calorimeter status and plans for mar-apr ‘01
DESCRIPTION
Summary Start with ~3-4 crate readout (CC) Debugging + commissioning 8/12 quad’s instrumented, 5/16 ICD tiles on ECS 12/12 by end of 6 weeks assuming some access Some trigger summers/drivers installed by end of 6 weeks Timed to L1 trigger. Calorimeter Status and Plans for Mar-Apr ‘01. - PowerPoint PPT PresentationTRANSCRIPT
DD
DØ Commissioning Meeting February 23, 20011
Leslie GroerColumbia University Calorimeter Running at Begin of Run II
1
Calorimeter Status and Plans for Mar-Apr ‘01
Summary Start with ~3-4 crate readout (CC) Debugging + commissioning 8/12 quad’s instrumented, 5/16 ICD tiles on
ECS 12/12 by end of 6 weeks assuming some
access Some trigger summers/drivers installed by
end of 6 weeks Timed to L1 trigger
DD
DØ Commissioning Meeting February 23, 20012
Leslie GroerColumbia University Calorimeter Running at Begin of Run II
2
Calorimeter Electronics Status
PS Boards PS Boards PS Boards PS BoardsP S P S
0 11
1 10
2 9
3 8
4 7
5 6
BLSPreampBLS Preamp
DD
DØ Commissioning Meeting February 23, 20013
Leslie GroerColumbia University Calorimeter Running at Begin of Run II
3
Calorimeter Commissioning Shifts
Shifts ongoing 2-3/day U. Bassler, M.
Bhattacharjee, V. Bhatnagar, L. Duflot, T. Eltzroth, S. Fu, M. Gao, R. Hauser, M. Hohlfeld, B. Kehoe, N. Parua, M. Ridel, D. Schamberger, M.Tuts
Concentrating on CC Working on software
(examines, GUIs etc.) for online debugging and commissioning
DD
DØ Commissioning Meeting February 23, 20014
Leslie GroerColumbia University Calorimeter Running at Begin of Run II
4
Calorimeter Electronics Install
Preamp 1 primary + 5 PS to
install + 1 ICD Cooling Fan needs
rework in one box (~1 day)
All 1152 m/boards with 48 preamps per board installed (55k)
All calibration pulsers installed and cabled
Commission
BLS 24/36 PS installed, 6
ready to be installed, 6 more in final assembly/testing
8/12 quadrants populated (768/1152). Need ~400 more
Board assembly and testing at SUNY-SB about 50-100/week
DD
DØ Commissioning Meeting February 23, 20015
Leslie GroerColumbia University Calorimeter Running at Begin of Run II
5
Calorimeter Electronics Install
ADC & T+C Run 1 ADC’s working fine ADC controllers modified
and being tested 4 prototype Timing and
Control cards being used 10 more on order (1-2
weeks) Still need T+C Crate
controller (1-2 week layout, 2 week production)
L1/L2 Trigger Trigger drivers at
assembler (doing all 2.3k) Trigger summer – parts
go out next week for CC (3k). Estimate 3 week production. Need testing. Installation in hall.
Will test and time in with a few prototype towers
Noise issues on readout are a concern
DD
DØ Commissioning Meeting February 23, 20016
Leslie GroerColumbia University Calorimeter Running at Begin of Run II
6
Calorimeter Electronics Install
ICD 5 tiles installed on
ECS-SW PMT box, HV + LV
power, electronics pulser installed
Readout tested next week
HV CC and ECN filled in
Dec and HV turned on to 2kV on all channels
All cryostats filling this week
HV cables reinstalled, tested and ready to turn on
DD
DØ Commissioning Meeting February 23, 20017
Leslie GroerColumbia University Calorimeter Running at Begin of Run II
7
Calorimeter Electronics Install
Calibration Pedestal calibration
data sent to L3 scriptrunner node
Data sent to CalibManager and then to Oracle dB
Python tools extract data to pickle files
Work on gain runs with pulser ongoing
Automatic validation and extraction tools needed
Downloads/controls Pedestal and limits
files read from pickle file in Comics and downloaded to ADC
Working on pulser control
General alarm monitoring of all systems needs to be implemented and more robust GUIs
DD
DØ Commissioning Meeting February 23, 20018
Leslie GroerColumbia University Calorimeter Running at Begin of Run II
8
Calorimeter Electronics Status
DD
DØ Commissioning Meeting February 23, 20019
Leslie GroerColumbia University Calorimeter Running at Begin of Run II
9
Calorimeter Comissioning
Jul 00 Assemble new BLS power supplies; ORC
Complete preamp board stuffingInstall cooling, power, preamps in ECN
Test with old BLS
ECN – SE (now), NE, SW, NW
debug + commission
(physicist shifts)
10-Jul-00 ECS moves onto platform and available ECS cleanup (power, cooling) (physicist shifts) Recable ECS (physicist shifts)
24-Jul-00 Lose access to detector/MCH for ~ 2 weeksAug-00 ** Receive and certify 10% BLS boards
Install CC cooling, power and preamps; checkout with final prototype BLS
CC SW started already (1 crate)(physicist shifts)
Cleanup ECN BLS (power + backplanes)Install ECS preamp cooling and powerCommission pulser control interface + calib.Start final T&C / fanout production
Sep-00 Install ECS fanouts, pulser cables, preamps
Start commissioning with prototype BLS (physicist shifts)Test prototype Trigger Pickoff/Summer cardsICD backplanes and cables installFill a cryostat and test seals and HV
Oct-00 Install ICD electronics and commissionNov-00 ** Receive and test final BLS
mother/daughterboards
(physicist shifts - SUNYSB)
Install ECN BLS power + recommission (physicist shifts)Dec-00 Cosmic ray testJan-01 ** Final BLS install; checkout of full detector (physicist shifts)Feb-01 Calorimeter checkout complete + ready to roll
in** = critical path
DD
DØ Commissioning Meeting February 23, 200110
Leslie GroerColumbia University Calorimeter Running at Begin of Run II
10
Goals
Commission ECN preamps, pulsers + cables with Run 1 BLS – (July/Aug)
Commission CC preamps, pulsers + cables + BLS crates with final prototype electronics (Aug/Sept)
Commission ECS full detector + readout with prototypefinal electronics (Oct/Nov)
Commission full detector (Dec/Jan) Ready for roll-in (Feb)