calorimeter status and plans for mar-apr ‘01

10
D D DØ Commissioning Meeting 1 Leslie Groer Columbia University Calorimeter Running at Begin of Run II 1 Calorimeter Status and Plans for Mar-Apr ‘01 Summary Start with ~3-4 crate readout (CC) Debugging + commissioning 8/12 quad’s instrumented, 5/16 ICD tiles on ECS 12/12 by end of 6 weeks assuming some access Some trigger summers/drivers installed by end of 6 weeks Timed to L1 trigger

Upload: melisande-faure

Post on 02-Jan-2016

23 views

Category:

Documents


0 download

DESCRIPTION

Summary Start with ~3-4 crate readout (CC) Debugging + commissioning 8/12 quad’s instrumented, 5/16 ICD tiles on ECS 12/12 by end of 6 weeks assuming some access Some trigger summers/drivers installed by end of 6 weeks Timed to L1 trigger. Calorimeter Status and Plans for Mar-Apr ‘01. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Calorimeter Status and Plans  for Mar-Apr ‘01

DD

DØ Commissioning Meeting February 23, 20011

Leslie GroerColumbia University Calorimeter Running at Begin of Run II

1

Calorimeter Status and Plans for Mar-Apr ‘01

Summary Start with ~3-4 crate readout (CC) Debugging + commissioning 8/12 quad’s instrumented, 5/16 ICD tiles on

ECS 12/12 by end of 6 weeks assuming some

access Some trigger summers/drivers installed by

end of 6 weeks Timed to L1 trigger

Page 2: Calorimeter Status and Plans  for Mar-Apr ‘01

DD

DØ Commissioning Meeting February 23, 20012

Leslie GroerColumbia University Calorimeter Running at Begin of Run II

2

Calorimeter Electronics Status

PS Boards PS Boards PS Boards PS BoardsP S P S

0 11

1 10

2 9

3 8

4 7

5 6

BLSPreampBLS Preamp

Page 3: Calorimeter Status and Plans  for Mar-Apr ‘01

DD

DØ Commissioning Meeting February 23, 20013

Leslie GroerColumbia University Calorimeter Running at Begin of Run II

3

Calorimeter Commissioning Shifts

Shifts ongoing 2-3/day U. Bassler, M.

Bhattacharjee, V. Bhatnagar, L. Duflot, T. Eltzroth, S. Fu, M. Gao, R. Hauser, M. Hohlfeld, B. Kehoe, N. Parua, M. Ridel, D. Schamberger, M.Tuts

Concentrating on CC Working on software

(examines, GUIs etc.) for online debugging and commissioning

Page 4: Calorimeter Status and Plans  for Mar-Apr ‘01

DD

DØ Commissioning Meeting February 23, 20014

Leslie GroerColumbia University Calorimeter Running at Begin of Run II

4

Calorimeter Electronics Install

Preamp 1 primary + 5 PS to

install + 1 ICD Cooling Fan needs

rework in one box (~1 day)

All 1152 m/boards with 48 preamps per board installed (55k)

All calibration pulsers installed and cabled

Commission

BLS 24/36 PS installed, 6

ready to be installed, 6 more in final assembly/testing

8/12 quadrants populated (768/1152). Need ~400 more

Board assembly and testing at SUNY-SB about 50-100/week

Page 5: Calorimeter Status and Plans  for Mar-Apr ‘01

DD

DØ Commissioning Meeting February 23, 20015

Leslie GroerColumbia University Calorimeter Running at Begin of Run II

5

Calorimeter Electronics Install

ADC & T+C Run 1 ADC’s working fine ADC controllers modified

and being tested 4 prototype Timing and

Control cards being used 10 more on order (1-2

weeks) Still need T+C Crate

controller (1-2 week layout, 2 week production)

L1/L2 Trigger Trigger drivers at

assembler (doing all 2.3k) Trigger summer – parts

go out next week for CC (3k). Estimate 3 week production. Need testing. Installation in hall.

Will test and time in with a few prototype towers

Noise issues on readout are a concern

Page 6: Calorimeter Status and Plans  for Mar-Apr ‘01

DD

DØ Commissioning Meeting February 23, 20016

Leslie GroerColumbia University Calorimeter Running at Begin of Run II

6

Calorimeter Electronics Install

ICD 5 tiles installed on

ECS-SW PMT box, HV + LV

power, electronics pulser installed

Readout tested next week

HV CC and ECN filled in

Dec and HV turned on to 2kV on all channels

All cryostats filling this week

HV cables reinstalled, tested and ready to turn on

Page 7: Calorimeter Status and Plans  for Mar-Apr ‘01

DD

DØ Commissioning Meeting February 23, 20017

Leslie GroerColumbia University Calorimeter Running at Begin of Run II

7

Calorimeter Electronics Install

Calibration Pedestal calibration

data sent to L3 scriptrunner node

Data sent to CalibManager and then to Oracle dB

Python tools extract data to pickle files

Work on gain runs with pulser ongoing

Automatic validation and extraction tools needed

Downloads/controls Pedestal and limits

files read from pickle file in Comics and downloaded to ADC

Working on pulser control

General alarm monitoring of all systems needs to be implemented and more robust GUIs

Page 8: Calorimeter Status and Plans  for Mar-Apr ‘01

DD

DØ Commissioning Meeting February 23, 20018

Leslie GroerColumbia University Calorimeter Running at Begin of Run II

8

Calorimeter Electronics Status

Page 9: Calorimeter Status and Plans  for Mar-Apr ‘01

DD

DØ Commissioning Meeting February 23, 20019

Leslie GroerColumbia University Calorimeter Running at Begin of Run II

9

Calorimeter Comissioning

Jul 00 Assemble new BLS power supplies; ORC

Complete preamp board stuffingInstall cooling, power, preamps in ECN

Test with old BLS

ECN – SE (now), NE, SW, NW

debug + commission

(physicist shifts)

10-Jul-00 ECS moves onto platform and available ECS cleanup (power, cooling) (physicist shifts) Recable ECS (physicist shifts)

24-Jul-00 Lose access to detector/MCH for ~ 2 weeksAug-00 ** Receive and certify 10% BLS boards

Install CC cooling, power and preamps; checkout with final prototype BLS

CC SW started already (1 crate)(physicist shifts)

Cleanup ECN BLS (power + backplanes)Install ECS preamp cooling and powerCommission pulser control interface + calib.Start final T&C / fanout production

Sep-00 Install ECS fanouts, pulser cables, preamps

Start commissioning with prototype BLS (physicist shifts)Test prototype Trigger Pickoff/Summer cardsICD backplanes and cables installFill a cryostat and test seals and HV

Oct-00 Install ICD electronics and commissionNov-00 ** Receive and test final BLS

mother/daughterboards

(physicist shifts - SUNYSB)

Install ECN BLS power + recommission (physicist shifts)Dec-00 Cosmic ray testJan-01 ** Final BLS install; checkout of full detector (physicist shifts)Feb-01 Calorimeter checkout complete + ready to roll

in** = critical path

Page 10: Calorimeter Status and Plans  for Mar-Apr ‘01

DD

DØ Commissioning Meeting February 23, 200110

Leslie GroerColumbia University Calorimeter Running at Begin of Run II

10

Goals

Commission ECN preamps, pulsers + cables with Run 1 BLS – (July/Aug)

Commission CC preamps, pulsers + cables + BLS crates with final prototype electronics (Aug/Sept)

Commission ECS full detector + readout with prototypefinal electronics (Oct/Nov)

Commission full detector (Dec/Jan) Ready for roll-in (Feb)