PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 1/20
1. SERVICE TENDERS
1.1. Introduction
Service contracts are used to obtain consultancy services. The services are usually either
in the form of studies or technical assistance.
Selecting the procurement procedure
The procurement procedure depends on estimated budget of the tender. The following
table explains which procedure should be used:
SERVICES
200,000 < 200,000
but >10,000 10,000
International restricted
tender procedure
1 Framework contracts
2 Competitive negotiated procedure
Single
tender
Selecting contract format
Study contracts include studies for the identification and preparation of projects,
feasibility studies, economic and market studies, technical studies, evaluations and audits.
Technical assistance contracts are used where a service provider is called on to play anadvisory role, to manage or supervise a project, or to provide the experts specified in the
contract.
As a rule, in case of study contracts only the final result matters and while in case of
technical assistance, advice is received continuously and the final result is not alwaysdefinite. When only the final result of the project is important, it is advisable to use the
global price contract format, otherwise the fee-based contract format should be used.
Duration of procurement procedures
It is important to know the approximate period of time that a procedure takes. The table
below indicates an average period from the moment the CFCA receives the final versionof the Terms of Reference from the PIUs until the day when the first expert(s) start(s)
working under the contract.
Procedure Time in calendar months
-
7/30/2019 C - Procurement 1 Services- V5.3
2/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 2/20
International restricted procedure 6-9
Framework Contracts 2-3
Competitive negotiated procedure 4-7
Single tender 2-3
Negotiated procedure 1-3
Drafting Terms of Reference
Terms of Reference is a key document in project implementation process prepared by thePIUs and should serve mostly two purposes:
1) it is a legal document and part of the contract that fixes the tasks and deliverables of
the contractor as well as the means and timing (deadlines);
2) it should link the implementation phase of the project to the programming andmonitoring phase making sure that the project is in line with a larger framework (e.g.
project fiche). It should also give relevant background information for monitoring the
project on all levels.
Therefore, the immediate outputs should be described in sufficient detail as the contractoris legally bound to deliver only the outputs explicitly mentioned in the Terms of
Reference. At the same time, for monitoring purposes, the Terms of Reference shouldcontain provisions that would link these to a programming document such as a project
fiche and the logical framework matrix.
The PIU submits the final version of the Terms of Reference (agreed with the CFCA
under EDIS system and the relevant Task Manager in the EUD under DIS system),
evaluation grid and budget estimate to the CFCA in hard copy as well as in electronic
form (email or CD). In EDIS, PIU should perform quality control of ToR beforesubmitting it to CFCA by using check lists for FWC Terms of reference, Terms of
reference and service Procurement Notice which are attached in annexes C4, C5 and C6.
Defining selection criteria for short-listing
The PIUs are, together with the CFCA, responsible for developing the selection criteriaused during the short-listing. There are three selection criteria for short-listing which
must be defined in the Procurement Notice: Economic and financial capacity of
candidate, Professional capacity of candidate and Technical capacity of candidate. Thecriteria should be designed with care in order not to exclude companies that could be the
best for the required task and to allow widest competion possible. At the same time, if the
-
7/30/2019 C - Procurement 1 Services- V5.3
3/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 3/20
requirements are too low, companies that would not be able to perform the contract might
be included (this risk is, however, less serious because if more than 8 companies would
be eligible, the number of companies should be reduced to 8 by applying additionalcriteria mentioned in the Procurement Notice).
Therefore, it is usually not advisable to require an annual turnover of more than 2 times
the projects annual budget. Also, it is advisable to keep the number of key experts low,
especially when the field of the contract is very specific. Furthermore, the number ofpersonnel required should be defined in terms of numbers, and not percentages. The
criterion of technical capacity should be clearly defined, e.g. the company has
successfully finished at least two projects that have included provision of training onStructural Funds. However, this condition should be realistic, i.e. not too restrictive.
Defining evaluation criteria for tender evaluation
One of the key decisions that has to be made and that will have direct influence on theresults of tenders in case of an international restricted procedure and a competitive
negotiated procedure is the decision on evaluation criteria in the evaluation grid. Due tothe fact that the technical evaluation of tenders is based on the evaluation grid, tenderers
pay special attention to the items in the grid that could potentially give a high number of
points.
It must be also noted that if the there are too many requirements per key experts underrespective category (i.e. specific professional experience) in the grid, the comparison of
offers could be more complicated as each item would give a relatively small number of
points and some differences between the offers would not be reflected in the number ofpoints. For this reason, it is advisable, unless there is some specific necessity, not to
include more than 4 key experts in ToR and consequently, in the evluation grid.
-
7/30/2019 C - Procurement 1 Services- V5.3
4/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 4/20
1.2. International Restricted Tender Procedure
An international restricted tender procedure must be used when the budget of the service
tender is equal to or higher than 200 000 EUR. Procedures stated in table below incursive letters are applicable only under DIS system.
Unit responsible Document Activity Time
1 DIS: CFCA +
EUD
EDIS: CFCA
Individual
contract forecast
(CF)
Publication of service
individual contract
forecasts
2 PIU ToR + budget
estimate +Procurement
Notice (PN) +evaluation grid
+ Declaration ofObjectivity and
Confidentiality
Drafts and checks the
quality of ToR, PN,evaluation grid and
budget estimate andsubmits to the CFCA
together with originalDeclarations of
Objectivity and
Confidentiality
3 CFCA ToR + PN +Tender Dossier
(TD)
Verification of ToR,PN, preparation of TD,
quality control and
submission to the EUD
for approval
15 Workingdays (WD)
after receipt
4 DIS: EUD
EDIS: PAO
TD + ToR + PN Issues notes on
approving the
documents, sends these
to CFCA and ensurespublication of the
announcement on the
EuropeAid website andin the Official Journal
of the European
Communities
Min. 15Calendar days
(CD)
5 DIS: CFCA +
PIU +EUD
EDIS: PIU +
CFCA + PAO
Letter with listof Evaluation
Committee
(EvCom)
members
Proposing thecomposition,
nomination and
approval of EvCom
(Shortlist Panel)
At the time ofpublication of
PN at the
latest
6 Candidates Applications Prepare and submit tothe CFCA their
Min. 30 CD
-
7/30/2019 C - Procurement 1 Services- V5.3
5/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 5/20
Applications for EC-
funded Service
Contracts
7 EvCom (Shortlistpanel)
Short-list report(SLR)
Proceeds with the short-listing of the
applications received
and establishes a Short
List1, drafts a report onthe short list meeting
(including shortlist
notice), signed by theChairperson, the
Secretary and the voting
members
5 WD after receipt of
applications
8 DIS and EDIS:CFCA
SLR Sends SLR and thecopies of the
applications to the
EUD (DIS) or submits
SLR to PAO for approval (EDIS)
5 WD
9 DIS: EUD
EDIS: PAO
SLR EUD issues notes on
approving the
documents to the CFCAand endorses report
(DIS).
PAO endorses report
(EDIS)
10
DIS and EDIS:CFCA
Letters of Rejection (LoR)
+ Invitation to
Tender + TD +Service Contract
Shortlist Notice
(SCSN)
Notifies theunsuccessful candidates
that they have not been
short-listed anddispatches the Invitation
to Tender and TD to
short-listed companies
(by registeredmail/courier service)
and submits SCSN to
the EUD for approvaland publication (in
2 WD after receiving
approval of
SLR fromEUD
1 The long list summarising all applications received is established by Evaluation Committee. The shortlist
should contain a minimum of four and a maximum of eight candidates (would-be service providers), as
specified in the procurement notice.
-
7/30/2019 C - Procurement 1 Services- V5.3
6/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 6/20
electronic form (after
approval of SCSN i.e.
SLR)
CFCA submits SCSNdirectly to AIDCO
publication office
(EDIS) for publication
11
DIS: EUD
EDIS: AIDCO
SCSN Publication onEuropeAid web-site and
in EC Official Journal
1
2
CFCA Confirmation of
Receipt (CoR)
Receives CoR and the
intent to (not) submit an
offer
13
DIS: PIU +CFCA+EUD
EDIS: PIU +
CFCA + PAO
Letter with listof EvCom
members
(standard EUCVs +
Declaration that
they are notlinked through
direct command
line)
Proposing thecomposition,
nomination and
approval of EvaluationCommittee
Max. 10 WDafter the
shortlisting
14
Tenderers Offers Prepare and submittheir offers to theCFCA (double
envelope system)
Min. 50 CDfrom the dateof Invitation to
Tender
1
5
CFCA Offers Receives, registers and
stores offers
16
EvCom EvaluationReport (EvRep)
Carries out theevaluation based on
agreed criteria and
methodology (as
specified in the TenderDossier), prepares
Evaluation Report
Max. 15 WDfrom the
beginning date
of evaluation
1
7
CFCA EvRep +
ContractDossier
Prepares and sends the
draft Contract Dossierand Evaluation report
to the EUD together
Max. 15 WD
from the endof evaluation
(Report)
-
7/30/2019 C - Procurement 1 Services- V5.3
7/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 7/20
with a copy of the
winning tender, copies
of the unsuccessful
tenders (DIS). Preparesand sends Evaluation
report and Contract toPAO for endoresement
(EDIS).
Immidietely
upon
verification of
eligigibilityproof
documents
(Contract)
1
8
DIS: EUD
EDIS: PAO
EvRep +
Contract
Dossier
Issues notes on
approving the
Evaluation report andContract Dossier,
endorses evaluation
report and the contract
(DIS).
Endorses evaluation
report and the contract
(EDIS)
19
CFCA Notification of Contract (NOC)
Sends to the successfultenderer a NOC and
requests documentary
evidence
Max. 10 WD
20
Successfultenderer
Documents Sends CFCA thedocumentary evidence
Max.15 CDafter the date
of NOC
2
1
CFCA Contract Examines documents
submitted by successful
tenderer for correctness
2 WD after
receipt of
documentation
22
CFCA Contract CFCA sends 3 originalsof the Contract to the
Contractor for signature
(by registeredmail/courier service)
2 WD
23
SuccessfulTenderer
Contract + pre-financing bank
guarantee
Keeps one original ofthe contract and returns
the rest of the
countersigned originalsto the CFCA
Max. 30 CD
2
4
CFCA Letter to
Unsusessful
Sends them to
unsuccessful tenderers
15 CD after
receiving
-
7/30/2019 C - Procurement 1 Services- V5.3
8/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 8/20
Tenderers signed
contract
2
5
CFCA Contract Sends one original of
the signed contract tothe EUD (one original
remains at CFCA), and
one copy of the original
is sent to the PIU (DIS).
Sends one original to
the financial service in
charge of payments and
the other to the ProjectManager. One copy of
the contract is sent to
PIU (EDIS).
1 WD
26
CFCA Service ContractAward Notice
Under DIS: Prepares aService Contract Award
Notice and submits to
the EUD for publication in
electronic form (in
EDIS Contract AwardNotice is sent to EC for
publication)
Under EDIS: CFCAsubmits CAN directlyto AIDCO on
publication on their web
site and in OJ
1 WD
-
7/30/2019 C - Procurement 1 Services- V5.3
9/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 9/20
1.3. Framework Contract
A Framework contract2 procedure should be used when the budget of the service tender is
less than 200.000 EUR but more than 10.000 EUR. Alternatively, the competitivenegotiated procedure (described in the next section) could be used.
The Terms of Reference may request the Framework Contractor to provide an outline for
the approach and methodology envisaged for the implementation of the assignment.
Concerning the budget estimation, the total cost of an assignment must be less than 200.000. The input of any expert in a given assignment may not exceed 260 working
days. The implementation period of the operation does not exceed 2 years (730 calendar
days) including all addenda. Terms of Reference must specify the category of
expert/expertise and related number of working days. Only the number of experts is anoption and in that case, the expertise must be clearly defined, as well as minimum
requirements covering the qualifications and skills (depending on the category ofexperts). Beneficiary has to reach a decision prior to drafting ToR whether the Specificcontract emerging from the ToR will be Fee based or Global price type.
Fee based type of ToR results in a contract under which the services are provided on the
basis of fixed fee rates for each day worked by experts. Fee based contracts are usually
associated with technical assistance, that is, where service provider is called upon to playan advisory role, to manage or supervise a project, or to provide the experts specified.
Global price ToR assumes that contract will be performed under an all inclusive fixed
price. Global price contract are usually associated with study type contracts;
identification and preparation of projects, feasibility studies, economic and marketstudies, technical studies, evaluations and audits. Therefore, final output of the contract is
easily established and visible.
Framework contractors are divided into 12 different lots or sectors of expertise. Only lot
5 (Organisation and logistics for conferences) is always contracted as a fee basedcontract.
In order to collect all necessary information required for launching of the assignment,
following resources ought to be consulted:
list and description of the content of the lots (to ensure rightful application of thespecific lot according to the specific needs of the beneficiary/nature and scope of
the task)
2 FWC procedures are guided by Users guide supplemented by Important messages which are regularly
updated along with standard templates and other FWC specific information by AIDCO and published on
the following WEB page: http://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-
2009/index_en.htm
Therefore, regular monitoring of updates is mandatory task in order to ensure compliance with specific
rules governing FWC procedures.
http://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-2009/index_en.htmhttp://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-2009/index_en.htmhttp://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-2009/index_en.htmhttp://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-2009/index_en.htmhttp://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-2009/index_en.htm -
7/30/2019 C - Procurement 1 Services- V5.3
10/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 10/20
list of the framework contractors from the particular lot accompanied by
contractually fixed price brackets for required category of expert (including
information concerning bank accounts on which payment shall be executed)
list of the signatories entitled to sign Request for offer and Letter of contract
General conditions of the contract (meaning global contract which Commissions
signs with all framework contractors)
Specific Terms of reference
Other forms
Procedures stated in table below in cursive letters are applicable only under DIS
system.
Unit responsible Document Activity Time1 PIU ToR + budget
estimate +
Declaration ofObjectivity
and
Confidentiality
Drafts and checks the
quality of ToR and budget
estimate and submits to theCFCA together with
original Declarations of
Objectivity andConfidentiality, short-list
of at least 3 possible
service providers and
submission to the CFCA
2 CFCA ToR + budgetestimate +
Declaration of
Objectivityand
Confidentiality
+ Request forServices (RfS)
Verification of ToR andbudget estimate, RfS,
quality control and
submission to EUD
5 WD fromthe receipt of
documentation
3 DIS: EUD
EDIS:PAO
ToR, budgetestimate
Approves ToR + budgetestimate. (under DIS).
PAO approves ToR +
budget estimate (underEDIS).
15 WD fromreceipt of
documentation
4 CFCA RfS, ToR,
budget
estimate
Completion of RfS,
signature of the RfS by the
PAO and submission to
5 WD
-
7/30/2019 C - Procurement 1 Services- V5.3
11/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 11/20
EUD
5 DIS: EUD
EDIS: PAO
RfS + ToR Checks and signs RfS and
sends the signed RfS back
to the CFCA.
PAO signs RfS andreturnes it to the CFCA
Project Manager
15 WD from
receipt of
documentation
6 CFCA RfS + ToR Indicates the deadline for
the receipt of offers (14days from dispatch),
submits to the relevant
framework contractors
1 WD
7 Framework
Contractor(FWC)
Certificate of
Receipt
Acknowledgment of
receipt of the RfS
2 WD from
the date of receipt of RfS
8 DIS: PIU +
CFCA + EUD
EDIS: PIU +
CFCA + PAO
List of EvCom
members +
CVs
Proposing the
composition, nomination
and approval of EvaluationCommittee by EUD (DIS)
or by PAO (EDIS)
5 WD from
the receipt of
the signed RfSat the latest
9 FWC Offers for
Services
Send their Offers for
Services to the CFCA
Max.14 CD
since dispatchof RfS
1
0
EvCom Evaluation
Report
Carry out the evaluation
and draft Offers
Evaluation Report, signed
by the EvCom members(and endorsed by PAO).
7 WD from
the deadline
for receipt of
offers
1
1
CFCA Evaluation
Report +
Letter of Contract
Prepares Letters of
Contract, (signed by
PAO), sends the OffersEvaluation Report and the
completed Letter of
Contract (in four originals) to the EUD
1 WD after
end of
evaluation
12
DIS: EUD
EDIS: PAO
Letter ofContract
The duly authorised EUDofficial checks, dates and
signs it and sends it back
to the CFCA (DIS).
PAO signs Letter of
5 WD ater receipt of
documentation
-
7/30/2019 C - Procurement 1 Services- V5.3
12/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 12/20
contract and returns it to
Contracting Officer within
CFCA (EDIS).
13
CFCA Letter of Contract
Sends a copy of the Letterof Contract (signed by
PAO) to the selected
framework contractor and
in addition four originals
1 WD
14
FWC Letter of Contract
Countersigns the threeoriginal LoCs and sends
back two originals to the
CFCA including a signedversion of the original
offer and an initialled
version of the ToR
Max. 30 CDafter receipt of
Letter of
Contract fromCFCA
15
CFCA Letter tounseucessful
FWC
Sends letter to theunsuccessful Framework
Contractors by (fax or
email)
1 WD after receipt of
Letter of
Contract fromFWC
1.4. Competitive negotiated procedure
A competitive negotiated procedure should be used if the use of an existing framework
contract is impossible or has been unsuccessful. The budget of the service tender is less
than 200.000 EUR and more than 10.000 EUR. In terms of rapidity, application of thecompetitive negotiated procedure is considered less favourable option than FWC.
It is recommended to invite at least 3 candidates
Procedures stated in table below in cursive letters are applicable only under DIS
system.
Unit
responsible
Document Activity Time
1 PIU + Letter of Seeks through the CFCA EUD
-
7/30/2019 C - Procurement 1 Services- V5.3
13/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 13/20
CFCA Request approval (in DIS system) or PAO
approval (in EDIS system) for using
competitive negotiated procedure
instead of FWC2 DIS: EUD +
CFCA
EDIS:
CFCA+PAO
Note Issues note on approving the
procedure and sends it to CFCA
(under DIS).
PAO approves the procedure (udnerEDIS).
10 WD
3 PIU ToR, short-
list, budget
estimate,
original
Declarationsof
Objectivityand
Confidential
ity
Drafts and checks the quality of ToR
and budget estimate, prepares short-
list of at least 3 possible service
providers, and submits them to the
CFCA together with originalDeclarations of Objectivity and
Confidentiality
4 CFCA TD, ToR,short-list,
budget
estimate
Verification of ToR, preparation ofTD, quality control and submission
to EUD for approval
12 WDafter
receipt
5 DIS: EUD
EDIS: PAO
TD Issues notes on approving thedocuments and sends these to CFCA(under DIS).
PAO approves TD (under EDIS).
15 WDafterreceipt
6 CFCA TD Initiates the competitive negotiated
procedure (sends Letter of Invitation
to Tender and TD to shortlistedcompanies)
3 WD after
approval
7 DIS: PIU+CFCA +
EUD
EDIS: PIU +
CFCA +
PAO
Letter with
list of
EvCommembers
(standard
EU CVs +Declaration
that they are
not linked
through
Proposing the composition,
nomination and approval of
Evaluation Committee by EUD(DIS) or by PAO (EDIS)
at the time
of initiating
procedure
-
7/30/2019 C - Procurement 1 Services- V5.3
14/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 14/20
direct
command
line)
8 Tenderers Offers Prepare and submit offers (doubleenvelope system) to the CFCA
Min. 30CD
9 CFCA Offers Receives, registers and stores offers
10 EvCom EvRep Carries out the evaluation based on
agreed criteria and methodology (as
specified in the Tender Dossier),
prepares Evaluation Report
10 WD
11 CFCA EvRep +Contract
Dossier
Prepares and sends the draft ContractDossier and Evaluation report to the
EUD together with a copy of the
winning tender, copies of theunsuccessful tenders
5 WD afterend of
evaluation
1
2
DIS: EUD
EDIS: PAO
EvRep +
Contract
Dossier
Issues notes on approving the report
and Contract Dossier, and returns
the report to the CFCA (DIS).
PAO approves the report and thecontract (EDIS).
10 WD
after
receipt
13 CFCA NOC Sends the successful tenderer a NOC
and requests documentary evidence33 WD
14 Successful
tenderer
Documents Sends to the CFCA the documentary
evidence
Max. 15
CD after the date of
NOC
15 CFCA Contract Examines documents submitted by
successful tenderer for correctness
2 WD after
receipt
16 CFCA Contract CFCA sends 3 originals of the
contract to the Contractor forsignature (by registered mail/courier
service)
2 WD
17 Successful
Tenderer
Contract Keeps one original of the contract
and returns the rest of the originalsof the countersigned originals to the
Max. 30
CD
3 PRAG, concerning requests for submission of documentary evidences: For contracts with a value less than the international
thresholds the Contracting Authority may waive this obligation, depending on its risk assessment. When this obligation has been
waived, the Contracting Authority may nevertheless, where it has doubts as to whether the tenderer to whom the contract is to be
awarded is in one of the situations of exclusion, require him/her to provide the evidence.
-
7/30/2019 C - Procurement 1 Services- V5.3
15/20
PIU Operational GuideC PROCUREMENT
IPA I Version : 5.3 Date : September 2012 Page 15/20
CFCA
18 CFCA Letters to
the
unsuccessfultenderers
Sends letters to the unsuccessful
tenderers
Max. 15
CD after
receivingsigned
contract
19 CFCA Contract +
Service
ContractAward
Notice
Sends one original of the signed
contract to the EUD (one original
remains with the CFCA), and onecopy of the original to the PIU
(under DIS).
Sends one original to the financial
service in charge of payments and
the other to the Project Manager.One copy of the contract is sent to
PIU (EDIS).
1 WD after
receiving
signedcontract
-
7/30/2019 C - Procurement 1 Services- V5.3
16/20
PIU Operational Guide
C PROCUREMENT
Management of CARDS, PHARE, IPA I Version :
5.2.1
Date : March 2012 Page 16/20
1.5. Single tender
A single tender procedure should be used when the budget of the service tender is smallerthan or equal to 10.000 EUR.
Notwithstanding the rather small amounts involved, in DIS system the EUD will be
involved in the award process.
Under this procedure the CFCA invites a single tender from a candidate of its choice. In
case the Candidate is technically competent to undertake the work as described in theTerms of Reference and is able to abide by the financial limitations of the budget a
contract may be signed with this service provider.
Procedures stated in table below in cursive letters are applicable only under DIS
system.
Unitresponsible
Document Activity Time
1 PIU ToR + budget
estimate +
originalDeclarations of
Objectivity and
Confidentiality
Drafts and checks the quality of
ToR including a budget estimate,
and submission to the CFCA withthe proposed company details,
including a brief explanation for
selecting the company andoriginal
Declarations of Objectivity andConfidentiality
2 CFCA TD + ToR +
budget estimate
Verification of ToR and budget
estimate, preparation of TD and
submission to EUD for approval(DIS)
Verification of ToR and budget
estimate, preparation of TD and
submission to PAO (EDIS)
10 WD
after
receipt
3 DIS: EUDEDIS: PAO
TD Issues notes on approving thedocuments and sends these to the
CFCA (DIS).
PAO approves TD.
10 WDafter
receipt
4 CFCA TD Initiates the single tender
procedure (sends Letter ofInvitation to Tender and TD to
3 WD
-
7/30/2019 C - Procurement 1 Services- V5.3
17/20
PIU Operational Guide
C PROCUREMENT
Management of CARDS, PHARE, IPA I Version :
5.2.1
Date : March 2012 Page 17/20
proposed service provider)
5 DIS: PIU+
CFCA +EUD
EDIS: PIU
+ CFCA +
PAO
Letter with list
of EvCommembers
(standard EU
CVs +
Declarationthat they are
not linked
through directcommand line)
Proposing the composition,
nomination and approval ofEvaluation Committee by EUD
(DIS) or by PAO (EDIS)
at the
time of initiating
procedure
6 Service
provider
Offer Prepares and submits an offer to
the CFCA
Max. 14
CD7 CFCA Offer Receives, registers and stores the
offer
1 WD
8 EvCom EvRep Carries out the evaluation andprepares an Evaluation Report
5 WD
9 CFCA EvRep Sends a copy of the report, 3
originals of the contract signed by
PAO to the EUD together with a
copy of the offer
5 WD
after the
end of
evaluation
1
0
DIS: EUD
EDIS: PAO
EvRep Issues notes on approving the
report and returns the report and
signed originals of the contracts tothe CFCA (DIS)
PAO approves the report and signs
the contracts (EDIS).
15 WD
after
receipt
11 CFCA NOC Sends the successful tenderer a
NOC and requests documentaryevidence4
3 WD
12 Successfultenderer
Documents Sends to the CFCA thedocumentary evidence
Max. 15CD after
4 PRAG, concerning requests for submission of documentary evidences: For contracts with a value less than the international
thresholds the Contracting Authority may waive this obligation, depending on its risk assessment. When this obligation has beenwaived, the Contracting Authority may nevertheless, where it has doubts as to whether the tenderer to whom the contract is to be
awarded is in one of the situations of exclusion, require him/her to provide the evidence. Depending on its risks assessment, the
contracting authority may refrain from requiring the declaration that the candidates or tenderers are not in one of the situations of
exclusions for contracts with a value equal to or less than 10,000.
-
7/30/2019 C - Procurement 1 Services- V5.3
18/20
PIU Operational Guide
C PROCUREMENT
Management of CARDS, PHARE, IPA I Version :
5.2.1
Date : March 2012 Page 18/20
date of
NOC
13 CFCA Contract Examines documents submitted bysuccessful tenderer for correctness
2 WDafter
receipt
14 CFCA Contract CFCA sends 3 originals of
Contract to the Contractor for
signature (by registeredmail/courier service)
2 WD
15 Service
provider
Contract Keeps one original of the contract
and returns the rest of the originals
of the countersigned originals to
the CFCA
Max. 30
CD
16 CFCA Contract Sends one original of the signed
contract to the EUD (one original
remains with the CFCA) and onecopy of the original to the PIU
(DIS).
Sends one original to the financial
service in charge of payments andthe other to the Project Manager.
One copy of the contract is sent to
PIU (EDIS).
1 WD
1.6. Negotiated procedure
A negotiated procedure may be used only in exceptional cases. Due to its exceptionalnature, the format of the negotiated procedure, especially the tendering and evaluation
phase, is not fixed and should be tailored for each specific case. However, before
launching a negotiated procedure, in DIS the EUD must approve the use of the negotiatedprocedure, while in EDIS the same must be approved by PAO. A short description of the
procedure should be submitted to the EUD. The whole negotiation process is documentedin the Negotiation Report.
Procedures stated in table below in cursive letters are applicable only under DIS
system.
Unit responsible Document Activity Time
-
7/30/2019 C - Procurement 1 Services- V5.3
19/20
PIU Operational Guide
C PROCUREMENT
Management of CARDS, PHARE, IPA I Version :
5.2.1
Date : March 2012 Page 19/20
1 CFCA + PIU Letter +
negotiation
strategy +list of
candidates
After consulting PIU, CFCA
seeks EUD approval to initiate a
negotiated procedure5
(DIS) (inEDIS PIU seeks the approval
from PAO).
2 DIS: EUD
EDIS: PAO
Note Issues note on approving theprocedure (DIS).
PAO approves negotiated
procedure.
15 WD afterreceipt of
letter
3 DIS: PIU +
CFCA + EUDEDIS: PIU +CFCA + PAO
Proposing the composition,
nomination and approval ofEvaluation Committee by EUD
(DIS) or by PAO (EDIS)
Upon
approval ofthe
procedure
4 EvComm Negotiation
Report +
Contract
Following the previously agreed
procedure, carry out the
negotiated procedure inaccordance with negotiation
strategy, drafts the Negotiation
Report.
5 CFCA CFCA drafts contract in three
originals signed by PAO andsubmits the report and the
contract to EUD for endorsement
(DIS).
CFCA drafts contract in threeoriginals and submits the report
and the contract to PAO for
endorsement (EDIS).
6 DIS: EUD
EDIS: PAO
Contract Issues notes on approving thedocuments and returns the
endorsed contracts to the CFCA(DIS).
Aproves the report and endorsesthe contract (EDIS).
15 WD afterreceipt
5 The negotiated procedure has to be clearly identified and justified (prior approval from the EUD is
required in DIS system, while in EDIS prior approval by CFCA is required). A brief description of the
procedure (negotiation strategy) should be included in the letter to EUD/CFCA.
-
7/30/2019 C - Procurement 1 Services- V5.3
20/20
PIU Operational Guide
C PROCUREMENT
Management of CARDS, PHARE, IPA I Version :
5.2.1
Date : March 2012 Page 20/20
7 CFCA Contract CFCA sends 3 originals of
Contract to the Contractor for
signature (by registeredmail/courier service).
2 WD
8 Service provider Contract Keeps one original of the contract
and returns the rest of the
originals of the countersignedcontract to the CFCA
30 CD after
receipt
9 CFCA Contract Sends one original of the signed
contract to the EUD (one original
remains with the CFCA) and onecopy of the original to the PIU
(DIS).Sends one original to the financial
service in charge of payments andthe other to the Project Manager.
One copy of the contract is sent to
PIU (EDIS).6
1 WD
6 PRAG: The award notice shall be published for procedures where a publication of the procurement notice has taken place or if the
value of the contract is above international thresholds (service > 200.000, supply > 150.000, works > 5.000.000), unless the
contract was declared secret of where the performance of the contract must be accompanied by special security measures, or when
theprotection of the essential interests of the European Union, or the beneficiary country so requires, and where the publication of the
award notice is deemed not to be appropriate.