STATE OF CALIFORNIA – NATURAL RESOURCES AGENCY EDMUND G. BROWN JR., Governor
June 28, 2013 Brian Harms General Manager Bottle Rock Power, LLC 7385 High Valley Road P.O. Box 326 Cobb, CA 95426 Kristen T. Castaños Stoel Rives, LLP 500 Capitol Mall, Suite 1600 Sacramento, CA 95814 John A. McKinsey Locke Lord LLP 500 Capitol Mall, Suite 1800 Sacramento, CA 95814 RE: BOTTLE ROCK GEOTHERMAL PROJECT AMENDMENT (79-AFC-4C) DATA REQUEST SET 1 (NOS. 1-5) Dear Mr. Harms: The California Energy Commission (Energy Commission) staff has reviewed the Bottle Rock Power, LLC’s, (BRP) Petition to Amend (PTA) and Decommissioning Cost Estimate for the Bottle Rock Geothermal Power Plant (power plant) and requires additional information to supplement the environmental analysis pursuant to Title 20, California Code of Regulations, section 1769(a)(1)(E). For the purposes of this data request the terms “closure” and “decommissioning” are synonymous. Energy Commission staff seek the information specified in the enclosed data requests. The information requested is necessary to: 1) more fully understand the scope and costs associated with the potential closure of the power plant; 2) assess the potentially significant and difficult to mitigate impacts that could result from an early or worst case closure scenario; and 3) assess potential mitigation measures. Staff requests data in the areas of General Conditions (No. 1), and a consolidated data request for Hazardous Materials, Waste Management, Worker Safety, Geology, Soil and Water Resources, and Biological Resources (Nos. 2-5) related to the BRP’s decommissioning cost estimate. Staff requests that written response to the enclosed data requests be provided on or before July 29, 2013. Staff encourages the Applicant to submit responses sooner if possible to facilitate the schedule.
CALIFORNIA ENERGY COMMISSION 1516 NINTH STREET SACRAMENTO, CA 95814-5512 www.energy.ca.gov
DOCKETEDCalifornia Energy Commission
JUN. 28 2013
TN 71454
79-AFC-4C
Mr. Harms, et al June 28, 2013 Page 2 If you are unable to provide the information requested, need additional time, or object to providing the requested information, please send a written notice to both the Committee and me within 20 days of receipt of this data request. The notification should contain an explanation of why the information will not be provided and the grounds for any objections. If you have any questions, please call me at (916) 654-3940, or email me at [email protected].
Sincerely, CAMILLE REMY OBAD Compliance Project Manager
Enclosure Data Requests
June 2013 1 General Conditions Data Requests Set 1
BOTTLE ROCK GEOTHERMAL PROJECT AMENDMENT (79-AFC-4C) DATA REQUESTS SET 1
Technical Area: (General Conditions) Compliance Authors: Camille Remy Obad
BACKGROUND: DECOMMISSIONING FINANCIAL ASSURANCES
As discussed in the California Energy Commission’s April 2007 Geothermal Permitting Guide, “facility closure refers to the process to officially discontinue the use of a power plant”. Licensees must go through an Energy Commission process for closure to assure that public health and safety and the environment are protected while decommissioning takes place, and for long term issues such as site stability, habitat restoration, and reclamation of the property. The extent of the site restoration and reclamation will be site specific, determined by staff and the Compliance Project Manager (CPM) on a case-by-case basis. Staff recognizes the petitioner’s proposal to submit detailed closure and site contingency plans for Compliance Project Manager’s (CPM) comment and approval ninety days after the Energy Commission’s final decision and adoption of the PTA. However, presently there is no discussion of how BRP, LLC will provide a readily available financial assurance mechanism to mitigate the potential impacts of an early (or “worst case”) closure scenario.
DATA REQUEST 1. Please provide a detailed description of alternative financial assurance
mechanisms, other than that proposed in your PTA, that would allow the Energy Commission (as the beneficiary) to access, within 30 days, the total amount of the CPM approved closure cost estimate and closure plan.
Consolodated Technical Areas 2 June 2013 Data Requests Set 1
BOTTLE ROCK GEOTHERMAL PROJECT AMENDMENT (79-AFC-4C) DATA REQUESTS SET 1
Technical Areas: Hazardous Materials, Waste Management, Worker
Safety, Geology, Soil and Water Resources, Biological Resources
Authors: Paul Marshall; Marylou Taylor, Ed Brady, Casey Weaver; and Amy Golden
BACKGROUND
On April 15, 2013 Bottle Rock Power submitted the Bottle Rock Power Plant Decommissioning Estimate prepared by Plant Reclamation. Staff’s preliminary review of the decommissioning estimate evaluated its adequacy to fund a closure with respect to proper disposal of hazardous and non-hazardous waste, worker safety, geological hazards, and protecting soil and water resources. This was done by reviewing of scope identified activities included in the estimate. Staff did not evaluate the individual costs of each activity. Staff made the following assumptions:
• Staff only considers the project footprint to include elements within the fence line, including the switchyard where the transformers are located (point of interconnection).
• Closure could occur anytime between now and the next 3 years.
• Closure is considered demolition and removal of everything except for the turbine generator plant building, water treatment and storage building, and perimeter access roads (which would require ongoing cost of maintenance and security, until an alternative use is implemented).
• The scope of near term closure must be sufficient to ensure there would be no environmental harm.
Staff believes that the decommissioning estimate of $1,875,000 dated April 15, 2013 may not adequately fund a closure in the near term. Page 2 of the estimate lists a number of assumptions identified when developing the estimate. The list includes items that are not incorporated into the cost estimate, because specific activities would be the responsibility of the project owner rather than the reclamation contractor. In addition, anticipated salvage values have been adequately verified.
DATA REQUEST 2. Please update the decommissioning estimate to include the following items which
are necessary to ensure potential environmental impacts can be mitigated:
• Include all hazardous waste testing, sampling, profiling, transportation and disposal costs
June 2013 3 Consolodated Technical Areas Data Requests Set 1
• Costs for grading, re-surfacing, and stabilization of exposed site soils (only backfill of pits, voids and basins was included in the estimate)
• Costs for non-hazardous waste transportation and disposal offsite
• Costs to remove all building utilities unrelated to the buildings that will remain(such as electrical and fire protection)
• Costs for permits and authorizations, such as modification of the Storm Water Pollution Prevention Plan(SWPPP), Section 401 Water Quality Certification and Regional Board Waste Discharge Requirements, and California Department of Fish and Wildlife Section 1600 Streambed Alteration Agreement (only California Occupational Health and Safety Administration (CalOSHA) and Air Quality permits were included in the estimate)
• Costs to remove the transformers
• Costs to remove underground equipment (pipes, valves, etc) within the fence line that are not associated with maintenance and future use of the buildings and access roads
• Costs to maintain stormwater drains within the fence line
• Costs to install or enhance erosion control measures (jute netting, straw waddles, etc) along southern and western fence line to control intermittent drainage1
• Costs to perform pre-demolition biological surveys, presence of an approved biological monitor, and any other measures to avoid or minimize the potential for impacts to nesting or foraging wildlife or offsite rare plant occurrences (such as dust abatement) during demolition activities.
• Costs for maintenance and security of the facility
3. If salvage value for metal waste is to be considered, the net value must be calculated after including the cost for loading and transportation costs.
4. If the salvage value of the turbine generator equipment is to be included, an
independent cost estimate from a salvage company qualified to assess the value should be provided.
BACKGROUND In the heavily redacted version of the “Amended and Restated Geothermal Lease and Agreement” dated July 25, 2012 between V.V.J. Coleman, LLC and Bottle Rock Power, LLC., item 8, Security; Damages Resulting From Lessee’s Operations is completely obscured. While it is unknown what was redacted from that section, any “damages resulting from lessee’s operation” on the physical setting of the site could have financial implications on the restoration of that site. While demolition of above ground and below
1 The Geyers 7.5-minute USGS topographic map identifies this feature as an intermittent drainage that is tributary to High Valley Creek. This drainage is identified as Cow Creek in various Bottle Rock environmental documents.
Consolodated Technical Areas 4 June 2013 Data Requests Set 1
ground structures and subsequent site rehabilitation can be estimated, costs for restoration of unknown “damages” is impossible. It is important that any damages known by the owner be disclosed if they have an impact on the cost for site restoration.
DATA REQUEST 5. Please provide a description of the damages contained in item 8 indicated above.
If the damages physically affect the site, please identify the nature, importance, volume and threat to the environment/personnel that would be exposed to the damage in the course of site restoration.
BEFORE THE ENERGY RESOURCES CONSERVATION AND DEVELOPMENT COMMISSION OF THE STATE OF CALIFORNIA
1516 NINTH STREET, SACRAMENTO, CA 95814 1-800-822-6228 - WWW.ENERGY.CA.GOV
DOCKET No. 79-AFC-04C
PROOF OF SERVICE
BOTnEROCKGEOTHERMAL POWER PLANT AMENDMENT
(REVISED 06/17/2013)
SERVICE LIST:
PETITIONERIPROJECT OWNER COMPLAINANT'S AND FRIENDS Douglas Gearhart Bottle Rock Power, LLC OF COBB MOUNTAIN'S Air Pollution Control Officer Brian Harms COUNSEL Lake County AQMD General Manager Donald B. Mooney 885 Lakeport Boulevard 7385 High Valley Road 129 CStreet, #2 Lakeport, CA 95453 P.O. Box 326 Davis, CA 95616 [email protected] Cobb, CA 95426 [email protected] [email protected] "Friends of Cobb Mountain
INTERESTED AGENCIES c/o Hamilton Hess PROJECT OWNER'S COUNSEL California ISO 255 Ursuline Road Kristen T. Castafios [email protected] Santa Rosa, CA 95403 Stoel Rives, LLP 500 Capitol Mall, Suite 1600 Sacramento, CA 95814 [email protected]
John A. McKinsey Locke Lord LLP
Department of Water Resources John Dunnigan Senior Staff Counsel 1416 Ninth Street, Room 1104 Sacramento, CA 95814 [email protected]
ENERGY COMMISSION STAFF Camille Remy Obad Compliance Project Manager "Siting, Transmission and Environmental Protection Division
500 Capitol Mall, Suite 1800 Sacramento, CA 95814 [email protected]
Department of Conservation Division of Oil, Gas, & Geothermal Resources
1516 Ninth Street, MS-2000 Sacramento, CA 95814-5512 [email protected]
PROJECT LANDOWNER V.V. &J. Coleman LLC c/o Mark Peterson Diepenbrock Elkin LLP 500 Capitol Mall, Suite 2200
Elizabeth Johnson Geothermal Officer 801 KStreet, MS 20-20 Sacramento, CA 95814 [email protected]
Richard Ratliff Staff Counsel "Office of the Chief Counsel 1516 Ninth Street, MS-14 Sacramento, CA 95814-5512
Sacramento, CA 95814 [email protected]
COMPLAINANT (in related case 12-CAI-04) David Coleman 3733 Canon Avenue Oakland, CA 94602 [email protected]
Lake County Community Development Department Planning Division c/o Will Evans Richard Coel 255 North Forbes Street Lakeport, CA 95453 [email protected] [email protected]
Kevin W. Bell Staff Counsel "Office of the Chief Counsel 1516 Ninth Street, MS-14 Sacramento, CA 95814-5512 [email protected]
"Indicates change
ENERGY COMMISSION PUBLIC ADVISER Blake Roberts Assistant Public Adviser *Public Adviser's Office 1516 Ninth Street, MS·12 Sacramento, CA 95814·5512 [email protected]
COMMISSION DOCKET UNIT California Energy Commission . Docket Unit Attn: Docket No. 79-AFC-04C 1516 Ninth Street, MS-4 Sacramento, CA 95814·5512 [email protected],gov
OTHER ENERGY COMMISSION PARTICIPANTS (LISTED FOR CONVENIENCE ONLY): After docketing, the Docket Unit will provide a copy to the persons listed below. Do not send copies of documents to these persons unless specifically directed to do so.
KAREN DOUGLAS Commissioner and Presiding Member
JANEASCOTT Commissioner and Associate Member
Paul Kramer Chief Hearing Adviser
Galen Lemei Adviser to Presiding Member
Jennifer Nelson Adviser to Presiding Member
Jim Bartridge Adviser to Associate Member
Eileen Allen Commissioners'Technical Adviser for Facility Siting
2
X
__ ... ~--..
DECLARATION OF SERVICE
I, _Camille Remy Obad ,declare that on June 28, 2013, I served and filed copies of the attached _Bottle Rock Geothennal Project Amendment (79-AFC-4C) Data Request Set 1(Nos. 15)_ dated _June 28, _, 2013. This document is accompanied by the most recent Proof of Service, which I copied from the web page for this project at: http://www.energy.ca.gov/sitingcases/bottlerock/.
The document has been sent to the other persons on the Service List above in the following manner:
(Check one)
For service to all other parties and filing with the Docket Unit at the Energy Commission:
I e-mailed the document to all e-mail addresses on the Service List above and personally delivered it or deposited it in the US mail with first class postage to those persons noted above as "hard copy required"; OR
Instead of e-mailing the document, I personally delivered it or deposited it in the US mail with first class postage to all of the persons on the Service List for whom a mailing address is given.
I declare under penalty of perjury under the laws of the State of California that the fOreaOllJQ-ftHW that I am over the age of 18 years.