california public utilities commission

30
California Public Utilities Commission: Weaknesses in Its Contracting Process Have Resulted in Questionable Payments March 2000 99117.2

Upload: others

Post on 12-Sep-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: California Public Utilities Commission

CaliforniaPublic UtilitiesCommission:Weaknesses in Its Contracting ProcessHave Resulted in Questionable Payments

March 200099117.2

Page 2: California Public Utilities Commission

The first copy of each California State Auditor report is free.Additional copies are $3 each. You can obtain reports by contacting

the Bureau of State Audits at the following address:

California State AuditorBureau of State Audits

555 Capitol Mall, Suite 300Sacramento, California 95814

(916) 445-0255 or TDD (916) 445-0255 x 216

OR

This report may also be availableon the World Wide Web

http://www.bsa.ca.gov/bsa/

Permission is granted to reproduce reports.

Page 3: California Public Utilities Commission

CALIFORNIA STATE AUDITOR

STEVEN M. HENDRICKSONCHIEF DEPUTY STATE AUDITOR

BUREAU OF STATE AUDITS555 Capitol Mall, Suite 300, Sacramento, California 95814 Telephone: (916) 445-0255 Fax: (916) 327-0019

MARY P. NOBLEACTING STATE AUDITOR

March 16, 2000 99117.2

The Governor of CaliforniaPresident pro Tempore of the SenateSpeaker of the AssemblyState CapitolSacramento, California 95814

Dear Governor and Legislative Leaders:

As requested by the Joint Legislative Audit Committee, the Bureau of State Audits presents itsaudit report concerning the California Public Utilities Commission (commission).

This report concludes that the commission does not adequately develop and manage its contracts.For example, it sometimes fails to perform important steps in developing its contracts, such asseeking competitive bids, including a clearly defined scope of work, and preparing reasonablydetailed budgets and progress schedules. It also does not always review its consultants’ invoicesto make sure that the charges are appropriate and sufficiently supported. As a result, thecommission has made hundreds of thousands of dollars in questionable payments to itsconsultants.

Respectfully submitted,

MARY P. NOBLEActing State Auditor

Page 4: California Public Utilities Commission

CONTENTS

Summary 1

Introduction 3

Audit Results

The Commission’s Weak ContractingPractices Have Led to QuestionablePayments to Consultants 7

Recommendations 19

Appendix

How the Commission Is ImplementingRecommendations From Its Own InternalAudit of Its Contracting Practices 21

Response to the Audit

California Public Utilities Commission 23

Page 5: California Public Utilities Commission

1C A L I F O R N I A S T A T E A U D I T O R

SUMMARY

RESULTS IN BRIEF

The California Public Utilities Commission (commission)does not always adequately develop and manage itscontracts. For example, it does not consistently seek

competitive bids, clearly define the scope of contracted work,and prepare reasonably detailed budgets and progress schedules.It also does not always review its consultants’ invoices to ensurethat all charges are appropriate and sufficiently supported. As aresult, the commission has paid hundreds of thousands ofdollars on invoices that included improper charges or lackedsufficient detail. Because the commission receives most of itsfunding from assessments on utility companies––which pass thecosts on to consumers—when it makes improper payments thepublic ends up paying higher utility rates than necessary.

The commission, which has broad authority to regulate theState’s investor-owned utility companies, employs a diverse staffof more than 800 people, including economists, engineers,administrative law judges, accountants, lawyers, and supportpersonnel. Despite the range of expertise on its staff, the com-mission needs to contract with consultants when it does nothave the necessary resources to provide certain services. In fiscalyear 1998-99, the commission allotted more than $11 million ofits $106 million budget to contracted services.

Although the commission consistently monitored the progressof its consultants’ work, weaknesses in its contracting processwere evident in our review of a sample of 25 commissioncontracts amended or entered into during fiscal year 1998-99 aswell as in our previous review of the commission’s contract tohave an outside consultant investigate the 1998 San Franciscopower outage. By failing to obtain competitive bids on contracts,inadequately reviewing invoices, and not requiring consultantsto adhere to state travel guidelines, the commission mademore than $662,000 in questionable payments to its consult-ants. During fiscal years 1997-98 and 1998-99, the commissionapproved payments totaling more than $650,000 to one consult-ant, even though the consultant did not provide adequatesupporting documents for more than $350,000 of the costs.More than $70,000 of these unsupported charges were approved

Audit Highlights . . .

Our review of the CaliforniaPublic Utilities Commission’s(commission) contractingpractices disclosed that:

� The commission doesnot always adequatelydevelop and manageits contracts and as aresult made morethan $662,000 inquestionable paymentsto its consultants.

� Despite the Bureau ofState Audits’ previousscrutiny of a pro-blematic contract,the commissionoverpaid the consultant$12,500 and paidanother $330,000without adequatelyreviewing thecontractor’s invoices.

� The commission did notsubject one of its contractsto the State’s standardcontracting process.

Page 6: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R2

for payment in fiscal year 1998-99. We also found significantweaknesses in one consumer education contract that the com-mission handled outside the State’s normal systems of control.

An internal audit of the commission’s consultant contractingprocess, conducted after our previous audit, identified severalweaknesses we include in this report. The commission has begunto address these weaknesses through training and the develop-ment of a procedures manual. However, the commission mustsustain these efforts to make sure that meaningful change occurswithin its organization.

RECOMMENDATIONS

To ensure that it properly develops and manages its contracts,the commission should establish controls over its contractingprocess. For example, it should include clearly defined scopes ofwork in all contracts, solicit competitive bids whenever possible,and properly review consultant invoices to verify that its needsare being met and that payments are made only for appropriateservices received.

The commission should require all contractors to comply withstate travel guidelines and should pay only for allowable travelexpenses. In addition, it should recover amounts it has overpaidto contractors for travel expenses.

The commission should use the State’s contracting process forall contracts it develops or manages, including contracts forconsumer education programs.

The commission should continue to implement the recommen-dations contained in the internal audit report on its contractingprocess.

AGENCY COMMENTS

The commission agrees with the report’s conclusions and notesthat it has already taken several actions to strengthen its con-tracting. ■

Page 7: California Public Utilities Commission

3C A L I F O R N I A S T A T E A U D I T O R

INTRODUCTION

BACKGROUND

The California Public Utilities Commission (commission)consists of five commissioners appointed by the gover-nor, with Senate approval, for six-year terms. The

commission has broad powers to regulate investor-owned andoperated natural gas, electric, telephone, water, sewer, steam,and transportation companies in California. During fiscalyear 1997-98, the commission had jurisdiction over more than5,000 utilities and carriers. The commission’s regulatoryactivities––such as establishing operating authority, overseeingservice standards, authorizing rate changes, and monitoringsafety––benefit consumers by giving them increased choicesamong new and upgraded utility products and services andby protecting them where competition otherwise does not.The commission employs more than 800 people, includingeconomists, engineers, administrative law judges, accountants,lawyers, and support staff. It is generally organized alongindustry lines, with a division dedicated to monitoring eachregulated industry.

The Commission Contracts for Services ItsStaff Cannot Provide

Despite its diverse staff, the commission contracts with consult-ants when it does not have the resources to provide requiredservices. Normally, when a division identifies a need for acontract, it appoints a contract manager who has knowledge ofthe services to be provided. The contract manager consults withthe commission’s contracts office to determine the type ofcontract needed and the process required to identify a contrac-tor. The contract manager also contacts the commission’s fiscalstaff to ensure that funds are available for the desired work.Once the work has begun, the contract manager monitors thework of the consultant to make sure that the commission’sneeds are being met and reviews the related invoices to verifythat the billed costs are appropriate. To ensure that billed costsdo not exceed available funds, the contract manager, contractsoffice, and fiscal office need to maintain payment ledgers.

Page 8: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R4

Some commission contracts are not part of the State’s usualcontracting process because they are exempt from competitivebidding requirements or Department of General Servicesapproval. For example, the Public Contract Code exemptsexpert witness contracts––which pay consultants to provideexpert guidance and testimony for matters pending before thecommission––from competitive bidding requirements. ThePublic Contract Code also exempts from competitive biddingany emergency contract, defined as “a sudden, unexpectedoccurrence that poses a clear and imminent danger, requiringimmediate action to prevent or mitigate the loss or impairmentof life, health, property, or essential public services.” Finally,the Public Utilities Code states that the Public Contract Codesections that require Department of General Services approvalon all consultant and advisory service contracts do not applywhen the commission finds that extraordinary circumstancesjustify expedited contracting. When the commission does notsolicit competitive bids or receive approval from the Departmentof General Services, it is still responsible for ensuring that itfollows proper contracting practices.

A Previous Bureau of State Audits’ Report Noted ProblemsWith One of the Commission’s Contracts

In May 1999, the Bureau of State Audits issued a report conclud-ing that the commission did not effectively manage a consultingcontract for investigating the massive power failure thatoccurred in San Francisco in December 1998. In this report, wefound that the commission poorly monitored its contract andcould not substantiate the cost of the consultant’s investigation.Specifically, we stated that the commission failed to review thequalifications of subcontractors, did not ensure the quality ofthe resulting investigative report, and was not able to substanti-ate the cost of the investigation. Since the consultant had notyet invoiced the State when we issued our report, we could notvalidate the total costs of the investigation or determinewhether the consultant complied with the contract’s billingspecifications. Therefore, we recommended that the commissionconduct another review of the investigative report before payingthe consultant for services rendered. We also stated that, inperforming the review, the commission should determinewhether the report complied with the contract’s specificationsand that, before paying the consultant’s invoices, the commis-sion should audit all charges to determine whether they wereappropriate and complied with contract provisions.

Page 9: California Public Utilities Commission

5C A L I F O R N I A S T A T E A U D I T O R

Additionally, we found that there was confusion regardingjurisdiction over the investigation of the San Francisco poweroutage. Both the commission and the California IndependentSystem Operator, a nonprofit corporation that controlsthe State’s electrical power grid, claimed jurisdiction. Werecommended that the commission continue to work with theCalifornia Independent System Operator to address the jurisdic-tional issues that surfaced during the investigation of the outage.

SCOPE AND METHODOLOGY

The Joint Legislative Audit Committee (committee) requestedthat the Bureau of State Audits review the commission’scontracting practices. Specifically, the committee was interestedin how the commission identifies the need for contracts; how itdevelops the scope of work to be performed; how it ensures thatthe work is completed, meets its needs, and is cost-effective; andwhether the commission complies with Public Contract Coderequirements such as using competitive bidding and avoidingconflicts of interest.

To obtain an understanding of the commission’s contractingrequirements, we reviewed applicable laws, regulations,and manuals. We interviewed key commission staff to identifythe commission’s contracting practices, and we reviewedcontracting documents.

To determine whether the commission’s contracting practicesare appropriate, we selected a sample of 25 contracts thatwere entered into or amended during fiscal year 1998-99.Our sample included consulting contracts, informationtechnology contracts, a master service agreement, and aninteragency agreement.

To ascertain whether the commission had adequately developedand managed the contracts in our sample, we interviewed thecontract managers and reviewed the contracts, related invoices,and evidence of delivered goods and services.

The committee also asked us to determine whether the commis-sion ever hired consultants to perform work that the consultantsthemselves had recommended while performing previouscontracts. These situations present a potential conflict because aconsultant’s recommendation may not always be in thecommission’s best interest. We determined that, although the

Page 10: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R6

commission had contracted with certain consultants more thanonce, the contracts were not for services recommended inprevious engagements.

We also followed up on the corrective action taken by thecommission in response to our May 1999 report of thecommission’s handling of a consultant hired to investigatethe 1998 San Francisco power outage. Specifically, we examinedwhether the commission had performed an additional reviewof the product received from the consultant to ensure that itmet the commission’s needs and that the associated costswere appropriate.

Furthermore, we inquired about the actions the commission hadtaken to clarify jurisdictional issues that arose between it andthe California Independent System Operator during the investi-gation of the San Francisco power outage. We found that thetwo agencies have together drafted a list of protocols to followshould another outage occur and are currently in the process offormally adopting mutually acceptable protocols.

Finally, to identify how the commission has responded toits own internal audit of its consulting contract process, weinterviewed key executive and line staff and reviewed relateddocuments provided by the commission. ■

Page 11: California Public Utilities Commission

7C A L I F O R N I A S T A T E A U D I T O R

AUDIT RESULTSThe Commission’s Weak ContractingPractices Have Led to QuestionablePayments to Consultants

SUMMARY

The California Public Utilities Commission (commission)allotted more than $11 million to contracts duringfiscal year 1998-99. However, it did not always adequately

develop and manage its contracts and as a result made question-able payments for some consultant services. Although thecommission was diligent in documenting its need for eachcontract and monitoring the work being performed to ensurethat its needs were met, the commission did not always ensurethat it received the best value for its contracting dollar.Weaknesses, such as a lack of competitive bidding and inad-equate review of consultant invoices, resulted in the commissionmaking at least $662,000 in questionable payments for fiscalyear 1998-99. Because the commission is financed primarily byfees assessed on utility companies––which pass the costs on toconsumers—when it makes improper payments the public paysmore than necessary for utilities.

These weaknesses in contract practices were present in acommission contract that we reviewed last year and in anothercontract that the commission had not subjected to the statecontracting process. Since our audit last year, the commissionhas conducted an internal audit that identified similar weak-nesses, and it has begun to address many of the concerns weraise in this report. However, the commission should continueto strengthen its contract development and managementactivities and ensure that all its contracts are processed throughthe state contracting system.

THE COMMISSION HAS NOT DEVELOPEDSOME CONTRACTS ADEQUATELY

Although the commission did consistently identify its need forcontracts, it did not always perform other important steps indeveloping the contracts that we reviewed. As a result, it could

Page 12: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R8

not ensure that the resulting contracts clearly established whatwas expected from the contractor and provided the best value.We measured the commission’s performance by determining theextent to which it performed each of the following six key stepswhen developing its contracts:

· Identify the need for the contract.

· Develop a detailed scope of work to be performed.

· Identify schedules for the progress and completion ofthe work.

· Determine a reasonably detailed budget.

· Determine how a contractor will be selected.

· Review the qualifications of contractors and subcontractors.

Each step is critical to the eventual success of the contract. Forexample, if an agency does not adequately identify its need for acontractor’s services, it cannot determine whether that need issatisfied by the services the contractor provides. If an agencydoes not review a contractor’s qualifications, it cannot ensurethat the contractor has the knowledge and experience neededto complete the contracted tasks. Conversely, if an agencyadequately performs all the steps in developing a contract, it iscontributing to the success of the resulting contract.

Our review of 25 contracts for fiscal year 1998-99 showed thatthe commission consistently identified the need for its contractsand almost always developed a detailed scope of work andreviewed the qualifications of contractors. However, the com-mission did not consistently use appropriate selection methods,establish progress schedules, and set reasonably detailed budgets.Figure 1 presents the results of our review of the commission’sdevelopment of these 25 contracts.

The commission did not always select its contractors appropri-ately. Of the 25 contracts we reviewed, 20 were not opened tocompetitive bidding because the commission claimed that theywere exempt. However, the commission did not have validreasons to exempt 5 of the 20 contracts from competition andthus should have used the competitive bid process. Withoutcompetitive bidding, the commission cannot ensure that it isreceiving the best value for its contracting dollar.

The commissiondid not use propermethods to selectcontractors, or establishadequately detailedprogress schedules orbudgets for somecontracts.

Page 13: California Public Utilities Commission

9C A L I F O R N I A S T A T E A U D I T O R

For example, one contract for $66,500 was not awarded bycompetitive bid because the commission invoked its authorityunder the Public Utilities Code, finding that extraordinarycircumstances justified the exemption. These extraordinarycircumstances, however, appear simply to have been a lack ofplanning on the part of the commission. The consultant washired to study the feasibility of “overlaying” a telephone areacode in Southern California rather than splitting up an existingarea code. Although the commission had started planning theoverlay as early as May 1998, it did not initiate the contractuntil January 1999, three months before the scheduled imple-mentation of the overlay. Rather than seeking competitive bids,the commission chose to use a consultant who had done previ-ous work for the commission.

The commission also did not always ensure that its contractsincluded reasonably detailed budgets and progress schedules.Of the 25 contracts we reviewed, 7 lacked reasonably detailedbudgets and 6 did not include progress schedules. For example,one commission contract with a consultant who providedexpert witness services in evaluating utility public safetyprograms included neither a budget nor a progress schedule.Although the commission established the contract inSeptember 1998 for $50,000, it amended the contract threetimes during fiscal year 1998-99, adding a total of $99,500 to

0 1 2 3 4 5 6 7 8

Include a reasonablydetailed budget

Identify progress schedules

Use appropriate selection method

Review the qualifications ofcontractors and subcontractors

Develop a detailed scopeof work to be performed

7

6

5

3

2

Number of contracts displaying weaknesses

FIGURE 1

Number of Contracts in Our Sample in Which theCommission Failed to Perform Key Steps

Extraordinarycircumstances cited bythe commission to justifynot using a competitivebid process to award onecontract appears simplyto be a lack of planning.

Page 14: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R10

the original amount. Each amendment was made to allow theconsultant to perform services in addition to those envisionedin the original contract.

Without a reasonably detailed budget and progress schedule, thecommission cannot adequately determine whether amendmentsto a contract are justified. Budgets ensure that contractorscontain costs within reasonable limits, and progress schedulesensure that contractors are on track and will be able to providethe services or products when the commission needs them.

ALTHOUGH THE COMMISSION MANAGED ITSCONSULTANTS’ WORK ADEQUATELY, ITSINCONSISTENT REVIEW OF INVOICES RESULTED INQUESTIONABLE PAYMENTS

Although in our review of 25 fiscal year 1998-99 contracts wefound that the commission generally monitored the workperformed under its contracts and ensured that the work met itsneeds, it did not always adequately review its contractors’invoices. The commission paid over $5 million on these25 contracts for work performed in fiscal year 1998-99. Due toinadequate review, the commission made at least $650,000 inquestionable payments to its consultants. Because the commis-sion receives most of its funding from fees assessed on utilitycompanies––which pass the costs on to the public––when itmakes improper payments the public ends up paying higherutility fees than necessary.

Good contract management ensures that the contractor issatisfactorily performing all services and receives paymentonly for services performed. The following are key elements ofeffective contract monitoring:

· Examining contractor work performance, for both quantityand quality, in relation to the contract terms and conditions.

· Reviewing requests for payment to ensure that payment isconsistent with the deliverables received as well as with theterms of the contract.

· Evaluating completed contracts to determine whethercontract objectives have been met.

The commission madeat least $650,000 inquestionable paymentsto its consultants.

Page 15: California Public Utilities Commission

11C A L I F O R N I A S T A T E A U D I T O R

One way an agency can make sure that a contract is monitoredeffectively is to designate a contract manager who acts as aliaison with the contractor and ensures that the contractor isfulfilling the agency’s needs. The contract manager must befamiliar with the services the contractor provides as well as withthe contract terms. For each of the 25 contracts we reviewed, thecommission designated a contract manager. Usually the contractmanager chosen was the staff member closest to the project, andthat person was involved in the contract from its developmentstages until its completion. This control helps the commissionverify that the contractor performs the work according to thecontract terms. A commission contract manager is also expectedto review and approve invoices that the contractor submits, thuspreventing the State from paying inappropriate charges.

Our review found that the contract managers generally main-tained contact with their contractors and were able to keepthem focused, ensuring that the commission received theproduct that it expected in the amount of time allowed.However, the contract managers did not always adequatelyreview invoices submitted by contractors. In fact, they did notdo so in 19 of the 25 cases we examined. One reason that wefound fault with the commission’s invoice review process is thatit did not establish guidelines to specify the level of detail thatits contractors’ invoices must contain. As a result, invoices wereviewed ranged from those containing detailed descriptions ofthe work being billed, cross-referenced to specific contractobjectives, to others providing no information other than themonth and amount being billed.

For example, one contract manager approved payments to aconsultant amounting to more than $650,000 during fiscal years1997-98 and 1998-99, even though the consultant did notprovide adequate supporting information for more than$350,000 of the amount. This consultant provided descriptionsof work performed by only a few of the participants in theproject and did not provide details or receipts for other expensessuch as travel costs, postage, and other administrative costs.More than $70,000 of the $350,000 in unsupported charges wasapproved for fiscal year 1998-99. This was not an isolatedexample. We found that for 14 of the 25 contracts we reviewed,the contract managers approved invoices for payment withoutgetting detailed descriptions of the work performed or support-ing documentation for consultants’ expenses. In total, theunsupported payments we noted in our sample of fiscal year1998-99 contracts amounted to more than $600,000.

In 19 of the 25 caseswe looked at, contractmanagers did notadequately review invoicesprior to payment.

Page 16: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R12

In addition, the contract managers did not always reviewinvoices adequately to ensure that payments were only forappropriate costs. As a result, the commission paid contractorsalmost $50,000 in charges that should not have been allowed.For example, the commission paid one contractor over $30,000more than the contract allowed for subcontractor markup fees,which a contractor charges to the commission to managesubcontractors for a project. In another example, the commis-sion reimbursed one contractor for first-class airfare, whichcost approximately $460 more than the typical coach fare forthe same flight.

The contract managers’ invoice reviews also failed to detectinaccuracies in invoices that included supporting information.In one case, because the commission did not follow the rulescontained in the State Administrative Manual, it overpaidanother state agency $10,900. In this instance, the commissiontemporarily used the services of an employee of another stateagency to assist the commission in its strategic planning.When the agency billed the commission, it included charges forvacation, sick leave, and holiday pay, although these amountswere already included in the hourly reimbursement rate. Thecontract manager did not detect this error and approved theinvoice. According to the commission, it requested and receivedreimbursement from the agency after we notified it of the error.

DESPITE THE BUREAU OF STATE AUDITS’ PREVIOUSSCRUTINY OF A PROBLEMATIC CONTRACT, THECOMMISSION OVERPAID THE CONSULTANT

In May 1999, we issued an audit report criticizing thecommission’s handling of a contract related to an investigationof the massive San Francisco power outage in December 1998. Inthe report, we recommended that the commission audit allcharges when the consultant submitted invoices to determinetheir appropriateness and compliance with contract provisions.Although the commission did review the invoices after theconsultant submitted them, the commission’s review was noteffective. Specifically, the commission did not require the con-sultant to invoice the State according to contract specifications.Rather, it accepted the consultant’s invoices and used threecommission staff members to prepare the state forms required toreimburse the contractor for out-of-pocket expenses, such as

The commission paid onecontractor over $30,000more in markup fees thanthe contract allowed.

Page 17: California Public Utilities Commission

13C A L I F O R N I A S T A T E A U D I T O R

meals and lodging. Despite this effort, the commission stilloverpaid the consultant by more than $12,500. Furthermore,the commission paid the consultant over $330,000 withoutadequately reviewing the invoices to ensure that it was payingfor proper services.

The Commission Did Not Require theConsultant to Submit Proper Invoices

Despite our recommendations and the likelihood that we wouldfurther scrutinize this contract, the commission did not requirethe consultant to comply with contract requirements wheninvoices were finally submitted. Specifically, the consultant didnot abide by state travel rules and regulations or reference thework order related to the services that were being billed. It isimportant that the commission address these weaknessesbecause on December 27, 1999, four days before the contractwith the consultant was to expire, the commission extended thecontract to include another year and an additional $110,000.This was done to allow the consultant to continue investigatingthe causes of the power outage. Specifically, the consultant willreview and analyze the utility’s rebuttals to the consultant’sMarch 1999 investigative report, address concerns arising fromany subsequent power outages, and assist commission staff inpreparing for commission hearings on the power outage.

Our previous audit reported that the consultant had notyet submitted an invoice for the first four months of thecontract term, even though the contract required monthlyinvoicing. The consultant did finally submit to the commissionsix invoices covering various periods between January andJune 1999. However, the consultant’s invoices did not complywith contract provisions. For example, one invoice included ahotel bill for almost $290 a night, three times the allowable rateof $79 a night. In addition, the consultant did not use therequired state expense report form and did not include receiptsfor many of the claimed items, even though state rules requirethem. Furthermore, although the contract required the consult-ant to reference the task related to each claimed expense, thecommission did not enforce this requirement. The commissionneeds this information to ensure that claimed expenses arereasonable. Finally, the consultant resubmitted an invoice formore than $14,000 that the commission had previouslydisallowed because it lacked supporting information. Thecommission paid this invoice, even though expenses totaling$3,700 were still unsupported.

The commission did notrequire the consultant toabide by state travel rulesor reference the workorder related to theservices being billed.

Page 18: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R14

The Commission Used Its Staff to Review the Invoices andPrepare the Proper Forms Yet Still Overpaid the Consultant

Rather than insisting that the consultant submit invoices thatcomplied with state rules and regulations, as required by thecontract, the commission dedicated more than 80 hours ofstaff time to review the invoices and expenses and fill out theproper expense claim forms for the consultant. The commissionassigned three auditors from its water division to review theinvoices and supporting documentation and then prepare travelexpense claims for the consultant. The auditors were to reviewthe expenses claimed by the consultant, determine the extent towhich they were reimbursable under state rules and regulations,and then prepare an expense claim on the standard state formrequired under the contract.

Even though its own auditors prepared the expense claims,the commission overpaid the consultant more than $12,500for such expenses as lodging that exceeded allowable rates,airfare for which no receipt was provided, and payments forservices for which the consultant had not billed. In addition,the commission reimbursed the consultant for meals notclaimed on any invoice. The auditors explained to us thatbecause the commission disallowed more than $20,000 inexpenses claimed on one of the consultant’s invoices, theyfelt compelled to pay the maximum amounts allowable formeals and incidentals, even though the consultant did notalways claim these costs. The consultant’s receipts did notcontain sufficient detail for us to determine the actual amountof unclaimed expenses the commission paid, but we estimate itto be at least $2,500 of the total $12,500 overpayment.

Moreover, the commission’s contract managers did not ad-equately review the consultant’s invoices. Rather, the commis-sion relied on its auditors’ review. As a result, the commissionpaid the consultant more than $330,000, or 85 percent of theinvoiced amounts, without adequate review to ensure that itwas paying for proper services. The commission used its auditorsso a more detailed review of the invoices could be performed.Although commission auditors may have the training needed toreview the out-of-pocket expenses included on the consultant’sinvoices, they do not have the expertise necessary to determinewhether the consultant’s time charges complied with contractprovisions. The contract managers would have been best suitedfor this review because of their frequent and direct contact withthe consultant.

Even though its ownauditors prepared theexpense claims, thecommission overpaida consultant morethan $12,500.

Page 19: California Public Utilities Commission

15C A L I F O R N I A S T A T E A U D I T O R

A COMMISSION CONTRACT WAS NOT SUBJECTTO SUFFICIENT CONTROLS

During our review of the commission’s contracts, we learnedthat several contracts related to consumer education, includingone for a program called Near Term Effort, were not subject tothe State’s usual contracting process. Selecting the consultantsand developing the scopes of work for most of these contractswere not done by the commission but by advisory panels com-prising industry representatives and other interested parties.Therefore, we did not review this type of contract.

In the case of the Near Term Effort program, however, thecommission, not an advisory panel, developed the scopes ofwork, selected the contractors, and reviewed and approvedinvoices. Therefore, we did review this program. The Near TermEffort program was a short-term effort to educate the publicabout options available to them under the deregulation of theelectric industry. It was intended to bridge the gap between twoother similar education efforts that were administered by advi-sory panels. We found that the commission’s contracts for thisprogram did not receive proper oversight, and consultants underthese contracts received payments before they provided services.

The Commission Has Several Contracts That AreNot Subject to the State’s Standard Contracting Process

The commission is involved in many programs, usuallyfocusing on consumer education activities, that are carried outby consultants hired outside the state contracting process. Thecommission authorizes the establishment of the programs andapproves their objectives, but the contracts are usually adminis-tered by advisory panels consisting of independent members,such as industry and consumer representatives. Utility compa-nies are often required, sometimes by the commission andsometimes by statute, to provide consumer education programswhen significant changes occur in the utility marketplace. Thecontracts for services needed by the programs are between theaffected utilities and the consultants, and payments are madedirectly by the utilities.

When the commission authorized the Near Term Effortprogram, it gave its Consumer Services Division (division) theresponsibility for developing a plan to continue educatingthe public regarding deregulation of electrical utilities. Thecommission gave this responsibility to the division because the

The Near Term Effortbridged the gap betweensimilar consumereducation programs.

Page 20: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R16

advisory panel that was to continue the education effort wasnot yet ready to administer the program. The Near Term Effortprogram was to bridge the gap between a similar educationprogram that concluded in May 1998, and another that was notready to begin until early 1999. The commission required theutilities––Pacific Gas and Electric, San Diego Gas and Electric,Southern California Water Company, and Southern CaliforniaEdison––to provide the almost $6 million needed to fund theNear Term Effort program from amounts that remained from theprogram that concluded in May 1998. The division selectedthree contractors to carry out the program.

The Commission Did Not Maintain Adequate ControlOver the Contracts for the Near Term Effort Program

Although the division developed the scopes of work, selectedthe contractors, and reviewed and approved invoices for theNear Term Effort program contracts, the actual contracts werebetween the consultants and the utilities and thus did notundergo the reviews and approvals involved in the normal statecontracting process. In addition, payments were not madethrough the commission’s accounting system. Rather, the divi-sion approved the invoices and forwarded them to the utilities,which in turn paid the consultants. Figure 2 depicts the differ-ences between the Near Term Effort program and the programsadministered by advisory panels.

The division’s administration of these contracts created anenvironment in which abuses could easily go undetected. Forexample, a commission employee could have created andapproved an invoice payable to him- or herself and forwardedit to the utilities for payment. Lacking any administrative func-tion in the program, and seeing that the employee hadapproved the payment, the utilities would likely have paidthe invoice. Moreover, because of the commission’s broadpowers over the utilities, the utilities may have been reluctantto question the employee’s approval of the payment.

Although we did not find such fraudulent activity, we did findinstances in which the division approved unearned payments.For example, in December 1998, the division authorized––andthe utilities paid––an invoice for almost $2 million to oneconsultant, even though the consultant had not yet incurred thecosts being billed. In fact, the contract had not yet been signedwhen the division approved the payment. In addition, thedivision approved––and the utilities paid––a contractor’s fee

The commissionauthorized a $2 millionpayment to oneconsultant without avalid contract.

Page 21: California Public Utilities Commission

17C A L I F O R N I A S T A T E A U D I T O R

FIGURE 2

Differences Between the Administration of the NearTerm Effort Program and Programs

Administered by Advisory Panels

7

Commission authorizes program

Commission authorizes program

Advisory Panel develops scopeof project, selects consultants,

and reviews invoices

Consumer Services Divisiondevelops scope of

project, selects consultants, and reviews invoices

Utilities sign contract withselected consultants and pay

approved invoices

Utilities sign contract withselected consultants and pay

approved invoices

Other ProgramsNear-Term Effort

Difference in Administration

totaling $233,000 for work performed before the commissionershad approved the Near Term Effort plan. One reason thesepayments were allowed might have been that the divisiondelegated the detailed review of invoices and supporting docu-mentation to one consultant with whom it had contracted forthe project. Because the division itself did not review the sup-porting documents, it was not able to ascertain whether theinvoices it approved were adequately supported. Had thesecontracts and payments been made within the State’s normalsystem of controls, the improper payments might have beencaught before they were made. More importantly, the contractswould have been exposed to a set of internal controls thatwould be more likely to detect any improper activities.

THE COMMISSION’S INTERNAL AUDIT OF ITSCONTRACTING PRACTICES FOUND WEAKNESSESSIMILAR TO THOSE WE HAVE IDENTIFIED

In response to our May 1999 report, the commission undertookan internal audit of its consultant contracting process. In itsreport issued in September 1999, the commission identifiedissues similar to several of those we discuss earlier in this report.

Page 22: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R18

For example, it found that the commission had inadequatecontrols for selecting consultants in contracts that are exemptfrom competitive bidding requirements, did not alwayspromptly identify selection criteria, and did not clearly identifycommission staff responsible for monitoring consultant travelexpenses. The commission characterized most of its auditors’recommendations as either issues that could be addressed byapplying existing procedures more consistently or issues thatit must address by developing new procedures. The appendixpresents a list of the 27 recommendations contained inthe internal audit report and how the commission plans toimplement them.

The commission’s executive director stated that the commissionwould implement all the recommendations contained inits internal audit report. As shown in the appendix, thecommission is implementing most of the recommendationsby developing a contracting policy and procedures manual.According to the commission, it will provide this manual to allmanagement and staff involved in the procurement of consult-ing contracts. Other recommendations, such as making legalcounsel available to the contracts officer and training contractmanagers, are being addressed by other commission actions.

The internal audit reported that one cause of the weaknesses inthe commission’s contracting practices is the inexperience andlack of training of its contract managers. The commission’sauditors found that none of the managers of the 13 contractsthey reviewed had any formal contract management training,and half had no contract management experience. Anotherreason given for the weaknesses was the lack of establishedauthority of the commission’s contracts officer, who is respon-sible for ensuring that the commission follows state contractingguidelines. The auditors noted that if a contract manager did notagree with the contracts officer on a contracting issue, thecontracts officer would defer to the contract manager andprocess the contract anyway because there was no recourse.

Although the commission’s initial response to the recommenda-tions appears adequate, many of its actions are not yet complete.For example, the contracting policy and procedures manualhas not yet been finalized and distributed, and not all of thecontract managers and other staff involved in the commission’scontracting process have received training in managing con-tracts. The commission should continue its efforts to strengthen

The commission says itwill implement all of therecommendationscontained in its internalaudit report.

Page 23: California Public Utilities Commission

19C A L I F O R N I A S T A T E A U D I T O R

its contracting practices and ensure that it fully addresses theconcerns raised in the internal audit.

RECOMMENDATIONS

To ensure that it properly develops and manages its contracts,the commission should take these actions:

· Include reasonably detailed budgets and progress schedulesin its contracts.

· Solicit competitive bids for contracts whenever possible.

· Establish a policy requiring a minimum level of detail forconsultant invoices prior to payment.

· Require contract managers to review charges and expensescontained in consultant invoices to ensure that only properpayments are made.

The commission should determine whether it has overpaidconsultants who did not provide adequate supporting informa-tion for amounts invoiced to and paid by the commission andrecover any overpayments.

The commission should reanalyze the invoices submitted by theconsultant that investigated the 1998 San Francisco poweroutage and recover amounts that were inappropriately paid tothe consultant.

The commission should provide all contractors with state travelguidelines and require its consultants to prepare expense claimson the standard state forms, following state guidelines, so that itcan quickly determine if claimed costs are allowable.

The commission should use the State’s contracting process for allcontracts that it develops or manages, including contracts forconsumer education programs.

The commission should continue to implement the recommen-dations contained in the internal audit report on its consultantcontracting process.

Page 24: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R20

We conducted this review under the authority vested in the California State Auditor bySection 8543 et seq. of the California Government Code and according to generally acceptedgovernment auditing standards. We limited our review to those areas specified in the auditscope section of this report.

Respectfully submitted,

MARY P. NOBLEActing State Auditor

Date: March 16, 2000

Staff: Ann K. Campbell, CFE, Audit PrincipalDavid E. Biggs, CPABryan BeyerPeter A. Foggiato, IIIRyan Storm

Page 25: California Public Utilities Commission

21C A L I F O R N I A S T A T E A U D I T O R

APPENDIXHow the Commission IsImplementing RecommendationsFrom Its Own Internal Audit of ItsContracting Practices

Recommendation Implementation

1. Clarify and strengthen contracts officer’s role. Included in draft policy andprocedures manual (PPM).

2. Establish an internal dispute resolution process. Included in PPM.

3. Assign legal counsel to contracts officer. Legal staff made available.

4. Establish a process to determine type of contract to use. Included in PPM.

5. Develop standard forms. Included in PPM.

6. Develop procedures for contracts exempt fromcompetitive bidding. Included in PPM.*

7. Interview at least five consultants for contractsexempt from bidding. Included in PPM.

8. Include member from outside division in selection panels. Included in PPM.*

9. Get commission authorization for contracts exemptfrom bidding prior to start. Included in PPM.

10. Provide contract managers with training in contractmanagement. Training in progress.

11. Select an experienced contract manager toassist others in each division. Included in PPM.*

12. Develop a contract manager handbook. Included in PPM.

13. Obtain guidance on how best to estimatecontract prices. Included in PPM.*

14. Ensure that clear selection criteria areprovided to potential consultants. Included in PPM.

15. Have contract managers complete evaluationsof consultants. Included in PPM.

16. Check for negative evaluations prior toselecting consultant. Included in PPM.*

* These items were not addressed in the initial version of the policy and procedures manual that the commission provided to us.The commission subsequently advised us that it has added these items to the manual.

Page 26: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R22

Recommendation Implementation

17. Implement records management requirements fromState Contracts Manual. Included in PPM.*

18. Ensure that work plans are developed atbeginning of contract. Included in PPM.

19. Develop records retention policies. Included in PPM.*

20. Clarify level of detail that consultantinvoices must contain. Still developing response.

21. Provide state travel guidelines to consultants. Included in PPM.*

22. Provide utilities with detailed invoices for reimbursement. Included in PPM.

23. Determine need for extension prior to end of contract. Included in PPM.

24. Notify contract manager before disencumbering funds. Included in PPM.*

25. Train commissioners and administrative law judges PPMs will be provided to(ALJs) in contracting time requirements. commissioners and ALJs.

26. Perform cost-benefit analysis of hiring staff rather Directors will do this as part ofthan contracting. the planning process.

27. Have legal division determine legality of requiring a Commission will determineutility to enter into a contract on behalf of the commission. on a case-by-case basis.

* These items were not addressed in the initial version of the policy and procedures manual that the commission provided to us.The commission subsequently advised us that it has added these items to the manual.

Page 27: California Public Utilities Commission

23C A L I F O R N I A S T A T E A U D I T O R

Agency’s comments provided as text only.

Public Utilities Commission505 Van Ness AvenueSan Francisco, CA 94102-3298

March 7, 2000

Mary P. NobleActing State AuditorBureau of State Audits555 Capitol Mall, Suite 300Sacramento, CA 95814

Dear Ms. Noble:

Thank you for the opportunity to respond to the draft report, “CaliforniaPublic Utilities Commission: Weaknesses in its Contracting Process HaveResulted in Questionable Payments”, received on March 1, 2000. While thelimited comment period does not allow for a formal Commission response, ingeneral, I do not dispute the criticisms contained in your draft. I appreciatethat you recognize we are working toward improving our contracting pro-cess. I concur with your recommendations.

Based on our exit interviews with your staff, a large part of the problemappears to be with insufficiently supported work products as opposed tounsupported work products. Going forward, Contract Development andManagement training will be mandatory for Contract Managers and will bedesigned to capture all of the recommendations of the State Auditor’s con-cerns. We are working with the Department of General Services to put onseveral sessions of training before the end of March 2000.

In addition, we are implementing your recommendations as detailed below:

Recommendation 1:

“To ensure that it properly develops and manages its contracts, the commissionshould take these actions:

· Include reasonable budgets and progress schedules in its contracts.· Solicit competitive bids for contracts whenever possible.· Establish a policy requiring a minimum level of detail for consultant

invoices prior to payment.· Ensure that contract managers review charges and expenses contained

in consultant invoices to ensure that only proper payments are made.”

Page 28: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R24

We implemented this recommendation for all new contract proposals.Our draft Policy and Procedures Manual (PPM) addresses each ele-ment of this recommendation. For contracts in progress, each Con-tract Manager will ensure that the budget, progress schedules andinvoices comply with this recommendation. Contract managers mustuse the competitive bid process; exceptions will require approval ofthe Executive Director.

Recommendation 2:

“The commission should determine whether it has overpaid those consultants thatdid not provide adequate supporting information for amounts invoiced to and paidby the commission and, if so, should recover the overpayments.”

We are reviewing all current contracts in progress. Where consultantshave been overpaid, we are requesting reimbursements from them.Where contractors have not provided sufficient supporting informa-tion, we are requesting it and will review it to justify payments. We willrecover any overpayments to contractors.

Recommendation 3:

“The commission should reanalyze the invoices submitted by the consultant thatinvestigated the 1998 San Francisco Power outage and recover amounts that wereinappropriately paid to the consultant.”

The San Francisco power contract is currently being reviewed by theExecutive Director, including all invoices already submitted. We willrecover any amounts not justified, including travel expense claims.The Commission’s General Counsel will assume the role of contractmanager for this consulting contract and all future invoices will beapproved by the Executive Director.

Recommendation 4:

“The commission should provide all contractors with state travel guidelines andrequire its consultants to prepare expense claims on the standard state forms,following state guidelines, so that it can quickly determine if claimed costs areallowable.”

Page 29: California Public Utilities Commission

25C A L I F O R N I A S T A T E A U D I T O R

The Commission has provided all current contractors with state travelguidelines and now requires contractors to utilize the state guidelinesand forms for expense recovery.

Recommendation 5:

“The commission should use the State’s contracting process for all contracts that itdevelops or manages, including contracts for consumer education programs.”

The Commission will use the State’s contracting process for all con-tracts it develops or manages, including contracts for consumer edu-cation programs. In addition, the Commission will review its policiesand options for strengthening contract oversight for advisory boardsand committees.

Recommendation 6:

“The Commission should continue to implement the recommendations contained inits own internal audit report on its consultant contracting process.”

The Commission will continue to implement the recommendations ofits own internal audit, including the distribution of a Contracts Policiesand Procedures Manual. A second draft of this manual has beencompleted and will be finalized for distribution on March 15, 2000.

Thank you for this opportunity to provide a written response to your draft, to beincluded in your final report.

Very truly yours,

(Signed by: Wesley M. Franklin)

Wesley M. FranklinExecutive Director

Page 30: California Public Utilities Commission

C A L I F O R N I A S T A T E A U D I T O R26

cc: Members of the LegislatureOffice of the Lieutenant GovernorMilton Marks Commission on California State Government Organization and EconomyDepartment of FinanceAttorney GeneralState ControllerState TreasurerLegislative AnalystSenate Office of ResearchCalifornia Research BureauCapitol Press