    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 1/20

    1. SERVICE TENDERS

    1.1. Introduction

    Service contracts are used to obtain consultancy services. The services are usually either

    in the form of studies or technical assistance.

    Selecting the procurement procedure

    The procurement procedure depends on estimated budget of the tender. The following

    table explains which procedure should be used:

    SERVICES

    200,000 < 200,000

    but >10,000 10,000

    International restricted

    tender procedure

    1 Framework contracts

    2 Competitive negotiated procedure

    Single

    tender

    Selecting contract format

    Study contracts include studies for the identification and preparation of projects,

    feasibility studies, economic and market studies, technical studies, evaluations and audits.

    Technical assistance contracts are used where a service provider is called on to play anadvisory role, to manage or supervise a project, or to provide the experts specified in the

    contract.

    As a rule, in case of study contracts only the final result matters and while in case of

    technical assistance, advice is received continuously and the final result is not alwaysdefinite. When only the final result of the project is important, it is advisable to use the

    global price contract format, otherwise the fee-based contract format should be used.

    Duration of procurement procedures

    It is important to know the approximate period of time that a procedure takes. The table

    below indicates an average period from the moment the CFCA receives the final versionof the Terms of Reference from the PIUs until the day when the first expert(s) start(s)

    working under the contract.

    Procedure Time in calendar months

  • 7/30/2019 C - Procurement 1 Services- V5.3

    2/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 2/20

    International restricted procedure 6-9

    Framework Contracts 2-3

    Competitive negotiated procedure 4-7

    Single tender 2-3

    Negotiated procedure 1-3

    Drafting Terms of Reference

    Terms of Reference is a key document in project implementation process prepared by thePIUs and should serve mostly two purposes:

    1) it is a legal document and part of the contract that fixes the tasks and deliverables of

    the contractor as well as the means and timing (deadlines);

    2) it should link the implementation phase of the project to the programming andmonitoring phase making sure that the project is in line with a larger framework (e.g.

    project fiche). It should also give relevant background information for monitoring the

    project on all levels.

    Therefore, the immediate outputs should be described in sufficient detail as the contractoris legally bound to deliver only the outputs explicitly mentioned in the Terms of

    Reference. At the same time, for monitoring purposes, the Terms of Reference shouldcontain provisions that would link these to a programming document such as a project

    fiche and the logical framework matrix.

    The PIU submits the final version of the Terms of Reference (agreed with the CFCA

    under EDIS system and the relevant Task Manager in the EUD under DIS system),

    evaluation grid and budget estimate to the CFCA in hard copy as well as in electronic

    form (email or CD). In EDIS, PIU should perform quality control of ToR beforesubmitting it to CFCA by using check lists for FWC Terms of reference, Terms of

    reference and service Procurement Notice which are attached in annexes C4, C5 and C6.

    Defining selection criteria for short-listing

    The PIUs are, together with the CFCA, responsible for developing the selection criteriaused during the short-listing. There are three selection criteria for short-listing which

    must be defined in the Procurement Notice: Economic and financial capacity of

    candidate, Professional capacity of candidate and Technical capacity of candidate. Thecriteria should be designed with care in order not to exclude companies that could be the

    best for the required task and to allow widest competion possible. At the same time, if the

  • 7/30/2019 C - Procurement 1 Services- V5.3

    3/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 3/20

    requirements are too low, companies that would not be able to perform the contract might

    be included (this risk is, however, less serious because if more than 8 companies would

    be eligible, the number of companies should be reduced to 8 by applying additionalcriteria mentioned in the Procurement Notice).

    Therefore, it is usually not advisable to require an annual turnover of more than 2 times

    the projects annual budget. Also, it is advisable to keep the number of key experts low,

    especially when the field of the contract is very specific. Furthermore, the number ofpersonnel required should be defined in terms of numbers, and not percentages. The

    criterion of technical capacity should be clearly defined, e.g. the company has

    successfully finished at least two projects that have included provision of training onStructural Funds. However, this condition should be realistic, i.e. not too restrictive.

    Defining evaluation criteria for tender evaluation

    One of the key decisions that has to be made and that will have direct influence on theresults of tenders in case of an international restricted procedure and a competitive

    negotiated procedure is the decision on evaluation criteria in the evaluation grid. Due tothe fact that the technical evaluation of tenders is based on the evaluation grid, tenderers

    pay special attention to the items in the grid that could potentially give a high number of

    points.

    It must be also noted that if the there are too many requirements per key experts underrespective category (i.e. specific professional experience) in the grid, the comparison of

    offers could be more complicated as each item would give a relatively small number of

    points and some differences between the offers would not be reflected in the number ofpoints. For this reason, it is advisable, unless there is some specific necessity, not to

    include more than 4 key experts in ToR and consequently, in the evluation grid.

  • 7/30/2019 C - Procurement 1 Services- V5.3

    4/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 4/20

    1.2. International Restricted Tender Procedure

    An international restricted tender procedure must be used when the budget of the service

    tender is equal to or higher than 200 000 EUR. Procedures stated in table below incursive letters are applicable only under DIS system.

    Unit responsible Document Activity Time

    1 DIS: CFCA +

    EUD

    EDIS: CFCA

    Individual

    contract forecast

    (CF)

    Publication of service

    individual contract

    forecasts

    2 PIU ToR + budget

    estimate +Procurement

    Notice (PN) +evaluation grid

    + Declaration ofObjectivity and

    Confidentiality

    Drafts and checks the

    quality of ToR, PN,evaluation grid and

    budget estimate andsubmits to the CFCA

    together with originalDeclarations of

    Objectivity and

    Confidentiality

    3 CFCA ToR + PN +Tender Dossier

    (TD)

    Verification of ToR,PN, preparation of TD,

    quality control and

    submission to the EUD

    for approval

    15 Workingdays (WD)

    after receipt

    4 DIS: EUD

    EDIS: PAO

    TD + ToR + PN Issues notes on

    approving the

    documents, sends these

    to CFCA and ensurespublication of the

    announcement on the

    EuropeAid website andin the Official Journal

    of the European

    Communities

    Min. 15Calendar days

    (CD)

    5 DIS: CFCA +

    PIU +EUD

    EDIS: PIU +

    CFCA + PAO

    Letter with listof Evaluation

    Committee

    (EvCom)

    members

    Proposing thecomposition,

    nomination and

    approval of EvCom

    (Shortlist Panel)

    At the time ofpublication of

    PN at the

    latest

    6 Candidates Applications Prepare and submit tothe CFCA their

    Min. 30 CD

  • 7/30/2019 C - Procurement 1 Services- V5.3

    5/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 5/20

    Applications for EC-

    funded Service

    Contracts

    7 EvCom (Shortlistpanel)

    Short-list report(SLR)

    Proceeds with the short-listing of the

    applications received

    and establishes a Short

    List1, drafts a report onthe short list meeting

    (including shortlist

    notice), signed by theChairperson, the

    Secretary and the voting

    members

    5 WD after receipt of

    applications

    8 DIS and EDIS:CFCA

    SLR Sends SLR and thecopies of the

    applications to the

    EUD (DIS) or submits

    SLR to PAO for approval (EDIS)

    5 WD

    9 DIS: EUD

    EDIS: PAO

    SLR EUD issues notes on

    approving the

    documents to the CFCAand endorses report

    (DIS).

    PAO endorses report

    (EDIS)

    10

    DIS and EDIS:CFCA

    Letters of Rejection (LoR)

    + Invitation to

    Tender + TD +Service Contract

    Shortlist Notice

    (SCSN)

    Notifies theunsuccessful candidates

    that they have not been

    short-listed anddispatches the Invitation

    to Tender and TD to

    short-listed companies

    (by registeredmail/courier service)

    and submits SCSN to

    the EUD for approvaland publication (in

    2 WD after receiving

    approval of

    SLR fromEUD

    1 The long list summarising all applications received is established by Evaluation Committee. The shortlist

    should contain a minimum of four and a maximum of eight candidates (would-be service providers), as

    specified in the procurement notice.

  • 7/30/2019 C - Procurement 1 Services- V5.3

    6/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 6/20

    electronic form (after

    approval of SCSN i.e.

    SLR)

    CFCA submits SCSNdirectly to AIDCO

    publication office

    (EDIS) for publication

    11

    DIS: EUD

    EDIS: AIDCO

    SCSN Publication onEuropeAid web-site and

    in EC Official Journal

    1

    2

    CFCA Confirmation of

    Receipt (CoR)

    Receives CoR and the

    intent to (not) submit an

    offer

    13

    DIS: PIU +CFCA+EUD

    EDIS: PIU +

    CFCA + PAO

    Letter with listof EvCom

    members

    (standard EUCVs +

    Declaration that

    they are notlinked through

    direct command

    line)

    Proposing thecomposition,

    nomination and

    approval of EvaluationCommittee

    Max. 10 WDafter the

    shortlisting

    14

    Tenderers Offers Prepare and submittheir offers to theCFCA (double

    envelope system)

    Min. 50 CDfrom the dateof Invitation to

    Tender

    1

    5

    CFCA Offers Receives, registers and

    stores offers

    16

    EvCom EvaluationReport (EvRep)

    Carries out theevaluation based on

    agreed criteria and

    methodology (as

    specified in the TenderDossier), prepares

    Evaluation Report

    Max. 15 WDfrom the

    beginning date

    of evaluation

    1

    7

    CFCA EvRep +

    ContractDossier

    Prepares and sends the

    draft Contract Dossierand Evaluation report

    to the EUD together

    Max. 15 WD

    from the endof evaluation

    (Report)

  • 7/30/2019 C - Procurement 1 Services- V5.3

    7/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 7/20

    with a copy of the

    winning tender, copies

    of the unsuccessful

    tenders (DIS). Preparesand sends Evaluation

    report and Contract toPAO for endoresement

    (EDIS).

    Immidietely

    upon

    verification of

    eligigibilityproof

    documents

    (Contract)

    1

    8

    DIS: EUD

    EDIS: PAO

    EvRep +

    Contract

    Dossier

    Issues notes on

    approving the

    Evaluation report andContract Dossier,

    endorses evaluation

    report and the contract

    (DIS).

    Endorses evaluation

    report and the contract

    (EDIS)

    19

    CFCA Notification of Contract (NOC)

    Sends to the successfultenderer a NOC and

    requests documentary

    evidence

    Max. 10 WD

    20

    Successfultenderer

    Documents Sends CFCA thedocumentary evidence

    Max.15 CDafter the date

    of NOC

    2

    1

    CFCA Contract Examines documents

    submitted by successful

    tenderer for correctness

    2 WD after

    receipt of

    documentation

    22

    CFCA Contract CFCA sends 3 originalsof the Contract to the

    Contractor for signature

    (by registeredmail/courier service)

    2 WD

    23

    SuccessfulTenderer

    Contract + pre-financing bank

    guarantee

    Keeps one original ofthe contract and returns

    the rest of the

    countersigned originalsto the CFCA

    Max. 30 CD

    2

    4

    CFCA Letter to

    Unsusessful

    Sends them to

    unsuccessful tenderers

    15 CD after

    receiving

  • 7/30/2019 C - Procurement 1 Services- V5.3

    8/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 8/20

    Tenderers signed

    contract

    2

    5

    CFCA Contract Sends one original of

    the signed contract tothe EUD (one original

    remains at CFCA), and

    one copy of the original

    is sent to the PIU (DIS).

    Sends one original to

    the financial service in

    charge of payments and

    the other to the ProjectManager. One copy of

    the contract is sent to

    PIU (EDIS).

    1 WD

    26

    CFCA Service ContractAward Notice

    Under DIS: Prepares aService Contract Award

    Notice and submits to

    the EUD for publication in

    electronic form (in

    EDIS Contract AwardNotice is sent to EC for

    publication)

    Under EDIS: CFCAsubmits CAN directlyto AIDCO on

    publication on their web

    site and in OJ

    1 WD

  • 7/30/2019 C - Procurement 1 Services- V5.3

    9/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 9/20

    1.3. Framework Contract

    A Framework contract2 procedure should be used when the budget of the service tender is

    less than 200.000 EUR but more than 10.000 EUR. Alternatively, the competitivenegotiated procedure (described in the next section) could be used.

    The Terms of Reference may request the Framework Contractor to provide an outline for

    the approach and methodology envisaged for the implementation of the assignment.

    Concerning the budget estimation, the total cost of an assignment must be less than 200.000. The input of any expert in a given assignment may not exceed 260 working

    days. The implementation period of the operation does not exceed 2 years (730 calendar

    days) including all addenda. Terms of Reference must specify the category of

    expert/expertise and related number of working days. Only the number of experts is anoption and in that case, the expertise must be clearly defined, as well as minimum

    requirements covering the qualifications and skills (depending on the category ofexperts). Beneficiary has to reach a decision prior to drafting ToR whether the Specificcontract emerging from the ToR will be Fee based or Global price type.

    Fee based type of ToR results in a contract under which the services are provided on the

    basis of fixed fee rates for each day worked by experts. Fee based contracts are usually

    associated with technical assistance, that is, where service provider is called upon to playan advisory role, to manage or supervise a project, or to provide the experts specified.

    Global price ToR assumes that contract will be performed under an all inclusive fixed

    price. Global price contract are usually associated with study type contracts;

    identification and preparation of projects, feasibility studies, economic and marketstudies, technical studies, evaluations and audits. Therefore, final output of the contract is

    easily established and visible.

    Framework contractors are divided into 12 different lots or sectors of expertise. Only lot

    5 (Organisation and logistics for conferences) is always contracted as a fee basedcontract.

    In order to collect all necessary information required for launching of the assignment,

    following resources ought to be consulted:

    list and description of the content of the lots (to ensure rightful application of thespecific lot according to the specific needs of the beneficiary/nature and scope of

    the task)

    2 FWC procedures are guided by Users guide supplemented by Important messages which are regularly

    updated along with standard templates and other FWC specific information by AIDCO and published on

    the following WEB page: http://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-

    2009/index_en.htm

    Therefore, regular monitoring of updates is mandatory task in order to ensure compliance with specific

    rules governing FWC procedures.

    http://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-2009/index_en.htmhttp://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-2009/index_en.htmhttp://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-2009/index_en.htmhttp://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-2009/index_en.htmhttp://ec.europa.eu/europeaid/work/framework-contract/beneficiaries-2009/index_en.htm
  • 7/30/2019 C - Procurement 1 Services- V5.3

    10/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 10/20

    list of the framework contractors from the particular lot accompanied by

    contractually fixed price brackets for required category of expert (including

    information concerning bank accounts on which payment shall be executed)

    list of the signatories entitled to sign Request for offer and Letter of contract

    General conditions of the contract (meaning global contract which Commissions

    signs with all framework contractors)

    Specific Terms of reference

    Other forms

    Procedures stated in table below in cursive letters are applicable only under DIS

    system.

    Unit responsible Document Activity Time1 PIU ToR + budget

    estimate +

    Declaration ofObjectivity

    and

    Confidentiality

    Drafts and checks the

    quality of ToR and budget

    estimate and submits to theCFCA together with

    original Declarations of

    Objectivity andConfidentiality, short-list

    of at least 3 possible

    service providers and

    submission to the CFCA

    2 CFCA ToR + budgetestimate +

    Declaration of

    Objectivityand

    Confidentiality

    + Request forServices (RfS)

    Verification of ToR andbudget estimate, RfS,

    quality control and

    submission to EUD

    5 WD fromthe receipt of

    documentation

    3 DIS: EUD

    EDIS:PAO

    ToR, budgetestimate

    Approves ToR + budgetestimate. (under DIS).

    PAO approves ToR +

    budget estimate (underEDIS).

    15 WD fromreceipt of

    documentation

    4 CFCA RfS, ToR,

    budget

    estimate

    Completion of RfS,

    signature of the RfS by the

    PAO and submission to

    5 WD

  • 7/30/2019 C - Procurement 1 Services- V5.3

    11/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 11/20

    EUD

    5 DIS: EUD

    EDIS: PAO

    RfS + ToR Checks and signs RfS and

    sends the signed RfS back

    to the CFCA.

    PAO signs RfS andreturnes it to the CFCA

    Project Manager

    15 WD from

    receipt of

    documentation

    6 CFCA RfS + ToR Indicates the deadline for

    the receipt of offers (14days from dispatch),

    submits to the relevant

    framework contractors

    1 WD

    7 Framework

    Contractor(FWC)

    Certificate of

    Receipt

    Acknowledgment of

    receipt of the RfS

    2 WD from

    the date of receipt of RfS

    8 DIS: PIU +

    CFCA + EUD

    EDIS: PIU +

    CFCA + PAO

    List of EvCom

    members +

    CVs

    Proposing the

    composition, nomination

    and approval of EvaluationCommittee by EUD (DIS)

    or by PAO (EDIS)

    5 WD from

    the receipt of

    the signed RfSat the latest

    9 FWC Offers for

    Services

    Send their Offers for

    Services to the CFCA

    Max.14 CD

    since dispatchof RfS

    1

    0

    EvCom Evaluation

    Report

    Carry out the evaluation

    and draft Offers

    Evaluation Report, signed

    by the EvCom members(and endorsed by PAO).

    7 WD from

    the deadline

    for receipt of

    offers

    1

    1

    CFCA Evaluation

    Report +

    Letter of Contract

    Prepares Letters of

    Contract, (signed by

    PAO), sends the OffersEvaluation Report and the

    completed Letter of

    Contract (in four originals) to the EUD

    1 WD after

    end of

    evaluation

    12

    DIS: EUD

    EDIS: PAO

    Letter ofContract

    The duly authorised EUDofficial checks, dates and

    signs it and sends it back

    to the CFCA (DIS).

    PAO signs Letter of

    5 WD ater receipt of

    documentation

  • 7/30/2019 C - Procurement 1 Services- V5.3

    12/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 12/20

    contract and returns it to

    Contracting Officer within

    CFCA (EDIS).

    13

    CFCA Letter of Contract

    Sends a copy of the Letterof Contract (signed by

    PAO) to the selected

    framework contractor and

    in addition four originals

    1 WD

    14

    FWC Letter of Contract

    Countersigns the threeoriginal LoCs and sends

    back two originals to the

    CFCA including a signedversion of the original

    offer and an initialled

    version of the ToR

    Max. 30 CDafter receipt of

    Letter of

    Contract fromCFCA

    15

    CFCA Letter tounseucessful

    FWC

    Sends letter to theunsuccessful Framework

    Contractors by (fax or

    email)

    1 WD after receipt of

    Letter of

    Contract fromFWC

    1.4. Competitive negotiated procedure

    A competitive negotiated procedure should be used if the use of an existing framework

    contract is impossible or has been unsuccessful. The budget of the service tender is less

    than 200.000 EUR and more than 10.000 EUR. In terms of rapidity, application of thecompetitive negotiated procedure is considered less favourable option than FWC.

    It is recommended to invite at least 3 candidates

    Procedures stated in table below in cursive letters are applicable only under DIS

    system.

    Unit

    responsible

    Document Activity Time

    1 PIU + Letter of Seeks through the CFCA EUD

  • 7/30/2019 C - Procurement 1 Services- V5.3

    13/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 13/20

    CFCA Request approval (in DIS system) or PAO

    approval (in EDIS system) for using

    competitive negotiated procedure

    instead of FWC2 DIS: EUD +

    CFCA

    EDIS:

    CFCA+PAO

    Note Issues note on approving the

    procedure and sends it to CFCA

    (under DIS).

    PAO approves the procedure (udnerEDIS).

    10 WD

    3 PIU ToR, short-

    list, budget

    estimate,

    original

    Declarationsof

    Objectivityand

    Confidential

    ity

    Drafts and checks the quality of ToR

    and budget estimate, prepares short-

    list of at least 3 possible service

    providers, and submits them to the

    CFCA together with originalDeclarations of Objectivity and

    Confidentiality

    4 CFCA TD, ToR,short-list,

    budget

    estimate

    Verification of ToR, preparation ofTD, quality control and submission

    to EUD for approval

    12 WDafter

    receipt

    5 DIS: EUD

    EDIS: PAO

    TD Issues notes on approving thedocuments and sends these to CFCA(under DIS).

    PAO approves TD (under EDIS).

    15 WDafterreceipt

    6 CFCA TD Initiates the competitive negotiated

    procedure (sends Letter of Invitation

    to Tender and TD to shortlistedcompanies)

    3 WD after

    approval

    7 DIS: PIU+CFCA +

    EUD

    EDIS: PIU +

    CFCA +

    PAO

    Letter with

    list of

    EvCommembers

    (standard

    EU CVs +Declaration

    that they are

    not linked

    through

    Proposing the composition,

    nomination and approval of

    Evaluation Committee by EUD(DIS) or by PAO (EDIS)

    at the time

    of initiating

    procedure

  • 7/30/2019 C - Procurement 1 Services- V5.3

    14/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 14/20

    direct

    command

    line)

    8 Tenderers Offers Prepare and submit offers (doubleenvelope system) to the CFCA

    Min. 30CD

    9 CFCA Offers Receives, registers and stores offers

    10 EvCom EvRep Carries out the evaluation based on

    agreed criteria and methodology (as

    specified in the Tender Dossier),

    prepares Evaluation Report

    10 WD

    11 CFCA EvRep +Contract

    Dossier

    Prepares and sends the draft ContractDossier and Evaluation report to the

    EUD together with a copy of the

    winning tender, copies of theunsuccessful tenders

    5 WD afterend of

    evaluation

    1

    2

    DIS: EUD

    EDIS: PAO

    EvRep +

    Contract

    Dossier

    Issues notes on approving the report

    and Contract Dossier, and returns

    the report to the CFCA (DIS).

    PAO approves the report and thecontract (EDIS).

    10 WD

    after

    receipt

    13 CFCA NOC Sends the successful tenderer a NOC

    and requests documentary evidence33 WD

    14 Successful

    tenderer

    Documents Sends to the CFCA the documentary

    evidence

    Max. 15

    CD after the date of

    NOC

    15 CFCA Contract Examines documents submitted by

    successful tenderer for correctness

    2 WD after

    receipt

    16 CFCA Contract CFCA sends 3 originals of the

    contract to the Contractor forsignature (by registered mail/courier

    service)

    2 WD

    17 Successful

    Tenderer

    Contract Keeps one original of the contract

    and returns the rest of the originalsof the countersigned originals to the

    Max. 30

    CD

    3 PRAG, concerning requests for submission of documentary evidences: For contracts with a value less than the international

    thresholds the Contracting Authority may waive this obligation, depending on its risk assessment. When this obligation has been

    waived, the Contracting Authority may nevertheless, where it has doubts as to whether the tenderer to whom the contract is to be

    awarded is in one of the situations of exclusion, require him/her to provide the evidence.

  • 7/30/2019 C - Procurement 1 Services- V5.3

    15/20

    PIU Operational GuideC PROCUREMENT

    IPA I Version : 5.3 Date : September 2012 Page 15/20

    CFCA

    18 CFCA Letters to

    the

    unsuccessfultenderers

    Sends letters to the unsuccessful

    tenderers

    Max. 15

    CD after

    receivingsigned

    contract

    19 CFCA Contract +

    Service

    ContractAward

    Notice

    Sends one original of the signed

    contract to the EUD (one original

    remains with the CFCA), and onecopy of the original to the PIU

    (under DIS).

    Sends one original to the financial

    service in charge of payments and

    the other to the Project Manager.One copy of the contract is sent to

    PIU (EDIS).

    1 WD after

    receiving

    signedcontract

  • 7/30/2019 C - Procurement 1 Services- V5.3

    16/20

    PIU Operational Guide

    C PROCUREMENT

    Management of CARDS, PHARE, IPA I Version :

    5.2.1

    Date : March 2012 Page 16/20

    1.5. Single tender

    A single tender procedure should be used when the budget of the service tender is smallerthan or equal to 10.000 EUR.

    Notwithstanding the rather small amounts involved, in DIS system the EUD will be

    involved in the award process.

    Under this procedure the CFCA invites a single tender from a candidate of its choice. In

    case the Candidate is technically competent to undertake the work as described in theTerms of Reference and is able to abide by the financial limitations of the budget a

    contract may be signed with this service provider.

    Procedures stated in table below in cursive letters are applicable only under DIS

    system.

    Unitresponsible

    Document Activity Time

    1 PIU ToR + budget

    estimate +

    originalDeclarations of

    Objectivity and

    Confidentiality

    Drafts and checks the quality of

    ToR including a budget estimate,

    and submission to the CFCA withthe proposed company details,

    including a brief explanation for

    selecting the company andoriginal

    Declarations of Objectivity andConfidentiality

    2 CFCA TD + ToR +

    budget estimate

    Verification of ToR and budget

    estimate, preparation of TD and

    submission to EUD for approval(DIS)

    Verification of ToR and budget

    estimate, preparation of TD and

    submission to PAO (EDIS)

    10 WD

    after

    receipt

    3 DIS: EUDEDIS: PAO

    TD Issues notes on approving thedocuments and sends these to the

    CFCA (DIS).

    PAO approves TD.

    10 WDafter

    receipt

    4 CFCA TD Initiates the single tender

    procedure (sends Letter ofInvitation to Tender and TD to

    3 WD

  • 7/30/2019 C - Procurement 1 Services- V5.3

    17/20

    PIU Operational Guide

    C PROCUREMENT

    Management of CARDS, PHARE, IPA I Version :

    5.2.1

    Date : March 2012 Page 17/20

    proposed service provider)

    5 DIS: PIU+

    CFCA +EUD

    EDIS: PIU

    + CFCA +

    PAO

    Letter with list

    of EvCommembers

    (standard EU

    CVs +

    Declarationthat they are

    not linked

    through directcommand line)

    Proposing the composition,

    nomination and approval ofEvaluation Committee by EUD

    (DIS) or by PAO (EDIS)

    at the

    time of initiating

    procedure

    6 Service

    provider

    Offer Prepares and submits an offer to

    the CFCA

    Max. 14

    CD7 CFCA Offer Receives, registers and stores the

    offer

    1 WD

    8 EvCom EvRep Carries out the evaluation andprepares an Evaluation Report

    5 WD

    9 CFCA EvRep Sends a copy of the report, 3

    originals of the contract signed by

    PAO to the EUD together with a

    copy of the offer

    5 WD

    after the

    end of

    evaluation

    1

    0

    DIS: EUD

    EDIS: PAO

    EvRep Issues notes on approving the

    report and returns the report and

    signed originals of the contracts tothe CFCA (DIS)

    PAO approves the report and signs

    the contracts (EDIS).

    15 WD

    after

    receipt

    11 CFCA NOC Sends the successful tenderer a

    NOC and requests documentaryevidence4

    3 WD

    12 Successfultenderer

    Documents Sends to the CFCA thedocumentary evidence

    Max. 15CD after

    4 PRAG, concerning requests for submission of documentary evidences: For contracts with a value less than the international

    thresholds the Contracting Authority may waive this obligation, depending on its risk assessment. When this obligation has beenwaived, the Contracting Authority may nevertheless, where it has doubts as to whether the tenderer to whom the contract is to be

    awarded is in one of the situations of exclusion, require him/her to provide the evidence. Depending on its risks assessment, the

    contracting authority may refrain from requiring the declaration that the candidates or tenderers are not in one of the situations of

    exclusions for contracts with a value equal to or less than 10,000.

  • 7/30/2019 C - Procurement 1 Services- V5.3

    18/20

    PIU Operational Guide

    C PROCUREMENT

    Management of CARDS, PHARE, IPA I Version :

    5.2.1

    Date : March 2012 Page 18/20

    date of

    NOC

    13 CFCA Contract Examines documents submitted bysuccessful tenderer for correctness

    2 WDafter

    receipt

    14 CFCA Contract CFCA sends 3 originals of

    Contract to the Contractor for

    signature (by registeredmail/courier service)

    2 WD

    15 Service

    provider

    Contract Keeps one original of the contract

    and returns the rest of the originals

    of the countersigned originals to

    the CFCA

    Max. 30

    CD

    16 CFCA Contract Sends one original of the signed

    contract to the EUD (one original

    remains with the CFCA) and onecopy of the original to the PIU

    (DIS).

    Sends one original to the financial

    service in charge of payments andthe other to the Project Manager.

    One copy of the contract is sent to

    PIU (EDIS).

    1 WD

    1.6. Negotiated procedure

    A negotiated procedure may be used only in exceptional cases. Due to its exceptionalnature, the format of the negotiated procedure, especially the tendering and evaluation

    phase, is not fixed and should be tailored for each specific case. However, before

    launching a negotiated procedure, in DIS the EUD must approve the use of the negotiatedprocedure, while in EDIS the same must be approved by PAO. A short description of the

    procedure should be submitted to the EUD. The whole negotiation process is documentedin the Negotiation Report.

    Procedures stated in table below in cursive letters are applicable only under DIS

    system.

    Unit responsible Document Activity Time

  • 7/30/2019 C - Procurement 1 Services- V5.3

    19/20

    PIU Operational Guide

    C PROCUREMENT

    Management of CARDS, PHARE, IPA I Version :

    5.2.1

    Date : March 2012 Page 19/20

    1 CFCA + PIU Letter +

    negotiation

    strategy +list of

    candidates

    After consulting PIU, CFCA

    seeks EUD approval to initiate a

    negotiated procedure5

    (DIS) (inEDIS PIU seeks the approval

    from PAO).

    2 DIS: EUD

    EDIS: PAO

    Note Issues note on approving theprocedure (DIS).

    PAO approves negotiated

    procedure.

    15 WD afterreceipt of

    letter

    3 DIS: PIU +

    CFCA + EUDEDIS: PIU +CFCA + PAO

    Proposing the composition,

    nomination and approval ofEvaluation Committee by EUD

    (DIS) or by PAO (EDIS)

    Upon

    approval ofthe

    procedure

    4 EvComm Negotiation

    Report +

    Contract

    Following the previously agreed

    procedure, carry out the

    negotiated procedure inaccordance with negotiation

    strategy, drafts the Negotiation

    Report.

    5 CFCA CFCA drafts contract in three

    originals signed by PAO andsubmits the report and the

    contract to EUD for endorsement

    (DIS).

    CFCA drafts contract in threeoriginals and submits the report

    and the contract to PAO for

    endorsement (EDIS).

    6 DIS: EUD

    EDIS: PAO

    Contract Issues notes on approving thedocuments and returns the

    endorsed contracts to the CFCA(DIS).

    Aproves the report and endorsesthe contract (EDIS).

    15 WD afterreceipt

    5 The negotiated procedure has to be clearly identified and justified (prior approval from the EUD is

    required in DIS system, while in EDIS prior approval by CFCA is required). A brief description of the

    procedure (negotiation strategy) should be included in the letter to EUD/CFCA.

  • 7/30/2019 C - Procurement 1 Services- V5.3

    20/20

    PIU Operational Guide

    C PROCUREMENT

    Management of CARDS, PHARE, IPA I Version :

    5.2.1

    Date : March 2012 Page 20/20

    7 CFCA Contract CFCA sends 3 originals of

    Contract to the Contractor for

    signature (by registeredmail/courier service).

    2 WD

    8 Service provider Contract Keeps one original of the contract

    and returns the rest of the

    originals of the countersignedcontract to the CFCA

    30 CD after

    receipt

    9 CFCA Contract Sends one original of the signed

    contract to the EUD (one original

    remains with the CFCA) and onecopy of the original to the PIU

    (DIS).Sends one original to the financial

    service in charge of payments andthe other to the Project Manager.

    One copy of the contract is sent to

    PIU (EDIS).6

    1 WD

    6 PRAG: The award notice shall be published for procedures where a publication of the procurement notice has taken place or if the

    value of the contract is above international thresholds (service > 200.000, supply > 150.000, works > 5.000.000), unless the

    contract was declared secret of where the performance of the contract must be accompanied by special security measures, or when

    theprotection of the essential interests of the European Union, or the beneficiary country so requires, and where the publication of the

    award notice is deemed not to be appropriate.