Guidelines for Preparing for a Temporary Steam Plant Nationwide Boiler, Inc.
![Page 2: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/2.jpg)
Agenda • Level of Preparedness • Reasons for Temporary Steam Plant
• Planning Stages • Qualifying a Rental Boiler Company
• Common Questions
• Equipment Offerings • Site Considerations • Advantages • Lessee/Lessor Scope • 5 - Reasons • Questions & Answers
![Page 3: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/3.jpg)
Are You Prepared for Possible Steam Interruptions?
• Management expects 24/7 operations. • Contingency plans in place? • Temporary tie-ins installed? • Adequate insurance coverage? • What is the loss of production worth? • How long can operations last without steam? • Rental boiler company?
![Page 4: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/4.jpg)
Reasons for a Temporary Steam Plant
Unplanned Outages
Planned Outages
Peak Loads
DelaysBringing
New Plant On-line
![Page 5: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/5.jpg)
Unplanned Outage: World Trade Center • Reason: 20” main steam line severed as a result of
WTC collapsing.
• Problem: Buildings nearby were left without heat.
• Solution: 2- 70,000 lb/hr trailer-mounted boilers and 140,000 lb/hr mobile feedwater van.
• Timing: Delivered, brought on-line, and operational in a matter of days.
![Page 6: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/6.jpg)
Unplanned Outage: World Trade Center
![Page 7: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/7.jpg)
Unplanned Outage: Ferndale, WA • Reason: Freeze damage to boiler sensing lines and
controls.
• Problem: Refinery operating with reduced capacity.
• Solution: 1- 120,000 lb/hr trailer-mounted boiler.
• Timing: 4-day delivery from CA, brought on-line, and operational in 10-days.
![Page 8: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/8.jpg)
Unplanned Outage: Ferndale, WA
![Page 9: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/9.jpg)
Planned Outages
![Page 10: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/10.jpg)
Planned Outages
![Page 11: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/11.jpg)
Increased Capacity: Seasonal Peak Load Paper Mill - Pomona, CA
• 120,000 lb/hr Nebraska Boiler • 400 psi design sat. • Low NOx Burner • CataStak™ SCR System • 5 PPM NOx
![Page 12: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/12.jpg)
Increased Capacity: Seasonal Peal Loads
District Heating - San Francisco, CA
• 70,000 lb/hr Nebraska Boiler • 400 psi design sat. • Low NOx Burner • CataStak™ SCR System • 5 PPM NOx
![Page 13: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/13.jpg)
New Plant Delays (Antonov Delivery) • Reason: New LNG plant in Australia
• Problem: Lost production
• Solution: 2 boilers needed for continued process steam
• Timing: 3 day delivery on the Antonov aircraft
![Page 14: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/14.jpg)
Planning Stages
1. Identify SteamRequirements
• capacity • operating press. • steam temp
(saturated orsuperheat)
• fuel type
2. Rental Duration
• 1 month • 3 month • 6 month • 12 month plus
3. Delivery Timing
• weekday vs.weekend
• winter vs. summer months
![Page 15: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/15.jpg)
Winter Installation:
Eielson AFB, Fairbanks, AK 140,000 lb/hr Temporary Steam Plant
![Page 16: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/16.jpg)
Planning Stages 4. Locate Utility
Tie-ins
• fuel • treated feedwater • boiler c hemicals • electrical • steam • blow dow ns • instrument air
5. Air Permits continued
• varies with AQMD• permit to
construct• permit to operate
• permit details:timingcostsource testvariances
![Page 17: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/17.jpg)
![Page 18: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/18.jpg)
Planning Stages
continued continued 6. Miscellaneous
• boiler placementand foundations
• review and implement a HAZOP procedure
• requestdescriptions and drawings fromequipmentsupplier
• Implement a Master Rental Agreementbetween Lessor & Lessee
![Page 19: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/19.jpg)
Qualifying a Rental Boiler Company How long have they been in business?
Types of boilers offered?
Do they offer rental / purchase / lease-buy?
Availability and when can they deliver?
Rental term / duration (price points)?
Offer ancillary equipment?
Offer turn-key services?
![Page 20: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/20.jpg)
Qualifying a Rental Boiler Company Ask for references?
Are there guarantees?
Where is the service support out of?
What is the age and condition of the rental boiler?
What is required from the Lessee to obtain a boiler rental?
Do the boilers meet Cal Code and ultra low Nox emission requirements?
![Page 21: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/21.jpg)
Qualifying a Rental Boiler Company
Does the rental company have insurance coverage?
The size of the rental fleet?
What is their safety record?
Do they have any pre-permitted units?
Are renting boilers their primary business, or just a sideline activity?
![Page 22: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/22.jpg)
Common Questions How long since the boiler was last inspected and tested?
When do rental charges begin and end?
Are rental charges suspended if the boiler fails?
What equipment and supplies are included in rental charges?
Are start up charges included or additional?
Certificates of Insurance?
![Page 23: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/23.jpg)
Common Questions (continued) Who provides the oil pump/tanks?
Who supplies the gas regulator?
Who provides the forced draft fan?
Who provides the smokestacks / EPA ports?
Who pays the freight?
Who makes freight arrangements?
![Page 24: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/24.jpg)
Common Questions (continued)
Who provides the hookup?
Who supplies the utilities?
What about feedwater treatment?
How should boilers be operated?
How about disconnecting?
How is boiler to be prepared for shipment?
Who pays for the loading / unloading?
![Page 25: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/25.jpg)
Equipment Offerings • Mobile / Stationary Steam Plants • Trailer-Mounted Watertube Boilers • Package Boilers In Stock • Water Treatment Equipment • Environmental Solutions
– CataStakTM SCR Systems
• Heat Recovery Solutions – EconoStak Economizers
![Page 26: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/26.jpg)
Equipment Offerings (continued)
![Page 27: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/27.jpg)
Equipment Offerings (continued)
World’s Largest Trailer-Mounted Boiler
![Page 28: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/28.jpg)
Equipment Offerings (continued) • Deaerators • Feedwater Pumps • Demineralizers, Water
Softeners, Chemical FS • Blowdown Tanks
• Diesel Generators • Air Compressors • Valves • Controls • Potable Hot Water
Systems
![Page 29: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/29.jpg)
Site Considerations
• Personnel Protection: Hot Piping
• Freeze Protection
• Fencing / Barriers
![Page 30: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/30.jpg)
Site Considerations (continued) Capacity Ship. Dims. Ship. Wt. Oper. Wt. 100 HP 8’ x 14’ x 30’ 30K lbs 45K lbs
200-300 HP 8’ x 14’ x 30’ 45K lbs 60K lbs
350-600 HP 8’ x 14’ x 30’ 50K lbs 65K lbs
20-40K lb/hr 10’ x 14’ x 50’ 60K lbs 80K lbs
40-60K lb/hr 10’ x 14’ x 50’ 80K lbs 100K lbs
75-100K lb/hr 12’ x 14’ x 30’ 100K lbs 125K lbs
150K lb/hr 10’ x 16’ x 40’ 130K lbs 160K lbs
250K lb/hr 13’ x 18’ x 50’ 255K lbs 302K lbs
![Page 31: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/31.jpg)
Site Considerations (continued)
Engineered Fill Asphalt Pad Concrete
Pad
FOUNDATION REQUIREMENTS
![Page 32: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/32.jpg)
Site Considerations (continued)
engineered fill & concrete
asphalt
concrete
![Page 33: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/33.jpg)
Site Considerations (continued)
All weight must be
off running gear on mobile boiler rooms and trailer-mounted boilers during operation!
NOTE: some sites require seismic tie-downs.
![Page 34: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/34.jpg)
Advantages of Trailer-Mounted Boilers • Up to 1,000 HP • Self-contained • Fast, easy hook-up • Secure • Aesthetical pleasing • Convenient
![Page 35: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/35.jpg)
Advantages of Trailer-Mounted Boilers • Up to 125,000 lb/hr • Quick response • No cranes or rigging required • Simple to position/install • Fast, easy start-up
![Page 36: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/36.jpg)
Advantages of Trailer-Mounted Boilers • Faster delivery vs. rail
car shipments • Removable gooseneck • Hydraulic ram / foot for
assisting in leveling and blocking
70,000 lb/hr Trailer-Mounted Boiler Front Tow End
![Page 37: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/37.jpg)
Advantages of Trailer-Mounted Boilers • Removable 3-axle deck
to shorten boiler foot print.
• Or rear deck can be utilized for an operator platform.
• Rear air-bags: leveling
70,000 lb/hr Trailer-Mounted Boiler Rear Deck
![Page 38: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/38.jpg)
Advantages of Mobile Boiler Rooms
• Typical storage when removed from boiler / trailer frame
![Page 39: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/39.jpg)
Top 5 Reasons as to “How a Rental Job Can Go Bad?”
Inadequate Planning and Budget Allotment
Non-engineered Installation
Lack of Qualified Operators
Poor or Lack of Water Treatment
Lack of Maintenance
![Page 40: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/40.jpg)
Partial Customer List • Tesoro • Chevron • Phillips 66 • Southern California
Edison • Sempra • San Onofre
• Weyerhaeuser • Georgia-Pacific • Newark Paperboard • International Paper • Smurfit Newsprint
![Page 41: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/41.jpg)
Partial Customer List • City of Los Angeles • East Mesa Detention
Center • County of San Diego • Southwest Marine • NASCO • NAS Coronado
• EJ Gallo • JG Boswell • Chicken of the Sea Tuna • Circle Foods • Del Monte Foods
![Page 42: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/42.jpg)
WHAT YOU WANT TO AVOID ...
![Page 43: California Boiler Inspectors Association 2016](https://reader031.vdocuments.us/reader031/viewer/2022012410/616a64ea11a7b741a352038d/html5/thumbnails/43.jpg)
Guidelines for Preparing a Temporary Steam Plant
Questions & Answers
Michael Medina & Jim Lieskovan 1-800-227-1966
www.nationwideboiler.com www.catastak.com
Emergency Preparedness Guide: http://www.nationwideboiler.com/literature_media/publications.html