c43 west basin reservoir...package 2 –irrigation ps s-476 (3) 65 cfs vertical line electric driven...
TRANSCRIPT
![Page 1: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/1.jpg)
C43 WEST BASIN
STORAGE RESERVOIR
PACKAGE 4 - CIVIL WORKS
INDUSTRY DAYMAY 7 2018
![Page 2: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/2.jpg)
SFWMD – Who We Are
Oldest and largest of the state’s five regional water management districts
• 16 counties; 7.9 million residents
• Regional responsibilities
• Water Quality
• Flood Control
• Natural Systems
• Water Supply
![Page 3: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/3.jpg)
SFWMD – Who We Are
Created in 1949 as local sponsorfor Federal C&SF System
Expanded responsibilities in1972
Today’s system consists of 2,100miles of canals and 2,000 milesof levees/berms and more than600 water control structures, 625culverts and 71 pump stations
Currently engaged in restorationof Everglades ecosystem
![Page 4: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/4.jpg)
Project Team
Janet Starnes – Project Manager
Joe Albers, P.E. – Engineering PM
Tom McKernan – Construction Manager
Bonnie Cantrell – Procurement
Partner – US Army Corps of Engineers
![Page 5: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/5.jpg)
Solicitation Process
Two Step Process
Request for Statement of Qualifications (SOQ)
Request For Bids
Requirements will be listed in SOQ
Must use District Forms that are included
Site Visits
Questions must be submitted to Bonnie Cantrell in writing, [email protected] or fax (561) 682-5319
![Page 6: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/6.jpg)
C43 Reservoir
Purpose
Project will improve timing, quality and quantity of water deliveries to the Caloosahatchee Estuary
Capture excess basin runoff and Lake Okeechobee releases
Provide dry season flows to restore salinity levels
Reduce wet season flows
C-43 West
Storage
Reservoir
![Page 7: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/7.jpg)
Project Site
![Page 8: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/8.jpg)
C43 Existing Conditions
![Page 9: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/9.jpg)
Existing Water ManagementT
ow
nsend C
anal
Duda NE Rim Ditch
LPDD1 LPDD2 LPDD3
Header Canal
Inverted Siphon
Roberts Canal
![Page 10: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/10.jpg)
Project Delivery Plan
4 Construction Contract Packages2 Prep Packages
![Page 11: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/11.jpg)
Package 1 – Preload & Demolition
Construct earthen Preload Mounds at 7 locations.
~285,000 CY ea. (2M CY Total)
Demolition of all agricultural facilities including small irrigation pump stations (excluding LPDD1, 2 and 3).
NTP – Nov 2015
COMPLETED - August 2017
S-473S-474
S-475S-472
Embankment
S-470S-471
SFWMD
Trailer Compound
![Page 12: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/12.jpg)
Package 1 – Preload & Demolition
S-473 Preload Mound Looking West
![Page 13: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/13.jpg)
Package 2 – Irrigation PS S-476
(3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total)
Power will be dropped from adjacent FPL Feeder Line along Townsend Canal
Replaces need for Header Canal to provide irrigation water to the east.
NTP - June 2016
Final Completion – August 2018
S-476
SFWMD
Trailer Compound
Header CanalLPDD
PS#1
LPDD
PS#2
Perimeter Canal
![Page 14: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/14.jpg)
Package 2 – Irrigation PS S-476
Setting Pumps
![Page 15: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/15.jpg)
Package 3 – Inflow Pump Sta S-470
(4) 375 CFS Vertical Mixed-Flow Electric Driven Pumps (1,500 CFS Total) @ 1,250 HP
300’ Microwave Tower & Control Bldg
SR-80 Bridge Armoring
Townsend Canal Improvements
Relocation of S-470 Preload Mound
Design TDH – 42’
NTP – March 2018
Final Completion – May 2022
S-470
SFWMD
Trailer Compound
![Page 16: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/16.jpg)
Pump Station and Discharge
Package 3 – Inflow Pump Sta S-470
Discharge
PipeFormed
Suction
Intake
Saxophone
Discharge
Structure
Mixed Flow Pump
Pump StationElectric Motor
Gear Drive
Package 3 Package 4
![Page 17: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/17.jpg)
Site Clearing
Areas 1 & 2 (Interior Cells) - Grubbing and Burning of all Trees (Cabbage Palm, Oak, Pine, Eucalyptus, & Cypress).
Area 3 (Reservoir Perimeter & Separator Dam Footprint – 2000’ wide) – Clearing & Grubbing & Mechanical Mowing & Burning of all Woody Vegetation.
NTP – October 2017
Final Completion – June 2019
![Page 18: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/18.jpg)
Site Clearing
![Page 19: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/19.jpg)
Access Roads
Construction of approximately 16 Miles of Shell Rock Rd.
Installation of approximately 2,500 LF of culverts
Design and installation of road crossing over the Roberts/Banana Branch Canal
Removal of existing culverts and temporary canal plugs
Installation of speed limit & street signs
NTP – April 2018
Final Completion – February 2019
![Page 20: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/20.jpg)
Threatened and Endangered Species
Multiple T&E Species on project site
Training required for all workers
Protection strongly enforced
Strict reporting requirements
![Page 21: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/21.jpg)
Package 4 – Civil Works
2-Cell Reservoir
~ 10,000 Acres
170,000 ac-ft of storage
Dam height 27 ft – 38 ft
~19 Miles of Dam Embankment
~14.7 Miles of Perimeter Canal
Soil Bentonite Seepage Barrier
Soil Cement Lining
Seepage Management System
Pressure Relief System
![Page 22: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/22.jpg)
Package 4 – Civil Works (cont.)
14 Water Control Structures
Discharge Piping for S-470 Pump Station
Recreation Features
Townsend Canal Improvements
Local & Site Access Bridges
Currently at Intermediate Design Review Stage
NTP – March 2019
![Page 23: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/23.jpg)
Perimeter Canal• Varies 50’ to 140’ top width
• Varying bottom width
• Varying bottom elevation
• Length: 14.7 Miles
• Excavation Volume: 2.8 M CY
Earth Dam • Dam Height: 27 - 37.5 Feet
• Length: 16.3 Miles (excludes Separator Dam)
• Crest Width: 14 feet
• Water Depth: 15 - 25 Feet
• Embankment Volume: 14.5 M CY
• Soil Bentonite Wall: 4.8 M SF
• Seeding: 590 AC
• Soil Cement: 582 K CY
Perimeter Canal
ReservoirToe
Road
Shallow
Interceptor
Swale Chimney Drain
Perimeter Access
Road/Corridor
Soil Cement Protection
Existing Ground
Project Boundary
Existing Limestone Layer Existing Clay Layer Drainage Blanket
with Toe Drain
Extended to Ditch
Soil Bentonite Wall
Culvert
Toe Ditch
Package 4 - Dam and Canal Typical Section
![Page 24: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/24.jpg)
Typical Dam Sectional Details
![Page 25: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/25.jpg)
Water Control Structures
25
S477
S478
S479
S480S481
A/B/C
S475
S473S474S482S471S483
Perimeter Canal Water Supply &
Stormwater Structures
Reservoir Operations Structures
Ungated Structures
S472
![Page 26: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/26.jpg)
Perimeter Canal – Stormwater
S478
Fixed Weir
S481C
Dual Leaf Weir
![Page 27: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/27.jpg)
Perimeter Canal – Water Supply
S476
195 CFS
TW 23’
S477
HW23’
TW 19’
S479
125 CFS
TW 25’
S480
ManualS481B
HW 18.75’
TW 16’
![Page 28: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/28.jpg)
Completed Project Components
![Page 29: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/29.jpg)
Funding
Project will be funded by annual State of Florida legislative appropriations
Corps will credit up to 50% of cost to District applicable to other projects.
![Page 30: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/30.jpg)
What’s Next
Site Visit – May 8, 2018
Issue RFQ – target mid-May 2018
RFQ Responses due – target early July 2018
Approval of Prequalified list – target tentative August 2018
![Page 31: C43 WEST BASIN RESERVOIR...Package 2 –Irrigation PS S-476 (3) 65 CFS Vertical Line Electric Driven Pumps (195 CFS Total) Power will be dropped from adjacent FPL Feeder Line along](https://reader036.vdocuments.us/reader036/viewer/2022081410/6092e700098c0012864fb7f7/html5/thumbnails/31.jpg)
Questions