 % MCR flow)
with safety function
two HP turbine valves (2 x 50 % MCR flow)
Training CAN Seite 30
D i ti f t
-
8/18/2019 CAN Training Boiler
31/207
Description of systems
P&I live steam
Training CAN Seite 31
D i ti f t
-
8/18/2019 CAN Training Boiler
32/207
Description of systems
HP safety devices
Safety device MCRflow
MCR operatingpressure
One HP safety valve atdrum
70 % +17 bar
One HP bypass controlvalve at SH 3 outlet
70 % + 10 bar
One HP safety valve atSH 3 outlet
Approx.30 %
+ 17 bar
Training CAN Seite 32
LP safety devices
Pressure control
Description of systems
-
8/18/2019 CAN Training Boiler
33/207
Description of systems
reheater
Two parallel steam lines
RH 1 convective heating surface in second pass
spray attemperator 1
RH 2 platen heating surface in furnace
Training CAN Seite 33
Description of systems
-
8/18/2019 CAN Training Boiler
34/207
Description of systems
Hot reheat steam piping
One LP start up standby control valve
( 30 % GCC)
one RH safety valve (MCR flow)
one LP bypass control valve
( > 315 t/h at 39.2 bar)
two LP turbine interceptor valves
(2 x 50 % MCR flow)
Training CAN Seite 34
Description of systems
-
8/18/2019 CAN Training Boiler
35/207
Description of systems
LP safety device
Safety device MCR
flow
MCR operating
pressure
One HP safety
valve at drum
70 % +17 bar
Training CAN Seite 35 Pressure control
Description of systems
-
8/18/2019 CAN Training Boiler
36/207
Description of systems
HP auxiliary systems
Filling line
Desalting system
start up drain system ( drum, flash tank,
boiler condensate tank )
drain system of heating surfaces
venting system
Training CAN Seite 36
Description of systems
-
8/18/2019 CAN Training Boiler
37/207
Description of systems
P&I SH drain station
Training CAN Seite 37
Description of systems
-
8/18/2019 CAN Training Boiler
38/207
Description of systems
air fluegas system
components
Training CAN Seite 38
2 secondary air (SA) fans with vane guide
function: supply of the CFB system withsecondary air
capacity: 2 x 70%
2 primary air (PA) fans with vane guide
function: supply of the CFB system with
primary air
capacity: 2 x 70%
Description of systems
-
8/18/2019 CAN Training Boiler
39/207
Description of systems
P&I PA / SA fan
Training CAN Seite 39
Description of systems
-
8/18/2019 CAN Training Boiler
40/207
Description of systems
air fluegas system
components
Training CAN Seite 40
4 steam air heaters (SAHs)
function: heating up the combustion air for start up and to prevent flue gas
temperature falling below dew point
2 regenerative air heaters (RAH)
function: heating up combustion air
Description of systems
-
8/18/2019 CAN Training Boiler
41/207
Description of systems
air fluegas system
components
Training CAN Seite 41
3 fluidizing air fans
function: fluidization of loop seals,supply of flame scanners, ignitors
and oil lances with cooling and
ignition air capacity: 3 x 50%
Description of systems
-
8/18/2019 CAN Training Boiler
42/207
Description of systems
air fluegas system
components
Training CAN Seite 42
2 ash coolers with immersed cooling surfaces
and 2 ash cooler fansfunction: cooling of the extracted bed ash from
850°C to 60°-140°C
capacity: 2 x 100%
Description of systems
-
8/18/2019 CAN Training Boiler
43/207
p y
air fluegas system
components
Training CAN Seite 43
2 electrostatic precipitators (ESP)
function: cleaning flue gas from ash particles capacity: 2 x 70%
2 induced draught (ID) fans with vane guide
function: leading flue gas to chimney
control flue gas pressure at cyclone
outlet
capacity: 2 x 70%
Description of systems
-
8/18/2019 CAN Training Boiler
44/207
p y
start-up burner
Use of start up burner
Training CAN Seite 44
start up burners are used for heating up of the
bed material in the furnace until the releasetemperature for coal feeding is reached
HFO shall be used with an combustion air temperature of at least 120 °C
Description of systems
-
8/18/2019 CAN Training Boiler
45/207
p y
start-up burner
components
Training CAN Seite 45
number of burners 8 (3 front wall, 3 rear wall,
1 left and 1 right side wall)
number of levels 1
fuel heavy oil N° 6/ light oil N° 2
type of burner jet burner
atomising system pressure atomisation
fitting position 30 °
Description of systems
-
8/18/2019 CAN Training Boiler
46/207
y
start-up burner
Releases
Training CAN Seite 46
LFO ignition permit time is running
(boiler is purged)or
>7 bed temperature >570° C
or
start up burner is on
HFO see LFOand
temperature HFO > 90°C
Description of systems
-
8/18/2019 CAN Training Boiler
47/207
start-up burner
Technical data light oil
Training CAN Seite 47
oil flow max. 1656 kg/h
oil flow min. 828 kg/h
oil pressure max. 75 bar
oil pressure min. 20 bar
control range 1 : 2
Description of systems
-
8/18/2019 CAN Training Boiler
48/207
start-up burner
Technical data heavy oil
Training CAN Seite 48
oil flow max. 1728 kg/h
oil flow min. 865 kg/h
oil pressure max. 70 bar
oil pressure min. 15 bar
control range 1 : 2
Description of systems
-
8/18/2019 CAN Training Boiler
49/207
start-up burner
operation
Training CAN Seite 49
Either light oil operation or heavy oil operation
can be preselected.Then oil supply must be started.
The start up burner can be started or stopped
manually from local panel in the field or controlroom.
Description of systems
-
8/18/2019 CAN Training Boiler
50/207
start-up burner
operation
Training CAN Seite 50
If oil lance is empty and heavy oil operation is
preselected, oil lance will be prewarmed for 90sec with steam
Signal "lance prewarmed" is displayed for 600
sec, if steam cleaning valves have been open for at least 80 sec
Description of systems
-
8/18/2019 CAN Training Boiler
51/207
start-up burner
operation
Training CAN Seite 51
If oil lance is empty, safety time is running for 12
secIf oil lance is not empty ( filled lance ) safety time
is running for 5 sec
Description of systems
t t b
-
8/18/2019 CAN Training Boiler
52/207
start-up burner
operation
Training CAN Seite 52
Start up burner shuts down automatically with FG
boiler shutdown or if ignition trial failed Scavenging is done with steam valve opened
and ignition in operation for 15 sec, then 5 min
without ignition.
Description of systems
t t b
-
8/18/2019 CAN Training Boiler
53/207
start-up burner
Training CAN Seite 53
impeller
oil lance
ignitor
flame scanner
core air
Description of systems
t t b
-
8/18/2019 CAN Training Boiler
54/207
start up burner
P&I start up burner
Training CAN Seite 54
Description of systems
start up burner
-
8/18/2019 CAN Training Boiler
55/207
start up burner
burner station
Training CAN Seite 55
Description of systems
bed lances
-
8/18/2019 CAN Training Boiler
56/207
bed lances
Use of bed lances
Training CAN Seite 56
ignition of bed lances possible with at least
500° C / 550 °C bed temperature
bed lances are used for heating up of the bed
material in the furnace until the releasetemperature for coal feeding is reached
bed lances are used for maintaining a constant
bed material temperature at low loads
Description of systems
bed lances
-
8/18/2019 CAN Training Boiler
57/207
bed lances
components
Training CAN Seite 57
number of burners 8 (2 front wall, 2 rear wall,
2 left and 2 right side wall)
number of levels 1
fuel heavy oil N° 6/ light oil N° 2
atomising system pressure atomisation
max. load 15 % of boiler load
fitting position 30 °
Description of systems
bed lances
-
8/18/2019 CAN Training Boiler
58/207
bed lances
Technical data light oil
Training CAN Seite 58
oil flow max. 612 kg/h
oil flow min. 300 kg/h
oil pressure max. 72 bar
oil pressure min. 17 bar
control range 1 : 2
Description of systems
bed lances
-
8/18/2019 CAN Training Boiler
59/207
bed lances
Technical data heavy oil
Training CAN Seite 59
oil flow max. 648 kg/h
oil flow min. 320 kg/h
oil pressure max. 75 bar
oil pressure min. 20 bar
control range 1 : 2
Description of systems
bed lances
-
8/18/2019 CAN Training Boiler
60/207
bed lances
Releases
Training CAN Seite 60
LFO start up burner in operationand
>7 bed temperature >500° Cor >7 bed temperature >570° C
HFO start up burner in operation
and>7 bed temperature >550° Cand
temperature HFO > 90°C
or >7 bed temperature >570° Cand
temperature HFO > 90°C
approx. values for
initial adjustment
Description of systems
start-up burner / bed lances
-
8/18/2019 CAN Training Boiler
61/207
start up burner / bed lances
Training CAN Seite 61
Description of systems
ash cooler
-
8/18/2019 CAN Training Boiler
62/207
ash cooler
components
Training CAN Seite 62
The bed ash discharge system extracts the bed
ash from the furnace automatically depending
on the pressure above primary air nozzle grid
The bed ash system is equipped with 4
horizontal L-valves , 2 to each ash cooler.
general
Description of systems
ash cooler
-
8/18/2019 CAN Training Boiler
63/207
ash cooler
pressure above nozzle grid versus load
Training CAN Seite 63
80
90
100
110
120
130
0 10 20 30 40 50 60 70 80 90 100
load BMCR (%)
p r e s s u r e a
b o v e g r i d ( m b a r )
setpoint 1
setpoint 2
setpoint 3
setpoint 4
general
description
L-valve
approx. values for
initial adjustment
Description of systems
P&I ash cooler
-
8/18/2019 CAN Training Boiler
64/207
P&I ash cooler
Training CAN Seite 64
furnace
from
ash cooler fan
general
Description of systems
ash cooler
-
8/18/2019 CAN Training Boiler
65/207
overview
Training CAN Seite 65 general
Description of systems
ash cooler
-
8/18/2019 CAN Training Boiler
66/207
components
Training CAN Seite 66
The bottom ash discharge via horizontal L-valve
is done discontinuously. The horizontal L-valve
is set into a basic position. The opening
sequence and amplitude of the horizontal L-
valve is controlled by the reference value,
pressure above primary air nozzle grid. During
normal operation both horizontal L-valves are in
operation and work alternating for each
sequence. The horizontal L-valve is kept at itsbasic position when the reference value is
below a specified minimum set point.
Setpoint L-valves
Description of systems
L-valve
-
8/18/2019 CAN Training Boiler
67/207
ash control valve
Training CAN Seite 67 Setpoint L-valves
Plug
Valve Seat
Water Cooled
Valve Shaft
Hydraulic
Actuator
Assembly
Refractory Lined
Valve Bodygeneral
Description of systems
auxiliaries
-
8/18/2019 CAN Training Boiler
68/207
arrangement
Training CAN Seite 68
Description of systems
air preheater
-
8/18/2019 CAN Training Boiler
69/207
regenerative air preheater
Training CAN Seite 69
Air preheaters consist of a large number of heat
transfer plates arranged like the spokes of a
wheel, which slowly rotate at speeds lower than
one revolution per minute and up to approximately
five r/mm from a hot side exhaust environment
into a cold side intake. The cold intake air is thus
"preheated" improving efficiencies and reducing
wasted process energy.
Description of systems
air preheater
-
8/18/2019 CAN Training Boiler
70/207
regenerative air preheater
Training CAN Seite 70
Air flow downstream of APH Flue gas upstream of APH
Air flow upstream of APH Flue gas downstream of APH
Description of systems
cyclones
-
8/18/2019 CAN Training Boiler
71/207
Purpose of cyclones
Training CAN Seite 71
Arrangement downstream of the furnace
cyclone inlets have a spiral shape
cyclones have an interior lining which isfireproof, wear resistant and insulates
particles above an significant size are completely
separated
solid mass flow is transported from the from the
loop seals to the furnace
loop seals prevent a backflow of fluegas from
furnace
flue gas leaves cyclones through exit tubes
Description of systems
cyclones
-
8/18/2019 CAN Training Boiler
72/207
Arrangement cyclones
Training CAN Seite 72
Çan
355.6 MW
Description of systems
cyclones
-
8/18/2019 CAN Training Boiler
73/207
Cyclone overview
Training CAN Seite 73
InclinedDownward
Inlet Duct
High PerformanceRefractory for Inlet Area
Eccentric VortexFinder Arrangement
Advanced VortexFinder Shape
Second Pass
Description of systems
cyclones
-
8/18/2019 CAN Training Boiler
74/207
cyclone performance
Training CAN Seite 74
Description of systems
cyclones
-
8/18/2019 CAN Training Boiler
75/207
velocity and dust loading
Training CAN Seite 75
velocity dust loading
Description of systems
loop seal
-
8/18/2019 CAN Training Boiler
76/207
P&I loop seal
Training CAN Seite 76
Description of systems
loop seal
-
8/18/2019 CAN Training Boiler
77/207
loop seal
Training CAN Seite 77
Description of systems
loop seal
-
8/18/2019 CAN Training Boiler
78/207
loop seal
Training CAN Seite 78
downcomer
lift
line
Description of systems
auxiliaries
-
8/18/2019 CAN Training Boiler
79/207
section lower furnace
Training CAN Seite 79
Description of systems
sootblower
-
8/18/2019 CAN Training Boiler
80/207
Rotary long retractable sootblower
Training CAN Seite 80
Description of systems
sootblower
-
8/18/2019 CAN Training Boiler
81/207
Rotary extended lance sootblower
Training CAN Seite 81
Description of systems
sootblower
-
8/18/2019 CAN Training Boiler
82/207
Installation 2nd pass
Training CAN Seite 82
No Level(m)
KKS-No Fluegastemperature
( °C)
Fluegaspressure(mbar)
Type of construction
1 33.630 01 HCB20 AT001 860 -1.0 Long retractable blower2 33.630 01 HCB20 AT001 860 -1.0 Long retractable blower
3 33.630 01 HCB20 AT001 860 -1.0 Long retractable blower
4 30.560 01 HCB20 AT001 700 -2.0 Long retractable blower
5 30.560 01 HCB20 AT001 700 -2.0 Long retractable blower
6 30.560 01 HCB20 AT001 700 -2.0 Long retractable blower7 25.170 01 HCB20 AT001 540 -4.0 Helical blower
8 25.170 01 HCB20 AT001 540 -4.0 Helical blower
9 25.170 01 HCB20 AT001 540 -4.0 Helical blower
10 19.250 01 HCB20 AT001 435 -6.0 Helical blower
11 19.250 01 HCB20 AT001 435 -6.0 Helical blower12 19.250 01 HCB20 AT001 435 -6.0 Helical blower
13 12.950 01 HCB20 AT001 375 -8.0 Helical blower
14 12.950 01 HCB20 AT001 375 -8.0 Helical blower
15 12.950 01 HCB20 AT001 375 -8.0 Helical blower
Description of systems
limestone feeding
-
8/18/2019 CAN Training Boiler
83/207
limestone feeding system
Training CAN Seite 83
two limestone silos
one fluidizing conveyor, divides the conveying
route in two parts
adjustable rotary feeders
adjustable drag link conveyors
two manual operated gate valves
<
Description of systems
limestone feeding
-
8/18/2019 CAN Training Boiler
84/207
P&I limestone feeding
Training CAN Seite 84
limestone silo
fluidizing conveyor
rotary feeders
drag link conveyors
<
Description of systems
coal and limestone feeding
-
8/18/2019 CAN Training Boiler
85/207
arrangement coal and limestone feeding
Training CAN Seite 85
Description of systems
coal feeding
-
8/18/2019 CAN Training Boiler
86/207
arrangement
Training CAN Seite 86
cyclone Coal bunker furnace
Gravimetric
coal feeder
Drag link
chain conveyor
Loop seal
Rotary
feeders
<
Description of systems
coal feeding
l f di t
-
8/18/2019 CAN Training Boiler
87/207
coal feeding system
Training CAN Seite 87
four coal bunkers each with two outflows
altogether eight adjustable gravimetric coal
feeders with clean out conveyor
eight adjustable drag link chain conveyors with
connection with limestone feeding
downstream of drag link conveyors route divides
in two conveying routes
each route is lockable with manual operated shutoff gate valves
<
Description of systems
coal feeding
l f di t
-
8/18/2019 CAN Training Boiler
88/207
coal feeding system
Training CAN Seite 88
each route is lockable with manual operated shut
off gate valves
each route consists of one rotary feeder downstream one manual operated shut off gate
valve
one auto operated shut off gate valve
both shut off gate valves, rotary feeder and drag
link chain conveyors are supplied with adjustable
sealing air
upstream of loop seal both conveying routes are
linked up<
Boiler protection
Boiler protection part I
I t l k
-
8/18/2019 CAN Training Boiler
89/207
ID fan protection
SA fan protection
secondary air way release
primary air way release
reheater release
general interlocking
Interlocks
Training CAN Seite 89
symbols
Logic diagram
Boiler protection
Boiler protection part II
Interlocks
-
8/18/2019 CAN Training Boiler
90/207
boiler purge
ignition release
start up burner release
bed lance burner LFO release
bed lance burner HFO release
oil burner purge release
coal feeder release
Interlocks
Training CAN Seite 90
Boiler protection
ID fan protection
Both ID fans are tripped if
-
8/18/2019 CAN Training Boiler
91/207
Both ID fans are tripped if
>=2 furnace pressure < min
>=2 reg air heater speed < min
one of four ID fan bearing temperature
> 90 °C
cooling air flow < min ( for > than 30 min)ID fan motor winding temperature > 140°C
ID fan motor cooling air inlet temperature
> 70°CID fan motor cooling air outlet temperature
> 110°C
ID fan vibration > 11 mm/sTraining CAN Seite 91 approx. values forinitial adjustment
Boiler protection
SA fan protection
-
8/18/2019 CAN Training Boiler
92/207
Both SA fans are tripped if
no ID fans in operation and ”command on”
SA fan ≤ 2 furnace pressure > max
SA fan bearing temperature > 95°C
SA fan motor winding temperature > 140°C SA fan motor cooling air inlet temperature
> 70°C
SA fan motor cooling air outlet temperature> 110°C
SA fan vibration > 11 mm/s
Training CAN Seite 92approx. values forinitial adjustment
Boiler protection
Secondary air way release
-
8/18/2019 CAN Training Boiler
93/207
Secondary air way release is available if
no boiler emergency switch is activated
furnace pressure is > min and < max
ID fan and SA fan are in operation
fluegas dampers are open
Failure of air and fluegas way release signal leads
to boiler trip.
Training CAN Seite 93
Boiler protection
Primary air way release
Primary air way release is available if following
-
8/18/2019 CAN Training Boiler
94/207
Primary air way release is available, if following
signals are available
secondary air way release
a minimum fluidising air pressure ( 300 mbar)
a minimum secondary air pressure ( 30 mbar) reheater release
water level in the drum < max ( 200 mm)
water level in the drum > min
Training CAN Seite 94approx. values forinitial adjustment
Boiler protection
Reheater release
-
8/18/2019 CAN Training Boiler
95/207
Training CAN Seite 95
Boiler protection
General interlocking
-
8/18/2019 CAN Training Boiler
96/207
master fuel fault is existing, if
failure of the primary air way release signal both PA Fans out of operation
furnace windbox pressure below a minimum( 40 mbar )
primary air flow below minimum (38570 Nm³/h) condenser level not > max
Training CAN Seite 96approx. values forinitial adjustment
Boiler protection
Boiler purge
The purging is done with 50% MCR air flow
-
8/18/2019 CAN Training Boiler
97/207
Training CAN Seite 97
The purging is done with ~50% MCR air flow(78.5 kg/s). The purge time is set to a value thatmeets the total volume of 3 times boiler fluegas
way volume (16 min). On completion of the presetvolumes i.e. 3 times volume change for fluegaspath the signal boiler purge time completed is
activated. Any interruption during this processresets the boiler purge time relay. In this case thepurge cycle has to start all over again. If the boiler was in operation and the bed temperature at the
nozzle grid level exceeded 570 °C there is noneed to purge the boiler.
approx. values forinitial adjustment
Boiler protection
Ignition release
-
8/18/2019 CAN Training Boiler
98/207
Once the purge is completed the ignition permit
time is set and a secondary air flow < 30% is
maintained. For the normal start time a maximumof 3 failstarts is allowed. The start attempts of the
burners is monitored through a fail start counter. If
the burner is not established within the allowedpreset number failstart counts the boiler has to be
purged again.
Training CAN Seite 98
Boiler protection
Ignition release
-
8/18/2019 CAN Training Boiler
99/207
Ignition oil burner release permit is available
provided there are the following
start up burner on
or
bed temperature > 570°C
boiler protection existing
or ignition permit time running
secondary air flow < 30%
Training CAN Seite 99approx. values forinitial adjustment
Boiler protection
Start up burner release
Oil burner burner release permit is available
-
8/18/2019 CAN Training Boiler
100/207
Oil burner burner release permit is availableprovided there are the following:
Primary air way release
Ignition release
Minimum primary air flow available or oil valvesstart up burners closed at least 10 min
Min LFO supply pressure available (if light oiloperation selected)
Min HFO supply pressure available (if heavy oiloperation selected)
control air pressure > min available ( 3,5 bar)
Training CAN Seite 100approx. values forinitial adjustment
Boiler protection
LFO bed lance burner release
b d l b LFO l it i il bl
-
8/18/2019 CAN Training Boiler
101/207
bed lance burner LFO release permit is available
provided there are the following:
Ignition release
boiler protection
Primary air flow > min (38570 Nm³/h)
control air pressure > min ( 3,5 bar)
bed temperature > 500 °C
Training CAN Seite 101approx. values forinitial adjustment
Boiler protection
HFO bed lance burner release
b d l b HFO l it i il bl
-
8/18/2019 CAN Training Boiler
102/207
bed lance burner HFO release permit is available
provided there are the following:
Ignition release
boiler protection
Primary air flow > min ( 38570 Nm³/h)
control air pressure > min ( 3,5 bar)
bed temperature > 550 °C
Training CAN Seite 102approx. values forinitial adjustment
Boiler protection
Oil burner purge release
Oil b rner p rge release permit is a ailable
-
8/18/2019 CAN Training Boiler
103/207
Oil burner purge release permit is available
provided there are the following:
bed lance burner LFO release
or
bed lance burner HFO release
or
start up burner release
and minimum purge steam pressure available
Training CAN Seite 103
Boiler protection
Coal feeder release
Coal feeder release permit is available provided
-
8/18/2019 CAN Training Boiler
104/207
Coal feeder release permit is available provided
there are the following
boiler protection existing
ignition release existing
>=2 primary air flow > min 52550 Nm³/h)
>=7 bed temperature > min ( 650° C)
Training CAN Seite 104approx. values forinitial adjustment
Boiler protection
unit load runback
one of two ID Fan is tripped
-
8/18/2019 CAN Training Boiler
105/207
one of two ID Fan is tripped
target: 70 % BMCR not delayed
one of two SA Fan is trippedtarget: 70 % BMCR not delayed
one of two PA Fan is trippedtarget: 70 % BMCR not delayed
one of two FB ash cooler fan
target: 70 % BMCR not delayed
turbine trip
target: 60 % BMCR not delayedTraining CAN Seite 105
approx. values forinitial adjustment
System operation
overview
fi t filli f b il
-
8/18/2019 CAN Training Boiler
106/207
first filling of boiler
cold start up boiler
warm start up boiler
hot start up boiler
normal operation
shut down boiler
blackout
failures
Training CAN Seite 106
System operation
first filling of boiler
Filling line is used for filling the evaporator after a
-
8/18/2019 CAN Training Boiler
107/207
Filling line is used for filling the evaporator after a
repair standstill. Evaporator and downcomer are
filled from bottom up to avoid thermal stress of drum during filling operation
all isolating valves upstream of measurementsshall be opened
Filling of eco, evaporator and of drum via fillingline ( 01 LAE10) until drum level > min
Training CAN Seite 107
System operation
General
Operation conditions for start / stop and
-
8/18/2019 CAN Training Boiler
108/207
Operation conditions for start / stop and
monitoring of the boiler is given in the form of
functional group logics whole system is divided into functional groups
and subgroups
function group control can be started in automode or manually.
group control is used to START or STOP in
steps.
Training CAN Seite 108
System operation
General
every step is activated when its previous step
-
8/18/2019 CAN Training Boiler
109/207
every step is activated, when its previous step
command is carried out and the necessary
conditions previous to this step are fulfilled step is overriden or overruled, if the subsequent
conditions meet the overruling criterias to this
step selection control blocks are for either one out of
two or three equipments
some operational conditions require manualintervention (e.g. start of oilburners, coalfeeding)
Training CAN Seite 109
System operation
Overview function groups
-
8/18/2019 CAN Training Boiler
110/207
Training CAN Seite 110
System operation
Overview function groups
-
8/18/2019 CAN Training Boiler
111/207
Training CAN Seite 111
System operation
Overview function groups
-
8/18/2019 CAN Training Boiler
112/207
Training CAN Seite 112
System operation
cold start
criterion for cold start up
-
8/18/2019 CAN Training Boiler
113/207
p
bed temperature < 100 °C
bed temperature control
The brick lining of the cyclone part admits amaximum rate of temperature change of approx.
100 K /h. Therefore, the bed temperature is used
as most important control variable during the start-up process, the required target being a bed
temperature increase of approx. 100 K/h.
Training CAN Seite 113
System operation
cold start
Steam pressure control
-
8/18/2019 CAN Training Boiler
114/207
p
The life steam pressure is controlled by the HPbypass control valve during start-up of the steam
generator. The hot reheat steam pressure is
controlled by the LP bypass control valve. In caseof failures, a steam flow of 30% at maximum can
be released to atmosphere via SH start-up standby
control valve.
Training CAN Seite 114
Adj live st
Adj reheat st
System operation
cold start
Steam temperature control
-
8/18/2019 CAN Training Boiler
115/207
p
spray attemperators are ready for operation to keepsteam temperatures below given limits
due to the very slow rate of bed temperature increase,
the steam temperature rate of change both of lifesteam and of hot reheat steam normally will be in a
safe range without any spray attemperator operation
as soon as the required turbine coupling temperature
in the life steam line or in the hot reheat line is reached,
the relevant spray attemperator will open and will keep
this temperature.
Training CAN Seite 115
System operation
cold start
Start-up of fans and of steam air preheater with Adjustment of firing
-
8/18/2019 CAN Training Boiler
116/207
Start up of fans and of steam air preheater with
FG air fluegas
Fill-in of required bed material
Purge via secondary air with FG purge
Training CAN Seite 116
System operation
cold start
Ignition of start-up burner (LFO) with a firing rate Adjustment of firing
-
8/18/2019 CAN Training Boiler
117/207
g p ( ) g
of approx. 10%
use HFO start up burners not until combustionair temperature has reached 120 °C
adjustment of primary air minimum flow
minimum air flow for
start-up burner 38570 Nm³/h bed lances 46400 Nm³/h
Training CAN Seite 117
approx. values for
initial adjustment
System operation
cold start
Ignition of bed lance LFO or HFO (minimum bed Adjustment of firing
-
8/18/2019 CAN Training Boiler
118/207
Ignition of bed lance LFO or HFO (minimum bed
temperature for bed lance release LFO 500° C
HFO 550° C )
Firing rate increase to approx 40%. The increase
takes place in steps adapted to avoid a rate of
change of the bed temperature > 100 K/h.
Start-up at least one ash cooler
Training CAN Seite 118
approx. values for
initial adjustment
System operation
cold start
Start-up of the first coal feeder after Adjustment of firing
-
8/18/2019 CAN Training Boiler
119/207
Start up of the first coal feeder after
bed temperature > 650 °C is reached
waiting time until coal ignition (coal ignition is
recognized by fast increasing of bed
temperature)
Increase of coal firing rate, synchronous
reduction of oil firing rate and oil firing turnoff
Training CAN Seite 119
approx. values for
initial adjustment
-
8/18/2019 CAN Training Boiler
120/207
System operation
cold start
SH and RH start-up drains are set to autoDrain system
-
8/18/2019 CAN Training Boiler
121/207
operated mode with starting FG air fluegas
condensate obtained in the HP and LP steam
system is automatically discharged
Training CAN Seite 121
System operation
cold start
controlled with HP bypass control valve Adjustment of live steam pressure
-
8/18/2019 CAN Training Boiler
122/207
yp
1. control valve opens to minimum position
pressure will increase in sliding pressure mode
2.pressure control mode with variable target rate
up to turbine coupling pressure3.fixed pressure setpoint (until steam turbine has
taken over all steam)
4.increase steam pressure to operation pressure
Training CAN Seite 122 Steam pr ctrl
System operation
cold start
controlled with LP bypass control valve Adjustment of hot reheat steam pressure
-
8/18/2019 CAN Training Boiler
123/207
yp
1. control valve opens to maximum position -
pressure will increase in sliding pressure mode
2.pressure control mode with fixed pressure
setpoint (until steam turbine has taken over allsteam)
Training CAN Seite 123 Steam pr ctrl
System operation
cold start
-
8/18/2019 CAN Training Boiler
124/207
Training CAN Seite 124
System operation
warm start
criterion for warm start up
-
8/18/2019 CAN Training Boiler
125/207
drum temperature > 100 °Cbed temperature < 650 °C
Training CAN Seite 125
System operation
warm start
start-up of fans and of steam air preheater with
FG air fluegas
Adjustment of firing
-
8/18/2019 CAN Training Boiler
126/207
FG air fluegas
if bed temperature < 570 °C :purge via secondary air
if bed temperature > 570 °C :
ignition of the oil firing ignition of the oil firing ( start-up burner ) with a
firing rate of approx. 10%
adjustment of primary air minimum flow( see cold start )
Training CAN Seite 126
approx. values for
initial adjustment
System operation
warm start
Ignition of bed lance LFO or HFO (minimum bed
Adjustment of firing
-
8/18/2019 CAN Training Boiler
127/207
temperature for bed lance release LFO 500° C
HFO 550° C )
Firing rate increase to approx. 40%. First the
increase is accelerated to reach quickly thesame bed temperature value, that was measured
before purge. The following increase takes place
in steps adapted to avoid a rate of change of the
bed temperature > 100 K/h.
Training CAN Seite 127
approx. values for
initial adjustment
System operation
warm start
start-up of the first coal feeder after both bed
Adjustment of firing
-
8/18/2019 CAN Training Boiler
128/207
temperature > 650 °C is reached and the cooling
of one FB-ash cooler at least is in service.
increase of coal firing rate, synchronous
reduction of oil firing rate and oil firing turnoff
Training CAN Seite 128
approx. values for
initial adjustment
System operation
warm start
usual feedwater flow control during start-up of
Feedwater supply
-
8/18/2019 CAN Training Boiler
129/207
the firing
discharge of obtained excess water from drum
by the drum blow down system
normally the feedwater will always be sent
through FB-ash coolers. However it is allowed to
send the feedwater via ash cooler bypass aslong as bed temperature < approx. 200 °C.
Training CAN Seite 129
System operation
warm start
SH and RH start-up drains are set to auto
Drain system
-
8/18/2019 CAN Training Boiler
130/207
operated mode with starting FG air fluegas
condensate obtained in the HP and LP steam
system is automatically discharged
Training CAN Seite 130
System operation
warm start
controlled with HP bypass control valve
Adjustment of live steam pressure
-
8/18/2019 CAN Training Boiler
131/207
1. control valve opens to minimum position -
pressure will increase in sliding pressure mode
2.pressure control mode with variable target rate
up to turbine coupling pressure
3.fixed pressure setpoint (until steam turbine has
taken over all steam)
4.increase steam pressure to operation pressure
Training CAN Seite 131
System operation
warm start
controlled with LP bypass control valve
Adjustment of hot reheat steam pressure
-
8/18/2019 CAN Training Boiler
132/207
1. control valve opens to minimum position
2.pressure control with pressure setpoint approx.
equal to the HRH pressure value at ignition until
LP bypass reaches maximum position
( approx.50% )
3.pressure control mode with fixed pressure
setpoint (until steam turbine has taken over allsteam)
Training CAN Seite 132
System operation
warm start
-
8/18/2019 CAN Training Boiler
133/207
Training CAN Seite 133
System operation
hot start
criterion for hot start up
-
8/18/2019 CAN Training Boiler
134/207
bed temperature > 650 °C
Training CAN Seite 134
System operation
hot start
restart of fans, adjustment of primary air
minimum flow ( > 52550 Nm³/h)
Adjustment of firing
-
8/18/2019 CAN Training Boiler
135/207
minimum flow ( 52550 Nm /h)
restart of first coal feeder rapid increase of firing rate to approx 40% in
order to keep the bed temperature above 650 °C.
Training CAN Seite 135
approx. values for
initial adjustment
System operation
hot start
Feedwater supply
-
8/18/2019 CAN Training Boiler
136/207
feedwater supply and drum blow down are
working in the warm start-up manner.
due to the high bed temperature the feedwater
shall always sent through FB ash cooler.
Training CAN Seite 136
System operation
hot start
Drain system
Adjustment of live steam pressure
Adjustment of hot reheat steam pressure
-
8/18/2019 CAN Training Boiler
137/207
Training CAN Seite 137
beginning at a higher pressure level
actions to be taken in warm start-up manner
System operation
hot start
-
8/18/2019 CAN Training Boiler
138/207
Training CAN Seite 138
System operation
Normal operation
feedwater supply and drum blow down
desalting of boiler water
overview
-
8/18/2019 CAN Training Boiler
139/207
desalting of boiler water
steam pressure
steam temperature
control O2
air distribution
primary air control
steam air preheater
Training CAN Seite 139
System operation
Normal operation
pressure and temperature condition in the
furnace
overview
-
8/18/2019 CAN Training Boiler
140/207
grain size distribution of the bed
sootblowing
limestone feeding desulphurization
formation of NOx
Training CAN Seite 140
System operation
Normal operation
boiler feedwater pumps have the control task to
ensure an appropriate differential pressure
Feedwater supply and drum blow down
-
8/18/2019 CAN Training Boiler
141/207
between inlet and outlet of the feedwater control
station respectively between inlet of feedwater
control station and drum.
the feedwater control valve in service has to
adjust the feedwater mass flow. All feedwater is
normally sent through the FB-ash cooler.
overfed water is automatically discharged fromdrum by drum emergency blow down system.
Training CAN Seite 141
System operation
Normal operation
blow down valve is used for keeping conductivity
of boiler water below 50 µS/cm
Desalting of boiler water
-
8/18/2019 CAN Training Boiler
142/207
of boiler water below 50 µS/cm
blow down valve can be operated intermittent or
continuously.
blow down valve shall be closed when boiler is
not in operation
Training CAN Seite 142
System operation
Normal operation
During normal operation the total live steam flow
and the total hot reheat steam flow are sent to
Steam pressure
-
8/18/2019 CAN Training Boiler
143/207
turbine. If the turbine is not able to take the total
steam flow, HP bypass and LP bypass take the
remaining steam flow up to 70% MCR. In this
case the load capability is restricted to approx.
70% MCR.
Fixed-pressure operation in the HP system
combined with sliding-pressure operation in the
LP system is the usual operation mode within the
whole range of load. Bypass operation at 70%
MCR load requires 100% hot reheat pressure.Training CAN Seite 143 Safety devices
System operation
Normal operation
At ignition the HP bypass control valve opens to a
given start-up minimum position
Superheated steam pressure control
-
8/18/2019 CAN Training Boiler
144/207
The first part of the pressure rise takes place insliding pressure mode with this HP bypass position
Then HP bypass is switched to pressure control
mode. The pressure setpoint is increased infunction of steam flow and pressure until required
steam turbine coupling pressure is reached
further pressure increase up to normal operationpressure after steam turbine has taken over all the
steam
Training CAN Seite 144
System operation
Normal operation
After ignition the LP bypass opens to a given start-
up maximum position
reheated steam pressure control
-
8/18/2019 CAN Training Boiler
145/207
the HRH pressure is rising in sliding pressuremode up to the required turbine coupling pressure
After that the start-up maximum position limit is
eliminated. The LP bypass is switched to pressurecontrol mode, setpoint being the required turbine
coupling pressure value
set-point is set somewhat above the operatingpressure. Thus, the LP bypass is kept close during
the further turbine load operation.
Training CAN Seite 145
System operation
Normal operation
life steam temperature is controlled by SH spray
attemperators 2.1 / 2.2. A constant temperature
i id d i th l d f 50 100 % GCC
Steam temperature
-
8/18/2019 CAN Training Boiler
146/207
is provided in the load range of 50-100 % GCC.
The task of the spray attemperators 1.1/ 1.2 is to
keep the control valve position of the spray
attemperators 2.1 / 2.2 within a well suited range.
hot reheat steam temperature is controlled by
RH spray attemperators. A constant temperature
is provided in the load range of 50-100 % GCC.
Below this load range, usually the hot reheat
steam temperature is lower and not yet
controlled, the spray control valves are closed.Training CAN Seite 146
System operation
Normal operation
The main steam temperature downstream of SH 3is controlled and adjusted to setpoint by means of
4 desuperheaters ( two downstream of SH 3 and
Superheated steam temperature control
-
8/18/2019 CAN Training Boiler
147/207
4 desuperheaters ( two downstream of SH 3 and
two downstream of SH 2)
maximum setpoint is 543 °C
or is set manually
or is set by unit master controller ( lower setpoint
during startup of boiler)
The spray mass flow for the four injections is
extracted by the feedwater control valvesTraining CAN Seite 147
System operation
Normal operation
The reheater steam temperature downstream of
RH2 is controlled and adjusted to setpoint by
means of 2 attemperators (downstream of RH 1)
reheated steam temperature control
-
8/18/2019 CAN Training Boiler
148/207
means of 2 attemperators (downstream of RH 1)
maximum setpoint is 542 °C
or is set manuallyor is set by unit master controller ( lower setpoint
during startup of boiler)
The spray mass flow for the two injections is
extracted by the feedwater control valves
Training CAN Seite 148
System operation
Normal operation
The air flow must be regulated in accordance
with the fuel flow
If th f l fl i t ll d ll h i
Control O2
-
8/18/2019 CAN Training Boiler
149/207
If the fuel flow is controlled manually, changes in
the fuel flow carried out too quickly are to be
avoided.
Training CAN Seite 149
System operation
Normal operation
Control O2
O2-content in flue gas downstream
2nd passapprox values for
-
8/18/2019 CAN Training Boiler
150/207
Training CAN Seite 150
11,31
3,44
0
2
4
6
8
10
12
0 20 40 60 80 100
GCC Load [%]
O
2 - c o n t e n t d r y [ V o l . - % ]
approx. values for
initial adjustment
System operation
Normal operation
Air distribution
70,00
80,00
The diagram gives approx.
values
for the initial adjustment.
-
8/18/2019 CAN Training Boiler
151/207
Training CAN Seite 151
0,00
10,00
20,00
30,00
40,00
50,00
60,00
40 50 60 70 80 90 100GCC [%]
a i r m a
s s f l o w
[ k g / s ]
primary air
upper secondary air
burner air
lower secondary air
coal feeding air
ash cooler fluidization
sealing air, cooling air ingnitor, flamescanner, limestone feeding air
ash loop seal fluidization
System operation
Normal operation
Primary air control
Primary air flow setpoint is formed of
an function of unit load demand of unit master
-
8/18/2019 CAN Training Boiler
152/207
Training CAN Seite 152
controller and primary air flow (valid for bedtemperatures > 650°C)
and an function of bed temperature and primary
air flow (valid for bed temperatures< 650°C)
there is a possibility to adjust primary air flowmanually
approx. values for
initial adjustment
System operation
Normal operation
Steam air preheaters
The task of steam air heater is
to keep constant the air outlet temperature
-
8/18/2019 CAN Training Boiler
153/207
Training CAN Seite 153
to avoid the operation of the regenerative air preheater below the flue gas dew point
System operation
Normal operation
During normal operation both ash coolers are in
operation. The bottom ash discharge from the
furnace is controlled automatically depending on
Pressure and temperature in the furnace
-
8/18/2019 CAN Training Boiler
154/207
furnace is controlled automatically depending on
the pressure above nozzle grid. The bedpressure in the lower level is supposed to be
between 80 and 90 mbar with 100 % BMCR.
The horizontal L-valves are opened alternating.
The bed temperature shall be
approx. 840 - 860 °C.
Training CAN Seite 154
approx. values for
initial adjustment
System operation
Normal operation
Pressure in the furnace
120
130
r )approx. values for
initial adjustment
-
8/18/2019 CAN Training Boiler
155/207
Training CAN Seite 155
80
90
100
110
0 10 20 30 40 50 60 70 80 90 100
load BMCR (%)
p r e s s u r
e a b o v e g r i d ( m b
a r
setpoint 1
setpoint 2
setpoint 3
setpoint 4
Descr ash cooler
initial adjustment
System operation
Normal operation
Grain size distribution of bed
30
Case 1 Case 2
m
-
8/18/2019 CAN Training Boiler
156/207
Training CAN Seite 156
+ 30
+ 20
+ 10
0 20 40 60 80 100 mbar
System operation
Normal operation
Tendency to a fine bed
to be recognized by:
Grain size distribution of bed
-
8/18/2019 CAN Training Boiler
157/207
decreasing bed temperature increased bed pressures on the upper levels
Measures
reduce ash cooler cooling air flow (min. flow)
feed coarse bed material
Training CAN Seite 157
System operationNormal operation
Tendency to a coarse bed
to be recognized by
Grain size distribution of bed
-
8/18/2019 CAN Training Boiler
158/207
increasing bed temperature low pressures on the upper levels
Measures
increase ash cooler air flow
increase primary air portion
Training CAN Seite 158
System operationNormal operation
Particle size distribution of solid inventory0.11.0(%)
10.020.030.040 0
solids
-
8/18/2019 CAN Training Boiler
159/207
Training CAN Seite 159
10 µm100 1000Grain size d
40.0
50.060.070.0
80.0
90.0
99.0
99.9
R e s i d u e R
approx. values for
initial adjustment
System operationNormal operation
Particle size distribution of lignite
Acceptable particle size
distribution:
99,9 % < 6.0-9.0 mm
0,1
1
10
20%
99,9
99
90
80%
0,1 0,2 0,5 1 2 5 20 50 100106
-
8/18/2019 CAN Training Boiler
160/207
Training CAN Seite 160
,
55 % < 1.0 mm
-
8/18/2019 CAN Training Boiler
161/207
- the boiler load
- the fouling of the heating surfaces
(CO increase)- the increase of fluegas temperature
The complete cycle is to be operated at leastonce per shift.
Training CAN Seite 161
System operationNormal operation
Even if the control is off, the limestone feeding
has to be carried out such that the admissible
SO2 limit values are kept in every operating
Limestone feeding
-
8/18/2019 CAN Training Boiler
162/207
phase if possible.
Training CAN Seite 162
System operationNormal operation
The task of the limestone control is to reduce the
SO2 content in the flue gas to a predefined value
control SO2 content
-
8/18/2019 CAN Training Boiler
163/207
by dosing limestone
To improve the dynamic response of the
controlled system due to its inertia - from
limestone dosing into boiler to SO2-
measurement in the stack - the lignite flow is
used as a feedforward signal
Training CAN Seite 163
CFB DesulfurizationChemical Reaction Basics
1. Calcination of LimestoneCaCO3 => CaO + CO2for temperatures above ca. 750 °CEndothermic reaction DH = +178 kJ/mol
-
8/18/2019 CAN Training Boiler
164/207
Training CAN Seite 164
Endothermic reaction DH 178 kJ/mol
2. Sulfur Dioxide Reaction
S + O2 => SO2
for temperatures above ca. 650 °CExothermic reaction, DH = - 297 kJ/mol
3. Desulfurization Reaction
CaO + 1/2 O2 + SO2 => CaSO4for temperatures between 750 °C and 900 °CExothermic Reaction DH = - 500 kJ/mol
CFB Desulfurizationreaction inside particles
macro pores
sulfated lime
unreacted
-
8/18/2019 CAN Training Boiler
165/207
Training CAN Seite 165
Calcination and Desulphurization Reaction inside Limestone Particles
micro pores lime
- CO2
CaCO3 CaO CaSO4
+ SO2 +1/2 O2
CFB Boiler - SO2 Capture
Achieved by limestone injection
CaCO3 --> CaO + CO2Optimum temperature:
CaO + SO2 + ½ O2 --> Ca SO4 850 °C
-
8/18/2019 CAN Training Boiler
166/207
Training CAN Seite 166
• Main parameter :
Furnace temperature control
- Limestone consumption varies enormously with
furnace temperature
No low cost remedial measure to
a poor furnace temperaturecontrol
790 810 830 850 890870 910
Temperature
Ca/S
Desulphurization Rate vsCFB Furnace Temperature
6
5
a t e
-
8/18/2019 CAN Training Boiler
167/207
Training CAN Seite 167
4
3
2
1
0
650 700 750 800 850 900 950 1000
Temperature (°C)
R e l a t i v e
S o r b e n t F l o w r a
Main Factors of influence
System operation
CFB NOX Emissions
Fuel Characteristics- Increase of NOx with fuel nitrogen content
- Increase of NOx with fuel volatile matter content
-
8/18/2019 CAN Training Boiler
168/207
Training CAN Seite 168
Furnace Temperature- Decrease of NOx with low temperature in furnace
( approx. 850 °C )
Excess Air - Decrease of NOx with low excess air level ( 20 % )
Air Staging- Decrease of NOx with low primary air feeding
Fuel / Air Mixing- Decrease of NOx with intense and homogeneous
fuel / air mixing
System operationshut down
Two different cases
-
8/18/2019 CAN Training Boiler
169/207
Shut-down with fast cooling down
(repair standstill)
Shut-down with pressure maintaining
(hot standby standstill)
Training CAN Seite 169
System operationshut down
load reduction to minimum load approx. 30%
the change from turbine mode to HP/LP bypass
First part
-
8/18/2019 CAN Training Boiler
170/207
mode takes place before the steam temperature
drops. During and after this change HP bypass
and LP bypass keep the operating pressure
values of life steam and of HRH steam.
turn off of the coal feeders
Training CAN Seite 170
System operationCooling down with pressure maintaining
To manage pressure maintaining without the risk
of excessive SH wall temperatures rise, a
i i b t
general
-
8/18/2019 CAN Training Boiler
171/207
compromise is necessary between
some cooling down of the cyclone refractory
lining on the one hand
and
maintaining hot the bed material on the other
hand
Training CAN Seite 171
System operationCooling down with pressure maintaining
After the turn off of the coal feeders the followingactions have to be done:
Primary air fan OFF. Lower secondary air
d l d
Air fluegas system
-
8/18/2019 CAN Training Boiler
172/207
dampers closed
The secondary air fan and the induced draught
fan remain in operation for a period of several
minutes. Some secondary air flow is adopted inorder to obtain sufficient cooling of the refractoy
lining. At the same time the bed temperature in
both FB ash coolers has to be reducedto < approx. 400 °C
Then all fans OFFTraining CAN Seite 172
System operationCooling down with pressure maintaining
The feedwater supply remains in operation,adjusting the drum level to a constant value. The
feedwater is still sent through the FB-ash cooler.
feedwater
-
8/18/2019 CAN Training Boiler
173/207
Shut-down of the feedwater supply not before the
response of the enabling criteria
maximum outside tube wall temperature of SH 1/1
< approx. 400°C for > 15 minutes
Some adjusting of the drum level before shut-downof the feedwater supply may be advantageous for
the following standstill and the restartTraining CAN Seite 173
System operationCooling down with pressure maintaining
HP bypass and LP bypass are switched to
pressure limiting control mode. Their task is
li iti f th lif t d HRH
HP and LP bypass
-
8/18/2019 CAN Training Boiler
174/207
limiting of the life steam pressure and HRH
pressure to values close below the response
pressure values of the safety devices
Training CAN Seite 174
System operationCooling down with pressure maintaining
After shut-down of the induced draught fan, theSH standstill cooling valve has to do a
temperature limiting control task. That means: In
case of maximum outside tube wall temperature
SH standstill cooling valve
-
8/18/2019 CAN Training Boiler
175/207
case of maximum outside tube wall temperatureof SH 1/1 > approx. 430°C,
it is opened to cooling position
Thus, a small steam flow of approx. 2,5 % BMCR
is produced and released via SH standstill
cooling valve to the ambient air, which ensures asufficient longterm cooling of the critical SH 1
heating surfaceTraining CAN Seite 175
System operationCooling down with pressure maintaining
The SH relief valve is closed again by the criterion
SH standstill cooling valve
-
8/18/2019 CAN Training Boiler
176/207
maximum outside tube wall temperature
of SH 1/1 < approx. 400°C
Training CAN Seite 176
System operationfast cooling down
The task is to cool the steam generator down as
f t ibl i h kf
general
-
8/18/2019 CAN Training Boiler
177/207
fast as possible in a shockfree manner.
After the turn off of the coal feeders the following
actions have to be done
Training CAN Seite 177
System operationfast cooling down
Air fluegas system
All fans remain in operation.
The cooling is practised with small air flow rates
of approximately 30 50 % of the GGC secondary
-
8/18/2019 CAN Training Boiler
178/207
Training CAN Seite 178
of approximately 30-50 % of the GGC secondaryair flow.
This cooling operation mode is continued untilthe bed temperature has dropped to the required
value.
System operationfast cooling down
feedwater
The feedwater supply remains in operation,adjusting the drum level to a constant value.
The feedwater ist still sent through the
ash cooler
-
8/18/2019 CAN Training Boiler
179/207
Training CAN Seite 179
ash cooler.
Shut-down of the feedwater supply not before
the response of the enabling criteria :
maximum outside tube wall temperature
of SH 1/1 < approx. 400°C for > 15 minutes
The cooling down process may possibly besupported by continuing the feedwater supply for
some time
System operationfast cooling down
HP and LP bypass
Cooling down of the water-steam system by well-
directed pressure reduction down to depressurized
state
-
8/18/2019 CAN Training Boiler
180/207
Training CAN Seite 180
state The operator has to open slowly HP bypass and
LP bypass to position values, that ensure to get a
rate of pressure change within the safe range.
In case of condenser being out of service the
pressure can be reduced manual via RH start-up
standby control valve.
System operationblack out
general
In case of a failure of the main power supply, asafe state of the plant must be achieved.
Besides an emergency shutdown of the firing it ist th fl id t d i th
-
8/18/2019 CAN Training Boiler
181/207
Training CAN Seite 181
Besides an emergency shutdown of the firing it isnecessary to use the fluid stored in the
HP system for well-directed long-term cooling of
endangered heating surfaces (support tubes at
the transition cyclone 2nd pass).
Any other loss of stored HP fluid is to be
prevented.
System operationblack out
Safe state water steam system
Final control element Safe state
Drum emergency blow down control
valve
Closed
-
8/18/2019 CAN Training Boiler
182/207
Training CAN Seite 182
valveDrum emergency blow down gate valve Closed
Demine drum gate valve Closed
SH standstill cooling valve controlledcooling position
Gate valve upstream SH standstill
cooling valve
Open
HP bypass control valve Closed
System operationblack out
First measures
If the failure of the main power supply cannot be
eliminated within approx 15 minutesth f ll i l t ti ti h t
-
8/18/2019 CAN Training Boiler
183/207
Training CAN Seite 183
eliminated within approx. 15 minutes,the following manual protection actions have to
be carried out
System operationblack out
measures
Final control element action target
swirl dampers of induceddraught fans,
swirl dampers of secondary air fans
open upto 100%
cooling by natural draught
-
8/18/2019 CAN Training Boiler
184/207
Training CAN Seite 184
y
upper secondary air dampers,
oil burner air dampers
open upto 100%
cooling by natural draught
manual shut-off valve01HAC10AA403Hin the economiser-
evaporator short circuitline
open The water contained in theeconomiser (approx. 29 t) isdrained into the evaporator.
Thus this water can be usedfor emergency coolingpurpose of the endangeredheating surfaces.
System operationblack out
Second measures
If the failure of the main power supply cannot be
eliminated within approx 45 minutes
-
8/18/2019 CAN Training Boiler
185/207
Training CAN Seite 185
eliminated within approx. 45 minutes,
the following manual protection actions can be
done for better cooling :
System operationblack out
measures
Final control element action target
cover of manhole,
arranged betweenf d l
open
withti
improved cooling
by natural draught
-
8/18/2019 CAN Training Boiler
186/207
Training CAN Seite 186
arranged betweenfurnace and cyclone
withcaution
by natural draught
upper secondary air
dampers
reduce
opening
keeping sub-
atmosphericpressure in thefurnace
Failuresleakages
Leakage boiler pressure parts
tube leaks or tube ruptures will ultimately lead toa boiler shut down
it is up to the operator or shift charge engineer
to decide when
-
8/18/2019 CAN Training Boiler
187/207
Training CAN Seite 187
to decide when
Generally boiler operation may continue for
some time if a tube leak is negligible small, easyto locate and easy to watch
Failuresleakages
Leakage evaporator
take the firing system out of service
separate the boiler from the common main steam
line
stop limestone dosing
-
8/18/2019 CAN Training Boiler
188/207
Training CAN Seite 188
stop limestone dosing
discharge bed material
reduction of the main steam pressure observingthe admissible gradient
maintain water level in the drum
by make-up feeding
Failuresleakages
Leakage evaporator
cooling of the boiler by means of the fans -observing the admissible temperature gradient in
the cyclone area
open overfire and oilburner air dampers to 50%
-
8/18/2019 CAN Training Boiler
189/207
Training CAN Seite 189
p pand set the minimum primary air flow
at a bed temperature of approx. 400°C
the make-up feeding can be stopped
Failuresleakages
Leakage evaporator
unpressurize boiler with attention toadmissible gradient
further cooling of the boiler by means of the
primary air fan until inspection temperature has
-
8/18/2019 CAN Training Boiler
190/207
Training CAN Seite 190
p y p pbeen reached
draining of evaporator or superheater
Failuresleakages
Leakage economizer
Small leaks are not very easy to detect (sounddetectors may help) and deviation of feedwater to
steam ratio or decreasing flue gas temperatures
after eco can only be noticed if leakage hasid bl i d
-
8/18/2019 CAN Training Boiler
191/207
Training CAN Seite 191
y gconsiderably increased.
The unit should be shut down in the normal way
and feeding should be stopped immediately after "fire out".
Failuresleakages
Leakage superheater, reheater
These leakages may easily be detected bysound detectors.
Decision should be a normal shut down as the
leakage can be neither located or judged
-
8/18/2019 CAN Training Boiler
192/207
Training CAN Seite 192
g j g
Feeding can continue after fire out to equally
decrease temperature in the boiler's water parts.
FailuresHP bypass
HP bypass
If the HP bypass doesn't open adequatelyalthough opening is required,
sufficient cooling of the RH heating surfaces is
impossible.
-
8/18/2019 CAN Training Boiler
193/207
Training CAN Seite 193
In addition, sufficient cooling of the SH heating
surfaces would also be impossible
as long as the pressure is below
the response pressure of the HP safety devices
FailuresHP bypass
HP bypass
In case of high bed temperatures (above approx.600 °C), an emergency firing shutdown must be
initiated within approx. 30 s to avoid damage of
the platen heating surfaces (SH2, RH2) in thefurnace
-
8/18/2019 CAN Training Boiler
194/207
Training CAN Seite 194
furnace.
In case of bed temperatures below approx.
600 °C, the operator shall reduce firing rate
to minimum.
If he does not succeed in opening the HP bypass,
he normally has to initiate a firing shut-down after
a maximum of 10 minutes.
FailuresLP bypass
after turbine trip
In case of turbine trip the load capability of thesteam generator is restricted to
approx. 55 % BMCR
The HP bypass ensures the cooling of theSH h ti f b l i t i t
-
8/18/2019 CAN Training Boiler
195/207
Training CAN Seite 195
SH heating surfaces by releasing steam into
the CRH system
If the LP bypass does not open (e. g. because of
condenser malfunction), the LP start-up standby
control valve is automatically opened, doing
some cooling releasing about 30% steam to
atmosphere
FailuresLP bypass
after turbine trip
The other steam is stored in the RH system, untilthe pressure is high enough to initiate opening of
HRH safety valves.
Then the HRH safety valves ensure a sufficient
-
8/18/2019 CAN Training Boiler
196/207
Training CAN Seite 196
longterm cooling of the the RH heating surfaces.
FailuresLP bypass
during start up
In case of malfunction of both LP bypass and theLP start-up standby control valve,
the RH pressure increase up to the HRH safety
valve response pressure value would take toomuch time because of small start-up steam
-
8/18/2019 CAN Training Boiler
197/207
Training CAN Seite 197
much time because of small start-up steam
production.
In case of high bed temperatures (above approx.600 °C), an emergency firing shutdown must be
initiated within approx. 60 s to avoid damage of
the platen reheat heating surfaces (RH2) in thefurnace during this period of HRH pressure
increase.
FailuresLP bypass
during start up
In case of bed temperatures below approx.600 °C, the operator shall reduce firing rate to
minimum.
If he does not succeed in opening the LP bypassfinally he shall initiate a firing shut down after a
-
8/18/2019 CAN Training Boiler
198/207
Training CAN Seite 198
finally, he shall initiate a firing shut-down after a
maximum of 10 minutes.
FailuresLP bypass
during start up
After a malfunction of the LP bypass only (e. g.because of condenser trip) the LP start-up
standby control valve is automatically opened to
100 % to ensure the cooling of the RH2 As soon as the LP bypass is ready for operation
-
8/18/2019 CAN Training Boiler
199/207
Training CAN Seite 199
As soon as the LP bypass is ready for operation
again, the LP start-up standby control valve has
to be closed manually If the operator does not succeed in opening the
LP bypass finally, he normally has to initiate a
firing shut-down after a short while
Failuresfiring permit signal
emergency fire shut down
-
8/18/2019 CAN Training Boiler
200/207
Training CAN Seite 200
Failuresfiring permit signal
emergency fire shut down
There are 4 possibilities to fulfill reheater release: Bed temperature < 570 °C (7 of 10)
During start-up firing the primary air flow
between 10 and 30 %
-
8/18/2019 CAN Training Boiler
201/207
Training CAN Seite 201
The turbine is in operation and the outlet
temperature of the reheater is < 562 °C
The HP-bypass is opened > 15 % and LP-
bypass is opened > 15 % or reheater start-up
valve is opened > 30 % and temperature of the
reheater is < 562 °C
approx. values for
initial adjustment
Failuresash cooler
temperatures
ash temperature 1st chamber > 500 °C
shut off L-valve and lock hoppering sequence
until temperature < 400 °C
-
8/18/2019 CAN Training Boiler
202/207
Training CAN Seite 202
ash cooler overflow > 200°C
shut off L-valve and rotary seal
until temperature < 150 °C
approx. values for
initial adjustment
Failuresash cooler
operation with one ash cooler
close L-valves
fluidization of the ash cooler has to be
-
8/18/2019 CAN Training Boiler
203/207
Training CAN Seite 203
maintained as sealing against the flue gas
atmosphere from the furnace
In case of worst coal a boiler load reduction
can be necessary
Failuresash cooler
cooling circuit of ash cooler
Detection of leaks
pressure increase in the ash cooler chamber temperature decrease in the ash cooler chamber
-
8/18/2019 CAN Training Boiler
204/207
Training CAN Seite 204
temperature decrease in the ash cooler chamber
increased moisture content of ash which may
lead to an increased plugging tendency
Failuresash cooler
cooling circuit of ash cooler
measures
shut off and emptying of the L-valves
shut off of the cooling water flow through
th h l
-
8/18/2019 CAN Training Boiler
205/207
Training CAN Seite 205
the ash cooler
maximum fluidization of the ash cooler has to bemaintained
emptying the ash cooler via lock hopper system
as fast as possible
Overview symbols
AND gate
OR gate
BISTABLE
PULSE t t
If any of all the inputs to an AND gate are logic 1,
then the output is logic 1 otherwise the output is
logic 0.If any one or more inputs to an OR gate is logic 1
then the output is logic 1, otherwise the output is
logic 0.
If S=1, while R=O then Q=1, Q’ =O, and flip flop is
in SETstate.
If R=1. while S=O then Q=O.Q’ =1, and flip flop isin RESET state.
Output goes to logic 1 immediately when input
goes to logic 1 Output remains at logic 1 for the
&
>=1
R S
-
8/18/2019 CAN Training Boiler
206/207
Training CAN Seite 207
PULSE output
DELAYED ON time
DELAYED OFF time
NOT gate
goes to logic 1. Output remains at logic 1 for the
specified time and then returns to logic 0
regardless of state of input in.
If input goes to logic 1, then after a timedelay of specified duration, output changes
to logic 1.Output goes to logic 0 as soon as
input returns to logic 0.
Output goes to logic 1 immediately when
input goes to logic 1.
When input returns to logic 0, outputremains at logic 1.
Lo