campbell river community information meeting presentation sept. 18, 2014

34
Campbell River Quarterly Public Meeting September 18, 2014

Upload: island-health

Post on 25-Jan-2015

1.139 views

Category:

Healthcare


4 download

DESCRIPTION

PowerPoint presentation from the North Island Hospitals Project community information meeting held at Campbell River's Discovery Inn Sept. 18, 2014

TRANSCRIPT

Page 1: Campbell River Community Information Meeting presentation Sept. 18, 2014

Campbell River Quarterly Public Meeting

September 18, 2014

Page 2: Campbell River Community Information Meeting presentation Sept. 18, 2014

• Laichwiltach Territory

o We Wai Kai Nation

o Wei Wai Kum First Nation

Acknowledgment of Traditional Lands

2

Page 3: Campbell River Community Information Meeting presentation Sept. 18, 2014

Approvals

• Treasury Board

• Cabinet

Project Agreement

• Commercial Close

• Financial Close

Construction Underway

• Groundbreaking

• Site Administration

• Excavation

• Concrete

• Steel

Since May 29, 2014

3

Page 4: Campbell River Community Information Meeting presentation Sept. 18, 2014

• Location: Next to existing hospital (375 - 2nd Avenue)

o 32,316 m2

o 95 beds

o $274.5 million`

o Comox Strathcona Regional Hospital District 40%

Campbell River Hospital

4

Webcam 10:15 a.m. September 18, 2014

4

Page 5: Campbell River Community Information Meeting presentation Sept. 18, 2014

• Location: 101 Lerwick Road, Courtenay

o 39,826 m2

o 153 beds

o $331.7 million

o Comox Strathcona Regional Hospital District 40%

5

Comox Valley Hospital

Webcam 11:52 a.m. September 16, 2014

5

Page 6: Campbell River Community Information Meeting presentation Sept. 18, 2014

Project Coordinator

Campbell River Site

(EA to CPO)

Monique Hebert

Chief Project Officer

Tom Sparrow

Technical Team

Lead: Kerry Beauchamp

Equipment Lead: Catherine Brooks

Clinical Team Lead: Norma Jones

IMIT Team Lead: Steve Carter

Smart Technologies

Team Lead: David Leadbetter

Financial Team Lead: Bill Boomer

Communication Team

Sr Project Coordinator

Comox Valley Hospital

Jennifer Singer

6

Island Health Project Team

Page 7: Campbell River Community Information Meeting presentation Sept. 18, 2014

7

Tandem Health Partners

7

Page 8: Campbell River Community Information Meeting presentation Sept. 18, 2014

Working Group Structure

COVER

8

Page 9: Campbell River Community Information Meeting presentation Sept. 18, 2014

9

Page 10: Campbell River Community Information Meeting presentation Sept. 18, 2014

Business

Case &

Design

Concept

Construction

Issue

RFQ

Issue RFP

Negotiate

Maintenance

3 years

5 months

to 2 years

Design

Concept

Plan

Contract Term

30 years

2 to 4

months We are here

10

Progress – Design & Construction Phase

Page 11: Campbell River Community Information Meeting presentation Sept. 18, 2014

Design

• Detail Design Review

• Clinical User Consultation

• Mockup Spaces

• Guidance

• Aboriginal Working Group

• Public Advisory Committee

Construction

• Excavation - Underway

• Foundation Work – Underway

Where we are going

11

Page 12: Campbell River Community Information Meeting presentation Sept. 18, 2014

Campbell River – Level 0

12

Page 13: Campbell River Community Information Meeting presentation Sept. 18, 2014

Campbell River – Level 1

13

Page 14: Campbell River Community Information Meeting presentation Sept. 18, 2014

Campbell River – Level 2

14

Page 15: Campbell River Community Information Meeting presentation Sept. 18, 2014

Campbell River – Level 3

15

Page 16: Campbell River Community Information Meeting presentation Sept. 18, 2014

Mockups

Sink

Paper Towel

Sharps

Soap

16

Page 17: Campbell River Community Information Meeting presentation Sept. 18, 2014

Mockup – Operating Room

17

Page 18: Campbell River Community Information Meeting presentation Sept. 18, 2014

Community Engagement & Consultation

Quarterly Public Meetings

Newsletters

Website

Webcams

Public Patient

Advisory Committee

(in recruitment)

Art Committee

(Terms of Reference in development)

Aboriginal Working Group

School Advisory

Committee

18

Page 19: Campbell River Community Information Meeting presentation Sept. 18, 2014

Public-Patient Advisory Committee

Expression of Interest – September 16

First Intake - Interviews – mid October

First Committee Meeting - end October

19

Page 20: Campbell River Community Information Meeting presentation Sept. 18, 2014

Education and Training

• Inter-agency Discussions – March 13, 2014

• North Island Employment Foundations Society, North Vancouver Island Aboriginal Training Society, Industry Training Authority, North Island College, SD72, SD71, Vancouver Island Construction Association, Island Health

Industry Training Authority

• Dialogue on Trades/Apprenticeships Opportunities – September 9, 2014

Community Benefits - Opportunities

20

Page 21: Campbell River Community Information Meeting presentation Sept. 18, 2014

Business and Industry

• Chambers of Commerce – Industry Speed Dating Sessions

• Campbell River: May 27, 2013 (Workshop: May 16)

• Comox Valley: May 28, 2013 (Workshop: May 16)

• Follow up Sessions (Planning in Progress)

Tender / Bid Opportunities

• Prequalification

• Work Packages

Community Benefits - Opportunities

21

Page 22: Campbell River Community Information Meeting presentation Sept. 18, 2014

Work Packages and Awards

22

Page 23: Campbell River Community Information Meeting presentation Sept. 18, 2014

Work Packages and Awards

23

Page 24: Campbell River Community Information Meeting presentation Sept. 18, 2014

Community Benefits - Today

24

Page 25: Campbell River Community Information Meeting presentation Sept. 18, 2014

25

Construction Fencing Parking Lot Closure Birch Street Closure Heliport Closure Implement Alternate Ambulance Access/Egress Route Access Roads Establish Site Administration Commence Bulk Excavation Commence Foundation / Concrete

Campbell River Construction – August, September

Page 26: Campbell River Community Information Meeting presentation Sept. 18, 2014

Campbell River - Excavation

26

Page 27: Campbell River Community Information Meeting presentation Sept. 18, 2014

27

Install Site Trailers – In Progress Continue Bulk Excavation Continue Foundation / Concrete Erect Cranes – end of September Commence Level 1 Suspended Slab

Campbell River Construction – October, November

Page 28: Campbell River Community Information Meeting presentation Sept. 18, 2014

Campbell River - Construction

28

Page 29: Campbell River Community Information Meeting presentation Sept. 18, 2014

Design and Construction of New Facilities

July 2014 – April 2017

Service Commencement – Project Completion April 30, 2017

Commissioning and Transition Period

Summer – Fall 2017

Move-In

Late Fall 2017

29

Project Schedule

Page 30: Campbell River Community Information Meeting presentation Sept. 18, 2014

What we have been hearing

• Traffic Safety

o Non-compliant street parking

o Big truck traffic

o Congestion

o Speed

• Construction Noise

o Project Agreement

o City of Campbell River Nuisance Bylaw

30

Page 31: Campbell River Community Information Meeting presentation Sept. 18, 2014

What we have been hearing

• Dust Control

o Preventive Measures

31 31

Page 32: Campbell River Community Information Meeting presentation Sept. 18, 2014

• Temporary Lots west of Yucalta Lodge (144 stalls)

• Parking Shuttle - Transit to/from temporary lots

o Weekday mornings

o Expansion of Service in October to early afternoon

Hospital Parking Shuttle

Parking

32

Page 33: Campbell River Community Information Meeting presentation Sept. 18, 2014

For more information and updates, visit our website:

http://nihp.viha.ca/

North Island Hospitals Project Website

33

Page 34: Campbell River Community Information Meeting presentation Sept. 18, 2014

Thank You!!

Questions?

34